transnet pipelines tariffs 2010/2011 - decision & reasons - nersa
TRANSCRIPT
IDMS No. 45374
NATIONAL ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding
TRANSNET LIMITED’S TARIFF APPLICATION FOR:
A 51.3% ALLOWABLE REVENUE INCREASE FOR ITS PETROLEUM PIPELINES SYSTEM FOR 2010/11
THE DECISION
On 25 March 2010 the Energy Regulator amended Transnet Limited’s licence to operate its
petroleum pipeline system by setting tariffs as a condition of that licence. The maximum
tariffs, set out in Table 1, are exclusive of VAT and will apply with effect from 1 April 2010.
(a) The tariffs in Table 1 will be adjusted, if necessary, after applying the claw back
mechanism contemplated in the Tariff Methodology for the Petroleum Pipelines
Industry adopted by the Energy Regulator (“the Methodology”) at the next tariff
review.
(b) The tariffs will enable the applicant to realise an 11.86% increase in Allowable
Revenue compared to the 2009/10 tariff period (an increase from R1,093.93 million
in 2009/10 to R1,223.63 million in 2010/11).
(c) The tariffs in Table 1 represent a 6.09% across-the-board increase over the 2009/10
tariffs without further tariff restructuring. The Energy Regulator will continue its
investigation and consultation process on tariff restructuring during 2010 and the
results of the investigation will be considered in the next tariff period.
IDMS No. 45374
Pg 2 of 31
Table 1: Transnet Petroleum Pipeline Network Tariffs
Destination Source
Maximum tariffs
cents per litre
% increase
over current
tariff
Alrode Sasolburg
2.26075 6.09%
Klerksdorp Sasolburg
3.87785 6.09%
Langlaagte Sasolburg
2.65937 6.09%
Pretoria West Sasolburg
3.45190 6.09%
Rustenburg Sasolburg
5.21225 6.09%
Tarlton Sasolburg
3.05611 6.09%
Waltloo Sasolburg
3.62436 6.09%
Alrode Secunda
3.38688 6.09%
Coalbrook Secunda
4.49887 6.09%
Langlaagte Secunda
3.62436 6.09%
Pretoria West Secunda
4.18224 6.09%
Waltloo Secunda
4.34150 6.09%
Witbank Secunda
2.56702 6.09%
Alrode Durban
11.61188 6.09%
Airport Durban
11.82863 6.09%
Klerksdorp Durban
12.37709 6.09%
Langlaagte Durban
11.86632 6.09%
Rustenburg Durban
13.91221 6.09%
Tarlton Durban
12.32432 6.09%
Waltloo Durban
12.60326 6.09%
Bethlehem Durban
8.71787 6.09% Coalbrook (diesel) Durban
9.02508 6.09%
Kroonstad Durban
10.40753 6.09%
Ladysmith Durban
5.28858 6.09%
Coalbrook Durban
7.87916 6.09%
Airport Sasolburg
2.80355 6.09%
IDMS No. 45374
Pg 3 of 31
(d) The increase in Allowable Revenue is reduced by claw back adjustments to the
value of R64.91 million arising from excess revenue accrued in previous years. (e) The Energy Regulator has used the applicant’s inflation adjusted 2006 modern
equivalent asset value (MEAV) Regulatory Asset Base (RAB) value for this tariff
period on an interim basis. The applicant’s starting regulatory asset base (SRAB)
has recently been verified and determined; and any consequential tariff adjustments
will be made in the next tariff period.
(f) The Energy Regulator has used the applicant’s estimated depreciation for this tariff
period only. The applicant’s depreciation will be determined once the SRAB
verification findings have been assessed. The depreciation amount allowed may
change depending upon the outcome of the SRAB verification.
(g) The Allowable Revenue includes a pre-tax claw back of R27.62 million (reduction of
Allowable Revenue) in respect of the final claw back relating to the 2008/09 tariff
period.
(h) The applicant’s operational expenses for the 2009/10 tariff period will be investigated
during the current tariff period and any adjustments will be made in the next tariff
review.
IDMS No. 45374
Pg 4 of 31
Reasons for Decision
The application 1. On 16 November 2009, Transnet Limited submitted an application for increases in
its allowable revenue for its petroleum pipeline tariffs (“the application”), licensed for
operation by the Energy Regulator on 29 March 2007 under licence number
PPL.p.F3/20/1/2006. This tariff application was made in terms of section 23 of the
Petroleum Pipelines Act, 2003 (Act No. 60 of 2003), (hereinafter referred to as “the
Act”).
The applicant 2. Transnet Limited (hereinafter referred to as “the applicant” or Transnet), is a public
company registered and incorporated as such in terms of the company laws of the
Republic of South Africa pursuant to the Legal Succession to the South African
Transport Services Act, 1989 (Act No 13 of 1989). The applicant’s company
registration number is 1990/000900/06 and its registered head office is at 47th Floor,
Carlton Centre, 150 Commissioner Street, Johannesburg. Transnet operates the
country’s rail network (Transnet Freight), its ports (National Ports Authority),
petroleum and gas pipelines (Transnet Pipelines) and other operations such as the
South African Ports Operations and Transwerk. Transnet Pipelines is a division of
Transnet Limited that operates petroleum pipelines and a gas pipeline.
3. Transnet Limited is a diversified transport and logistics group wholly owned by the
South African Government.
4. Through its Transnet Pipelines division the applicant operates approximately
2,775 km of pipelines conveying refined petroleum products, crude oil and gas as
well as a storage facility for petroleum products at Tarlton near Krugersdorp. It is the
IDMS No. 45374
Pg 5 of 31
dominant pipeline operator in South Africa and has a de facto monopoly of the
pipeline conveyance of petroleum from Durban to inland destinations.
5. This decision concerns only the petroleum pipelines activities of Transnet.
6. On 12 September 2007, Transnet Limited was granted a construction licence
(Licence Number PPL.p.F1/74-75/2007) to construct a 24-inch diameter petroleum
products pipeline from Durban to Jameson Park and pipelines from Jameson Park to
Alrode/Langlaagte and from Kendal to Waltloo, inclusive of accumulation facilities at
Durban and Jameson Park. The applicant has named this project the New Multi-
Products Pipeline (NMPP).
The decision-making process 7. A public version of the tariff application received on 16 November 2009 was
published on the NERSA website on 24 November 2009. This version excluded
certain information that the Energy Regulator had decided was confidential.
8. Notices inviting the public to comment on the tariff application were placed in the
Sowetan, Independent Newspapers (Business Report) and Business Day on
24 November 2009.
9. The following stakeholders commented on Transnet’s tariff application: BP Southern
Africa (Pty) Ltd. (BPSA), Chevron South Africa (Pty) Limited (Chevron), Engen
Petroleum Limited (Engen), Petroline RSA (Proprietary) Limited (Petroline) and
Sasol Oil (Pty) Limited (Sasol).
10. The comments from stakeholders were published on the NERSA website on
20 January 2010.
11. In order to process the application, the Energy Regulator requested additional
information from Transnet. In view of the time involved in obtaining the information
IDMS No. 45374
Pg 6 of 31
from Transnet and completing the analysis, the Energy Regulator was not in a
position to publish a draft tariff determination for this tariff application. The Energy
Regulator will issue minimum information requirements for future tariff applications.
12. On 9 February 2010 the Energy Regulator published a Discussion Document for
public comment about selected matters pertaining to Transnet’s application.
13. The matters raised in the Discussion Document and on which stakeholders’
comments were requested included:
• the starting regulatory asset base (SRAB);
• tariff design; and
• the beta.
14. Comments from the following stakeholders were received: Transnet, Total South
Africa (Pty) Limited (Total), Sasol and Petroline.
15. A public hearing on the tariff application was held on 4 March 2010. The following
entities presented their views at the hearing: Transnet, BPSA, Total, Sasol and
Petroline.
Applicable law 16. The Energy Regulator derives its mandate to set tariffs for petroleum pipelines from
the Act.1
17. The manner in which tariffs must be set is prescribed by regulation (see GN R342
Government Gazette No. 30905 of 4 April 2008).
18. In terms of section 28 of the Act, tariffs set by the Energy Regulator to be charged by
licensees must be based on a “systematic methodology applicable on a consistent
1 See sections 4(f) and 28 of the Act.
IDMS No. 45374
Pg 7 of 31
and comparable basis”2. To this end the Energy Regulator approved a Tariff
Methodology for the Petroleum Pipelines Industry (hereinafter “the Methodology”)
that outlines the approach taken in this decision. On 26 November 2009, the
Methodology was revised (4th Amendment of the Methodology) after following the
appropriate administrative processes. The Methodology is available on the NERSA
website.3
Overview of the application 19. Transnet applied for an increase in its allowable revenue of 51.3% for the period
1 April 2010 to 31 March 2011. In its application, Transnet also performed a
calculation using the NERSA approved Tariff Methodology (available at that time
and which has subsequently been amended) and the calculation resulted in an
Allowable Revenue increase of 17.9%. The main difference between the two
methodologies applied by the applicant is attributable to the determination of the
cost of equity (Ke) and claw backs.
20. Transnet plans to bring into use a part of its NMPP project at a cost of R2,075 million
in June 2010. Therefore a pro rata value of 75% of the cost has been included in the
RAB in the 2010/11 tariff period. These assets were also planned to be taken into
operation in September 2009 and were taken pro rata (50%) into the RAB
calculation for the 2009/10 tariff period. Since the implementation has been
postponed to this tariff period (June 2010), a claw back will be applied on the value
included in the previous period.
21. The applicant applied for Allowable Revenue of R1,655.6 million (51.3% increase).
Transnet states in its application that it arrived at the Allowable Revenue by
deviating from the Tariff Methodology. When following its interpretation of the
Methodology, Transnet arrived at an Allowable Revenue of R1,289.85 million (17.9%
increase).
2 Section 28(2)(a) of the Act 3 www.nersa.org.za
IDMS No. 45374
Pg 8 of 31
22. The application did not include pipeline tariffs; it only requested an Allowable
Revenue.
ASSESSMENT OF THE APPLICATION
Calculation of Allowable Revenue
23. The formula for the calculation of Allowable Revenue (AR) is:
Allowable Revenue = (RAB x WACC) + E + T + D + F ± C Where: RAB = Regulatory Asset Base
WACC = weighted average cost of capital
E = Expenses: maintenance and operating expenses for the tariff period
under review
T = Tax: estimated tax expense for the tariff period under review
D = Depreciation: the charge for the tariff period under review
F = approved revenue addition to meet debt obligations for the tariff period
under review
C = Claw-back adjustment (to correct for differences between actuals and
forecasts in formula elements as well as efficiency gains and volume
differences) from a preceding tariff period in relation to the latest
estimates for that tariff period
24. Data as supplied by Transnet was used for most of the calculations performed in this
determination. Where this was not the case, the reasons for not using the applicant’s
data are supplied throughout the assessment.
IDMS No. 45374
Pg 9 of 31
25. The values of several of the components in the Allowable Revenue formula provided
in the Methodology had to be calculated for the purpose of assessing the applicant’s
tariffs.
26. NERSA’s calculations lead to an increase of 11.86 % in Allowable Revenue from
R1,093.93 million for 2009/10 to R1,223.63 million for the 2010/11 tariff period.
27. This increase would have been higher (20.1% instead of 11.86%) if not reduced by the
claw back provisions arising from excess revenue allowed in previous years.
28. Appendix A presents the NERSA calculated Allowable Revenue in comparison with
the Allowable Revenue as calculated by Transnet in its application.
Regulatory Asset Base (RAB) 29. The Methodology prescribes the RAB value determination as follows:
Regulatory Asset Base = Trended Original Cost of Property, Plant, Vehicles &
Equipment (V) – depreciation and amortisation of inflation write-up accumulated up
to the commencement of the tariff period under review (d) + Net Working Capital (w)
± deferred tax (dtax). The formula for determining the RAB is:
RAB = V – d + w ± dtax Where: V = Value of property, plant, vehicles and equipment
d = depreciation accumulated up to the commencement of the tariff period
under review
w = net working capital
dtax = deferred tax
30. The relevant regulation pertaining to the determination of the Regulatory Asset Base is
regulation 5(2) of the Regulations made in terms of the Petroleum Pipelines Act
(Government Notice No. R342 of 4 April 2008).
IDMS No. 45374
Pg 10 of 31
31. The applicant submitted that the value of its operating non-current Assets (V-d) is
R5,526.8 million based on the 2006 modern equivalent asset valuation (MEAV)
performed by AD Little adjusted for inflation using inflation indices obtained from the
Bureau for Economic Research (BER).
32. During this tariff period capital asset expenditure (CAPEX) projects to the value of
R2,075 million will be taken into operation (which are part of the New Multi-Product
Pipeline (NMPP) project from June 2010 and hence 75% (R1,556 million) of that value
has been admitted to the RAB. (See Table 2 for the value of Capital Expenditure.)
Table 2: Capital expenditure
Value (V-d) (R m)
Net borrowing
Cost (R m)
Capitalized value (R m)
Working Capital (w)
(R m)
Deferred taxation
(R m)
Total RAB (R m)
New NMPP 16 inch- Pro rata (9/12) 1,327.10 229.44 1,556.54 87.00 (28.60) 1,614.94 New NMPP 16 inch-100% 1,769.46 305.92 2,075.38 116.00 (38.13) 2,153.25
33. The applicant estimates its working capital (w) during the tariff review period to be
R372.6 million or R342.10 million using the NERSA methodology. NERSA calculated
the working capital to be R334.87 million in line with the calculated Allowable
Revenue.
34. The applicant therefore submits that its average Regulatory Asset Base (RAB) is
R6,080.90 million (R5,929.70 million based on NERSA approved Methodology). (See
Table 3.)
Table 3: Transnet application
R million Transnet application 2010/2011
Network Component
Value (V-
d) Net borrowing
Cost Working Capital
(w) Deferred taxation Total RAB
a b c d e=a+b+c-d 5,526.80 217.40 372.60 (36.00) 6,080.80
IDMS No. 45374
Pg 11 of 31
35. The Energy Regulator calculated the RAB value by adjusting the deduction of deferred
taxation credit and the allowance of the capitalised borrowing costs.
36. The deferred taxation liability to be deducted from the RAB has been calculated to
take into account timing differences relating only to the assets. Non-asset related
balances are not taken into account in the calculation of the notional tax and therefore
the applicant is not expected to receive the cash flow benefit in the calculation of
Allowable Revenue.
37. Since the notional taxation calculation has only been applied since the 2008/09 tariff
period, only deferred taxation balances relating to periods from 2008/09 and onwards
are deducted. This is done as the applicant did not benefit from the positive cash flow
from such deferred tax movements prior to 2008 as the tariff was calculated using flow
through basis. This has to be confirmed and will be clawed back if proven not to be
correct. (See Table 4.)
Table 4: Deferred taxation
R million Movement 2008 year 9.40 Movement 2009 year 11.70 Movement 2010 year 24.20 Pipeline inspection costs post 2008 23.50 Deducted from RAB 2010/11 68.80
Movement 2011 year (get benefit only in next year) 114.50 Total Balance relating to Assets post-2008 183.30 Plus Total Balance relating to Assets pre-2008 114.47 Opening balance March 2008 57.97 Pipeline inspection costs pre-2008 56.50 Total Balance relating to Assets 297.77 Non-asset related tax balances 144.67 Prov Refractionator fuel 39.12 Decommissioning provision 16.56 Other provisions 88.99 Total Deferred tax balance 442.44
IDMS No. 45374
Pg 12 of 31
38. Note that the deferred taxation credit which accrues during the current (2010/11) tariff
period is not deducted from the asset base as the applicant will only receive the cash
flow benefit thereof in years to come and therefore the applicant should not be
penalised for it during this tariff period.
Valuation of property, plant, vehicles and equipment (V)
39. The Regulations require the use of historic cost.
40. Section 4.1.2 of the Methodology states that non-current assets are to be valued on
the Trended Original Cost (TOC) basis or in accordance with Regulation 4(7)(b) -
Regulations made in terms of the Petroleum Pipelines Act (Government Notice No. R
342 of 4 April 2008).
41. When determining the RAB the Energy Regulator considered regulation 4(7)(b) of the
Regulations, which states that:
“...for assets in operation at the time of promulgation of these Regulations and for
which historical cost records do not exist, an estimated value that the Authority
accepts as most closely approximating their historical cost…”
42. The applicant has used the modern equivalent asset valuation (MEAV) to calculate its
RAB which is not in compliance with the Regulations.
43. The Energy Regulator has been confronted with this situation before and decided
previously that:
“the Energy Regulator has used the applicant’s inflation adjusted 2006 modern
equivalent asset value (MEAV) Regulatory Asset Base (RAB) for this tariff period
only and on an interim basis. The starting RAB (SRAB) will be determined in due
course and these tariffs may be adjusted thereafter if warranted;”4
4 NATIONAL ENERGY REGULATOR OF SOUTH AFRICA, in the matter regarding, TRANSNET LIMITED’S TARIFF APPLICATION FOR: A 74.42% TARIFF INCREASE FOR THE PETROLEUM PIPELINES NETWORK FOR 2009/10 (AS REVISED ON 26 FEBRUARY 2009), 30 April 2009, page 3.
IDMS No. 45374
Pg 13 of 31
44. A verification exercise to determine a suitable SRAB has been undertaken, however
only on a high level basis thus far. The Energy Regulator is still analysing the results.
Initial indications are that the RAB will be lower than the RAB values used in the
2008/09 and 2009/10 tariff determinations.
45. For the 2010/11 tariff period, the Energy Regulator will continue to use the MEAV
values as supplied by Transnet. Once the necessary detailed calculations have been
performed and assessed, it is the intention of the Energy Regulator to use these
amounts to recalculate the Allowable Revenues for 2008/09, 2009/10 and 2010/11. If,
as expected, there is a resulting reduction in the RABs for 2008/09, 2009/10 and
2010/11, then a claw back will be made in the 2011/12 tariff year.
46. Assets that will be brought into use in the tariff period under review will be three
16-inch pipelines5 with a cost of R2,075 million constructed as part of the NMPP
project. Commencement of operation is expected at the end of June 2010. Therefore
a pro rata value of 75% of the cost has been included in the RAB.
47. An asset valued at R1,090 million should have been in operation as of
September 2009 as per the 2009/10 tariff application. This asset was not taken into
operation at that date and it forms part of the R2,075 million NMPP project to be taken
into operation in July 2010. Since this asset was not taken into operation at the
projected date, a claw back for 2009/10 has been made which will reduce the
Allowable Revenue in this decision. This claw back calculation is set out below in
Table 5.
5 (i) from Jameson Park to Alrode; (ii) from Alrode to Langlaagte; and (iii) from Kendal to Waltloo.
IDMS No. 45374
Pg 14 of 31
Table 5: Claw backs relating to the NMPP
2009/10 Claw back on new NMPP ASSET not taken into operation R million 16-inch NMPP line added to RAB 1,090.80 included from September 2009 545.40
Ke 5.43% 20.73 Kd 2.89% 4.73 WACC 25.46 Depreciation (used 6 months over 50 years) 10.91
Total pre-tax 36.37 Taxation (part of notional tax)
8.06
Total Allowable Revenue derived from asset included in RAB but not taken into operation
44.43
48. Regulation 4.1.3 states that inflation adjustments must be based on appropriate
inflation indices. The Methodology stipulates that the determination of Trended
Original Cost (TOC) should be calculated using the consumer price index (CPI). The
Energy Regulator used historical CPI data from April 1984 to March 2009 obtained
from Statistics South Africa.
Depreciation and amortisation of inflation write-up accumulated (d)
49. Paragraph 4.2.1 of the Methodology states that accumulated depreciation and
amortisation of inflation write-up accumulated (d) is the cumulative depreciation
against plant, property, vehicles and equipment in service.
50. The total value of the RAB compared to the value arrived at by the applicant and the
final adjusted value applied by the Energy Regulator are set out below in Table 6.
IDMS No. 45374
Pg 15 of 31
Table 6: Summary of the RAB values
Application NERSA
decision Regulated Asset Base (V-d) 5,526.80 5,526.80 Net borrowing costs 217.40 186.20 Deferred taxation (35.90) (68.80) Working capital (w) 372.60 334.87
Regulated Asset base (RAB) 6,080.90 5,979.07
Net working capital (w)
51. According to the Methodology, net working capital is to be determined by the following
formula:
Net working capital = inventory + receivables + operating cash + minimum cash balance – trade payables.
52. Table 7 presents the Energy Regulator’s determination and compares it with
Transnet’s calculation. The differences are due to the higher receivables based on a
higher Allowable Revenue used by the applicant.
Table 7: Net working capital
Net working capital (w) Application NERSA Decision Allowable Revenue 1,655.60 1,223.63 Operational expenditure 661.80 661.80 -Inventory 234.30 234.30 -Receivables 138.30 100.57 -Operating cash 81.80 81.59 -Less payables (81.80) (81.59) Total working capital 372.60 334.87
Number of days Receivables/AR 30.49 30.00 Number of days Cash/Opex 45.11 45.00 Number of days Payables 45.11 45.00
IDMS No. 45374
Pg 16 of 31
Weighted average cost of capital (WACC)
53. Section 5.1 of the Methodology prescribes the formula to determine the WACC.
54. The gearing used to calculate the WACC is a function of the RAB as defined by the
Methodology. Capital work in progress (CWIP) has been specifically excluded from
the RAB in accordance with the Regulations. A 30% minimum debt level has been
used as required by the Methodology.
55. NERSA’s calculations have yielded a real WACC of 4.43 % (detailed calculation in
Table 8). Following various written and verbal presentations by the applicant and other
parties and the fact that Financial and Industrial Index (FNDI) data is only available
from 1995, the Energy Regulator did not follow the Methodology but used the Allshare
Index (ALSI) as a basis to calculate the market return (Rm) for this tariff period.
Table 8: WACC calculation
WACC Calculation Applicatio
n NERSA
decision
MRP 5.48% 7.30% Industry beta 0.85 0.52 Adjustment for beta 0.15 Adjusted beta 0.85 0.67 Risk-free 1 (Rf1) – post-tax 3.61% 0.49% Cost of equity (Ke) real 8.27% 5.38% Small company adjustment (25%) 2.07% 0.00%
Cost of equity (Ke) real 10.34% 5.38% Cost of debt (Kd) pre-tax 10.89% 10.89% Cost of debt (Kd) post-tax 7.84% 7.84% Projected CPI 2010/11 5.50% 5.50% Cost of debt (Kd) real pre-tax 5.11% 5.11%
Cost of debt (Kd) real post-tax 2.22% 2.22% Debt ratio 30.00% 30%
Equity ratio 70.00% 70%
WACC 7.90% 4.43%
Corporate Taxation Rate 28.00% 28.00%
IDMS No. 45374
Pg 17 of 31
Cost of equity (Ke)
56. The cost of equity is determined as per paragraph 5.6 of the Methodology which
prescribes that the risk-free rate should be the average of the monthly market-to-
market risk-free rate for the preceding 300 months for all Government bonds with at
least a 10-year maturity as at 12 months before the commencement of the tariff period
under review. This results in a real post-tax risk-free rate of 0.49%.
57. All economic data used is as of a year prior to the tariff period under review, in
accordance with the Methodology.
58. Transnet claims in its application that the Energy Regulator has made an error in the
Methodology regarding the risk-free rate by applying an interest tax shield to the risk-
free rate in the cost of equity.
59. Calculating Ke using risk-free (Rf) pre-tax: Transnet submits that theoretically the
Methodology is incorrect to use a post-tax Rf to calculate the market risk premium
(MRP) and eventually the Ke. The Methodology consistently treats all values on a
post-tax real basis to perform calculations. It is true that the Methodology gives the
difference between pre- and post-tax risk-free quantum back to the applicant in the
calculation of the MRP as MRP is calculated using this “post-tax” risk-free rate to
calculate the premium earned by the equity markets. The “gap” between market return
(Rm) and risk-free (Rf) post-tax is then higher and results in a higher MRP which
probably explains some of the differences pointed out by the applicant in paragraph
5.1.2 of the application. This higher MRP “benefit” is obviously enhanced (if the beta is
greater than 1 or reduced (if the beta is less than 1) by the beta applied to the MRP.
In short, the Methodology gives some of the taxation deduction from the Rf back in a
higher MRP, but this higher MRP is enhanced or reduced by multiplying it with a beta
greater or less than 1.
Inflation
60. The Energy Regulator calculated the average inflation to be 9.18% using 300 months
of data up to March 2009 sourced from Statistics South Africa.
IDMS No. 45374
Pg 18 of 31
Market risk premium (MRP)
61. The applicant determined a market risk premium (MRP) of 5.48% for the period
01 April 1984 to 31 March 2009 based on the difference between the Allshare Index
total real return versus a pre-tax real risk-free rate on which monthly excess MRP
returns were annualised by compounding them and averaging the annualised MRP
over a specified 25-year period.
62. Transnet arrived at a MRP of 7.13% using the NERSA approach using ALSI instead of
the FNDI (as per the Methodology).
63. The Energy Regulator calculated a MRP of 7.30%.
64. The market return (Rm) was calculated by the Energy Regulator using the JSE ALSI
index data, converted from a nominal to a real value for the previous 300 months
(April 1984 to March 2009). This yielded a result of 16.45%. The average month-to-
month CPI over the same period (April 1984 to March 2009) is 9.18%. The CPI data
used is sourced from Statistics South Africa. The average real market risk premium
(MRP) over 300 months is 7.30 %.
65. The Methodology requires the Energy Regulator to use the Financial and Industrial
Index (FNDI). The Energy Regulator deviated from the Methodology in calculating the
Rm value as data for the FNDI is only available for 15 of the 25 years. Furthermore, it
represents a move towards consistency across the three industries (electricity,
petroleum pipelines and piped gas) in determining the Rm value.
Beta (β)
66. The Energy Regulator does not calculate the beta for proxy companies but uses
publicly available data sourced from an independent source, Zacks. The Energy
Regulator has initiated a review of the calculation of the beta in order to enhance the
approach in future.
IDMS No. 45374
Pg 19 of 31
67. The Energy Regulator used the procedure set out in Note 3 of the Methodology to
calculate beta, as at 12 months prior to the commencement of the tariff period under
review.
68. To determine the beta, the following companies were used as proxies:
68.1 El Paso Energy Corporation 68.2 Enbridge Inc 68.3 EQT Corporation 68.4 Magellan Midstream Holdings, Limited Partnership
68.5 Plains all American Pipeline, Limited Partnership 68.6 Provident Energy Trust.
69. These proxy companies are all North American pipeline companies that are in the
petroleum transportation industry.
70. Transnet has included the proxy companies’ short-term and long-term interest-bearing
debt when determining their gearing and in the weighting formula in relation to the size
of the debt.
71. For the purposes of determining the beta, the Energy Regulator applied the minimum
gearing of 30% as specified in the Methodology.
72. The levered (industry) beta is calculated to be 0.52 as at 12 months prior to the
commencement of the tariff review period in accordance with the Methodology.
73. Currently the debt ratio applied to lever the raw beta is a very low 30%. Once the
applicant’s new NMPP project is completed and taken into operation, and with it, its
corresponding debt, the gearing is expected to increase substantially with a
concomitant impact on the beta.
74. To account for South African business conditions, a risk component of 0.15 was
deemed to be appropriate to add to the industry beta yielding a beta of 0.67. (See
Table 9 below.)
IDMS No. 45374
Pg 20 of 31
Table 9: Risk components
Risk Component Value Industry beta - Calculated industry beta – using 6 proxy North American firms as determined by the ER
as prescribed in the Methodology.
0.52
Size of company. - A beta factor adjustment is proposed to accommodate the fact that Transnet Pipelines
excluding CWIP is considered to be relatively small in comparison with the proxy companies.
0.15
TOTAL BETA 0.67
75. Transnet, in its application, added 25% to the Ke before adjustments. The Energy
Regulator added a risk component of 0.15 to the industry beta in accordance with the
Methodology. (See Table 11 for a comparison.)
76. Beta adjustments: as per the NERSA Methodology, the economic and risk factors are
compensated by adjusting the beta. The Transnet application deals with these factors
by adding them to the WACC. Although this may be a different approach to use, the
results are very close. (See Table 10).
77. The resultant real cost of equity is 5.38%.
Table 10: WACC calculation comparison
Application NERSA Decision
NERSA Decision with risk factors
outside beta A C C Risk free over 25 years (Rf) post-tax 3.61% 0.49% 0.49% MRP 5.48% 7.30% 7.30% Industry beta 0.85 0.52 0.52 Adjustment for beta - 0.15 - Adjusted beta 0.85 0.67 0.52 Risk free 1 (Rf1) – post-tax 3.61% 0.49% 0.58% Cost of equity (Ke) real 8.27% 5.38% 4.37% Small company adjustment (25%) 2.07% 0.00% 1.09% Cost of equity (Ke) real 10.34% 5.38% 5.47% Cost of debt (Kd) real post-tax 2.22% 2.22% 2.22% Debt ratio 30.00% 30.00% 30.00% Equity ratio 70.00% 70.00% 70.00% WACC 7.90% 4.43% 4.49%
IDMS No. 45374
Pg 21 of 31
Consumer price index (CPI)
78. The CPI used in calculating the MRP is the average of the month-to-month CPI from
April 1984 to March 2009 (9.18%) using Statistics South Africa data. The CPI used in
calculating the real cost of debt is a forecasted CPI for the next 12 months (5.5%)
obtained from BER.
Cost of debt (Kd)
79. The applicant estimates a weighted average cost of debt (WACD) for the end of
March 2010 to be 10.77% and for the end of March 2011 to be 11.01% yielding an
average of 10.89%, resulting in a post-tax real cost of debt of 2.22% for financial year
2010/11.
Expenses (E)
80. The Energy Regulator has used Transnet’s estimated expenses of R661.8 million. Any
difference between estimated expenses and actual expenses will be subject to a
give-back or claw-back in the next tariff period
Tax (T)
81. Paragraph 7.1 of the Methodology states that each licensee must make a once-off
election between the use of either (a) “flow through” (actual tax) payment, or
(b) “normalised” (notional tax) payment.
82. Transnet elected to use the normalised (notional) tax approach in its tariff application
and arrived at a sum of R192.5 million. Transnet states that using the Methodology the
tax that would apply is R90.1 million.
83. Taxation was calculated using a normalised tax expense for the tariff period under
review.
84. The South African corporate tax rate (Tr) is 28%. Notional taxation is calculated by
using the following formula:
IDMS No. 45374
Pg 22 of 31
Tr*Tr - 1
allowance tax excl NPBT Tax ⎥⎦⎤
⎢⎣⎡=
85. Tax penalties and interest on tax due are not allowed.
86. Calculated in this fashion the notional tax is R109.66 million as per Table 11.
Table 11: Notional tax calculation
NPBT excl tax allowance={(RAB*WACC)+E+D(historic & write up)+F+-C}-{E+D(historic)}
Using Application numbers NERSA decision (R million)
Ke a 225.27 Kd(real) b 39.82 WACC c=a+b 265.09 E d 661.80 D (historic) e 170.20 D (write-up) ee 81.80 F f 0 C [claw back excl tax claw back] g (64.91)
Allowable revenue before tax allowance h=c+d+e+ee+f+g 1,113.98
Tr j 28%
NPBT excl tax allowance={(RAB*WACC)+E+D+F+-C}-{E+D(historic)} [Note interest not deducted to allow tax shield] k=h-d-e
281.98 Allowable revenue pre tax 1,113.98 Tax={(NPBT excl tax allowance)/(1-Tr)}*Tr l={k/(1-j)}*j 109.66 Total Allowable Revenue m=h+l 1,223.63
Depreciation and amortisation of inflation write-up (D)
87. The Methodology states that the depreciation amount calculated on a straight line
basis over the service life of each of the assets or classes of assets in the RAB for the
tariff period under review is included in the Allowable Revenue.
88. Depreciation is to be calculated by using the method given in the example in Note 4 of
the Methodology: Method to Determine Depreciation.
89. The applicant estimated its depreciation expense to be R252 million (historic
depreciation R170.2 million and amortisation of write-up balances of R81.80 million).
IDMS No. 45374
Pg 23 of 31
The Energy Regulator has in the interim accepted the depreciation expense as
provided by the applicant pending finalisation of the SRAB as discussed above.
Approved revenue addition to meet debt obligations (F)
90. Section 9 of the Methodology provides for an addition to the Allowable Revenue to put
an entity in a position to meet its debt obligations. It also states that if the applicant
does not seek such an adjustment, the Energy Regulator will not consider such an
adjustment.
91. Transnet did not apply for any additional revenue or “F factor” for this purpose and the
Energy Regulator has not allocated any additional revenue for this purpose.
92. Notwithstanding the above NERSA performed certain checks and is satisfied that
Transnet Pipelines will have an interest cover ratio, in this tariff period, within the
range published by NERSA (1.5 to 4) taking into account those elements of the NMPP
project included in the RAB.
Claw back adjustment (C)
93. The claw back adjustment was determined using the formula as stated in paragraph
10.1 of the Methodology.
Volume Adjustment (VA)
94. Paragraph 10.2 of the Methodology allows for compensation arising from differences
in projected and actual volumes.
95. Transnet’s volume projection for the 2008/09 tariff period was 17,827 million litres. The
Transnet actual volume for that period was 16,965 million litres. The difference is
862 million litres.
96. The applicant also states that the previous tariff decision was only implemented on
6 August 2009. The total revenue earned by the applicant in the 2008/09 financial year
IDMS No. 45374
Pg 24 of 31
was R1,194.4 million versus the calculated Allowable Revenue of R1,250.39 million.
The total volume adjustment in the claw back is therefore R55.99 million which is a
result of volume differences, late price implementation and differences in the volume
mix. An amount of R27.4 million has already been allowed in the 2009/10 year leaving
a balance of claw back amounting to R28.59 million.
Expenses
97. An in-depth review on Transnet’s expense allocation was conducted for the following
three periods:
- 12 months ending March 2008
- 12 months ending March 2009
- 6 months ending September 2009
98. In the 2008/09 tariff decision the Energy Regulator allowed expenses to the value of
R483.1 million as per the application. The actual expenses for that period amount to
R471.18 million. This difference between expenses claimed and expenses actually
incurred to the value of R11.92 million has therefore been clawed back.
99. Included in the corporate head office cost allocation in the tariff periods 2008/09 to
2010/11 is social investment costs. According to paragraph 6.4.9 of the Methodology,
these are not allowed unless demonstrated to be of benefit to the consumer. These
amounts are therefore also clawed back as the applicant failed to demonstrate such
benefit.
R million 2008/09 2009/10 2010/11 Social investment costs 14.09 13.61 -
F-Factor adjustment (FA)
100. The applicant did not claim any F-factor adjustment.
Debt cost adjustment
IDMS No. 45374
Pg 25 of 31
101. Paragraph 10.5 of the Methodology allows for an adjustment if there is a difference
between the estimated cost of debt in the Allowable Revenue and the actual cost of
debt for that tariff.
102. The formula used to determine the debt cost adjustment is:
Debt cost adjustment = Allowable Revenue recalculated with actual cost of debt - Allowable Revenue projected6
103. In the 2008/09 tariff decision, a debt ratio of 45% was used. In the claw back
calculations for the 2009/10 tariff decision, it was decided that the CWIP should not be
allowed as RAB and subsequently should also not influence the Debt/Equity ratios
used in calculating returns. The effect therefore would be that in 2008/09 the
proportion of return on equity in the WACC would be higher and subsequently the
proportion of the return on debt in WACC would be lower. This is set out in Table 12
below.
Table 12: Net WACC return claw back
NERSA
approved (Rfd)
(R million)
Final Transnet actual as
per 2010/2011
application (R million)
Total actual claw
back for 2008/09
(R million)
Claw back allowed in 2009/2010
(as per 2009/2010
Rfd) (R million)
Total claw back to be allowed in
2010/11 (R million)
Claw back requested by Transnet in
2010/11 application (R million)
Debt cost adjustment 187.70 130.50 (57.20) 19.10 (76.30) (76.30) Equity cost adjustment 201.10 276.40 75.30 3.60 71.70 71.70 Net WACC return claw back 388.80 406.90 18.10 22.70 (4.60) (4.60)
104. The claw back on excess reduction of RAB as a result of deferred taxation for the
2009/10 period is reflected in Table 13.
6 Note: All other factors and quantum in estimated Allowable Revenue remain the same.
IDMS No. 45374
Pg 26 of 31
Table 13: Claw back on excess reduction of RAB by deferred taxation (2009/10)
Claw back on "excess" reduction of deferred taxation in 2009/10 tariff year
As in 2009/10 tariff decision Should be Claw back
R million Deferred taxation balance deducted from RAB 230.15 Should be: Movement 2008 year 9.40 Movement 2009 year 11.70 Pipeline inspection costs post-2008 23.50 Deferred taxation balance deducted from RAB 230.15 44.60 185.55
% Ke 5.43% 10.08 Kd 2.89% 5.36 Total Pre tax claw back 15.44
Depreciation adjustment
105. In the interim the Energy Regulator accepts Transnet’s latest estimate for its
depreciation (R232.50 million) compared with what it estimated in its 2008/09 tariff
application (R251.7 million). The credit difference of R19.2 million together with the
claw back of R6.9 million claimed in the 2009/10 tariff application, totalling
R26.1 million is clawed back. This credit claw back is due mainly to the increased
remaining life of certain assets classes.
106. However, since these values are based on the applicant’s MEAV asset values and not
the correct SRAB values, this amount will have to be reconsidered in future and
possibly adjusted when the SRAB verification exercise is concluded and implemented.
Taxation
107. Transnet claimed an amount of R61.40 million for the actual taxation paid during the
2008/09 tariff period (higher than the value of taxation allowed in the 2008/09 tariff
determination) on the basis that the flow through taxation method was used in
determining the taxation. This amount has been disallowed as the notional taxation
calculation was used in the said tariff determination.
IDMS No. 45374
Pg 27 of 31
Time value of money
108. Transnet received more revenue (R77.60 million) for the 2008/09 and 2009/10 tariff
periods than estimated and should therefore compensate the consumer for the time
value of money. The Energy Regulator’s calculation of the real WACC of 4.43% (see
Table 8) multiplied by the net claw back (R62.16 million) for 1 year is used to calculate
a time value of money of R2.75 million (see Table 14).
109. A taxation claw back is not included in the time value of money calculation as the
taxation would only be paid in the year the revenue is actually earned (2010/11).
IDMS No. 45374
Pg 28 of 31
Claw back summary
110. A summary of the claw back adjustment is presented in Table 14.
Table 14: Summary of the claw back adjustments
R million Application Difference NERSA
Decision Claw back 68.80 (133.71) (64.91)
Volume 28.60 (0.01) 28.59 Cost of debt (76.30) 0.00 (76.30) Cost of equity 71.70 0.00 71.70 Depreciation (26.10) 0.50 (25.60) Operational expenses 2008/09 (11.92) Social investment expenses disallowed for 2008/09 (14.09) Taxation (incl in notional total tax) 61.40 (61.40) - Total claw back 2008/09 59.30 (60.91) (27.62) Social investment expenses disallowed for 2009/10 (13.61) (13.61) Claw back on "over" deduction of deferred taxation in 2009/10 tariff year 15.44 15.44 Total Allowable Revenue on 16-inch NMPP not taken into operation (36.37) (36.37) Subtotal before time value of money 59.30 (95.45) (62.16) Time value of money @WACC (this year’s WACC) 9.50 (12.25) (2.75) Taxation (incl in notional total tax) 0.00
Tariff structure
111. The Energy Regulator commenced setting tariffs in the 2007/08 financial year. The
basis for determining tariffs prior to 2007/08 could not be established.
112. In the 2008/09 tariff decision, the Energy Regulator went some way towards correcting
the imbalances in the inherited historical tariffs, given the information limitations within
which it had to work.
IDMS No. 45374
Pg 29 of 31
113. After the adjustments in 2008/09, intended as a step towards moving from an
unknown historical basis to a known systematic basis, some stakeholders requested
the Energy Regulator not to continue with tariff restructuring until a full consultation
was held. No tariff restructuring was included in the 2009/10 tariff determination.
114. On 31 August 2009, a discussion paper on the 2009/10 Transnet Tariff Structure and
Design (2009) was published by the Energy Regulator. This was followed by a
workshop with stakeholders held on 18 September 2009 on the topic of tariff design.
115. Subsequently NERSA published a Discussion Document on certain matters pertaining
to the application by Transnet Limited for the Setting of its 2010/11 Petroleum Pipeline
Tariffs on 9 February 2010 and written comments thereon were received from
Transnet, Total, Sasol and Petroline.
116. At the NERSA public hearing held on 4 March 2010 Transnet, BPSA, Total, Sasol and
Petroline presented their views on the tariff application and the Discussion Document.
117. Stakeholders have different and opposing views on an appropriate tariff structure for
the industry.
118. In light of the opposing views submitted by various stakeholders and insufficient time
to fully investigate issues raised at the public hearing, the Energy Regulator will
continue its investigations and consultations on tariff structuring during 2010 with the
intention of reaching a well informed position on tariff structuring in time for the next
tariff period.
119. The year to year percentage change in Allowable Revenue will therefore be applied to
the historical tariffs. These tariffs will only be applicable for Transnet’s financial year 1
April 2010 until 31 March 2011.
120. The applicant forecasts a 6.87% increase in the volumes for the 2010/11 tariff period
above the volumes for the 2009/10 tariff period (from 16,774 mega litre in 2009/10 to
17,927 mega litre for 2010/11). When taking the increase in volumes into
consideration in converting the Allowable Revenue increase of 11.86% to a tariff
IDMS No. 45374
Pg 30 of 31
increase, the tariff increase based on a percentage increase over the historic tariffs is
6.09%.
Economic impact
121. The economic impact of the tariff increase in the inland region of South Africa is
expected to be limited. For example, if the Minister of Energy decides to use the
pipeline tariff as a proxy for the cost of transporting fuel from Durban to Johannesburg,
as has been the case in the past, then we expect the consequential petrol price rise to
be 0.7 cents per litre. Such an increase is within the range of monthly petrol price
adjustments Gazetted by the Minister of Energy in recent months. In the month of
January 2010 it was 9 cents per litre decrease, in February 18 cents per litre increase
and in March 2010 6 cents per litre increase.
122. The increase for all tariffs is 6.09% which is below the current inflation rate for January
2010 of 6.2% as published by Statistics South Africa.
123. The tariffs set in this decision are maximum tariffs thus permitting the licensee to
discount.
Other matters
124. In the 2010 budget, the Minister of Finance announced a national fuel levy of 7.5 cents
a litre to contribute to the funding of the New Multi-Product Petroleum Pipeline
(NMPP) between Durban and Gauteng. How this will impact on Transnet Pipelines is
not yet known. No adjustment for the levy has been made during this tariff period
(2010/11).
Conclusion
125. On the conspectus of the facts and evidence, it is appropriate and in compliance with
the requirements of the National Energy Regulator Act, 2004 (Act No. 40 of 2004) to
make the decision set out above. It finds a reasonable balance between the interests
of customers on the one hand and the interests of investors on the other hand.
IDMS No. 45374
Pg 31 of 31
Appendix A: The Allowable Revenue as determined by NERSA is presented in the last column.
Tariff Methodology
Transnet Application NERSA
Decision Allowable Revenue = (RAB x WACC) +E+T+D+F+C Amount (Rm)
or % Amount
(Rm) or %
Regulatory Asset Base (RAB)
Value of assets (V) – accumulated depreciation (d) - Deff taxation
5,708.30 5,644.20
Net Working Capital (W) 372.60 334.87
RAB = V – d + W 6,080.90 5,979.07
WACC Components
Inflation: average over 25 years 9.180%
Inflation: 12 months forecasted 5.50% 5.50%
Rf 3.61% 0.49%
Market return (Rm) Not provided 17.73%
MRP (Market risk premium) 5.48% 7.30%
Proxy industry beta 0.52
Beta adjustment
0.15
Total beta
0.85
0.67
Cost of debt (Kd) 2.22% 2.22%
Cost of equity (Ke) (real) 10.34%
Includes a 25% small company
adjustment
5.38%
WACC 7.90% 4.43%
Expenses 661.80 661.80
Tax 192.50 109.66
Depreciation 252.00 252.00
Claw back adjustment 68.80 (64.91)
Allowable Revenue
1,655.73
1,223.63