TRANSMISSION LINE & SUBSTATION PROJECTS COMPANY: ENTERGY SERVICES, INC. CUSTOMER ENTERGY SERVICES, INC. FACILITIES STUDY EJO NO. F4PPLA0351 ICTT-2010-142/-143/-144/-145 TRANSMISSION SERVICE REQUEST OASIS 74899972_74_76_80 Revision: 0 Rev Issue Date Description of Revision Prepared By Approved By A 5/09/11 Submitted to TPD, JET, and Director for review/comments RP RG B 5/13/11 Approved with Revisions per comments from JET,TPD, and Director RP RG 0 5/16/11 ICT Determines Upgrade Classification SM BR

Upload: others

Post on 02-Dec-2020

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

TRANSMISSION LINE & SUBSTATION PROJECTS

COMPANY: ENTERGY SERVICES, INC.

CUSTOMER ENTERGY SERVICES, INC.

FACILITIES STUDY

EJO NO. F4PPLA0351

ICTT-2010-142/-143/-144/-145

TRANSMISSION SERVICE REQUEST OASIS 74899972_74_76_80

Revision: 0

Rev Issue Date

Description of Revision Prepared

By Approved

By

A 5/09/11 Submitted to TPD, JET, and Director

for review/comments RP RG

B 5/13/11 Approved with Revisions per

comments from JET,TPD, and Director RP RG

0 5/16/11 ICT Determines Upgrade Classification SM BR

Page 2: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

2

TABLE OF CONTENTS

1. PROJECT SUMMARY ....................................................................... 3

1.1 Background and Project Need ...................................................................... 3

1.2 Scope Summary ........................................................................................... 3

1.3 Cost Summary .............................................................................................. 4

1.4 Schedule Summary ...................................................................................... 4

SAFETY REQUIREMENTS & GENERAL ASSUMPTIONS ......................... 4

3. GENERAL SCOPE OF WORK .......................................................... 5

3.1 Upgrade the Ninemile – Southport 230kV Lines 1 and 2 .............................. 5

3.2 Upgrade the Gretna-Harvey 115kV Line .................................................... 10

4. COST ............................................................................................... 16

5. UPGRADE CLASSIFICATION ......................................................... 17

6. SCHEDULE ...................................................................................... 17

7. RISK ASSESSMENT ....................................................................... 18

8. CONFIRMED RESERVATIONS ....................................................... 19

9. PRE-888 TRANSACTIONS .............................................................. 23

10. STUDY QUEUE ................................................................................ 24

11. ATTACHMENTS .............................................................................. 25

11.1 Table of Acronyms .................................................................................. 25

11.2 Drawings ................................................................................................. 26

11.3 Duration Schedule ................................................................................... 31

Page 3: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

3

1. PROJECT SUMMARY

1.1 Background and Project Need

The purpose of this Facilities Study is to determine the availability of transfer capability across Entergy’s transmission system from Entergy (EES) to Entergy (EES) to evaluate the Entergy Services request for 584MW of yearly network transmission service. ATC for OASIS 74899980 was evaluated with the proposed undesignations cited in OASIS requests 74899972, 74899974, and 74899976. The time period for this transfer is from 1/1/2015 until 1/1/2045. The direction of the transaction is EES to EES. The study was performed on the latest available 2014-2020 winter and 2015-2020 summer peak seasonal models using PSS/E and MUST software by Power Technologies Incorporated (PTI). The Facilities Study identifies any transmission constraints resulting from the requested power transfer. The Facilities Study also includes cost estimates to correct any transmission constraints.

1.2 Scope Summary

The Facilities Study has identified some transmission constraints.

1.2.1 Upgrade the Ninemile - Southport 230kV transmission lines 1 and 2

The Ninemile - Southport 230kV transmission line 1 / 2 overloads for the loss of the Ninemile - Southport 230kV transmission line 2 / 1. It is required that the Ninemile - Southport 230kV transmission lines 1 and 2 be upgraded from 641MVA to at least 747MVA. The proposed upgrade rating is 780MVA. The amount of capacity created by this upgrade is 139MW for each line, and the customer’s use of the capacity created is 109MW on each line.

1.2.2 Upgrade the Harvey - Gretna 115kV transmission line

The Harvey - Gretna 115kV transmission line overloads for the loss of the Ninemile - Westwego 115kV or Ninemile - Estelle 230kV transmission line. It is required that the Harvey - Gretna 115kV transmission line be upgraded from 120MVA to at least 161MVA. The proposed upgrade rating is 228MVA. The amount of capacity created by this upgrade is 108MW, and the customer’s use of the capacity created is 12MW.

1.2.3 Pmax of the generating plant is exceeded

Only 570MW is available (beyond which Pmax of the generator would be exceeded).

Page 4: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

4

1.3 Cost Summary The estimated total project cost in 2011 dollars is $2,262,916. This does not include Tax Gross Up, which may apply (rate at this time is 30%). The ICT has assigned $0 as Base Case upgrades and $2,262,916 as Supplemental Upgrade based on Attachment T of Entergy’s Open Access Transmission Tariff (OATT).

1.4 Schedule Summary

The requested in-service date is January 1, 2015. The duration of work scoped and estimated below is eighteen (18) months starting from June 4, 2012, and is expected to be completed by December 2013.

SAFETY REQUIREMENTS & GENERAL ASSUMPTIONS

Safety: Safety is a priority with Entergy. Safety will be designed into substations and lines. The designs will be done with the utmost safety for personnel in mind for construction, operation, and maintenance of the equipment. All employees working directly or indirectly for Entergy shall adhere to all rules and regulations outlined within the Entergy Safety manual. Entergy requires safety to be the highest priority for all projects. All Entergy and contract employees must follow all applicable safe work procedures.

General Assumptions:

Sufficient time will be allowed in approving the project, enabling Entergy to prepare a Project Execution Plan (PEP) and be able to complete the project, as per the schedule described below. The use of a Facilities Study and estimates is not favored to commence an approved project.

Assumptions have been made in developing estimates without performing site visits, surveys, and soil borings. During PEP, these tasks will be completed and could have an impact on estimates and schedule.

All costs above represent good faith estimates in today’s dollars and are based on existing data, and could change considerably after development of detailed PEP. Price escalation for work in future years has not been included.

Page 5: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

5

3. GENERAL SCOPE OF WORK

3.1 Upgrade the Ninemile – Southport 230kV Lines 1 and 2

Transmission Line Increase the capacity of the Southport - Ninemile line to 747MVA. This will be accomplished by removing the existing 1780 ACSR conductor and replacing it with a 1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 °F.

Remove approximately 10,100’ (21,008 lbs.) of existing 1780 ACSR conductor on line 1 of the Southport - Ninemile line.

Remove approximately 9,150’ (19,032 lbs.) of existing 1780 ACSR conductor on line 2 of the Southport to Ninemile line.

Install approximately 11,040’ (15,787 lbs.) of 1272 ACSS conductor on line 1 of the Southport - Ninemile line.

Install approximately 10,005’ (14,307 lbs.) of 1272 ACSS conductor on line 2 of the Southport - Ninemile line.

Remove and replace approximately 72 dead end insulators and 12 tangent (braced post) insulators.

It is assumed that the shield wire is adequate and does not require replacement.

It is assumed that the river crossing is currently strung with an adequate conductor.

It is assumed that all structures are adequate and do not require replacement.

Spans requiring remediation:

Structure 10 - Southport Sub (Ninemile Line 1 bay).

Structure 10 - Southport Sub (Ninemile Line 2 bay).

Ninemile Sub (Southport line 1 bay) - Structure 7.

Ninemile Sub (Southport line 2 bay) - Structure 7.

Page 6: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

6

Long Lead Time Equipment

Quantity Material Description *Lead Time (weeks)

30,094 lbs. 1272 ACSS conductor 12-14

72 each Dead-end insulators 10-12

12 each Tangent insulators 10-12

*As of 5/13/2011

Relaying No Relay upgrades are required. RTU configuration and settings

Southport 230kV Substation:

Update four (4) breaker control settings. Update two (2) line panel settings. Update RTU configuration.

Joilet 230kV Substation:

Update one (1) line panel setting. Update RTU configuration.

Labarre 230kV Substation:

Update one (1) line panel setting. Update RTU configuration.

Ninemile 230kV Substation:

Update four (4) breaker control settings.

Update two (2) line panel settings. Update two (2) bus differential settings. Update RTU configuration.

Substation Scope

Site: No site work is required. Foundation: No foundation work is required. Electrical:

South Port 230kV Substation:

Increase capacity of all components in the ring and Ninemile lines to at least 747MVA or 1875A.

Page 7: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

7

Replace 1780MCM ACSR line bay bus and line bay risers with two (2) 1780 MCM ACSR conductors in Ninemile 1 line bay.

Replace 1780MCM ACSR breaker S2708 and S4169 jumpers with two (2) 1780 MCM ACSR conductors.

Replace 1780MCM ACSR line bay bus and line bay risers with two (2) 1780 MCM ACSR conductors in Ninemile 2 line bay.

Ninemile 230kV Substation: Increase capacity of all line bay components to at least 747MVA or 1875A

Replace 1780MCM ACSR line bay bus and line bay risers with two (2) 1780 MCM ACSR conductors in Southport 1 line bay.

Replace 2336MCM ACAR breaker S2037 and S2034 jumpers with two (2) 1780 MCM ACSR conductors.

Replace 1780MCM ACSR line bay bus and line bay risers with two (2) 1780 MCM ACSR conductors in Southport 2 line bay.

Construction and Outage Plan

If this project is approved and enters the Energy Delivery’s (PM&C) process for executing projects, there will be constructability reviews performed during the definition phase. These reviews will try to incorporate any known hazards from a safety perspective, as well as any obstacles that could/would be experienced during the construction and installation process. After receipt of the final design drawings and details for each discipline of work, a determination will be made to either use the preferred supplier resources, perform a competitive bid process to award the work to an Entergy-approved contractor, or to allow internal Entergy Resources to perform the work. This project does not consist of any site, foundation, grounding, or conduit work. All work associated with this job will need to be done under an outage. Normally, outages on 230kV facilities require a half year’s advanced notice, with no guarantees that said outage will be granted at the time requested. This poses risk to all schedules. The sequence of work will consist of multiple crews. There will be transmission line crews performing work on the Southport end of the line and transmission line crews working on the Ninemile end of the line. At the same time, there will be a substation crew changing out jumpers on the breakers and traps in order to complete the upgrade work on each line before energizing them.

Page 8: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

8

Ninemile - Southport 2: For the installation of the new 1272 ACSS conductor on the transmission line Ninemile - Southport 2, an outage consisting of several weeks duration will be required. For the work on the Ninemile - Southport 2 line, outages will be needed on the south bus at Ninemile, the line going to the SVC at Ninemile, and the section of the ring bus between breakers S3191 and S2708, which de-energizes the Ninemile - Southport line 1. This outage is needed when working in the Southport substation and working around the back span dead end on the west bank side of the river. The plan is to mobilize a transmission line crew to start the reconductoring work on the Ninemile end first. The crew will start restringing the conductor across the south bus. The crew will then move to reconductoring the section over the SVC. Then, the crew will continue reconductoring the transmission line up to the span before the back span dead end on the west bank side of the river. At this time, a second transmission line crew will be mobilized to the Southport end to reconductor the span of line in the substation, and the crew on the Ninemile side will complete the reconductoring to the back span dead end and tie the new 1272 ACSS into the river crossing conductor. During this time of the reconductoring, the Ninemile - Southport 1 line will need to be de-energized. While the crew is reconductoring in the Southport substation, they will need to be aware that the line dead ends on the same structure as the transformer. The transformer will be energized; therefore, designated spotters will need to be used during the entire time the work is being performed. Replace Jumper on Trap and Breaker (S2708) Ninemile - Southport 2 (Southport Side): During the outage on the Ninemile - Southport 2 line, the jumpers on the trap will be replaced with bundled 1780 ACSR conductor. It is estimated that the substation crew will mobilize and start the work on the jumpers about one (1) week into the outage. When the crew makes up the jumpers on the trap, they shall leave the jumpers long on the line side so the second transmission line crew can make up the jumper to the new 1272 ACSS dead end shoes once the reconductoring is complete. Once the jumpers on the trap are replaced, the substation crew will start replacing the jumper on breaker S2708 with bundled 1780 ACSR. This work will be completed prior to starting the transmission line reconductoring portion inside of Southport substation. Replace Jumper on Trap Ninemile - Southport 2 (Ninemile Side): This work will also be done during the outage for the reconductoring of the transmission line. Once the substation crew has completed the work on the Southport end of the line, they will mobilize to the Ninemile end to replace the jumpers on the trap. The transmission line crew should be clear of the Ninemile substation and the substation crew should have adequate space to replace the jumpers on the trap. Since the transmission line work will be

Page 9: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

9

completed in this area, the substation crew will be responsible for making up the jumpers all the way to the new 1272 ACSS dead end shoe. The jumper will be replaced with bundled 1780 ACSR. A transition plate may be needed on the dead end shoe in order to attach the 1780 ACSR jumper terminals. Upon completion of reconductoring the Ninemile - Southport 2 line, replacing jumpers to the traps and replacing jumpers to the breaker, all phasing, checkouts and commissioning can be made. Once this work is completed, the transmission line crews and the substation crews will continue their work on the Ninemile - Southport 1 line. Ninemile - South Port 1: For the installation of the new 1272 ACSS conductor on the transmission line Ninemile - Southport 1, an outage consisting of several weeks duration will be required. For the work on the Ninemile - Southport 1 line, outages will be needed on the north bus at Ninemile, and the section of the ring bus between breakers S1488 and S2708, which de-energizes the Ninemile - Southport line 2. This outage is needed when working in the Southport substation and working around the back span dead end on the west bank side of the river. Once the work is completed on the Ninemile - Southport 2 line, the two (2) transmission line crews will resume work on the Ninemile - Southport 1 line. The crew on the Ninemile side will start by completing the reconductoring near the back span dead end, and the crew working in the Southport substation will resume work on the 1 line. Once this work is completed, the Ninemile - Southport 2 line can be energized. Then, the crew on the Ninemile end will continue reconductoring the next section of line. The transmission line crew that was working in the Southport substation will mobilize to the Ninemile side and will reconductor the section over the north bus. Once this work is completed, the two (2) crews will continue working until the lines is completely reconductored to 1272 ACSS conductor. Replace Jumper on Trap Ninemile - Southport 1 (Ninemile Side): During the outage on the Ninemile - Southport 1 line, the jumpers on the trap will be replaced with bundled 1780 ACSR conductor. When the crew makes up the jumpers on the trap, they shall leave the jumpers long on the line side so the second transmission line crew can make up the jumper to the new 1272 ACSS dead end shoes once the reconductoring is complete. This work will be completed prior to starting the transmission line reconductoring portion over the north bus at Ninemile substation. Replace Jumper on Trap Ninemile - Southport 1 (Southport Side): Once the jumpers on the trap are completed at Ninemile, the substation crew will mobilize back to Southport substation to replace the jumpers on the trap. The transmission line crew should be clear of the Southport substation and

Page 10: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

10

the substation crew should have adequate space to replace the jumpers on the trap. Since the transmission line work will be completed in this area, the substation crew will be responsible for making up the jumpers all the way to the new 1272 ACSS dead end shoe. The jumper will be replaced with bundled 1780 ACSR. A transition plate may be needed on the dead end shoe in order to attach the 1780 ACSR jumper terminals. Upon completion of reconductoring the Ninemile - Southport 1 line and replacing jumpers to the traps, all phasing, checkouts and commissioning can be made once this work is completed. Replace Jumpers on Ninemile Breakers S2034 and S2037: These breakers have single conductor jumpers on one side of the breaker. These jumpers need to be changed to bundled 1780 ACSR. These breakers are setup in a breaker and a half scheme; therefore, outages should be able to be obtained easily to perform this work. This work will also be scheduled as fill in work for the substation crew while performing the rest of the work on the job. Replace Jumpers on Southport Breakers S4169: This breaker has single conductor jumpers on each side of the breaker. These jumpers need to be changed to bundled 1780 ACSR. This breaker is setup in a ring bus scheme; therefore, outages should be able to be obtained easily to perform this work. This work will be scheduled after all the reconductoring work is completed.

3.2 Upgrade the Gretna-Harvey 115kV Line

Transmission Line No Line Upgrades required. Gretna 115kV Substation:

Site: No site work required. Foundations: No foundation work required. Electrical:

Increase capacity of the Ninemile Line Bay to 161MVA or 808A.

Replace 600A switch S9187L with 2000 amp switch.

Page 11: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

11

Relaying

No Relay work required. Relay settings No Relay Settings required. Construction and outage plan:

Replace Switch S9187L, Grounds Switch S2558GR, and Jumpers to Breaker S9187 The switch S9187L has a ground switch. Both of these switches must be replaced. The jumpers going to breaker S9187 are rigid and will need to be replaced once the new switch is installed. The tower is an AM 115kV tower. Therefore, the switch will need to be manufactured in such a way to be able to mount onto the tower. Also, the ground switch will need to swing towards the switch in order to maintain electrical clearances.

3.3 Construction Schedule and Required Outages:

Week 1: No outages required. Transmission line crew mobilization to Ninemile. Week 2: Outage on Ninemile south bus. Outage on Ninemile - Southport 2. One shot on Ninemile - Southport 1. At the end of week 1, the south bus can be energized. Week 3: Outage on SVC Line. Continue outage on Ninemile - Southport 2. Continue one shot on Ninemile - Southport 1. Substation crew to replace jumpers on trap at Line 2 (Southport Side). At the end of week 2, the SVC line can be energized. Week 4: Continue outage on Ninemile - Southport 2. Continue one shot on Ninemile - Southport 1. Replace jumpers on breaker S2708 (Southport Side). Mobilize substation crew to Ninemile substation. Week 5: Continue outage on Ninemile - Southport 2. Continue one shot on Ninemile - Southport 1.

Page 12: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

12

Replace jumpers on trap at Ninemile on Line 2. Mobilize second transmission line crew to Southport substation. Week 6: Continue outage on Ninemile - Southport 2. Outage on Ninemile - Southport 1. Substation crew to replace jumpers on breakers S2034 and S2037 at Ninemile. Week 7: Continue outage on Ninemile - Southport 2. Continue outage on Ninemile - Southport 1. Replace jumpers on trap at Ninemile on Line 1. At the end of week 7 the Ninemile - Southport 2 line can be energized. Subsequently mobilize substation crew to Southport substation to replace the jumpers on line trap on the Ninemile - Southport 1 Line. Mobilize transmission line crew from Southport to Ninemile. Week 8: Continue outage on Ninemile - Southport 1. Outage on north bus at Ninemile. One shot on Ninemile - Southport 2. Replace jumpers on trap at Southport on the Ninemile - Southport 1 Line. Week 9: Continue outage on Ninemile - Southport 1. One shot on Ninemile - Southport 2. At the end of week 9, the Ninemile - Southport 1 line can be energized. Substation crew off this week. Week 10: Outage on breaker S4169 at Southport substation. Replace jumpers.

Required Outages for Gretna work: Week 1: No outages needed. Mobilize substation crew. Receive materials and pre-build switches. Week 2: Outage on Ninemile - Harvey tap - Gretna line bay. Replace switch, ground switch, and jumpers to breaker S9187.

Page 13: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

13

3.3.1 Assumptions

Notes to Duration Schedules:

All construction work requiring outages will be performed during off-peak load season. Line outages will be discussed with the SOC and TOC and the assumption is made that line outages will be executed as planned. However, last minute denial of outages by the SOC/TOC along with resulting schedule delay is possible.

Transmission line project will begin subsequent to the design.

Scheduled durations are high level estimates at this time. Upon project approval, a detailed schedule will be produced.

Due to the layout of the lines and the bus configuration, both the 1 and 2 lines will need to be de-energized at the same time during part of the construction.

Due to underground facilities (duct banks, pipe lines, etc.) near the back span dead end on the west bank side of the river, the use of matting materials will be required to cross them.

Reuse existing structures.

The capacity of the river crossing conductor is adequate for the new line rating.

The shield wire will not be replaced with this project.

3.3.2 Safety Awareness Special Safety Considerations during Construction:

1. Entergy is firmly committed to prevention of injuries and accidents.

Safety will always be of first consideration in all construction activities. Compliance with all safety and environmental rules promulgated by local, state and federal agencies and regulatory bodies must be adhered to without exception. Zero tolerance is expected.

2. Each employee is responsible and accountable for his/her safety

compliance, both in facilities and work procedures. 3. Supervisors are responsible for job assignment, planning, and

supervising to assure that safety rules and procedures are followed. 4. Clearances should be taken on all applicable equipment by the

designated supervisor of the construction project.

Page 14: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

14

5. All conductors and equipment shall be grounded according to

Equipotential Zone Grounding Procedures, Entergy Safe Work Procedures, OSHA or contractors’ standards. The best applicable standard shall supersede given the specific task at hand.

6. Rubber goods utilized for working on or near energized conductors

shall be tested and in acceptable working condition. 7. Insulated cover-up goods and guard structures shall be utilized when

working over, under and near energized conductors. 8. Housekeeping will be performed on an ongoing basis, all materials

and equipment will be stored in such a manner that the safety and protection of the equipment and any being in its presence is optimized. Debris and refuge shall be promptly disposed of in a proper manner/order.

9. Cranes, aerial baskets and hoisting equipment shall be positioned in

such a manner as to not come in contact with any adjacent conductors or utilities according to all applicable safe work procedures.

10. Proper matting will be utilized to stabilize equipment, and also to

protect sub-surface utilities and pipelines. Matting will also be utilized to protect all terrains as designated by Entergy’s Right-Of Way Specialist, Entergy’s Policies and Property Owners request.

11. Work performed within the confines of any Entergy Switchyard shall be

planned, reviewed and approved by Entergy’s on-site designee prior to the start of any project.

12. All Personal Protective Equipment shall be utilized at all times. 13. Fall Protection: 100% Fall Protection is required at all times. 14. All applicable Entergy Construction and Design Standards and

Specifications shall be adhered to; all manufacturers’ installation procedures shall be followed as stated by the manufacturer. Any deviation is not acceptable.

15. Traffic signals shall be utilized and put into place before commencing

any construction activities (i.e., law enforcement officers, cones, barricades, men working signs, flagmen, etc.) It is the responsibility of the contractor to adhere to all state, local and regulatory agencies requirements.

Page 15: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

15

16. Guard Structures of sufficient size and capacity shall be utilized when installing, removing or lifting any conductor or equipment over other utilities, highways, railroads or driveways, etc.

17. All vehicles and heavy equipment shall be operated below minimum

designated speeds limits while on all roads, right-of-ways and properties associated with this construction project. If no speed limit is designated than, it is expected that no vehicle or heavy equipment will be operated beyond five (5) miles per hour.

18. Access and egress to all property and facilities shall be properly

maintained and secured at all times, before, during, and after all construction activities.

19. Material substitution and alteration is not acceptable without the

approval of Entergy’s designee. 20. Interpretation of any part herewith in this document can be directed to

Entergy’s Construction Management Department. 21. All personnel must complete Entergy’s Substation Awareness training

prior to entering Entergy’s property or facilities. 22. All personnel must complete Power Safe training prior to entering

Entergy’s property or facilities.

23. Daily requirements include the preparation and execution of tailboards and Job Safety Analysis (JSA).

24. A full time Safety Coordinator may be requested or required by

Entergy. It will be the contractor’s responsibility to supply this qualified personnel.

25. Contractor is required to proactively notify the responsible Operations

Center of his presence. The correct TOC or DOC can be obtained from Entergy’s Construction Management Department.

26. Contractor is required to proactively notify the responsible agency for

all one calls (“Dig Alerts”) for the region in which any work will be performed. Contractor shall also request a face to face appointment with participants of the one call operation in order to ensure that due diligence has been executed.

27. Contractors must obey all railroad crossing laws, remember and

communicate this aspect as part of the tailboard and JSA process. All personnel should be reminded periodically through the course of the day. Stop / Look / Listen / Live!!!

Page 16: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

16

Entergy requires safety to be the highest priority for all projects. No work shall be carried out without performing a JSA, and have the appropriate JSA form filled out. All safety hazards shall be identified in the JSA. The employee in charge must ensure that the crew performing the work is familiar with the status of the equipment and surrounding area. When working within operating substations, the employee in charge shall identify parts that are energized, establish location and placement of protective grounds, and define the limits of the working space(s) and what switches or breakers disconnect the equipment from the source of supply. Before switching is performed in a substation where work is in progress, the employee performing the switching shall notify all personnel working within the substation. All personnel shall check the status of the structures, lines, and equipment before resuming work. If an employee arrives after switching is completed, the employee in charge shall “walk through” the work plan to update the late arrival on the job at hand. For work on the existing transmission lines, the contractor employee in charge shall ensure that the crew is familiar with working near energized overhead conductors, performing proper grounding procedures, safety on road crossings, and working in adverse terrain, inside substation, and inside of a plant environment.

4. COST

The ICT has reviewed and determined whether each required upgrade will be considered a Base Plan Upgrade or a Supplemental Upgrade. For more information on cost responsibility for Base Plan and Supplemental Upgrades, see Attachment T to Entergy’s OATT. The costs shown in the table include all applicable overheads but do not include tax gross up. Entergy incurs a tax liability proportional to the amount of customer contributions.

Projected Costs including indirect cost through 2014 dollars

Description 2011 2012 2013 2014 Total

Gretna-Harvey 115kV Line $ 6,758 $ 14,118 $ 47,390 $ 100,207 $ 168,473

Nine Mile - South Port 230kV Lines 1 & 2

$ 18,310 $ 121,901 $ 240,396 $ 1,713,837 $ 2,094,443

Total: $ 25,068 $ 136,019 $ 287,786 $ 1,814,044 $ 2,262,916

Page 17: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

17

5. UPGRADE CLASSIFICATION

The ICT has reviewed and determined whether each required upgrade will be considered a Supplemental Upgrade. For more information on cost responsibility for Base Plan and Supplemental Upgrades, see Attachment T to Entergy’s OATT.

Task Total Cost Base Plan Supplemental FFR

Payment Reference

Ninemile – Southport 230kV Lines 1& 2 $ 2,094,443

-- $ 2,094,443

-- 3.1

Gretna – Harvey 115kV Line $ 168,473

-- $ 168,473

-- 3.2

Total: $ 2,262,916 -- $ 2,262,916 --

6. SCHEDULE

A detailed schedule will be prepared subsequent to customer approval to proceed with the project. Based on the Task duration schedules listed below, the overall project in-service date is projected to be January 1, 2015. Based on an assumed customer approval date of November 1, 2011, the following are approximate schedule dates:

All construction work requiring outages will be performed during acceptable periods of system condition to ensure reliable operation of the system, which most often is the off-peak load season. Line outages will be discussed with the SOC and TOC and the assumption is made that line outages will be executed as planned. However, an evolving system condition may result in cancellation of approved outages by the SOC/TOC and may also result in additional schedule delay.

Substation construction will be coordinated with the transmission line outages when possible.

Construction resources are available when required.

Transmission line and substation projects will begin subsequent to definition phase of the PEP.

This schedule does not account for non-typical adverse weather conditions.

Schedule durations are high level estimates at this time. A detailed schedule will be prepared upon project approval.

Scheduling assumptions and completion dates:

Receive customer approval by November 1, 2011.

Completion of PEP/Estimates by end of March 2012.

Page 18: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

18

Approval from customer to proceed with the project followed by creation of FP and WOs in place by the end of May 2012.

Commence engineering, and permitting work in June 2012.

Order long delivery material by July 2012 for delivery by January 2, 2013.

Issue design packages to construction by October 2012.

Secure environmental permits by October 2012.

Construct substations and line work starting in January 2013, and complete it by the December 31, 2013.

It is assumed the outages of the bus nodes at 230kV Ninemile and South Port substations are available as per Construction Plans.

7. RISK ASSESSMENT

Risk Comment Impact

Material costs steel & Equipment Rising steel, copper, fuel and other

market conditions could greatly affect estimated cost.

****

Storm-water plan implementation

Best guess on SWPPP creation, implementation and monitoring can

vary greatly dependant on outcome of environmental study.

**

Weather & Equipment Lead Times (Poles)

Unexpected delays on material lead times, unusually inclement weather

will impact schedule but might impact AFUDC costs as well.

**

Wetland mitigation Undetermined until environmental

analysis is complete. ***

Outages may not be available

Preliminary schedule only considers general outage constraints. Specific project schedule may be delayed by

days, weeks or months dependant on system conditions. Delays of months

= increased project costs.

****

Scope based on design assumptions which may change

Varied impact on cost and schedule. ***

*-low impact to cost, ** - moderate impact to cost, ***- high impact to cost, **** - very high impact to cost.

Page 19: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

19

The following transactions were included in this Facilities Study:

8. CONFIRMED RESERVATIONS

Confirmed Reservations OASIS PSE MW Begin End

250778 (undesignation) Entergy Services, Inc. (EMO) 1 7/2/1998 7/1/2011

569011 Entergy Services, Inc. (EMO) 242 3/1/2000 1/1/2014

759196 Entergy Services, Inc. (EMO) 143 1/1/2001 1/1/2021

759294 East Texas Electric Cooperative 31 1/1/2001 1/1/2018

1096986 Tennessee Valley Authority 73 9/1/2003 9/1/2013

1099991 (renewal) City Water & Light, Jonesboro 83 1/1/2010 1/1/2016

1099997 (renewal) City Water & Light, Jonesboro 168 1/1/2010 1/1/2016

1105665 Entergy Services, Inc. (EMO) 236 2/1/2003 2/1/2016

1105666 Entergy Services, Inc. (EMO) 91 2/1/2003 2/1/2027

1105668 Entergy Services, Inc. (EMO) 77 2/1/2003 2/1/2027

1126821 Entergy Services, Inc. (EMO) 101 5/1/2004 5/1/2029

1151106 Entergy Services, Inc. (EMO) 20 6/1/2010 6/1/2029

1168061 Entergy Services, Inc. (EMO) 80 8/1/2004 2/1/2028

1168408 Entergy Services, Inc. (EMO) 247 8/1/2004 2/1/2028

1289686 (undesignation) Entergy Services, Inc. (EMO) 1 6/1/2007 6/1/2030

1294132 Entergy Services, Inc. (EMO) 526 1/1/2006 1/1/2035

1309874 (renewal) East Texas Electric Cooperative 75 1/1/2009 1/1/2017

1309875 (renewal) East Texas Electric Cooperative 50 1/1/2009 1/1/2017

1309876 (renewal) East Texas Electric Cooperative 50 1/1/2009 1/1/2017

1356328 Muni Energy Agcy of Miss 40 6/1/2010 6/1/2040

1373643 City of Conway 25 3/1/2010 3/1/2040

1375299 Louisiana Generating LLC 11 3/1/2006 3/1/2013

1375559 CLECO Power LLC (Gen) 675 12/1/2006 12/1/2016

1380484 Osceola Light & Power 9 9/1/2009 9/1/2039

1381398 Constellation Energy Commodities Grp. 34 1/1/2006 1/1/2036

1381400 Constellation Energy Commodities Grp. 34 1/1/2006 1/1/2036

1381404 Constellation Energy Commodities Grp. 17 1/1/2006 1/1/2036

1381406 Constellation Energy Commodities Grp. 17 1/1/2006 1/1/2036

1383852 Arkansas Electric Cooperative Corp. 550 1/1/2007 1/1/2017

1385158 NRG Power Marketing 13 10/1/20070 10/1/2027

1387272 CLECO Power LLC (Gen) 11 4/1/2006 4/1/2016

1410022 Constellation Energy Commodities 60 3/1/2010 3/1/2040

1422708 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2007 1/1/2027

1425495 East Texas Electric Cooperative 50 3/1/2010 3/1/2045

1437089 Arkansas Electric Cooperative Corp. 349 1/1/2007 1/1/2012

1440189 Arkansas Electric Cooperative Corp. 84 1/1/2008 1/1/2012

1440190 Arkansas Electric Cooperative Corp. 104 1/1/2008 1/1/2012

1442453 NRG Power Marketing 320 6/1/2007 6/1/2026

1449495 Entergy Services, Inc. (EMO) 322 6/1/2009 6/1/2059

1456636 CLECO Power Marketing 10 10/1/2007 10/1/2012

1460876 Aquila Networks-MPS 75 3/1/2009 3/1/2029

1460878 Aquila Networks-MPS 75 3/1/2009 3/1/2029

1460879 Aquila Networks-MPS 75 3/1/2009 3/1/2029

1460881 Aquila Networks-MPS 75 3/1/2009 3/1/2029

1460898 Louisiana Energy & Power Authority 3 1/1/2009 1/1/2030

1460899 Louisiana Energy & Power Authority 5 1/1/2009 1/1/2030

1461442 Louisiana Energy & Power Authority 12 1/1/2009 1/1/2030

1464028 East Texas Electric Cooperative 168 1/1/2010 1/1/2040

1468113 Muni Energy Agcy of Miss 20 6/1/2011 6/1/2041

Page 20: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

20

OASIS PSE MW Begin End

1470484 City of West Memphis 20 1/1/2011 1/1/2041

1470811 East Texas Electric Cooperative 186 1/1/2010 1/1/2040

1472304 (renewal) South Miss Electric Power Assoc. 75 6/1/2009 6/1/2011

1472315 South Miss Electric Power Assoc. 100 6/1/2010 6/1/2011

1477069 Entergy Services, Inc. (EMO) 10 11/1/2007 11/1/2037

1480164 Entergy Services, Inc. (EMO) 725 1/1/2005 9/1/2033

1495910 Southwestern Electric 78 5/1/2010 5/1/2013

1498122 Constellation Energy Commodities Grp. 30 4/1/2012 4/1/2042

1498129 City of Conway 50 4/1/2012 4/1/2042

1499610 Entergy Services, Inc. (EMO) 300 1/1/2008 1/1/2038

1500582 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2008 1/1/2038

1500584 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2008 1/1/2038

1502952 Arkansas Electric Cooperative Corp. 330 1/1/2008 1/1/2030

1514102 East Texas Electric Cooperative 29 1/1/2008 1/1/2017

1514104 East Texas Electric Cooperative 35 1/1/2008 1/1/2017

1514105 (undesignation) East Texas Electric Cooperative 1 1/1/2008 1/1/2017

1517005 (renewal) NRG Power Marketing 103 1/1/2011 1/1/2026

1525820 (renewal) NRG Power Marketing 3 7/1/2009 7/1/2014

1527816 Westar Energy 6 10/1/2007 10/1/2012

1530287 Empire District Electric 50 3/1/2010 3/1/2030

1530288 Empire District Electric 50 3/1/2010 3/1/2030

1546108 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2011 1/1/2051

1552148 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2009 1/1/2014

1555717 (undesignation) East Texas Electric Cooperative 1 1/1/2010 1/1/2015

1555718 Entergy Services, Inc. (EMO) 158 1/1/2010 1/1/2015

1557220 (undesignation) Entergy Services, Inc. (EMO) 1 7/1/2009 7/1/2018

1557221 Entergy Services, Inc. (EMO) 520 7/1/2009 7/1/2018

1557602 (undesignation) East Texas Electric Cooperative 1 1/1/2009 1/1/2017

1564001 (renewal) Louisiana Energy & Power Authority 6 4/1/2009 4/1/2014

1564356 (renewal) NRG Power Marketing 5 9/1/2009 9/1/2025

1566302 NRG Power Marketing 300 1/1/2008 1/1/2013

1585225 (renewal) City of Prescott 22 4/1/2009 4/1/2039

1585239 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2009 1/1/2013

1585240 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2009 1/1/2013

1598022 (renewal) NRG Power Marketing 103 7/1/2010 7/1/2015

1598291 Entergy Services, Inc. (EMO) 206 6/1/2012 6/1/2042

1598885 (renewal) Morgan Stanley Commodities Group 102 1/1/2009 1/1/2014

1598886 (renewal) Morgan Stanley Commodities Group 102 1/1/2009 1/1/2014

1601111 Constellation 5 1/1/2010 1/1/2015

1602650 NRG Power Marketing 5 7/1/2010 7/1/2020

1615102 (renewal) MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014

1615103 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014

1615105 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014

1615108 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014

1629240 MidAmerican Energy, Inc. 7 3/1/2009 3/1/2014

1630065 NRG Power Marketing 40 1/1/2010 1/1/2015

1632265 Merrill Lynch Commodities 1 4/1/2009 4/1/2014

1632268 Merrill Lynch Commodities 25 4/1/2009 4/1/2014

1633701 NRG Power Marketing 20 1/1/2010 1/1/2019

1633702 NRG Power Marketing 20 1/1/2010 1/1/2016

1633703 NRG Power Marketing 20 1/1/2010 1/1/2016

1639337 Entergy Services, Inc. (EMO) 587 3/1/2009 1/1/2019

1639338 Entergy Services, Inc. (EMO) 103 3/1/2009 1/1/2019

1639339 Entergy Services, Inc. (EMO) 32 3/1/2009 1/1/2019

1639340 Entergy Services, Inc. (EMO) 122 3/1/2009 1/1/2019

Page 21: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

21

OASIS PSE MW Begin End

1639341 Entergy Services, Inc. (EMO) 134 3/1/2009 1/1/2019

1640629 CLECO Power Marketing 58 5/1/2001 1/1/2021

1640630 CLECO Power Marketing 32 5/1/2001 1/1/2021

1643983 (renewal) NRG Power Marketing 300 1/1/2010 1/1/2015

1643984 (renewal) NRG Power Marketing 100 9/1/2010 9/1/2015

1644155 CLECO Power Marketing 9 4/1/2009 5/1/2016

1644215 NRG Power Marketing 83 1/1/2010 1/1/2025

1644908 CLECO Power Marketing 41 5/1/2009 5/1/2018

1648049 (undesignation) Entergy Services, Inc. (EMO) 1 6/1/2010 6/1/2013

1648050 Entergy Services, Inc. (EMO) 100 6/1/2010 6/1/2013

1648591 (undesignation) Entergy Services (SPO) 1 6/1/2010 6/1/2012

1648592 Entergy Services (SPO) 485 6/1/2010 6/1/2012

1655366 Missouri Joint Municipal 6 10/1/2009 10/1/2014

1658087 (undesignation) Entergy Services (SPO) 1 6/1/2012 6/1/2042

1658088 SMEPA 21 6/1/2012 6/1/2042

1659388 NRG Power Marketing 25 1/1/2011 1/1/2016

1665168 (renewal) Merrill Lynch Commodities 60 11/1/2009 11/1/2014

1665288 Merrill Lynch Commodities 15 1/1/2011 1/1/2017

1665492 (renewal) Merrill Lynch Commodities 16 11/1/2009 11/1/2014

1665493 (renewal) Merrill Lynch Commodities 4 11/1/2009 11/1/2014

1665899 Ameren Energy, Inc. 75 9/1/2009 9/1/2014

1668165 Entergy Services (SPO) 600 1/1/2013 1/1/2043

1669126 (renewal) Cargill Power Markets, LLC 103 1/1/2011 1/1/2016

1669127 (renewal) Cargill Power Markets, LLC 103 1/1/2011 1/1/2016

1676674 NRG Power Marketing 100 1/1/2011 1/1/2020

1676675 NRG Power Marketing 100 1/1/2011 1/1/2020

1677749 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2013 1/1/2015

1679179 (renewal) NRG Power Marketing 100 1/1/2011 1/1/2016

1679181 (renewal) NRG Power Marketing 100 1/1/2011 1/1/2016

1682716 (renewal) NRG Power Marketing 206 1/1/2011 1/1/2012

1685869 (renewal) Muni Energy Agcy of Miss 19 1/1/2010 1/1/2018

1689499 Missouri Joint Municipal 3 9/1/2009 9/1/2014

1690613 NRG Power Marketing 25 1/1/2011 1/1/2016

1694305 Entergy Services (SPO) 15 5/1/2010 5/1/2020

1694306 Entergy Services (SPO) 30 5/1/2010 5/1/2020

73454527 Hope Water & Light 10 10/1/2009 10/1/2032

73457918 South Miss Electric Power Assoc. 180 10/1/2009 10/1/2014

73573797 (renewal) American Electric Power 45 1/1/2011 1/1/2029

73586299 (renewal) American Electric Power 6 1/1/2011 1/1/2029

73595626 NRG Power Marketing 13 1/1/2012 1/1/2017

73659139 NRG Power Marketing 50 5/1/2010 5/1/2011

73723105 Arkansas Electric Cooperative Corp. 270 1/1/2010 1/1/2015

73724303 Arkansas Electric Cooperative Corp. 104 1/1/2010 1/1/2015

73741113 (renewal) Entergy Services, Inc. (EMO) 150 5/1/2010 5/1/2020

73741122 (renewal) Entergy Services, Inc. (EMO) 135 5/1/2010 5/1/2020

73774729 Arkansas Electric Cooperative Corp. 84 1/1/2010 1/1/2015

73820650 MOWR 5 3/1/2010 3/1/2040

73942862 (renewal) Muni Energy Agcy of Miss 13 6/1/2010 6/1/2015

73970673 Cargill Power Markets, LLC 40 1/1/2012 1/1/2016

73987480 South Miss Electric Power Assoc. 100 5/1/2010 5/1/2040

73987507 South Miss Electric Power Assoc. 180 6/1/2010 6/1/2015

73990804 South Miss Electric Power Assoc. 100 5/1/2010 5/1/2040

74001787 NRG Power Marketing 100 1/1/2011 1/1/2016

74001895 NRG Power Marketing 100 1/1/2011 1/1/2016

74001897 NRG Power Marketing 22 1/1/2011 1/1/2016

Page 22: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

22

OASIS PSE MW Begin End

74001904 NRG Power Marketing 28 1/1/2011 1/1/2016

74001930 NRG Power Marketing 42 8/1/2006 8/1/2036

74001931 NRG Power Marketing 60 3/1/2010 3/1/2040

74001934 NRG Power Marketing 60 4/1/2012 4/1/2042

74233619 WRGS 15 4/1/2012 4/1/2017

74233670 (undesignation) Entergy Services, Inc. (EMO) 1 8/1/2012 1/1/2038

74236787 NRG Power Marketing 75 6/1/2012 6/1/2017

74236794 NRG Power Marketing 100 6/1/2012 6/1/2017

74236798 NRG Power Marketing 100 6/1/2012 6/1/2017

74305315 NRG Power Marketing 10 1/1/2014 1/1/2017

74305339 NRG Power Marketing 10 1/1/2013 1/1/2023

74356639 NRG Power Marketing 103 1/1/2011 1/1/2016

74356652 NRG Power Marketing 206 6/1/2012 6/1/2017

74356666 NRG Power Marketing 50 1/1/2013 1/1/2014

74370625 NRG Power Marketing 10 7/1/2010 7/1/2012

74514903 Entergy Services, Inc. (EMO) 20 6/1/2013 6/1/2029

74514911 Entergy Services, Inc. (EMO) 101 6/1/2013 6/1/2029

74691007 NRG Power Marketing 60 1/1/2013 1/1/2018

74758974 Entergy Services, Inc. (EMO) 804 5/1/2013 5/1/2058

74777205 (renewal) NRG Power Marketing 300 1/1/2013 1/1/2033

74777208 (renewal) NRG Power Marketing 300 1/1/2015 1/1/2035

74829975 (renewal) CLECO Power LLC (Gen) 35 1/1/2011 1/1/2016

74835023 AECI / APM 103 1/1/2012 1/1/2017

74881866 (renewal) NRG Power Marketing 8 3/1/2011 3/1/2021

74899954 (undesignation) Entergy Services, Inc. (EMO) 1 2/1/2012 2/1/2014

74899956 Entergy Services, Inc. (EMO) 100 2/1/2012 2/1/2014

74899968 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2013 1/1/2015

74899969 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2012 1/1/2015

Page 23: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

23

9. PRE-888 TRANSACTIONS

OASIS PSE MW Begin End

1332606 East Texas Electric Cooperative 55 1/1/2006 1/1/2017

1412155 Entergy Services, Inc. (EMO) 1718 1/1/2007 1/1/2038

1412156 Entergy Services, Inc. (EMO) 741 1/1/2007 1/1/2038

1412158 Entergy Services, Inc. (EMO) 1867 1/1/2007 1/1/2038

1412160 Entergy Services, Inc. (EMO) 1142 1/1/2007 1/1/2038

1412161 Entergy Services, Inc. (EMO) 59 1/1/2007 1/1/2038

1412162 Entergy Services, Inc. (EMO) 148 1/1/2007 1/1/2038

1412163 Entergy Services, Inc. (EMO) 194 1/1/2007 1/1/2038

1412164 Entergy Services, Inc. (EMO) 1157 1/1/2007 1/1/2038

1412165 Entergy Services, Inc. (EMO) 1219 1/1/2007 1/1/2038

1412166 Entergy Services, Inc. (EMO) 683 1/1/2007 1/1/2038

1412167 Entergy Services, Inc. (EMO) 140 1/1/2007 1/1/2038

1412168 Entergy Services, Inc. (EMO) 456 1/1/2007 1/1/2038

1412169 Entergy Services, Inc. (EMO) 739 1/1/2007 1/1/2038

1412170 Entergy Services, Inc. (EMO) 183 1/1/2007 1/1/2038

1412171 Entergy Services, Inc. (EMO) 64 1/1/2007 1/1/2038

1412172 Entergy Services, Inc. (EMO) 870 1/1/2007 1/1/2038

1412173 Entergy Services, Inc. (EMO) 129 1/1/2007 1/1/2038

1412174 Entergy Services, Inc. (EMO) 140 1/1/2007 1/1/2038

1412175 Entergy Services, Inc. (EMO) 130 1/1/2007 1/1/2038

1412176 Entergy Services, Inc. (EMO) 65 1/1/2007 1/1/2038

1412177 Entergy Services, Inc. (EMO) 947 1/1/2007 1/1/2038

1412178 Entergy Services, Inc. (EMO) 61 1/1/2007 1/1/2038

1412179 Entergy Services, Inc. (EMO) 304 1/1/2007 1/1/2038

1412180 Entergy Services, Inc. (EMO) 351 1/1/2007 1/1/2038

1412181 Entergy Services, Inc. (EMO) 692 1/1/2007 1/1/2038

1412182 Entergy Services, Inc. (EMO) 1641 1/1/2007 1/1/2038

1412183 Entergy Services, Inc. (EMO) 433 1/1/2007 1/1/2038

1412184 Entergy Services, Inc. (EMO) 1926 1/1/2007 1/1/2038

1412185 Entergy Services, Inc. (EMO) 946 1/1/2007 1/1/2038

1412186 Entergy Services, Inc. (EMO) 1233 1/1/2007 1/1/2038

1498278 Entergy Services, Inc. (EMO) 75 8/1/2007 1/1/2017

1498281 Entergy Services, Inc. (EMO) 86 8/1/2007 1/1/2017

1498283 Entergy Services, Inc. (EMO) 68 8/1/2007 1/1/2017

1498284 Entergy Services, Inc. (EMO) 78 8/1/2007 1/1/2017

1498285 Entergy Services, Inc. (EMO) 11 8/1/2007 1/1/2044

1498286 Entergy Services, Inc. (EMO) 69 8/1/2007 1/1/2044

1498287 Entergy Services, Inc. (EMO) 14 8/1/2007 1/1/2044

Page 24: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

24

10. STUDY QUEUE

OASIS PSE MW Begin End

74597193 NRG Power Marketing 300 1/1/2013 1/1/2018

74597198 NRG Power Marketing 300 1/1/2013 1/1/2018

74728369 Brazos Electric Cooperative 100 1/1/2012 1/1/2017

74728395 Brazos Electric Cooperative 100 1/1/2012 1/1/2017

74728400 Brazos Electric Cooperative 100 1/1/2012 1/1/2017

74728415 Brazos Electric Cooperative 100 1/1/2012 1/1/2017

74728420 Brazos Electric Cooperative 100 1/1/2012 1/1/2017

74789476 undesignation Entergy Services (SPO) 1 1/1/2012 1/1/2016

74799834 Cargill Power Markets 101 7/1/2012 7/1/2017

74799836 Cargill Power Markets 101 7/1/2012 7/1/2017

74799837 Cargill Power Markets 101 7/1/2012 7/1/2017

74799848 Cargill Power Markets 101 7/1/2013 7/1/2018

74799851 Cargill Power Markets 101 7/1/2013 7/1/2018

74799853 Cargill Power Markets 101 7/1/2013 7/1/2018

74846159 AEPM 65 1/1/2015 1/1/2020

74899933 Entergy Services (SPO) 322 2/1/2011 2/1/2041

Page 25: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

25

11. ATTACHMENTS

11.1 Table of Acronyms

ACSR Aluminum Conductor Steel Reinforced

ACSS Aluminum Conductor Steel Supported

AFUDC Allowance for Funds Used During Construction

ATC Available Transfer Capability

CCN Certificate of Convenience and Necessity

EES Entergy Control Area

EHV Extra-High Voltage

ICT Independent Coordinator of Transmission

JSA Job Safety Analysis

kV Kilo-Volt

MCM (M) Thousand Circular Mils

MVA Mega-Volt Amp

MW Mega-Watt

NPDES National Pollution Discharge Elimination System

OASIS Online Access and Same-time Information System

OATT Open Access Transmission Tariff

OG&E Oklahoma Gas & Electric

PEP Project Execution Plan

POR Point of Receipt

SES Steam Electric Station

SOC System Operations Center

SHV Super High Voltage

SW Switch Station

TOCSWEPCO Transmission Operations Center Southwest Electric Power Company

TOC Transmission Operations Center

USACE United States of America Corp of Engineers

Page 26: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

26

11.2 Drawings

Location Description Drawing Number

Ninemile 230kV Substation L0080S02

Ninemile 230kV Substation L0080S03

Southport 230kV Substation L0055S01

Gretna 115kV Substation L0659S01

Page 27: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

27

Page 28: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

28

Page 29: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

29

Page 30: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

30

Page 31: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

31

11.3 Duration Schedule

Page 32: TRANSMISSION LINE & SUBSTATION PROJECTS ...1272 ACSS conductor. The 1272 ACSS conductor is rated 1957A, 780MVA at 230kV, 347 F. Remove approximately 10,100’ (21,008 lbs.) of existing

OASIS 74899972_74_76_80 Entergy Services, Inc. Facilities Study

32