Transport for London, London Rail

London OvergroundEast London Railway & Stations Improvements

Public Meeting: Naborhood Centre, Sydenham Road14th March 2007

Page 2: Transport for London, London Rail London Overground

Introducing ‘London Overground’

NLR and ELR Connection; the Orbirail Network

Dalston Curve

Page 3: Transport for London, London Rail London Overground

Overground - the regeneration railway

ELL Phase 2 (Uncommitted)

BrockleyHonor Oak ParkForest Hill Sydenham

Dalston Curve

Page 4: Transport for London, London Rail London Overground

4

Example: Sydenham, 2006Station challenges

Difficult station access and poor signage

Poor waiting facilities and accommodations

Poor interior station layout (difficult access to ticket office)

Page 5: Transport for London, London Rail London Overground

5

Overground stations• November 2007:

TfL takes over existing North London stations

• Four stage approach:� Enabling works/Oyster/Gating� Blitz clean� Refurbishment: includes upgraded

information, help points and CCTV� Rebuild some stations

• Lewisham stations served by London Overground:� Sydenham; Honor Oak Park; Brockley;

Forest Hill; New Cross Gate; New Cross� Network Rail via the DfT funding under

Access for All will introduce step free access

• Improvement package for refurbished stations: better waiting facilities, better lighting, CCTV, help points, provision of Oyster validators and ticket vending machines

Page 6: Transport for London, London Rail London Overground

6

New trains on London Overground

• Contract awarded to Bombardier

• £223M contract to deliver:– 20 x 4 car units (ELR) December 09– 24 x 3 car units (NLR) December 08

• Constructed in Derby & maintained at New Cross Gate

• Key features include: wider seats, wheelchair provision, CCTV, audio and visual real time information, wider gangway, better hand rail, air conditioning, walk through carriages, regenerative braking

Page 7: Transport for London, London Rail London Overground

7

Overground infrastructure; East London Line Project

• £40m Enabling Works finished January 2007 included bridge works, arch repairs and preparation of track formation

• Main Works Contract let in October 2006, includes remainder of works including a dedicated new depot at New Cross Gate

• Line closure 22nd December 2007

• Re-opening to West Croydon and Crystal Palace by June 2010

• Link to Highbury & Islington secured

Page 8: Transport for London, London Rail London Overground

8

Improved services on the East London Railway

• Regular ELL services:8 trains per hour, all day, and 7 days a week

• Overground train stopping at all stations

• Operating hours to match LU

• Faster journey time to Canary Wharf(between 7 - 11 minutes saving)

• Provide improved links to the Docklands, where demand is forecast to increase by circa 80% to 2016