transmission lines june 24-27, 2014 nashville, tn 2014 transmission & distribution benchmarking...

58
Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Upload: madeline-byrd

Post on 16-Jan-2016

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Transmission Lines

June 24-27, 2014

Nashville, TN

2014 Transmission & Distribution BenchmarkingData Review Conference

Page 2: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Agenda

◼ Introduction◼ Statistics and System Activity◼ Financial◼ Initiatives and Practices◼ Next Steps

Picture source: www.energy.gov

2

Page 3: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Key benchmarking Issues in Transmission

◼ Transmission Systems are unique and designed to serve a particular geography, customer base, and other generation source and load constraints.

◼ Costs are particularly uneven over time, so really need to be evaluated on a longer time horizon.

◼ FERC capital additions do not reflect actual spending because of CWIP; Activity –based costs provide a more realistic spending level as well as the purpose of expenditures.

◼ There is no agreement on cost normalization; asset base is the best predictor, but circuit miles, structure miles, MWh transmitted, MW-miles can be used to “triangulate” your performance.

◼ Reliability is based primarily on “availability”, but also on contribution to ”End use” Customer reliability.

Regulatory◼ NERC regulations; other Regulatory bodies◼ NERC compliance audits◼ NERC performance standards (TADS)

System Challenges◼ Distributed Generation◼ Interconnections (e.g. Windmill Farms)◼ Aging infrastructure◼ New transmission corridors◼ ROW management under increasing

regulations and restrictions◼ Capacity Constraints◼ Transfer Capability Crisis (mitigated by the

recession)◼ Intelligent Grid (or more intelligent Grid)◼ Upgrading EMS systems◼ Equipment lead times

Organizational Challenges◼ Aging Workforce -- Brain Drain◼ Contractor Management◼ Cross-silo prioritization and involvement in

projects

Industry Methodology

2014:• Cyber security• FERC politicization

3

Page 4: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Statisticsand

System Activity

Landsnet – National Grid, Iceland

4

Page 5: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Transmission versus Distribution

◼ For purposes of this survey, we define distribution to be a voltage level of 45kV and below. The distinction is somewhat arbitrary, but picks a point between 69kv which is generally considered a transmission (or at least sub-transmission) level and 21kV which would generally be considered distribution.

◼ It is unrealistic to ask utilities to redefine their cost or reliability reporting on the basis of these definitions. However, a utility that has very different definitions may want to restate these statistics to better compare their performance.

Distribution Voltage Classes◼ 5kV class (>1kV, <=9kV)◼ 15kV class (>9kV, <=15kV) ◼ 25kV class (>15kV to <=26kV) ◼ 35kV class (>26kV to <=36kV) ◼ 44kV class (>36kV to <=44kV)

Transmission classes >=45kV ◼ <69kV class (>=45kV <69kV)◼ 69kV class (>=69kV <100kV) ◼ 100kV class (>=100kV <200kV) ◼ 200kV Class (>=200kV <300kV) ◼ 300kV Class (>=300 kV <400 kV) ◼ 400kV and above

5

Page 6: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Transmission Lines Demographic Profile

Min Mean Max # of BarsService Territory  Wage Rate: Transmission Journey Level Line Worker $36.89 $39.78 $42.15 6

  Transmission Staffing: FTEs per $100M Transmission Assets0.00 9.83 23.72 9

ROW Miles Managed per Structure Mile 0% 75% 144% 8  Line work done while the line is energized: Transmission 0.0% 18.7% 50.0% 10System - Demographics  Transmission Structure mile per Transmission Circuit 0.00 15.54 38.02 10

Transmission Voltages on system by circuit    <69kV 0.0% 4.5% 39.6% 12

69kV 0.0% 20.4% 79.4% 12    100kV class 8.2% 53.6% 93.8% 12

200kV Class 0.0% 12.0% 49.7% 12    300kV Class 0.0% 6.7% 25.2% 12

400kV and above 0.0% 2.8% 9.8% 12Transmission structures on system

    Wood poles 0.00% 53.21% 96.63% 10Steel poles 0.30% 14.10% 33.47% 10

    Concrete poles 0.00% 1.67% 14.82% 10Steel lattice towers 0.07% 31.02% 71.29% 10

Financial - Demographics

Transmission Line Assets per Circuit Mile $49,469 $188,022 $282,384 9

Add % contracting; % new lines

ADD Financial Demographics: depreciation, CWIPThese were removed at the leaders conference

Contracting of what? We have numbers for every category.

6

Page 7: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

TYPES OF TRANSMISSION STRUCTURES ON SYSTEM

Calculation used

ST150.1 / ( ST150.1 + ST150.2 + ST150.3 + ST150.4 ) *

100 , ST150.2 / ( ST150.1 + ST150.2 + ST150.3 + ST150.4 )

* 100 , ST150.3 / ( ST150.1 + ST150.2 + ST150.3 +

ST150.4 ) * 100 , ST150.4 / ( ST150.1 + ST150.2 + ST150.3

+ ST150.4 ) * 100

ST p28

7

Page 8: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

TRANSMISSION VOLTAGES ON SYSTEM BY OH CIRCUIT

Calculation used

ST120.3C / ( ST120.1C + ST120.2C + ST120.3C + ST120.4C +

ST120.5C + ST120.6C ) * 100 , ST120.4C / ( ST120.1C +

ST120.2C

+ ST120.3C + ST120.4C + ST120.5C + ST120.6C ) * 100 ,

ST120.5C / ( ST120.1C + ST120.2C + ST120.3C + ST120.4C +

ST120.5C + ST120.6C ) * 100 , ST120.1C / ( ST120.1C +

ST120.2C

+ ST120.3C + ST120.4C + ST120.5C + ST120.6C ) * 100 ,

ST120.2C / ( ST120.1C + ST120.2C + ST120.3C + ST120.4C +

ST120.5C + ST120.6C ) * 100 , ST120.6C / ( ST120.1C +

ST120.2C

+ ST120.3C + ST120.4C + ST120.5C + ST120.6C ) * 100

ST p29

8

Page 9: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

TRANSMISSION CIRCUIT MILE PER TRANSMISSION CIRCUIT

Calculation used

(ST120|5_Trans OH & UG Circ Mile v.13) / ( ST120.1C + ST120.2C

+ ST120.3C + ST120.4C + ST120.5C + ST120.6C )

ST p30

9

Page 10: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

OH TRANSMISSION STRUCTURE MILE PER OH TRANSMISSION CIRCUIT

#35 and #40 show too little structure miles

Calculation used

( ST120.1A + ST120.2A + ST120.3A + ST120.4A + ST120.5A

+ ST120.6A ) / ( ST120.1C + ST120.2C + ST120.3C +

ST120.4C + ST120.5C + ST120.6C )

ST p31

10

Page 11: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

TRANSMISSION CIRCUIT MILES PER TRANSMISSION STRUCTURE MILES

Change to Ratio not %#35 should be close to 1.0;

Calculation used

(ST120|5_Trans OH & UG Circ Mile v.13) / (ST120|5_OH &

UG Structure miles) * 100

ST p32

11

Page 12: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

ANALYSIS: T&D PLANT IN SERVICE PER DISTRIBUTION END-USE CUSTOMER [FERC]

Calculation used

( DF70.1 ) / (ST5_T&D Dist End Use Customers) , ( DF70.2 +

TF65.2 ) / (ST5_T&D Dist End Use Customers) , TF65.1 /

(ST5_T&D Dist End Use Customers)

Mean $5,071

Quartile 1 $4,460

Quartile 2: $4,901

Quartile 3: $5,020

ST p33

12

Page 13: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

ANALYSIS: TRANSMISSION LINES PLANT IN SERVICE PER TRANSMISSION CIRCUIT MILE

Calculation used

TF65.1 / (ST120_Trans Circ Mile 09)

Mean $188,795

Quartile 1 $129,110

Quartile 2: $213,938

Quartile 3: $244,047

ST p39

13

Page 14: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

NEW TRANSMISSION CIRCUIT MILES

Calculation used

SA40.1 / (ST120_Trans Circ Mile 09) * 100

SA p26

14

Page 15: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

TRANSMISSION WOOD STRUCTURE TEST/INSPECTION/TREATMENT/REPLACEMENT

#27 has very high % of wood structures replaced

Calculation used

SA65.1 / ST150.1 * 100 , SA65.2 / ST150.1 * 100 , SA65.3

/ ST150.1 * 100

SA p29

15

Page 16: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Issues found: Transmission Line System Statistics and Activity

Page # Q # Primary Issue Who

ST 31 ST120 Too little structure miles 35; 40

ST 32 ST120 #35 too high a ratio of circuit miles/structure miles

35

ST32 ST120 Should be shown as ratio and not % 1QC

SA29 SA65 Very high wood pole replacement rate 27

NA Demographic profiles could use additional metrics: % contracted; % new lines

1QC

16

Page 17: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Financial – Overview of the Cost Model

Working with an adjusted FERC model

Conceptual transmission tower design by Choi Shine Architects17

Page 18: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

2013YE 2012YE

Mean Q1 Q2 Q3# of Bars

Mean Q1 Q2 Q3# of Bars

O&M Costs

Trans Lines O&M Expense per Circuit Mile

$5,996 $3,350 $6,085 $6,907 9 $8,992 $3,067 $6,868 $11,593 16

Trans Line O&M per MWh transmitted

$0.90 $0.43 $0.64 $1.29 7 $0.63 $0.33 $0.51 $0.67 15

Trans Line O&M per Total Trans Assets

3.51% 2.17% 3.23% 4.38% 8 2.98% 1.98% 2.43% 4.02% 15

Investment Rate                    

Trans Line Capital Spending less New Lines per Asset [Activity Based]

13.66% 16.16% 7.81% 2.86% 9 7.11% 8.05% 4.27% 3.24% 14

Trans Line Cost Profile

Investigate why investment rate is high compared to last year

18

Page 19: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Substations

General Plant FERC Costs

Transmission

Capital

Trans Lines

Exclusions

Trans Substations

O&M

Trans Lines

Exclusions

Trans Substations

Distribution

Capital

Dist Lines

Exclusions

Dist Substations

O&M

Dist Lines

Exclusions

Dist Substations

A&G

FERC: The ADJUSTED FERC COST MODEL

FERC provides a general framework Certain costs must be excluded to provide fair comparisons that focus on operations Substation costs must be separated out, including certain allocations

19

Page 20: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

FERC: Specific Adjustments

◼ The following page is a schematic of how basic FERC cost data will be adjusted for this benchmarking study. A&G costs will be excluded – Utilities are asked to adjust their costs to exclude costs typically

reported as A&G (e.g. pensions and benefits) from their O&M data. General plant costs will be excluded – Utilities are asked to adjust their costs to exclude costs

typically reported as General Plant (e.g. IT/Communications infrastructure) from their T&D Capital data.

Other T&D Capital exclusions:• Transmission: Land acquisitions and extraordinary items• Distribution: Land acquisitions, street lighting and extraordinary items

Other O&M exclusions:• Transmission: Wheeling, Rents/Leases, IT costs, extraordinary items. If you charge IT

support to account 569, you should exclude it. Regional Market Expenses (Accts 575, 576).• Distribution: Streetlight Maintenance, Rents/Leases, IT costs, extraordinary items. If you

charge IT support to Distribution O&M accounts, you should exclude it.• If you normally charge R&D, such as EPRI dues, to O&M, include it, unless it is an unusually

large amount for this year Substation costs will be allocated from Transmission and Distribution accounts, and similar

adjustments made. ◼ The goal of the exclusions is to provide a fairer comparison of T&D operational performance, by

excluding certain costs that relate to demographic differences not under the control of T&D management.

20

Page 21: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

TRANSMISSION LINE O&M & CAPITAL PER ASSET [FERC]Mean 11.06 %

Quartile 1 7.19 %

Quartile 2: 9.79 %

Quartile 3: 10.91 %

Calculation used

(TF20_Trans Lines O&M FERC) / TF65.1 * 100 , (TF5_Trans

Lines Capital FERC) / TF65.1 * 100

TF p2

21

Page 22: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

TRANSMISSION LINE O&M & CAPITAL PER CIRCUIT MILE [FERC] [V.13]

#40 does not show up on assets graph;

Calculation used

(TF20_Trans Lines O&M FERC) / (ST120|5_Trans OH & UG Circ

Mile v.13) , (TF5_Trans Lines Capital FERC) / (ST120|5_Trans OH

& UG Circ Mile v.13)

Mean $19,164

Quartile 1 $11,802

Quartile 2: $12,885

Quartile 3: $19,862

TF p3

22

Page 23: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

DV| % OF FERC - TRANSMISSION LINE CAPITAL

#31 does not add to 100%

Calculation used

( TF5.6 ) / TF5.1 * 100 , TF5.2 / TF5.1 * 100 , TF5.3 / TF5.1 *

100 , TF5.4 / TF5.1 * 100 , TF5.5 / TF5.1 * 100

Mean 96 %

Quartile 1 100 %

Quartile 2: 100 %

Quartile 3: 100 %

TF p32

Very few adjustments to Capital Additions (FERC) beyond Substation allocations . . .

23

Page 24: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

DV| % OF FERC - TRANSMISSION LINES O&M EXPENSE

#31 does not at to 100%; all wheeling costs?

Comments

Calculation used

TF20.8 / TF20.1 * 100 , TF20.2 / TF20.1 * 100 , TF20.3 / TF20.1 *

100 , TF20.4 / TF20.1 * 100 , TF20.5 / TF20.1 * 100 , TF20.6 /

TF20.1

* 100 , TF20.7 / TF20.1 * 100

Mean Quartile

Mean 100 %

Quartile 1 100 %

Quartile 2: 100 %

Quartile 3: 100 %

TF p33

Very few adjustments beyond wheeling.

24

Page 25: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

FINANCIAL COSTS ADJUSTMENTS - TRANSMISSION O&M

#31 does not at to 100%; all wheeling costs?

Comments

Calculation used

TF20.8 / TF20.1 * 100 , TF20.2 / TF20.1 * 100 , ( TF20.3 + TF20.4

+ TF20.5 + TF20.6 + TF20.7 ) / TF20.1 * 100

TF p34

25

Page 26: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Financial – Overview of the activity-based

Cost Model

Photo source: Scientific American26

Page 27: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Develop Network Strategy

Develop and Approve Asset Plans

Project/Portfolio Management

A Process Model for Managing the Network

Expand Network

Operate Network

Sustain Network

Add New Customers

Respond to Emergencies

27

Page 28: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

ACTIVITY-BASED Cost Model

While FERC has the benefit of being a uniform system of accounts, there are several important shortcomings:

•FERC capital spending lags behind actual spending; costs for large projects go into a Construction Work in Progress (CWIP) account and are not transferred until the assets are placed into service, sometimes a several year lag. •FERC capital accounts generally follow plant accounts and units of property (e.g. poles, towers, and fixtures) – not the typical reasons why utilities spend (e.g. new business)•FERC O&M accounts tend to be more activity-oriented, but do not necessarily track important categories (e.g. vegetation management)

For those reasons, a simplified Activity-Based Costing system was developed to get current year spending by activity. The following diagram depicts the Activity-Based approach

28

Page 29: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Activity-Based Cost Model

Activity-Based Costs

Transmission Lines

Transmission Subs Distribution Subs Distribution Lines

Transmission Line Capital• Serve New• Expand• Sustain• Other • CIAC

T&D Substation Capital• Serve New• Expand• Sustain• Other• CIAC

Distribution Line O&M• Sustain• Other

T&D Substation O&M• Sustain the Network• Operate the Network• Other

Transmission Line O&M• Sustain the Network• Operate the Network

Distribution Line Capital• Serve New• Expand• Sustain• Other • CIAC

The activity-based cost model breaks the expenditures into capital and O&M, and then splits them into the activities shown on the process model introduced above. The following 3 pages provide more details of the individual activities for Transmission, Substations, and Distribution.

2014 Data Collection Guide

29

Page 30: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Activity Based Costs – Transmission Lines

While capital expenditures are split among several different processes from the overall process model, O&M expenses are almost entirely associated with sustaining the network.

Transmission Line Capital• Serve New: Extension to new customers

or utility substations [Industrial/Generation/Wholesale]

• Expand: Capacity Additions (Adding additional lines to existing substations, increasing capacity of existing lines)

• Sustain: Replace/Repair in kind• Sustain: system improvements

(reliability/efficiency)• Sustain: Service Restoration• Sustain: Line Relocations• Sustain: Transmission Operations Center• Sustain: Asset Retirement Costs for

Transmission Plant (FERC 359.1) • Other • CIAC

Transmission Line O&M• Inspection and Maintenance

Expense (except 569.1-4)• ROW/Vegetation Management • Service Restoration• Transmission Operations Center• Engineering/Design O&M

(including FERC 561.5-8)• Other

2014 Data Collection Guide

30

Page 31: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Transmission Line Capital spending (Activity-based) on sustain is decreasing

 Spending Category

2013 Q2

2012Q2

2011Q2

Total Capital Spending 6.6% 5.3%

Less Serve New 1.0% 0.6%

Subtotal Cap Add & Sustain

5.6% 4.7%

Less Capacity Adds 3.4% 1.9%

Subtotal: Sustain 2.2% 2.8%

The “replacement” rate can be estimated by successively subtracting activities, such as serve new, capacity adds, line relocations, and storm restoration.

Update for 2014

31

Page 32: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

32

TRANSMISSION LINE CAPITAL SPENDING PER ASSET [ACTIVITY-BASED] [V.14]

Calculation used

TF45.1 / TF65.1 * 100 , TF45.2 / TF65.1 * 100 , TF45.3 / TF65.1 *

100 , TF45.1 / TF65.1 * 100 , TF45.4 / TF65.1 * 100 , TF45.5 /

TF65.1

* 100 , TF45.6 / TF65.1 * 100 , TF45.1 / TF65.1 , TF45.7 / TF65.1

* 100

Mean Quartile

Mean 15.08 %

Quartile 1 18.53 %

Quartile 2: 10.16 %

Quartile 3: 6.40 %

TF p11

Page 33: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

TRANSMISSION LINE CAPITAL SPENDING SUSTAIN- EX SERVE NEW, EXPAND PER ASSET [ACTIVITY-BASED] [V.14]

• #31 has very high TOC capital activity cost

• See change in title to refer to “Sustain”

Comments

Calculation used

TF45.1 / TF45.1 / 1000000 , TF45.2 / TF45.2 / 1000000 , TF45.3

/ TF65.1 * 100 , TF45.1 / TF65.1 * 100 , TF45.4 / TF65.1 * 100 ,

TF45.5 / TF65.1 * 100 , TF45.6 / TF65.1 * 100 , TF45.1 / TF65.1

, TF45.7 / TF65.1 * 100

Mean Quartile

Mean 4.40 %

Quartile 1 5.31 %

Quartile 2: 2.91 %

Quartile 3: 1.61 %

TF p13

33

Page 34: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

OTHER ACTIVITY BASED COSTS: TRANSMISSION LINE CAPITAL SPENDING

Calculation used

TF46.1

Responses

Total Participants 19

Number of Respondants 8

ID Response31 Capital Tools, R&D, Premise Equipment, Facilities28 N/A23 NA38 Environmental/Legislative/Regulatory30 Under line relocations, reimbursements exceeded costs in 201333 Tools and Equipment27 n/a32 Not applicable

34

Page 35: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

TRANSMISSION LINE O&M EXPENSE PER ASSETS [ACTIVITY-BASED] [V.14]

Comments

Calculation used

TF55.1 / TF65.1 * 100 , TF55.1 / TF65.1 * 100 , TF55.2 / TF65.1 *

100 , TF55.4 / TF65.1 * 100 , TF55.5 / TF65.1 * 100 , TF55.1 /

TF65.1

* 100 , TF55.6 / TF65.1 * 100

Mean Quartile

Mean 2.91 %

Quartile 1 1.77 %

Quartile 2: 2.29 %

Quartile 3: 4.06 %

• #23, 32, 35 don’t show TOC

• Why isn’t #40 on this chart?? But on the next?

TF p17

35

Page 36: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

TRANSMISSION LINE O&M EXPENSE EX OPS CTR PER ASSETS [ACTIVITY-BASED] [V.14]

#27; 35 no inspection costs#35 no ROW#40 Why zero? on this chart but not the previous?

Comments

Calculation used

TF55.1 / TF65.1 * 100 , TF55.1 / TF65.1 * 100 , TF55.2 / TF65.1

* 100 , TF55.4 / TF65.1 * 100 , TF55.5 / TF55.5 / 1000000 ,

TF55.1 / TF65.1 * 100 , TF55.6 / TF65.1 * 100

Mean Quartile

Mean 1.95 %

Quartile 1 1.37 %

Quartile 2: 1.69 %

Quartile 3: 2.72 %

TF p18

36

Page 37: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

OTHER ACTIVITY BASED COSTS: TRANSMISSION LINE O&MComments

Calculation used

TF56.1

Responses

Total Participants 19

Number of Respondants 10

ID Response31 Management/Admin, R&D28 Planning and Operating Costs that are not directly charged to the work programs above23 NA38 na40 Misc transmission expense net of O&M Substation included in Pension & Benefits30 N/A33 miscellaneous transmission expenses FF127 n/a35 Internal building rents32 Studies, compliance

TF p23

37

Page 38: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

CWIP AS A % OF CAPITAL EXPENDITURES - TRANSMISSION LINE

#32 very low CWIP#28 very high CWIPShow as a ratio

Comments

Calculation used

TF80.1 / TF5.6 * 100

Mean Quartile

Mean 273.3 %

Quartile 1 57.3 %

Quartile 2: 88.2 %

Quartile 3: 350.2 %

TF p24

38

Page 39: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

ANALYSIS: SUBSTATION ALLOCATIONS - TRANSMISSION CAPITAL SPENDING

Mean Quartile

Mean 47 %

Comments

This graph shows the percent of total FERC Capital Additions

that have been allocated to Substations.

Calculation used

TF5.2 / TF5.1 * 100

TF 2539

Page 40: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

ANALYSIS: SUBSTATION ALLOCATIONS - TRANSMISSION O&M SPENDING

Mean Quartile

Mean 9 %

Comments

This graph shows the percent of total FERC O&M Expenses

that have been allocated to Substations.

Calculation used

TF20.2 / TF20.1 * 100

TF p26

40

Page 41: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Vegetation Management

Expense/Miles Managed (TF p27)

Expense/Mile Trimmed (TF p30)

Expense/Acre Managed (TF p28)

Q2

201

2 (N

=5)

Expense/Acre Trimmed (TF 29)

10x 5x

41

Page 42: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

FERC VS ACTIVITY SPENDING: TRANSMISSION LINE CAPITAL PER ASSET [V.14]

#31 did not provide FERC capital#28 Activity capital is much higher than FERC

Comments

Calculation used

TF5.6 / TF65.1 * 100 , (TF45_Trans Line Cap ABC v.14) / TF65.1

* 100

TF p36

42

Page 43: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

FERC VS ACTIVITY SPENDING: TRANSMISSION LINE O&M PER ASSET [V.14]

#31 did not report FERC#33,35 FERC O&M is greater than Activity; should be the same.

Comments

Calculation used

TF20.8 / TF65.1 * 100 , (TF55_ABC Trans Line O&M v.14) / TF65.1

* 100

TF p37

43

Page 44: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Issues found: transmission financial

Page # Q # Primary Issue Who

TF 3 #40 is not on chart 1QC

TF 13 #31 high TOC capital; See change in title to refer to “Sustain”

31

TF 17 Why is #40 not on this chart; #23, 32, 35 don’t show TOC

1QC

TF 18 #27; 35 no inspection costs; #35 no ROW;#40 Why zero?;

23,27,32, 35,40

TF24 #32 very low CWIP; #28 very high CWIPShow as a ratio

8,32

TF 25,26 Show as stacked bar 1QC

TF 32,33,34 #31 does not add to 100% 31

TF 36 #31 did not provide FERC capital#28 Activity capital is much higher than FERC

28,31

TF 36 Typo “Capital” 1QC

TF37 #31 did not report FERC#33,35 FERC O&M is greater than Activity; should be the same.

31, 33,35

44

Page 45: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Transmission LinePractices and initiatives

Page 46: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Develop Network Strategy

Develop and Approve Asset Plans

Project/Portfolio Management

A Process Model for Managing the Network

Expand Network

Operate Network

Sustain Network

Add New Customers

Respond to Emergencies

46

Page 47: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Transmission Line Practices/initiatives

2013 Sections◼ Asset Management -- Role of Asset Management,

replacement programs, and problematic equipment◼ Planning/Engineering/Design –Improvement

initiatives and changes to standards ◼ T-line Field Activities – Initiatives underway and

maintenance approaches◼ Work management systems – WMS Vendor and

efforts to improve usefulness◼ Contractor Productivity – Challenges, measures

and initiatives◼ Transmission Operations Center (TOC) – Changes

and challenges.◼ Right of Way –Growth inhibitors, ROW uses,

challenges and practices.◼ Transmission Automation – Technology initiatives

underway◼ NERC Standards – Impact of NERC standards on

transmission organizations, especially Critical Infrastructure Protection (CIP), Protection and Control (PRC), and Facilities Design (FAC).

◼ Maintenance – Inspections, impact of deferred maintenance, initiatives to reduce outages

2014 Sections (by process)◼ Strategy (including Transmission

Automation, and NERC standards) ◼ Asset Management ◼ Transmission Operations Center (TOC)◼ Maintenance (including ROW)◼ Planning/Engineering/Design ◼ T-line Field Construction Activities

(including WMS and Contractor Productivity

47

Page 48: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Transmission Practice Questions

Strategy - Transmission Automation• Top 5 technologies being deployed for Transmission Automation• Other transmission automation technologies

Asset Management• Predicting condition of various critical components • Role of the Asset Management organization in your decision -making• Key responsibilities of the Transmission Asset Management organization• What keeps you up at night worrying about your system• Infrastructure replacement programs underway• Classes of equipment that are becoming problematic: Transmission• Initiatives undertaken to improve getting a job from planning to delivery• Practices around permits and certifications that make planning effective• Transmission line standard changed recently and why• Measure used to track the success of engineering/design function

Transmission Operations Center• Transmission energy control centers• Changes in energy control centers in the last few years• Major challenges facing the energy control center• Initiatives that have been successful in improving the energy control function• Response to External Forces• Changes being made to energy management system (benefits or

challenges)

2014 Sections (by process)◼ Strategy (including

Transmission Automation, and NERC standards)

◼ Asset Management ◼ Transmission Operations

Center (TOC)◼ Maintenance (including

ROW)◼ Planning/Engineering/Design ◼ T-line Field Construction

Activities (including WMS and Contractor Productivity

48

Page 49: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Transmission Practice Questions (cont)

NERC Compliance• Impact of CIP5 and the change from requirements

to results-based regulation• Handling and structuring audits• Separate NERC audits for Critical Infrastructure

and Reliability Standards• People fully-dedicated to the NERC compliance

organization• Process changes implemented for Critical

Infrastructure Protection [CIP]• Organization and staffing levels for Critical

Infrastructure Protection [CIP]• Process changes implemented for Protection and

Control [PRC]• Organization and staffing levels for Protection and

Control [PRC]• Process changes for Facilities Design,

Connections, and Maintenance [FAC]• Positions added for compliance with [FAC]• Future changes coming that will impact on

transmission organization

2014 Sections (by process)◼ Strategy (including Transmission

Automation, and NERC standards) ◼ Asset Management ◼ Transmission Operations Center (TOC)◼ Maintenance (including ROW)◼ Planning/Engineering/Design ◼ T-line Field Construction Activities

(including WMS and Contractor Productivity

49

Page 50: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Transmission Practice Questions (cont)

Maintenance- ROW• Technologies/tools/practices that have improved ROW

management: Chemical growth inhibitors; Herbicides; Other• Use of ROW land• Major challenges - near and long term - being faced by ROW

management• Initiatives successful in improving ROW management operations• Initiatives successful in improving ROW contract management

Field Construction• Number of reporting locations transmission line field personnel

work out of• Most important initiative underway to improve

◼ Transmission line construction◼ Transmission line maintenance practices◼ Transmission line reliability

• Important initiative underway to improve Transmission line reliability: Poles/Towers; Cable; Insulators; Other

• WMS vendor and year of implementation or last major upgrade• Challenges seen in managing a contract workforce: Transmission• Productivity measures in place for contract crews• Practices that have been successful for improving contractor

management

Transmission Maintenance• Regulatory drivers for Transmission Line inspection and

maintenance• Regular inspections performed• Inspections added in the last year

2014 Sections (by process)◼ Strategy (including Transmission

Automation, and NERC standards) ◼ Asset Management ◼ Transmission Operations Center (TOC)◼ Maintenance (including ROW)◼ Planning/Engineering/Design ◼ T-line Field Construction Activities

(including WMS and Contractor Productivity

50

Page 51: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Practice topics

The amount of raw information we gather on initiatives and practices Is voluminous. For the most part it is mostly of interest to subject matter experts – and only if it is an area of immediate concern. Additionally, the answers are presented as text results.

In the past, we have summarized text responses on a few key questions at Data Review. We then more fully developed the summaries for our Insights Conference, and then asked leaders to identify specific areas of concern for presentation at the on-sites presentations.

Last year we did an extensive review and identified key topics. We then developed “themes” or “key success factors (KSF’s)” based upon the questionnaire responses. The following pages show the result of that review and describes the four major topical areas and the “KSF’s” within each topic.

For 2014, we reorganized our questionnaire around these topical areas. Our proposal this year is to validate the responses against our KSF’s, and to develop each topic area as a stand-alone module that can be presented as requested.

51

Page 52: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Key Success Factors:Transmission Network Planning

Deploy automation strategy; microprocessor relays, cyber security, and digital fault recorders are most frequently addressed

Assure NERC compliance; CIPS, protection and control, and FAC are noted as having most impact

Use a comprehensive scheduling and permitting process, with early engagement of stakeholders

Use a well-designed process for getting jobs from planning to delivery, with accurate estimating and effective project management

Have current, comprehensive standards covering many specifics, including use of high temperature conductors

52

Page 53: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Key Success Factors:Transmission asset management

Develop and use processes to assess condition using both observational and model-based efforts

Identify risk categories including aging assets, reduced budgets, and specific equipment

Strengthen asset management role

Conduct replacement programs. Wood pole inspection and replacement are most common

Identify problematic equipment

53

Page 54: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Key Success Factors:Operate the Transmission system

Involve stakeholders in planning system outages

Continue to upgrade EMS

Conduct Timely and Safe Switching Operations

Monitor and Restore Operations

54

Page 55: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Key Success Factors:Maintain the Transmission Network

Address challenges to ROW maintenance

Conduct regular inspection programs

Improve maintenance practices; scheduling is most mentioned

55

Page 56: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Organization: Strategy on priorities and contracting strategies

Design tools including WMS and compatible units

Construct scheduling and coordination using developers and contractors

Closeout and Follow-up

Key Success Factors:Engineering/Design of sustain/capacity additions

56

Page 57: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Key Success Factors:Build Infrastructure (Field Construction)

Improve contracting; oversight, schedule planning, and routine meetings and feedback are some successful practices for improving contractor management

Improve field productivity; initiatives focus on crew size, training, and system changes

Use a Work Management System to schedule jobs. SAP and Maximo are the most used

57

Page 58: Transmission Lines June 24-27, 2014 Nashville, TN 2014 Transmission & Distribution Benchmarking Data Review Conference

Thank you for your Input and Participation!

Corporate Offices

California

400 Continental Blvd. Suite 600El Segundo, CA 90245(310) 426-2790

Maryland

3 Bethesda Metro Center Suite 700Bethesda, MD 20814(301) 961-1505

New York | Texas | Washington | Wisconsin

First Quartile Consulting is a utility-focused consultancy providing a full range of consulting services including continuous process improvement, change management, benchmarking and more. You can count on a proven process that assesses and optimizes your resources, processes, leadership management and technology to align your business needs with your customer’s needs.

Visit us at www.1stquartileconsulting.com | Follow our updates on LinkedIn

About 1QC

Satellite Offices

Debi McLain Cook [email protected]

Tim. [email protected]

Dave [email protected]

Dave [email protected]

Your Presenters

Ken Buckstaff [email protected]

58