toshiba git

Upload: karunamcs

Post on 04-Apr-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Toshiba Git

    1/12

  • 7/29/2019 Toshiba Git

    2/12

    199

    3

    199

    6

    188

    5

    189

    4

    190

    3

    193

    9

    195

    2

    196

    7

    200

    2

    50kV-4kVA TR

    Start manufacturing in 1894

    Worlds first by Ganz 1050kV-3000/3MVAUHV TR

    330kV-400MVA GIT(Worlds largest)

    66kV-3000kVA GIT

    (Japans first)

    275kV-99MVA TR(Japans first)

    220kV-80MVA TR(Asias first)Almost sameyear as Europes

    first operation

    525kV-1450MVA TR(Worlds largest) Fig.1

    Toshiba TransformersHistory & Background

    Only 9 years after the worlds first transformer was manufactured, Toshiba started supplying transformers

    to the market in 1894. Since then, Toshiba has been one of the most innovative transformer manufacturersin the world. In 1967, Toshiba delivered the first GIT, 66kV, 3MVA transformer to the market, which features

    excellent characteristics for safety and environmental friendliness.

    As power consumption in urban areas increases, a large number of substations have been constructed

    underground, beneath commercial buildings, parks and public spaces. Safety and the avoidance of fireincidents is the most important consideration for substations in urban areas. Compact and cost effective

    solutions are required for substations installed in areas where space is limited. Gas insulated transformers(GITs) instead of Oil immersed transformers (OITs) offer the best solution for overcoming the sharp increase

    in electric power demand in large cities.

    History of Toshiba Power Transformers

    GIT World wide application Underground Substation within a business complex

    1

    Application: GITs excel in explosion-proof safety and are

    widely used in underground and indoor substations in urban

    areas. GITs are also installed in environmentally critical

    areas where oil leakage is prohibited.

    Toshiba has supplied a large number of GITs all over

    the world and there are many GIT projects planned for

    the future.

    As of 2008

    Supplied

    Under discussionFig.2 Fig.3

  • 7/29/2019 Toshiba Git

    3/12

    Pressure rise during fault is small

    SF6 Insulation Non-flammable

    Non-explosive

    0

    20

    40

    60

    80

    100

    0 0.2 0.4 0.6 0.8 1 1.2

    OIT

    GIT

    Fault Time(sec)

    PressureRise(%) Tank Strength

    Pressure rise of GIT is very small

    TRANSFORMER ROOM

    GIT

    GIB

    GISROOM

    CONSERVATOR

    OIL TRANSFORMEROILCABLEBOX

    PRESSURERELIEFDEVICE

    > Close Arrangement of

    Transformers and GISWithout Partitions> Low Ceiling Substation Room

    * No Conservator andPressure Relief Device

    150MVA-275kV Shunt Reactor

    300MVA-275kV GIT GIS

    Advantages of GIT Technology

    Excellent features of GIT

    GITs employ SF6 gas as the insulation & cooling medium, which avoids the need for fire

    fighting equipment, oil collection tanks and pits outside the transformer room.

    Since the rise in tank pressure for an internal fault is very small compared with the GIT

    tank withstand strength, the GIT tank will not explode on internal fault ensuring the safety

    of equipment within the substation.

    Since neither a conservator nor pressure relief arrangement is required, the height of the

    transformer room can be reduced. For the case of a 275kV 300MVA class application,

    approximately 2 to 2.5 meter reduction in height can be achieved.

    The application of GIT together with GIS offers a very compact substation design as the

    equipment is installed in the same room. A significant cost reduction for civil construction

    can thus be achieved.

    Features Advantages with GIT

    Non-flammability

    Non-explosive feature

    Compactness

    Excellent interface withGas Insulated Switchgear(GIS)

    Pressure rise on internal fault

    Compact substation design throughapplication of GIT

    2

    As oil is not used in a GIT, a fire wall between the GIT and

    GIS or separate rooms are not required. Therefore GITand GIS can be instal led in the same room. This

    arrangement enables a compact substation to beachieved.

    Significant tank pressure increases do not occur during

    internal failures due to the Gas characteristics. The risk of

    a tank explosion or fire incident can be completelyeliminated.

    Fig.4

    Fig.5

  • 7/29/2019 Toshiba Git

    4/12

    Insulation / Cooling

    Insulating Oil SF6Pressure 0.14 or 0.43MPa-g(20)

    Solid Insulation Material

    Oil Impregnated Paper, Pressboard PET Film,PPS Film, Aramide Paper,Pressboard

    Conservator

    Necessary Unnecessary

    On-Load Tap Changer

    Diverter Switch

    Arcing Switching in Oil Vacuum Interrupter

    Tap Selector

    Slide Contact Roller Contact

    Construction

    The construction of a GIT is basically the same

    as an OIT, with the exception of insulatingmaterial and cooling medium. Therefore, broad

    experience of OIT technology can be applied toGIT design, manufacturing and maintenance.

    Features of GIT

    3

    Oil Immersed Transformer(OIT)

    Gas Insulated Transformer(GIT)

    Fig.6

  • 7/29/2019 Toshiba Git

    5/12

    Air Outlet

    Air Inlet

    Cooling Fan

    Air Cooler

    Commercial building

    Cooling system

    The concept of the external cooling design for a GIT is nearly the same as that for an OIT; for this reason

    various types of cooling method can be applied.

    4

    Cooling design for GIT

    Since the head pressure of SF6 gas is negligiblylow, cooling equipment can be located above the

    GIT level as indicated in the figure. The GIT offersexcellent flexibility when locating components

    such as radiators or coolers.

    A water cooling system is widely used in large-capacity

    underground and/or indoor substations. The heat

    generated from a GIT is efficiently transferred towater-air heat exchangers by water flow. The coolingsystem is usually located on the top floor of the

    substation building.

    Flexibility in substation design Water cooling system forurban substations

    GDAN/GDAF-20/63MVA - 110kV GIT

    1. GNAN Type 2. GDAN Type 3. GDAF Type 4. GDWF Type

    RadiatorGas Blower

    Radiator

    Gas Blower Gas - WaterHeat-Exchanger

    Cooler

    Water

    Gas to Water

    Circulating water pumpUnderground

    Gas Watercooler

    Gas Blower

    Silencer

    Water to Air

    Gas to Water

    P

    Fig.7

    Fig.8 Fig.9

  • 7/29/2019 Toshiba Git

    6/12

    Fig.10

    Fig.11

    Computer AidedEngineering (CAE)

    Radiator coolingWinding cooling

    Transformer room cooling

    5

    Temperature analysis for GIT design and GIT room considerations

    In the cooling design for the GIT winding or substation buildings, Computer Aided Engineering (CAE)

    methods can be applied. The calculation using CAE for the airflow inside the building and/or outside isvery useful during the planning stage of the substation building.

    The calculation result used in the figure shows that the top cooler arrangement is suitable in terms of

    efficient substation cooling for this case. Positions of coolers can be decided by carrying out the CAE

    analysis taking into consideration the arrangement of the substation.

    Air Temperature distribution Air velocity vector and distribution

    Exhaust Flow Late = 760m3/min, No-Duct

    Coil

    HorizontalCooling Duct

    Gas Stopper

    Gas Stopper

  • 7/29/2019 Toshiba Git

    7/12

    Fig.12

    Interface with other substationequipment

    Cable connection

    6

    There are various types of terminal construction for GIT applications. In order to reduce the space required

    for the terminal construction, cable connection or GIB direct connection is widely applied instead of airbushing connection especially for underground or indoor substations.

    The cable interface construction is well defined and termination

    work can be done in a secure manner in accordance with theinternational standard (IEC or others).

    Plug-in connector interface

    Gas treatment work at the cable compartment is not required

    during installation work in the case of the plug-in connector. Aplug-in connector is usually only applied for small capacity, low

    voltage GITs due to availability of the connector.

    Gas Insulated Busbar (GIB) direct connection

    GITs can be installed together with GIB or GIS in the same

    room by applying either GIB or GIS direct connection as shownin Fig. 5 on Page 2.

  • 7/29/2019 Toshiba Git

    8/12

    Type GVT-D100AL GVT-M100CL GVT-100DH

    Photo

    Step Voltage

    Rated Current

    1200V 1500V 2500V

    380A 600A 870A

    On-Load Tap Changers (OLTC)& Accessories

    Temperature indicationSudden gas pressure relay

    Line-up of OLTC for GIT

    7

    Comparison between accessories for GIT and OIT

    Item GIT OIT

    ProtectiveDevice &

    Accessory

    Air ventilation

    Temperature

    Leak

    Protection

    Others

    Gas Temperature IndicatorWinding Temperature Indicator

    Oil Temperature IndicatorWinding Temperature Indicator

    Oil Preservation SystemDehydrating Breather

    Ventilation with fireproof dampers tooutdoors

    Buchholtz relay, Gas detection relay,Pressure relief device,

    Gas density relayCompound gauge

    Sudden gas pressure relay (OLTC)

    Oil Level gauge

    Ventilation to outdoors

    SENSING UNIT

    DIAL TYPE THERMOMETER

    RESISTANCEBULB

    GAS WTI

    Fig.14 Fig.15

    Fig.13

    Table.1

  • 7/29/2019 Toshiba Git

    9/12

    Diagnostics & Maintenance

    GIT Diagnostics

    GIT Maintenance Program (Example)

    8

    NO. Maintenance Item

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    Gas analysis

    Replenish the bearing grease of gas blower

    Gas blower bearings

    Exchange Gas blower

    Indication and protection devices

    Exchange Gas pressure sensor

    Exchange Bushing

    Exchange control cable Wiring

    Inspection of OLTC

    Exchange a Cooler

    Exchange O-ring, Gasket

    Running repairs of small gas leakage

    when failureoccur

    30 yearsEvery

    15 years

    Every

    10 years

    Every

    5 years

    Every

    3 years

    Every

    2 years

    Required maintenance period

    Maintenance cycle & items for GITs

    Fig.16

    Table.2

    The integrity of GITs can be checked and a failure cause analysis can be made using gas chromatography.Using a simple gas detective tube device, GIT integrity can be confirmed at site.

    Gas sampling bag

    Gas detective tube

  • 7/29/2019 Toshiba Git

    10/12

    Typical application

    400MVA GIT in underground substation15/50MVA - 110kV GIT in underground substation

    OIT and GIS application GIT and GIS application

    9

    As oil is not used in both GIT and GIS equipment,neither a fire wall nor separate rooms are required. Byinstalling both GIT and GIS in the same room, acompact substation can be realized.

    Toshiba supplies a wide range of GITswith low pressure gas and high pressuregas technology.

    OIT and GIS must be separated by a fire wall orinstalled in separate rooms dependent upon the firerisk.

    Low pressure design:

    0.14MPa-g

    High pressure design:0.43MPa-g

    Applied Voltage, Capacity & Gas pressure

    Voltage

    (kV)

    Capacity (MVA)

    275

    154

    500

    66

    22

    10 200 30010068

    Low PressureSmall Capacity

    High PressureLarge Capacity

    Water cooling system is applied

    Fire extinguisher

    Gravel fillingoil catch pit

    Long GISinterface

    High ceiling

    Fire wall

    GIT substation is simple & small

    Lower ceiling

    Substation size is half

    Fig.17 Fig.18

    Fig.19

    Fig.20

    Fig.21

    0.43Mpa-g

    0.14Mpa-g

  • 7/29/2019 Toshiba Git

    11/12

    Environmentally friendly feature

    39MVA-132kV GIT near Australian national park

    SF6 gas emission from gas-insulated equipment in Japan Gas leak test at the factory

    10

    In order to confirm no gas leakagefrom the GIT tank, gas leak testsare performed at the factory for allGIT tanks. At site the gas leaktest is performed on re-assembledparts to ensure no leakage.

    Electric power companies and Electric equipment manufacturers in Japan have made tremendous efforts to reduce

    SF6 gas emissions based on an agreed voluntary target. With careful gas treatment and complete SF6 gas recoverysystems, the amount of SF6 gas emission from gas insulated equipment has been dramatically reduced as indicatedby the green bars.If no action had been taken, the amount of SF6 gas emissions would still be increasing as indicated by the orangebars.

    The Hydro Power station shown in this photograph is located in the wet tropical area within a worldheritage site. A GIT was provided at the power station to remove the risk of oil leakage.

    With Action Without Action700

    600

    500

    400

    300

    200

    100

    0

    1990

    1992

    1994

    1996

    1998

    2000

    2002

    2004

    2006

    2010

    SF6Emissions(t)

    Control for SF6 gas emission

    28.729405065

    86117

    209

    378449

    491

    Fig.22

    Fig.23

    Fig.24

  • 7/29/2019 Toshiba Git

    12/12