topic i: the review process from the identification of the ......topic i: the review process –...
TRANSCRIPT
Topic I: The review process – from the identification of the
problem during the review week to the participation in the
expert hearing of the compliance committee
Presented at the:
REFRESHING SEMINAR ON GOOD PRACTICE APPROACHES TO INVENTORY
ISSUES IDENTIFIED DURING THE REVIEW PROCESS
Simon Eggleston, Jongikhaya Witi, Sandro Federici, Kiyoto Tanabe,
Introduction
• This presentation
a) A short introduction to the compliance committee
b) Three Case Studies:
i. Simple Case leading to Compliance Committee decision
ii. National System Issues with Saturday Paper leading to improvement Plan. ERT
OK with this but Compliance Committee not happy!
iii. Lack of completeness and national system issues leading to Compliance
Committee declaring Party not compliant, but subsequent ERT finds this has
been corrected and Compliance Committee agrees
c) Some final thoughts and questions
n.b. Cases i and ii were actually the same party but they illustrate very different situations
Compliance Committee
From ERT to Compliance Committee
ERT Issues “Saturday Paper”
Party has 6 weeks to respond
ERT has to judge response
If not OK: the ERT produces
Question of Implementation
and/or Adjustment
Compliance Committee – Enforcement
Branch - Considers AAR
Enforcement Branch may give
preliminary decision and hold
hearing
Evidence from ERT, Independent Experts and Party
Enforcement Branch
deliberates and issues decision
Enforcement Branch Confirms
Decision
Enforcement Branch Reviews Party’s Progress
Compliance Committee
• A public process
a) Hearing public - webcast
b) Committee’s deliberations closed, but adopted in open session
c) Present are:
• Party representatives
• Independent Experts & ERT Representatives
• Hearing:
a) Presentation from Lead Reviewer
Important to link findings to mandatory requirements
b) Questions from Committee (to both ERT and Independent Experts)
May cover ERT findings, requirements of UNFCCC and IPCC Guidelines and
other technical issues
c) Questions from Party to the ERT
d) Other Independent Experts asked to comment
e) Statement(s) by Party on issue and subsequent improvements. Questions by
Committee. ERT may be asked to comment
f) LR asked to prepare “Issues Document” covering all issues with mandatory
requirements (national system, lack of completeness, transparency etc.)
Issues Document
Issue Where in
AAR
Requirements Status as at 7th
Sep. 2011
Failed to ensure sufficient capacity for the timely performance of
the functions defined in the Guidelines for national systems
under Article 5, paragraph 1, of the Kyoto Protocol (decision
19/CMP.1), including data collection for estimating anthropogenic
GHG emissions by sources and sinks.
Para 16, 184-
189
19/CMP.1 annex para
10(b)
Unresolved
Failed to prepare national annual inventories and supplementary
information in a timely manner in accordance with Article 5 and
Article 7, paragraph 1, and relevant decisions of the COP/MOP.
Para 20, 184-
189, 191,193
19/CMP.1 annex para
10(d)
Unresolved
Failed to provide information necessary to meet the reporting
requirements defined in the Guidelines for the preparation of the
information required under Article 7 of the Kyoto Protocol
(decision 15/CMP.1).
Para 20, 184-
189
19/CMP.1 annex para
10(e)
Unresolved
Failed to ensure areas of KP-LULUCF land subject to articles 3.3
and 3.4 are identifiable
Para 16, 20
187
16/CMP.1 annex para
20
Unresolved
Failed to document that there is no double counting of land
subject to KP-LULUCF has not been met (9(c) of the annex
to15/CMP.1)
Para 188 15/CMP.1 annex para
9(c)
Unresolved
Failed to prepare estimates in lines with the IPCC Guidelines and
IPCC GPG-LULUCF
Para 20,
186,187
19/CMP.1 annex para
14(b)
IPCC GPG
Unresolved
Failed to collect sufficient activity data or emission factors Para 20, 187 19/CMP.1 annex para
14(c)
Unresolved
Failed to provide information on which of the 5 carbon pools
were include or excluded
Para 190 15/CMP.1 annex para
6(e)
Unresolved
Issue 1
Overview
• ERT found no KP LULUCF Data
• With-in six weeks:
a) Party re-submitted with only land use data
• After six week period
a) Party re-submitted with data but no explanation or revised NIR
b) ERT could not review this and raised a Question of Implementation
• Compliance Committee agreed this was an issue of non-compliance
Submissions
• KP-LULUCF Initial Submission
a) The Submission of 15th April did NOT include information concerning activities under
Article 3, paragraphs 3 (afforestation, reforestation and deforestation) and 4 (forest
management)
b) The ERT recommended the Party to resubmit its KP-LULUCF inventory ensuring it
was in line with paragraphs 5-9 of the annex to decision 15/CMP.1
• KP-LULUCF resubmitted 9 Nov 2010
a) This does contain information about activities under Articles 3 paras. 3 & 4 as
required under Article 7 para 1 of the Kyoto Protocol
b) A section following the outline in the annex I to 15/CP.10 with all of the headings was
included
c) HOWEVER: information restricted to land areas only, no information on emissions
and removals as required by para 5 of the annex to 15/CMP.1
d) Resubmitted CRF tables did NOT contain any numeric data except on area and
changes in area in worksheet “NIR-2” and forest management cap in worksheet
“Accounting”
KP-LULUCF Area Data
• The Party reported under the KP-LULUCF more forest (2,158.3 kha) than reported under
the convention (2,133.95 kha)
a) There is no discussion of this in the NIR or any spatially representative information
about areas of land subject to KP-LULUCF activities,
b) The ERT concluded that the requirement to document that there is no double
counting of land subject to KP-LULUCF has not been met (9(c) of the annex
to15/CMP.1)
KP-LULUCF CRF Tables of 14/1/2011
• Late Submission on 14 Jan 2011
a) The Party also provided CRF tables for 2008 and 2009, which do contain numeric
information on activities under Articles 3 para 3 & 4 of the Kyoto Protocol
• The ERT noted that the areas reported in worksheet “NIR-2” differed from those
submitted in November 2010
• No new NIR was submitted at this time
• The ERT was unable to assess the CRF tables provided in January 2011
a) As there is no explanations and supporting information in the NIR
b) 2009 is not part of the 2010 Submission
c) Any review of the KP-LULUCF would require submission of consistent CRF, detailed
NIR and probably other documentation, followed by exchanges of questions and
answers
KP-LULUCF Conclusions
• The ERT concluded that:
a) This 2010 KP-LULUCF submission does not meet the requirements of Article 7 para
1 of the Kyoto Protocol
• No data!
b) The national system is not able to ensure areas subject to KP-LULUCF activities are
identifiable in accordance with para 20 of the annex to 16/CMP.1
• data but no identification or explanation how this differs form convention inventory
c) The national system does not fully comply with 19/CMP.1, the general functions in
para 10(b), (d) & (e) or the specific functions 14(b) & (c) of the annex to that decision
• Data and Supplementary information not, supplied, not timely, insufficient
resources …
d) The ERT concluded that the requirement to document that there is no double
counting of land subject to KP-LULUCF has not been met (9(c) of the annex
to15/CMP.1)
Requirements of 19/CMP.1
Para Item
10(b) … shall ensure sufficient capacity for the timely performance
of the functions…
10(d) …shall prepare national annual inventories and
supplementary information in a timely manner…
10(e) …shall provide information necessary to meet the reporting
requirements (15/CMP.1)…
14(b) Prepare estimates in accordance with the [IPCC Guidelines]…
14(c) Collect sufficient activity data, process information and
emission factors as are necessary
The ERT role with the CC
• To the CC the ERT provides:
a) additional clarification on ARR findings;
b) technical support on:
• Party’s hearing (including current status and planned improvements)
• Reporting requirements
• Reporting methods
Compliance Committee
• The Compliance Committee agreed with the ERT that this did not meet the mandatory
requirements as described by the ERT.
a) Formal announcement in public part of meeting
b) Documents
• Decision to seek expert advice (CC-2011-3-3/Lithuania/EB)
• Report of Meeting (CC/EB/16/2011/2) 26th Nov 2011
• Preliminary Finding (CC-2011-3-6/Lithuania/EB) 26th Nov 2011
• Final Decision (CC-2011-3-6/Lithuania/EB) 21 Dec 2011
• Note:
a) Re-submission resulted in additional problem in inventory!
b) ERT did not review re-submitted LULUCF data as no accompanying information
Issue 2
Overview
• ERT raised National System Issue during review
• After six weeks
a) Party submitted plan to improve National System
b) ERT agreed this was a good plan and did not raised question of implementation
• This was questioned by Compliance Committee during discussion of issue 1
a) During hearing, the party voluntarily produced the “Saturday paper” of the following
ERT which indicated they had not implemented all the improvement plan.
b) This, combined with Issue 1, led to a decision the party was non-compliant
Potential Problem – National System
• During the review the ERT notes that the party
a) has not been able to collect the necessary activity data, process information and
emission factors for a number of key categories
b) This issue has been raised in the review reports since 2007
c) Identified 15 sectors with missing or non-transparent estimates
• The ERT recommended improvements to the national system to
a) Ensure appropriate methods can be used
b) Resource constraints identified by the Party are resolved
c) Ensure the collection of sufficient activity data and emission factors to estimate all
missing estimates
• The ERT requested the party to provide information on how it would address these
recommendations including, issues, allocation of tasks, schedule and deadlines.
Response to the ERT (1)
• 14 Jan 2011 the party submitted its Plan for improvement for its GHG inventory
• This addressed:
a) Legal Basis & Institutional Arrangements
• Determined responsibilities for data collection
• Improving F-gas data collection by allocating clear responsibilities
• Defining the inventory compiler and other inventory compilation
responsibilities
b) Inventory preparation (including work plan, allocation of responsibilities and
deadlines)
c) Quality Assurance and Quality Control,
d) Planned Sectoral Improvements
e) Long-term financing and data collection will be included in the State Environmental
Monitoring Programme for 2011-2016
• As a result the ERT determined that, in future, the party should be in a position to fulfil its
responsibilities in regard to AD and EF
Compliance Committee
• The compliance committee questioned if the ERT correct in saying that issue 2 was
resolved when the party produced a reasonable plan?
a) Compliance Committee were not convinced
b) Subsequent ERT noted issues not fully resolved
• Party voluntarily submitted the “Saturday Paper” from the 2011 Review
• Experts were asked (based on “Saturday Paper”) if 2011 submission had resolved
National System Issues. It had not! (e.g. No archiving.)
• Compliance Committee decided the national system did not meet the mandatory
requirements (combined with Issue 1)
Issue 3
Overview
• During the 2010 review (centralized) the ERT found failures in the national system and
lack of completeness in estimates of the Party
• During Six weeks
• Resubmission by the Party failed to address all national system issues and provide
complete revised estimates in the 6 weeks time
• After the six week period
• Adjustment made by ERT to fill gaps in estimates
• Compliance Committee declares non-compliance of Party with national system
requirements
• 2011 review cycle (in country) the ERT found national system functions in line with
requirements as reported in the 2011 AAR (January 2012)
• First hearing of the Compliance Committee deferred adoption of a new decision for
seeking advice (January 2012)
• Compliance Committee declared Party compliant with national system requirements
(March 2012)
2010 review findings “Saturday paper”
• 2010 Centralized review, potential problems: lack of completeness (a principle of the
UNFCCC reporting guidelines)
• Several Annex A Sources were reported as “NE”:
a) several categories of fugitive emissions from oil and natural gas,
b) halocarbons and SF6
• Completeness – being a principle in reporting there is an obligation for Parties under the
annex to decision 19/CMP.1 paragraph 14 b and c to collect sufficient data/information for
supporting estimates to be prepared according with IPCC methods
• ERT recommendation: check whether the activity is occurring in the country and either
provide a revised estimate or use the notation key NO
2010 review findings “Saturday paper”
• 2010 Centralized review, potential problems identified in national system:
• Land Identification – identification of land subject to Article 3.3 and 3.4 activities is a
mandatory requirement, see annex to decision 16/CMP.1 paragraph 20
• ERT recommendation: set up a system able to identify land subject to Article 3.3 and 3.4
activities (e.g. by identifying and tracking land subject to land use and land use changes).
• Collection of data/information needed for preparing estimates in a timely manner: The
ERT noted persistent non-implementation of improvement plans for collecting
data/information for reporting KP-LULUCF activities (a mandatory requirement see annex to
decision 19/CMP.1 paragraph 10 b and 14 c).
• ERT recommendation set up arrangements to collect sufficient information and data for
preparing estimates in a timely manner
2010 review findings “Saturday paper”
• 2010 Centralized review, potential problems identified in supplementary information to be
reported for Article 3.3 and 3.4 activities (decision 15/CMP.1).
• The following mandatory requirement supplementary information was note supplied:
• demonstrate that an unaccounted carbon pool is not a source, (paragraph 6 e )
• demonstrate that activities reported under Article 3.3. and 3.4 are direct human
induced (paragraph 8 a )
• ERT recommendation provide complete supplementary information.
2010 resubmission by Party
• Party’s Resubmission within 6 weeks:
a) Party provided revised estimates for the for the energy sector. Party did not provide
supplementary information
• Provided KP-LULUCF data however it did not provide required supplementary
information
• The Party’s justification was a lack of financial resources as a national
circumstance; however the Party indicated that it has the potential of getting
financial resources from the carbon market
• Did not provide revised halocarbon and SF6 estimates
• The Party’s justification was lack of activity data; The Party informed the ERT
that research is planned to be conducted using finical resources form the
carbon market
2010 ARR
• In its 2010 ARR the ERT reported:
a) Adjustments for the omitted estimates (halocarbons and SF6)
b) Questions of implementation in respect of the national system failing to:
• ensure sufficient capacity for data collection for estimating anthropogenic GHG
emissions by sources and removals by sinks (para. 10(b) decision 19/CMP.1);
• prepare national annual inventories and supplementary information in a timely manner
(para. 10(d) decision 19/CMP.1);
• prepare estimates in accordance with the method and ensuring that appropriate
methods are used to estimate emissions from key categories (para. 14(b) decision
19/CMP.1);
• collect sufficient AD, process information and EFs as are necessary to support the
methods (para. 14(c) decision 19/CMP.1);
• provide ERT with access to all archived information used to prepare the inventory
(para. 16(b) decision 19/CMP.1);
• respond to requests for clarifying inventory information (para. 16(c) decision
19/CMP.1);
Compliance Committee
• The Compliance Committee concurred with the ERT and declared the Party did not
comply with the mandatory requirements, both completeness and national system
2011 ARR
• In its 2011 ARR the ERT reported that the national system performs its required functions
as set out in the annex to decision 19/CMP.1;
Compliance Committee on the 2011 review cycle
• In February 2012
a) The Party presented to the Enforcement Branch the “First progress report submitted
in accordance with paragraph 5 of the Decision on the review and assessment of
the plan submitted under paragraph 2 of section XV (…) adopted by the
Enforcement Branch concerning the Party and in accordance with section XV,
paragraph 3 of the Procedures and mechanisms relating to compliance under the
Kyoto Protocol.”
b) The Enforcement Branch considered this and the latest ERT report (2011 ARR)
which:
• Concluded that the national system performs its required functions
• Recognized that .parts of the national system relating to the LULUCF sector of
the inventory and reporting of activities under KP-LULUCF need to be further
improved.
• Identified that there is .a need to further incorporate the LULUCF sector into
the national system.
• Concluded that some areas of the Party’s inventory are not completely in line
with the IPCC GPG LULUCF guidelines
Compliance Committee (2)
• Compliance Committee again decided to seek expert advice on Party’s request of
eligibility reinstatement
• In March 2012 the compliance committee heard from 2 of the 2011 ERT who
a) clarified a number of issues in relation to the recommendations contained in the 2011
ARR.
b) provided an assessment of the relationship between measures to be implemented in
the 2012 and 2013 annual submissions as presented in the Party’s plan submitted
pursuant to the final decision of the enforcement branch and the performance by
party’s national system of the mandatory functions. (annex to decision 19/CMP.1)
Compliance Committee (3)
• The Compliance Committee meeting:
a) Questioned the correct implementation of UNFCCC decisions related to the GHG
reporting and review process
b) Heard a Party statement on the current status of the issue;
c) Raised the issue of consistency of LULUCF system with KP requirements since
recommendations on improvements to be implemented before the accounting year
(i.e. the last year of the Commitment Period) have been reported in the 2011 ARR;
d) Questioned
• Is the national system for LULUCF properly working if for the current year it is not
performing all its functions but it is expected it will properly work at the end of the
CP?
• Is the national system working properly if ARR includes recommendations for
improving it?
e) Decided to re-instate the Party’s eligibility to participate in the mechanisms
Summary
• 3 Case Studies:
a) Simple Case leading to Compliance Committee decision
b) National System Issues, leading to improvement Plan. ERT OK with this but
Compliance Committee not happy!
c) Lack of completeness and national system issues leading to Compliance Committee
declaring Party not compliant, but subsequent ERT finds this has been corrected and
Compliance Committee agrees
• ERT needs to be clear which mandatory requirements have not been met
• ERT needs to be able to explain this and defend their decision to the Compliance
Committee
• Re-submission may lead to more problems as well as solving them!
Questions
a) Should ERT accept assurances that a problem will be fixed (with a good improvement
plan)?
b) Do ERT recommendations for improvements to National System mean a Party is not
compliant?
c) If it is assured a National System Problem will be fixed before the end of the
commitment period does this mean that the party complies with the mandatory
requirements this year?
d) If an inventory is not complete, does that mean there is a national system problem?
e) How much time should ERT allow party to respond? Should it refuse to look at
material submitted after the 6 week period?