Page 1: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

WELCOME!

Airport Master Plan Public MeetingNovember 13, 2013

Page 2: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Where are We In the Process

Page 3: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

What the Plan Will Include

Master Plan Topics

• Community Process• Facility / Policy Inventory• Aviation Demand Forecasts• Facility Requirements• Alternatives Analysis• Implementation Plan

Page 4: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Meeting Objectives

• Bring you up to date on plan progress.

• Obtain specific feedback / support for new annoyance mitigation initiatives.

• Capture some plan highlights.

Page 5: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

1998 Master Plan

Page 6: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Current Master Plan Concept

Page 7: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Plan Comparison

Then: Airport-Driven(1998)

Now: Community Driven(2013)

• Maximum Growth • Annoyance Mitigation• More Runways • Multi-Use Hangar• All-Weather Access • Non-Aviation Uses• More T-Hangars • Technology Upgrades• Non-Aviation Uses • Box Hangars

Page 8: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Annoyance Mitigation

• New Runway– To avoid / reduce residential overflights

• Changes to the Primary Runway– To increase the height of airplane overflights

• Changes to the Secondary Runway– To better balance runway utilization

• Off-Airport Alternatives– To increase the range of options.

Alternatives Considered

Page 9: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Alternatives Dismissed

New Runway• $27.4M• Wetlands

~ WETLANDS ~

Page 10: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Alternatives Dismissed

1A: Extend Runway 11-29 East and Displace Landings

1B: Extend Runway 11-29 East / Shorten West

• $6.5M• Limited Benefit

Page 11: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Alternative 1B: Airspace Impacts

Page 12: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Jet Departure Profile

Page 13: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Piaggio Departure Profile

Page 14: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 29, Jet Departure - Existing

Page 15: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 29, Jet Departure - RW Alt 1

Page 16: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 29, P180 Departure - Existing

Page 17: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 29, P180 Departure - Alt 1

Page 18: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 29, C172 Departure - Existing

Page 19: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 29, C172 Departure - Alt 1

Page 20: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 11, Jet Arrival - Existing

Page 21: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 11, Jet Arrival – Alt 1

Page 22: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 11, P108 Arrival - Existing

Page 23: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 11, P108 Arrival - Alt 1

Page 24: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

OPINION

• No significant change to height or noise

• Dismiss from consideration

Alternative 1: Runway 11-29

Page 25: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Alternatives Dismissed

• Widen Runway 2-20– $3.5M– Minimal change in

runway utilization

• Extend North– $5M to $15M– Significant Fill or– Pylon-bridge

construction

Page 26: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Alternatives Retained

Widen and extend Runway 2-20 South• $6.9M• Greater dispersion of runway utilization

Page 27: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway Selection Factors• Wind direction and velocity• Runway length • Pavement strength• Local communication efforts• Taxi distance• On course / arrival direction• Glider activity • Runway width

Runway 2-20 Utilization

Page 28: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

DEPARTURES ARRIVALS

Existing Alt 2A Existing Alt 2A

29Piston 77% 58% ↓ 66% 47% ↓Turboprop 88% 76% ↓ 82% 64% ↓Turbo Jet 96% 88% ↓ 94% 83% ↓

2Piston 8% 16% ↑ 8% 16% ↑Turboprop 2% 8% ↑ 2% 8% ↑Turbo Jet 0.5% 6% ↑ 1% 4% ↑

20Piston 11% 22%↑ 22% 33% ↑Turboprop 6% 12% ↑ 12% 24% ↑Turbo Jet 0.5% 3% ↑ 2% 10% ↑

Runway 2-20 Utilization

Page 29: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

CA-267 Eastbound View to NE

Existing

Page 30: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

With Extension

CA-267 Eastbound View to NE

Page 31: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Existing

CA-267 Westbound View to NW

Page 32: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

With Extension

CA-267 Westbound View to NW

Page 33: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

CA-267 Elevated View to NW

Existing

Page 34: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

With Extension

CA-267 Elevated View to NW

Page 35: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Widen and Extend Runway 2-20

OPINION / RECOMMENDATION• Extending and widening will disperse operations more

effectively• Dispersion can be influenced by TTAD actions/policy• Views of Martis Valley not impacted significantly• Proceed with implementation planning

Page 36: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Alternatives Retained

OFF-AIRPORT MITIGATION• Annual Funding Allocation• Current models under consideration:– Expansion of Open Space Preservation Policy– Voluntary Home Improvement (Sound Insulation)– Voluntary Home Acquisition– Additional Possibilities– Flight Track Optimization– Requires Additional Community Outreach

Page 37: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Arrivals DeparturesOff-Airport Alternative

June 2012

Page 38: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Off-Airport Alternative

• 160 homes in Zone B1

• 70 homes in Zone C

Page 39: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 29, Jet Departure - Existing

Page 40: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 29, Jet Departure - Straight

Page 41: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 29, C172 Departure - Existing

Page 42: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Runway 29, C172 Departure - Straight

Page 43: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

Off-Airport Mitigation

OPINION/RECOMMENDATION• Increases Options Available to Residents and District• Proceed with Implementation Planning

ITEMS TO BE CLARIFIED• Funding Prioritization / Geographic Boundaries• Disposition of Acquired Property• Policy/Legal Implications

Page 44: Truckee Tahoe Airport Master Plan Public Meeting Nov 13

THANK YOU