TOWN OF EDENTON NEW POLICE DEPARTMENT Aerial XXXX Program Floor
Plan Schedule 2014 2016 31 days 17 days 12 days 40 days 34 days 9
days
Preliminary/Schematic Design Dec 15 - Jan 26 17 days Jan 27 - Feb
18 Design Development 12 days Community Meetings Feb 19 - Mar 6 40
days Mar 16 - May 8 Construction Documents 34 days May 11 - Jun 25
Permitting/Bidding Period 9 days Contract Preparation/ Approvals
Jun 30 - Jul 10 210 days Jul 13 - Apr 29 Construction Period 2014
2015 2016 2014 Dec Feb Apr Jun Aug Oct Dec Feb Apr 2016 Today Jun
25 Receive Bids May 8 Jun 29 Award of Construction Contract
Construction Documents Complete Budget QUESTIONS?