transition to isms verification at the idaho cleanup project
DESCRIPTION
Transition to ISMS Verification at the Idaho Cleanup Project. Integrated Safety Management Champions Workshop. Brookhaven National Laboratory November 29, 2007. William W. Gay III ICP Operations Technical Support Director. Idaho National Laboratory Safety Landscape. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/1.jpg)
Integrated Safety Management Champions Workshop
Transition to ISMS Verification at the Idaho Cleanup Project
Brookhaven National LaboratoryNovember 29, 2007
William W. Gay IIIICP Operations Technical Support Director
![Page 2: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/2.jpg)
2
Idaho National Laboratory Safety Landscape
![Page 3: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/3.jpg)
3
Idaho National Laboratory Transition History
![Page 4: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/4.jpg)
4
Active involvement by the CWI President enables Phase I ISMS.Safety Axiom
Active involvement by the CEO enables ISMS verification.
ISMS AXIOM
ISMS Implementation
ISMS Project Office Expert Technical Lead with continuity Experienced team members Span and overlap Phases I and II to build the
ISMS infrastructure— Requirements— Processes— Knowledge
Functional support managers team with line management Subject-matter experts embedded in line organizations Total commitment from the Chief
Executive Officer and Chief Operating Officer
Strategic Plan (PLN-1993): ISMS vision
![Page 5: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/5.jpg)
5
Comprehensive, integrated strategy Identify functional support managers and
subject-matter experts Requirements rolldown (Critical Assessment
Institutional Verification Tool)
— Everyone uses the tool
— Consistent approach Learn requirements and ISMS, but
verifying not “training” Review processes for gaps
ISMS Phase I Implements Guiding Principles
ISMS Implementation
Scrub the processes to remove nonrequirements and redundancy Contractor External Assist Visit
— Identified deficiency: Had not trained middle line management on Phase I ISMS “Interview line managers who are or will be responsible for administering the
mechanisms of the ISMS” (DOE-HDBK-3027-99)
![Page 6: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/6.jpg)
6
ISMS
ISMS Implementation
![Page 7: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/7.jpg)
7
ISMS Phase II Equals VPP Readiness
Capture VPP Handbook requirements with tools
Apply feedback from Phase I Capture VPP Handbook with work
force tools ICP Toolbox
— Creative way of presentingtechnical information
— Pocket guide— Relevant— Worker supported— Targeted to verification readiness (ISMS, VPP, OA)
ICP Desktop Guide— Addressed Phase I deficiency— Line management teams with workers
ISMS Implementation
![Page 8: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/8.jpg)
8
WATCH WORK (this is the key)
Are processes being used? Are the processes effective? Technical experts have 1 on 1
with key personnel Multiple data points for
external review Management
involvement
ISMS <=> Rubik’s cubeSafety AxiomISMS <=> Rubik’s cube
ISMS AXIOM
ISMS Implementation
![Page 9: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/9.jpg)
9
ICP ISMS Phase II Verification Flow Chart
ISMS Implementation
ISMS Implementation
![Page 10: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/10.jpg)
10
Key ISMS Implementation Lessons Learned
Use “verification”—a “reverification mindset” will miss the mark with new management
Don’t be fooled by great metrics—the longer since the previous ISMS verification, the more underlying weaknesses and gaps there will be; transition adds more
New management needs to adopt and adapt current practices to support workers, not management
Key personnel from the previous verification can provide continuity, direction, and invaluable lessons learned for the (re)verification process
Implement a formal plan identifying vision, strategy, and tasks Ask the DNFSB for help and it will be given
Lessons Learned: “Don’t change for the sake of change.” Management, not workers, needs to adjust if possible.
Safety AXIOM
Lessons Learned: “Don’t change for the sake of change.” Management, not workers, needs to adjust if possible.
ISMS AXIOM
![Page 11: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/11.jpg)
11
Key ISMS Implementation Lessons Learned
New management needs to understand that verification is a rigorous, structured assessment— GET READY— Involve the DOE Operations Office— Have external verification beforehand (CEAV) (DOE dress rehearsal)— Schedule work, interviews, and document reviews to support the DOE Verification Team’s objectives— Match each CEAV and DOE team member with a “shadow”— Distribute lessons learned from each day’s outbrief (“War Room”)
With active support of the CEO and COO— Phase I: 6 months— Phase II: 12 months— VPP: 14 months
WALK DON’T RUN (“Leave No Worker Behind”)— Implement ISMS prior to high-risk activities— Multiple data points to observe and verify not “train”
![Page 12: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/12.jpg)
12
![Page 13: Transition to ISMS Verification at the Idaho Cleanup Project](https://reader035.vdocuments.net/reader035/viewer/2022062519/56814f4c550346895dbcf147/html5/thumbnails/13.jpg)
13
Result of ISMS Verification