Under the supervision of: Prof. Ibrahim Alhammad
Prepared by:
Abdullah Khaled Al omar 430102501 Saleh Abdulaziz Alothman 430103321 Saud Abdulaziz Alothman 430102739 Ibrahim Othman Al Rasheed 429102041 Abdullah Motlaq Alotaibi 430104051 Abdullah Mansour Almazyad 430103024 Abdulaziz Saleh Bin Khenayn 429401577
Introduction
• Riyadh Metro Project is the present and future work experience as a new megaproject in Saudi Arabia.
• It consists of 6 lines integrated to each other by 4 Main Stations.
• A total length of 176 km linked with 85 stations
Metro Lines
• Line 1: “Olaya Street” 38 km
• Line 2: “King Abdullah Road” 25.3 km
• Line 3: “Almadinah Road” 40.7 km
• Line 4: “King Khalid Airport” 29.6 km
• Line 5: “King Abdulaziz Road” 12.9 km
• Line 6: “Abdulrahman bin Awf” 30 km
Underground Trains
Length (km) Total Length Tunnel At Grade Elevated
Line 1 38 17.3 4.8 15.9
Line 2 25.3 3.3 16.6 5.4
Line 3 40.7 9.4 5.2 26.1
Line 4 29.6 5.9 6.9 16.7
Line 5 12.9 12.9 0 0
Line 6 30 8 2 19.7
Line 1 has the tallest tunneling path
Line 1 Contractors
• “BACS” CONSORTIUM
- Bechtel
- Almabani
- CCC
- Siemens
• The contract is “Design and Build” contract
Project Time Schedule
60
60 Months Overall Program
Contract Award
Design &
Long-lead
Procurment
48 Months Core Construction
Test &
Commission
Start Construction
SCHEDULE
OVERALL SCHEDULE
8-month
LD Holiday
Stations
• Line 1 is connecting 3 Main stations and has 22 Pick-Up stations.
• The main stations are:
• 1- King Abdullah Financial District Station
• 2- Olaya Station
• 3- Qaser Al Hokm Station
• One Example of the Pick-Up stations is 1A2 “shown in figure”
Olaya Station
o Location: South of King Abdullah
road at the intersection of Line 1
Olaya-Batha with Line 2 king
Abdullah road.
oArea: 11,000 m2.
oDesigner: Gerber Architekten (Germany).
BLUE TBM ORANGE TBM BROWN TBM PURPLE TBM
DRIVE NORTH FROM LAUNCH SHAFT
SOUTH OF 1B3 INTO RECEPTION SHAFT
SOUTH OF 1A2
3947m
TOTAL DIST.
4155m 5125m 3250m
DRIVE SOUTH FROM LAUNCH SHAFT
SOUTH OF 1B3 INTO RECEPTION SHAFT
NORTH OF 1C4
DRIVE NORTH FROM LAUNCH SHAFT
BETWEEN 1F2 & 1F4 INTO RECEPTION
SHAFT SOUTH OF 1C4
DRIVE SOUTH FROM LAUNCH
SHAFT BETWEEN 1F2 & 1F4 INTO
RECEPTION SHAFT NORTH OF 1F8
1A2 1B4
1B3
1C4
1F2
1F8 1F4
TBM Launching Shafts
TBM General Information
• The excavation depth in Line 1 starts from 11 m and reaches a maximum of 36 m depth at the segment between (1B1-1B2).
• Design life of TBM Bored tunnel is 100 years.
• Design fire resistance is 3 hours.
Geotechnical Design Consideration
• In almost half of the route of Line 1 competent limestone with limited weathering and without groundwater table is expected.
• From station “1F2” to “1F4” in line 1, TBM cross a silty clayey sand layer.
• Typically settlements over the tunnel (0-10mm).
• Some areas of greater predicted settlement (10-30mm) in the southern section of the Line 1 tunnel, near Station “1F2”.
Geometry of TBM
• The tunnel internal diameter is 9.0m
• This diameter is further increased by 0.2 meter to accommodate TBM construction tolerance as required.
• The proposed TBM final lining is precast segments of 360mm thick.
Lining Thickness
(mm)
360
Internal diameter (mm)
9200
External diameter (mm)
9920
3635.874328.4174674.694674.694328.417
31164.599
3817.663
1887.19
3817.663
91
1.9
02
90
3.9
86
91
0.9
81
90
5.0
71
3649.721
3950.1131623.1563949.247
17
71
.71
6
17
83
.73
1
17
97
.90
7
18
14
.98
4
18
29
.25
4
18
38
.45
18
39
.26
5
17
78
.24
2
17
79
.39
8
17
66
.07
8
17
60
.15
2
17
62
.41
2
17
71
.71
6
18
16
.26
9
3371.9764014.2574335.3984335.3984014.257
3524.518
1782.33
3524.518
28902.652
3663.411
17
73
.76
9
17
98
.05
9
18
27
.13
1
18
36
.41
5
90
3.5
94
91
1.1
22
91
0.2
04
90
4.6
8
17
80
.89
4
17
63
.04
4
17
73
.76
9
17
84
.91
1
18
13
.89
7
18
35
.66
18
15
.08
9
17
68
.54
17
65
.14
3384.8222060.923385.625
1505.3463662.608
2222.2093650.587
18
00
.00
0
18
00
.00
0
18
00
.00
0
18
00
.00
0
17
60
.00
0
18
37
.09
7
17
62
.90
3
18
40
.00
0
PROJECT
DRAWN BY
REVISIONS
No Date Description
NAME
CHECKED BY
NAME NAME
DRAWING TITLE
DRAWING NUMBER
BACS CONSORTIUM
CONSULTANT / SUB-CONTRACTOR
Drawn Checked Approved
DRAWING STATUS
SCALE
APPROVED BY LDE
NAME
APPROVED BY
DOCUMENT REVIEW STATUS
DATE DATE DATE DATE
16151413121110987654321
M
L
K
J
H
G
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A
B
C
D
E
F
G
H
J
K
L
M
LEAD DESIGN ENTITY (LDE)
AREVIEWED
Work may proceed
DREJECTED
EREVIEW NOT REQUIRED
Work may proceed
COBJEC TION
Revise and re-submit. Work may not proceed
BREVIEWED WITH COMMENTS
Revise and re-submit. Work may proceed subjec t to
incorporation of comments
www.bacsrmp.com
LINE 1 - TBM TUNNEL
PRECAST SEGMENTAL LINING
GENERAL ARRANGEMENT-
RIGHT HAND TAPER
M-BD2-100000-CTLI-EDR-000002 00A
00Av1
09/04/1408/04/1407/04/1409/04/14
G. CHARLESWORTHW.LIEWC.D . ZHONGM. MIRZAKASHANI
60% DEVELOPED DESIGN
1:50G.C.W.L.C.D.Z.60% DEVELOPED DESIGN09/04/1400A 09 APRIL 2014
3635.874328.4174674.694674.694328.417
31164.599
3817.663
1887.19
3817.663
91
1.9
02
90
3.9
86
91
0.9
81
90
5.0
71
3649.721
3950.1131623.1563949.247
17
71
.71
6
17
83
.73
1
17
97
.90
7
18
14
.98
4
18
29
.25
4
18
38
.45
18
39
.26
5
17
78
.24
2
17
79
.39
8
17
66
.07
8
17
60
.15
2
17
62
.41
2
17
71
.71
6
18
16
.26
9
3371.9764014.2574335.3984335.3984014.257
3524.518
1782.33
3524.518
28902.652
3663.411
17
73
.76
9
17
98
.05
9
18
27
.13
1
18
36
.41
5
90
3.5
94
91
1.1
22
91
0.2
04
90
4.6
8
17
80
.89
4
17
63
.04
4
17
73
.76
9
17
84
.91
1
18
13
.89
7
18
35
.66
18
15
.08
9
17
68
.54
17
65
.14
3384.8222060.923385.625
1505.3463662.608
2222.2093650.587
18
00
.00
0
18
00
.00
0
18
00
.00
0
18
00
.00
0
17
60
.00
0
18
37
.09
7
17
62
.90
3
18
40
.00
0
PROJECT
DRAWN BY
REVISIONS
No Date Description
NAME
CHECKED BY
NAME NAME
DRAWING TITLE
DRAWING NUMBER
BACS CONSORTIUM
CONSULTANT / SUB-CONTRACTOR
Drawn Checked Approved
DRAWING STATUS
SCALE
APPROVED BY LDE
NAME
APPROVED BY
DOCUMENT REVIEW STATUS
DATE DATE DATE DATE
16151413121110987654321
M
L
K
J
H
G
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A
B
C
D
E
F
G
H
J
K
L
M
LEAD DESIGN ENTITY (LDE)
AREVIEWED
Work may proceed
DREJECTED
EREVIEW NOT REQUIRED
Work may proceed
COBJEC TION
Revise and re-submit. Work may not proceed
BREVIEWED WITH COMMENTS
Revise and re-submit. Work may proceed subjec t to
incorporation of comments
www.bacsrmp.com
LINE 1 - TBM TUNNEL
PRECAST SEGMENTAL LINING
GENERAL ARRANGEMENT-
RIGHT HAND TAPER
M-BD2-100000-CTLI-EDR-000002 00A
00Av1
09/04/1408/04/1407/04/1409/04/14
G. CHARLESWOR THW.LIEWC.D . ZHONGM. MIRZAKASHANI
60% DEVELOPED DESIGN
1:50G.C.W.L.C.D.Z.60% DEVELOPED DESIGN
09/04/1400A 09 APRIL 2014
Soil Excavation Quantity
• In a simple calculation, we can assume the quantity of soil to be excavated.
• Area of tunneling= 77.29 m2
• Tunneling Length= 17.3 km
• Soil Volume= 17300*77.29= 1337117 m3