trusted bim: accurate as-builts for project coordination

39
Trusted BIM: Accurate As- Builts for Project Coordination Presenter: Daniel Niziolek, Ramboll UK Presenter: Les Carter Jr., PLS, Cannon Host: Kevin Williams, ClearEdge3D

Upload: clearedge3d-inc

Post on 09-Apr-2017

501 views

Category:

Technology


1 download

TRANSCRIPT

PowerPoint Presentation

Trusted BIM: Accurate As-Builts for Project CoordinationPresenter: Daniel Niziolek, Ramboll UKPresenter: Les Carter Jr., PLS, CannonHost: Kevin Williams, ClearEdge3D

1

AgendaIntroductions, Goals & ContextTrusted Building Information ModelCommercial Building Daniel NiziolekTechnology Academy Building Les CarterAsk the Experts Q&A

2

HousekeepingParticipants are muted during the presentationAsk questions via chat during the session Questions will be taken during the Q&A sessionThe Webinar is being recordedYoull receive a recording link after the webinar

3

Service Provider PerspectiveProduce a quality productDeliver in increasingly shorter timeframesReduce man-hours and costEarn repeat businessTrusted BIM: Accurate As-Builts for Project CoordinationImperative for SuccessOwners PerspectiveGet the project into operation as fast as possibleMinimize waste, rework and riskUse BIM for ongoing O&M

Accurate and reliable project information is a foundational requirement for project success.

4

Trusted BIM: Accurate As-Builts for Project CoordinationIntroductionsDaniel NiziolekAssistant EngineerRamboll UKKevin WilliamsChief ScientistClearEdge3D, IncAt Ramboll almost 9 yearsWealth of experience modeling from pointcloud data

Founded ClearEdge3D in 2007Expert in Automated Feature from Point CloudsRecipient of numerous National Science Foundation R&D grants

5

Firm Name

Global engineering, design and consultancy company.Advanced Engineering team provides simulationLaser scan data used to build models for well over 10 yearsProcesses developed for analysis and BIM

Ramboll

6

Commercial BuildingCentral LondonProject Scope: Accurate as-built model for fitting in additional equipment

7

Building renovation projectClient was a Ramboll Building Services team They designed original services, but was built with major differences to construction drawings/modelsClient needed new design to fit around what was actually builtBrief was to survey and Revit model the as-built environmentAbout the ProjectCommercial Building Redevelopment

8

Building renovation projectClient was a Ramboll Building Services team They designed original services, but was built with major differences to construction drawings/modelsClient needed new design to fit around what was actually builtBrief was to survey and Revit model the as-built environmentAbout the ProjectCommercial Building Redevelopment

9

Short timeframe client needed immediate start and fast turnaroundTook over from another survey company who couldnt meet the deadlinesGetting enough coverage of the pipes and services in/out of reach areasUnique Challenges FacedCommercial Building Redevelopment

10

Firm Name

Z+F Imager 5010c scannerActive construction site safety and planning issues33 scanner locationsOver 3 billion points1 day on site for 2 surveyors1 day office post processing (in Leica Cyclone)Target based registration

Field Collection Workflow

11

300 GB of data Process locally on SSD drives1 modelerApprox. 8 days total modeling time (6 in Edgewise and 2 in Revit)Edgewise used for modeling walls, pipes, columns and beamsRevit used to model floor slab, ceiling, plant (masses), windows and doorsBack-office Modeling WorkflowCommercial Building Redevelopment

12

Auto wall detection found vast majority of wallsDetermines wall thickness if scan data is on both sides, otherwise default thicknessLevel extraction useful in RevitWindow detection didnt workEdgeWise BuildingEdgeWise in Action

13

Used Pattern Extract wherever possibleNot a perfect structure and not very repetitiveStandard tools work great for bracing / non-vertical / non-horizontal membersBiggest time-saving with Edgewise Structure was sizing beams and columnsEdgeWise StructureEdgeWise in Action

14

Some beams are fabricated from steel plateModel used for clashes/reference, not structuralDecided to define custom I-Beam in EdgewiseTip: You need to include correct k value!EdgeWise StructureEdgeWise in ActionTypenamed depth (m)b width (m)tf flange thickness (m)tw web thickness (m)x neutral axis (m)y neutral axis (m)k distance from outer flange face to toe of fillet (m)IBeamB010.40.350.030.0150.035IBeamB020.40.30.030.0150.035IBeamB030.40.30.020.0150.025IBeamB040.40.20.0150.0120.02IBeamB050.60.40.0350.0150.04

15

EdgeWise StructureEdgeWise in Action

16

Auto pipe extraction found majority of the pipesSome manual work needed, but this is pretty quick and easyNeeded to manually extract about 25% additional pipes and extend/connect those that were foundTip: be methodical in moving around the site finish an area before moving onTip: For UK users, make sure you use the US Metric Systems templateEdgeWise MEPEdgeWise in Action

17

EdgeWise MEPEdgeWise in Action

18

Firm Name

As built Revit model in just 10 work days from survey to model deliveryDelivered to Ramboll team for their design workA happy client

Final Deliverable

19

EdgeWise Workflow Time SavingsCommercial Building RedevelopmentEstimated time savingsOld Workflow: 20 daysEdgeWise Workflow: 10 daysAt least 50% Savings with EdgeWise Workflow

20

EdgeWise Workflow Time SavingsCommercial Building Redevelopment

Automatically detected pipe modelCleaned up final pipe model

21

EdgeWise Workflow Time SavingsCommercial Building RedevelopmentExample on different projectOld Workflow: 2 days (incomplete)EdgeWise Workflow: 0.5 days (additional post processing required)At least 75% Savings with EdgeWise Workflow

22

Trusted BIM: Accurate As-Built for Project CoordinationIntroductionsZoltan NagySr. Structural DesignerRevit/BIM LeadLes CarterSurvey Director

Jason HarlessCADD Manager20 years multi-discipline experience in design and production AutoCAD and REVIT 3D Reality Capture Lead for Architectural, Mechanical and CivilQA/QC of Point Cloud data and registrationLicensed Land Surveyor with 38 years experience.At Cannon for 10 Years.Sr. Land Surveyor with City of San Diego for 26 years.Head of 18 member Survey Division.15 Years 3D CADD and Laser Scanning Experience.FARO Scene and Leica Cyclone Registration expertExpert in Automated Feature Extraction from Point CloudsBIM Modeling

Technology Academy BuildingSanta Monica, CAProject Scope: Scan and Revit Model for Phase 1 Construction As-Built

Est. 1976CannonCelebrating 40 years of service. Providing laser scanning & modeling services since 2008. Surveying/Mapping; Scanning; GIS; UAV Mapping = All things 3D

Civil, Structural and Mechanical EngineeringInstrumentation and Electrical; SCADA SystemsPermitting and Construction ManagementGrant Funding AssistanceOffices in Los Angeles, Ontario, Santa Barbara, Bakersfield and San Luis Obispo

25

About the ProjectTechnology Academy Building

2-story Building Expansion and retro-fit.Scan area: 34,000 ft2.Client; College DistrictProvide point cloud and prepare a REVIT Model.Client needed the updated As-Built conditions of the building Required a high level of detail.

Coordination of scanning during ongoing construction operationsScanner locations obstructed by equipment and construction materialsDim lighting requiring battery operated lights

Unique Challenges FacedTechnology Academy Building

Smaller diameter pipe has to have sufficient point cloud coverage so It can be extracted manually.More scans had to be taken due to the density and size of the piping.Creating the level of detail needed in REVIT Model was a key challenge.Unique Challenges FacedTechnology Academy Building

Dense structural features interfered with the scanner line of site for the piping3D Modeling of unique non-standard structural featuresClient required the model to show any blocking and supports added as additional structural reinforcement during construction process.

Unique Challenges FacedTechnology Academy Building

Firm NameCreated scanner location map for each floor.On site field recon to verify site conditions and access.Used FARO x330 Scanner.Used battery LED work lights in some rooms for photo draped color scans.Scans were performed during ongoing construction. Required close coordination with GC.

Field Collection Workflow Pre-Planning

Firm NameNumber of controlled scans: 134Field collection time: 7 daysExisting multi story building with drop ceilings, interior walls and existing rooms.Project had to be in contractors coordinate system.Registration software used: FARO Scene

Field Collection Workflow Field Operations

Created Clear View and Recap point clouds Working copies of point clouds were stored locally on workstations.Extracted walls, structure, and piping in Edgewise. Point cloud and auto extraction was ran overnight.Minimizes potential errors in human judgement.

Back-office Modeling WorkflowTechnology Academy Building

2 modelers worked together in parallel. One working on mechanical features and Revit model, and the other working on Steel and piping details.A great deal of user extraction of smaller piping and custom structural details was necessary.Back-office Modeling WorkflowTechnology Academy Building

REVIT files were updated with extracted elements.Wall openings and Custom features were modeled in Revit using a ReCap pointcloud. Revit project files were stored on server location.

Back-office Modeling WorkflowTechnology Academy Building

Firm Name

Our Client needed a Revit as-built which reflected detailed Reality Capture of the building.Finished Project was 244GB of data.We also provided the full registered point cloud as Autodesk ReCap files.

Final Deliverables

Edgewise Workflow Time SavingsTechnology Academy BuildingOld Workflow: 160+ hoursEdgewise Workflow: 80 HoursBy extracting walls, structure and piping in Edgewise we achieved a 50% cost savings in the modeling workflow.

As for any project, the keys to success are:A well defined scope of work and a very specific and detailed description of the level of details to be shown in the CAD/Revit Model. For this project:Highly detailed and non-standard Structural features.Small diameter conduits.Non-standard HVAC features.

Project Tips & TricksTechnology Academy Building

Ask the Expert PanelUnique Challenges Trusted BIM Accurate As-Builts for Project Coordination

38

Thank You!A link to the recorded webinar will be sent to you soon.

www.ClearEdge3D.com+1 (866) [email protected]