Transmission Projects Update
Board of Public Utilities October 5, 2012
Casa Blanca Power Project
Major System Improvement
Demolition of old 33 kV to 4 kV substation Construction of new 69 kV to 12 kV substation Property acquisition for new substation 4-12 kV conversion of existing 4 kV circuits HMPE cable replacements New 69 kV Lines into substation New 12 kV feeders out of substation
Identified through the Electric System Master Plan
Casa Blanca Power Project Budget
Project Elements and Approved Budget Substation: $ 9,000,000 Property Acquisition: $ 1,540,000 4-12 kV Conversion: $ 800,000 HMPE Cable Replacement: $ 380,000 Dist. Feeders and Transmission: $ 3,330,000
Total: $15,050,000
Final project costs pending and will be under budget
Riverside Transmission Reliability Project (RTRP)
RTRP - a second connection to the state electric transmission grid
RTRP consists of: A) 230 kV Transmission Line
Travels through City of Riverside, City of Norco, Riverside County, and City of Jurupa Valley
B) 230-69 kV Substations Two stations adjacent to each other in the City of
Riverside C) 69 kV Subtransmission Lines
Entirely within the City of Riverside
RTRP Project Costs
Original Estimate: $150 - $185M
Riverside portion - Substation and 69kV Grid: Approximately 75% of the project
SCE portion – Substation and Transmission Lines: Approximately 25% of the project
RTRP Phase 1 Work
Estimated Cost $3.9M SCE Studies Preliminary
Environmental Public Input Transmission Route Options Reimbursement Agreement (RPU – SCE) Interconnection Facilities Agreement (RPU – SCE –
FERC) Final approval required by CAISO and FERC Recommended Phase 2 Work Q1 2007
RTRP Phase 1 Work
Environmental surveys Public outreach efforts Drafting of the Environmental Impact Report (EIR) Comment Responses/Disposition Preparation of Final EIR Meetings support Detailed design Material procurement assistance Construction Management Technical assistance with FAA
RTRP Riverside Public Utilities’ Costs and Budget
PHASE 1 $ 3,900,000
PHASE 2 $ 11,477,600
CONSTRUCTION $121,622,400 TOTAL $137,000,000
Riverside Transmission Reliability Project (RTRP)
Draft Environmental Impact Report (DEIR) out for public comment Aug-2011 to Nov-2011
More than 100 commenters provided comments
City Planning Commission reviewed DEIR in Apr-2012, found it consistent with CEQA, and recommended item to City Council for approval
Also in April-2012, County’s Airport Land Use Commission found project to be consistent with County’s land use plan
Regional Conservation Authority review is underway – favorable Joint Project Ruling sought prior to City Council’s consideration
Final Environmental Impact Report nearly complete – targeting 12/4/2012 City Council meeting
Estimated Total Project Cost estimated at $171 million (Power Engineers Phase 1 Report, Sep-2006)
Riverside Transmission Reliability Project (RTRP)
Subtransmission Project (STP)
Major System Improvement and Reconfiguration of 69KV Transmission Network affecting 8 Substations
→ Vista Substation → Hunter Substation → University Substation → La Colina Substation → Riverside Substation → Springs Substation → Plaza Substation → Freeman Substation
Improvements Required for RTRP and System Reliability
Key Milestones
CEQA IS/MND approved 9/2009 Phases I, II, and III are complete Project Completion contingent upon completion of final phase
Construction of Phases I, II, and III are complete
Property rights for final phase through UCR are being negotiated
Project Budget is $20,500,000 (Board approved Nov-2009)
Subtransmission Project (STP)