tunnelling journal feb-mar2015 managing monitoring data
DESCRIPTION
bla.. bla..TRANSCRIPT
7/18/2019 Tunnelling Journal Feb-Mar2015 Managing Monitoring Data
http://slidepdf.com/reader/full/tunnelling-journal-feb-mar2015-managing-monitoring-data 1/9
COPENHAGEN’S NEW CITYRINGENMETRO line consists of 15.2km of twin
bored tunnels, 17 new stations and fourshafts. Circling the city centre, the line
passes near some of its most historic 18thand 19th century buildings including theMarmorkirken, or marble church. The city
also has a high water table, which must bemanaged for excavation while its level is
maintained underneath existing buildings.
Contractor Copenhagen Metro Team(CMT), a joint venture of Salini Impregilo,Tecnimont Civil Constuction and Seli, must
keep a close eye on many differentelements: movements of ground and
buildings, loads on struts, deflections ofretaining walls, data from fourTBMs, stress and strain in the
tunnel lining segments, waterlevels and water flows, noise and
vibration.“Due to the size of the project
and the technical requirements,we decided we had to go to
someone who had the know-how to do automated
measurements and a databasewhich met most of thespecifications, and could be
easily extended to add theproject –specific requirements,”
says CMT monitoring managerAntonis Charalambides.
CMT chose Geodata’s Kronosdata management software, a
package which collects andpresents data from several
sources and subcontractors. ‘Off-the-shelf’ solutions such asKronos, or Soldata’s Geoscope
can be suited to large projects orprogrammes with numerous data
sources to manage and compare.
For other projects, bespoke systems offer amore reliable and cost-effective solution for
those firms with the right capabilities.A newly emerging tool which promises
some exciting applications in several fields
of civil engineering, is analytics. Arup,Atkins and QuantumBlack have developed
the AIM (Adaptive Instrumentation andMonitoring) application that integrates
analytics to interpret monitoring data.
Analytics have been used in otherindustries such as Formula 1 and aredesigned to work with huge and fast flows
of data. Analytics for tunnelling applicationscan help spot patterns and trends andoptimise monitoring regimes.
Why are you monitoring?There’s a question which seems to be
missing from some monitoring regimes:why? Designers look at what’s been usedpreviously, third parties are looking for as
much monitoring as possible on theirassets, contractors are looking for the
cheapest solution and specialist monitoringcontractors just want to make sure that
data keeps coming, to meet their
contractual obligations.“You can end up with monitoringsystems that are over-the-top,” says Peter
Wright, regional practice manager (tunnelsEurope) at CH2M Hill who is working onthe monitoring strategy for HS2. Over-
18 TUNNELLING JOURNAL
MONITORING
Managingmonitoring data
Figure 1: The basics of Sample Analytics
With data flowing from all directions and multiple sources, how can
clients, contractors and designers ensure they are seeing what they
need to see? Kristina Smith finds out about a number of different
solutions to managing and presenting data.
7/18/2019 Tunnelling Journal Feb-Mar2015 Managing Monitoring Data
http://slidepdf.com/reader/full/tunnelling-journal-feb-mar2015-managing-monitoring-data 2/9
MONITORING
specification doesn’t just mean that youhave more information to handle, it can
mean that monitoring is less effective thanit could have been had a more modest and
appropriate solution been chosen.“It’s about asking the right questions,”
says Wright. “Is it safety critical? What
activity are you carrying out? If you aredemolishing a building over a tunnel for
instance, manual monitoring of the tunnel
or infrequent automatic monitoring issufficient. If a TBM is passing under anexisting asset, you may need real time
monitoring.”“Some clients take a blanket approach
and say ‘everything needs monitoring’,”says Stewart Harrison, chief surveyor forBam Ferrovial Kier (BFK) on the C300/C410
Western tunnels and stations contracts forCrossrail. Specifications can be vague, he
says, simply stating that a structure shouldbe monitored and some contractors don’t
have an understanding of what particularmovement or mechanism monitoring
should be watching for.Third-party asset owners can also demand
unnecessarily large quantities of monitoringdata. “You need to talk to third party assetowners up front and get economic and
efficient monitoring agreed if you want toavoid systems that are over-specified,” says
Wright. “The key is to actually getmonitoring experts in place at the design
stage. That’s what I am proposing for HS2.We need people who can write guidelines
for monitoring equipment up front.”One knock-on effect from huge amounts
of data is problems with the quality of thedata produced. False alarms are a commonproblem. “With these flows of data
approaching all the time, you do get badresults which mean that there are
disturbances to the systems so that errors
can happen,” says Klaus Rabensteiner, CEOof Geodata.
“If the values are not verified, we have alot of false alerts so we need algorithms tocheck the validity of the data, to sort out
the false alarms,” says Rabensteiner. Theway various packages do this varies widely
from provider to provider, he adds.Stewart thinks that problems with false
alarms are due to a much more
fundamental issue. Rather than algorithmsto remove rogue results, monitoring systemsshould be properly designed so that the
rogue results don’t occur. The waymonitoring contracts are procured does notnecessarily encourage this approach:
“Subcontractors are concerned withdelivering data, because that is how their
contracts measure them,” he says. “Theredoesn’t seem to be anything in any contract
that says the data has to be any good.”An industry-led group in the International
Tunnelling and Underground SpaceAssociation (ITA) is currently working to set
minimum standards on what informationand monitoring management systemsshould look like for various project types.
Led by Rabensteiner, the group isdeveloping guidelines on what it calls ‘plug
and play’ data management systems (seebox).
“Contractors are confronted with anoverload of data,” says Rabensteiner. “They
need that data to be easy to handle andthey need a clear concept of what to do
with all the data, how to collect it fromdifferent sources, how to combine and
connect the data in order to extract the realinformation.”The guidance should help designers
define monitoring regimes, saysRabensteiner: “Monitoring is part of the
feedback process. It has to be seen in a
bigger context. Monitoring gives feedbackto the design and allows adjustments forthe next steps.”
Kronos in CopenhagenThough European metro specifications havebeen requiring monitoring databases for
over ten years, the Cityringen project calledfor something Charalambides has not seen
before: multiple subcontractors feeding
information into the one database.“We had never worked this way before,”he says. “On other projects, there was onepartner sending TBM data and the
monitoring department collecting its owndata; only two sources. On this project we
have a large number of subcontractors andsources which are uploading different types
of data and information.”In addition to monitoring and TBM data,
the database receives data from thegroundwater management department, the
environmental department additional waterlevel measurements from two external
sources, construction progress from sites,borehole profiles from two drillingcompanies and evaluation data from the
geotechnical designer.This is a trend which Charalambides
believes is set to continue. Cityringen hasbrought some useful lessons for CMT and
specialist monitoring subcontractor SMT.“It did raise an issue of quality of
measurements, who checks, who corrects,who has responsibility?” saysCharalambides. “In the future we will put
more weight on the description of the
quality requirements for uploading data,cleaning, correcting measurements, anddefine a clear grid of responsibilities.”
Though false alarms are commonplacewhere large amounts of automated data are
involved, the frequency was a problem for
TUNNELLING JOURNAL 19
Defining A Plug-And-Play SystemITAtech was set up in 2011 in a bid to keep the industry up-to-date with
advances in materials, practice and technology and encourage speedier
take-up of ‘new’ products and systems. Unlike the International Tunnelling
and Underground Space Association’s (ITA’s) more academic committees, theITAtech Activity Groups (AGs) are made up of manufacturers, designers and
contractors with a remit to put guidance and standards together as swiftly
as possible in order to encourage adoption of newer technologies.
The Monitoring AG, headed up by Felix Amberg, president and owner of
Amberg Technologies, has already published one document ‘Guidelines on
Monitoring Frequencies in Urban Tunnelling’ in 2014, which sets out how
often hydro-geotechnical and structural parameters should be measured.
Now a Monitoring Sub-AG, headed up by Klaus Rabensteiner CEO of
Geodata, is working to produce guidance on information and
communication systems. The guidance, ‘Effective Data Management in
Tunnelling’, will define what a ‘plug and play’ system for all data on site
should look like.
The overarching aim of the guidance is to demonstrate the benefits that
a well thought-out communication and information system can bring to a
project in terms of safety, risk management and cost. It will tackle issues
such as how to write good specifications, how to choose between available
systems and make recommendations on exchange standards for data.
The paper aims to communicate what data management systems can dothrough a series of case studies. “We want to share experiences from a lot
of different projects, and from various viewpoints,” explains Rabensteiner.
“We have produced the paper in draft but it does not fully achieve this aim
in an appropriate way yet.”
Ideally, Rabensteiner would like case studies to illustrate success stories
and lessons learned, although finding people who are willing to reveal all
about their projects is tricky. Another challenge for Rabensteiner is finding
companies and individuals who are willing to invest time in developing the
guidelines.
The following firms are involved in the sub-AG: ITMsoil, Soldata,
Geodata, Amberg Technologies, Babendererde Engineers, Astrium Services,
Herrenknecht, VMT and Seli. ITAtech would welcome other companies,
particularly consultants, to join the group. Those interested should contact
7/18/2019 Tunnelling Journal Feb-Mar2015 Managing Monitoring Data
http://slidepdf.com/reader/full/tunnelling-journal-feb-mar2015-managing-monitoring-data 3/9
MONITORING
TUNNELLING JOURNAL 21
Cityringen initially. “It happened too often at
first which is why we added a first levelfunction which filtered out measurements
which we are sure to be incorrect. This doesallow for a number of measurements everyday which are false and these are captured
on a second level, where they are manuallyconfirmed or deactivated.”
The first-level data handling process,developed by CMT and SMT, sees automatic
checking using algorithms to recognise andfilter out the majority of incorrect
measurements, followed by manualverification of measurements by SMT, and
finally interpretation of the measurements byCMT.
“The automatic checking was something
we recognised as very essential to the
operation of the system,” says
Charalambides.” It was not described in thetechnical specifications but you either need
lots of people continuously looking atcomputers and finding out where the wrongmeasurements are or you need the system
itself to be able to recognise wheremeasurements are certainly wrong and clean
itself.“One of the challenges we had in
developing it was how to regulate it toremove most of the incorrect measurements,
while reducing the risk of removingmeasurements that could be correct andwould generate real alarms.”
The client was kept informed about thesystem’s architecture and how the cleaning
algorithms would work. “We developed it
with common knowledge and acceptance of
all the implicated parties,” saysCharalambides. “One of the fundamentalthings is that we don’t delete anything. Users
can select to see the ‘cleaned’ or all themeasurements.”
Kronos’ alarming system has providedCMT with early warnings several times, says
Charalambides. “On at least three occasionswe were able to mitigate risks when we
found out that loads on struts weredeveloping faster than expected,” he says.
“In one case we moved the position of amobile crane, in the second we moved astockpile of excavated materials and in the
third instance we placed an additional strutin order to maintain the excavation safe.
After those remedial actions, excavation
Figures 2 and 3:The upgrade of
London BridgeStation involvesdemolishingmasonry arches
which are currently
supporting thetracks to make wayfor a huge newconcourse. Arches
either side arebeing retained bybuttresses andmonitored closely
during the works.
7/18/2019 Tunnelling Journal Feb-Mar2015 Managing Monitoring Data
http://slidepdf.com/reader/full/tunnelling-journal-feb-mar2015-managing-monitoring-data 4/9
MONITORING
could continue. The early warnings allow usto mitigate problems before they become
significant.”Charalambides makes the point that all
data management systems must be bespoketo some degree. “I don’t think a plug-and-play system that covers everything exists,” he
says. “There are always local requirementsand needs. You need a good basic system
that can be easily adapted.”For example Denmark also has its own
format for recording and exchanginggeotechnical information, GeoGIS. Kronos
was set up to be compatible to AGS, awidely used format for recording and
exchanging geotechnical information. So aninterface to make Kronos compatible with
data in the GeoGIS format was required to
be included.Monitoring regimes will also vary betweenregions. On Cityringen the specifications
suggested moderate-to-high frequencymanual measurement in stations and some
parts of the tunnels, but this would not havebeen cost-effective. Says Charalambides:
“When we started planning how the
entire monitoring system would be set up,we realised that we would need an extensive
team to perform, verify and upload therequired measurements. In Northern Europe
this is not really an option – the cost ofpersonnel does not allow it. The only cost-
effective way was to introduce automation. ”In other parts of the world, manual
measurements could be a better solution.
Geoscope 7 at London BridgeThe overground station at London Bridge iscurrently undergoing a circa £750M
upgrade, courtesy of Costain, which willincrease the number of trains it can
accommodate from a maximum of 70 to 88an hour. At the heart of the project is a
massive new concourse which will allowaccess via escalators and lifts up to all the
station’s 15 platforms. At the moment, theplatforms are in two groups, each with itsown access.
London Bridge’s tracks are built on top of150-year old masonry arches. In order to
create the new underground space for the
concourse, the arches and tracks above themmust be demolished and a new structure and
tracks constructed. This is happening in ninephases to minimise disruption to the station.
Having won monitoring contracts for the
gigantic glass Shard building right next toLondon Bridge station, and on the Shard’s
baby brother The Place, Soldata completed ahat trick of wins when Costain appointed it
to work on the station redevelopment in2011. It is using its Geoscope 7 software,
launched commercially last year after fiveyears of development, to marshal and
compare multiple sources of data.Geoscope 7 is also being used on
Tottenham Court Road underground station
redevelopment in London, on the AlaskanWay viaduct in Seattle, and on metro projects
in Rennes, France, Riyadh, and Doha.Unlike its predecessors, Geoscope 7 canhandle much more than monitoring data,
says Soldata marketing manager AidanLaimbeer. “It’s a risk management tool whichenables you to integrate any database in a
timely manner and present the data in a waythat’s open, accessible and understandable.
The amount of databases you can have isphenomenal.”
Information related to compensationgrouting, TBM progress and weather
conditions, as well as monitoring data couldall be presented. “In some cases we are
using it as an observational method tool,”says Soldata technical manager MatthieuBourdon. “We can link into the pre-
excavation grouting contractor’s databasesand compare pressure and volume with
ground movement.”“The user interface is more graphical and
more intuitive than the previous version andit works with tablets,” says Alex Lawson,
duty operation engineer for Costain atLondon Bridge. “You can have any
combination of data you want very easily. Sofor example, you can overlay track settlement
with arch settlement to see if they arerelated.”Since the contract began, Costain has
chosen to direct more and more informationthrough Geoscope 7. “If somebody’s data is
good, but we don’t like their interface, we
put it on this,” says Lawson.
The instrumentation at London Bridgeincludes over 30 automatic total stations
(ATSs), electrolevels underneath the masonryarches, tilt meters on London Underground
escalators, inclinometers inside piles forretaining walls, strain gauges and
piezometers. There was also vibrationmonitoring earlier in the programme.
“The project is very dynamic,” says Soldataproject manager Nathalia Arevalo. “Because
they are demolishing two tracks at a time,we have to get in there and install theinstruments before the next phase of the
works starts.”In addition to Soldata and Costain,
geotechical engineers, surveyors, specialistcontractors, London Underground and
Network Rail can all see the informationrelevant to them through Geoscope 7. Each
has their own user rights for accessing the
database.With a project as complex as London
Bridge, there have been several instanceswhere ground and building movements have
required further investigation, such as whenpiling for a buttress wall to support
remaining arches is underway. At thesetimes, the ability to quickly compare and
overlay different information is invaluable,says Lawson.
“One of the really useful features ofGeoscope 7 is the layer management: you
can compare ten different sources of data,
and if you see something that you want toalert other people to, you can save that view
and send it to the relevant people,” saysLawson. “Overall, it’s so much more efficient
which means you have more time to spendon other tasks.”
Tight and bespoke at PaddingtonFor the excavation of the TBM tunnels underPaddington Station box for Crossrail, BFK
elected to use an in-house designedmonitoring system. “We didn’t want to domonitoring just for monitoring’s sake,” says
Harrison. “The system was scientifically
designed to meet our needs as thecontractor.”
One of the factors behind BFK’s decision to
design its own monitoring system was that ithad experienced data quality issues with
monitoring subcontractors. Harrison feelsstrongly that algorithms to remove rogue data
are not what’s needed here; a properlydesigned system should avoid erroneousreadings, and use advanced survey concepts
to take out the noise or undulations inmeasurements.
The challenge at Paddington was that
programme constraints meant thatCostain/Skanska JV had to construct the 24m-deep station box as the tunnels beneath –
eventually to be broken out – were still servingthe TBMs. Movements in the tunnels had to
be predicted before the contractor could
22 TUNNELLING JOURNAL
“This method stabilises the results,reducing system noise and iscalibrated specifically to follow theexpected slow trendingmovements during and after theperiod of excavation,”
7/18/2019 Tunnelling Journal Feb-Mar2015 Managing Monitoring Data
http://slidepdf.com/reader/full/tunnelling-journal-feb-mar2015-managing-monitoring-data 5/9
MONITORING
24 TUNNELLING JOURNAL
decide to take this approach, and themonitoring system had to check the actual
movements to ensure the stability of thetunnels and the safety of the operation.
The in-tunnel monitoring system wasmodelled virtually and checked using Star*net
software, which carries out least-squaresadjustments of survey networks. Least squares
adjustment is a mathematical procedurewhich looks at multiple measurements in a
network and finds the best-fit solution and it’ssomething Harrison has been applying since
2007. The monitoring network consisted ofthree automated total stations in each tunnel,
with prisms every five to six rings at sevenpositions round each ring. The virtual model
allowed BFK to check lines of site andinstrument positions among the ventilation
bagging, tracks, walkway and
other services to minimise theamount adjustment required once
the kit was installed on site.Harrison describes the system as
an ‘organic network’. By this hemeans that the network fixes
points outside the zone ofinfluence of the works and
partially fixes points within thezone of influence to the lastknown value, allowing those
points to be used as a control.“This method stabilises the
results, reducing system noise and
is calibrated specifically to followthe expected slow trendingmovements during and after the
period of excavation,” saysHarrison.
The results obtained frommonitoring during the excavationcorrelated closely with those
predicted during the design phase.And no filtering or smoothing of
the data was required, saysHarrison.
This was an efficient solution for
the excavation of the PaddingtonStation box, made possible by thefact it has in-house expertise.
However, contractors may nothave the resource to build bespokesystems, especially where large
projects and programmes requiremultiple data sources to be
managed at once.
Formula 1 comes to FarringdonArup and Atkins are employing a
technique honed in Formula 1 tohelp their engineers make sense of
monitoring information. Theconsultants have been workingwith analytics specialist Quantum
Black to develop something theycall Adaptive Instrumentation and
Monitoring (AIM).Having carried out a pilot study,
Arup proposed the use of AIM onCrossrail’s Farringdon and
Whitechapel Stations. Other metrodevelopers including MTR in Hong
Kong and LTA in Singapore arealso reported to be interested in
what AIM can do.“With many monitoringcontractors’ software packages,
the graphical interpretation is clearbut they don’t introduce
construction progress and trying to
Figure 4: Sample Daily Report Sheet from Paddington (Movement Time Plotsvs Construction Activity)
Figure 5: Predicted vs Actual Tunnel Movement at Paddington
7/18/2019 Tunnelling Journal Feb-Mar2015 Managing Monitoring Data
http://slidepdf.com/reader/full/tunnelling-journal-feb-mar2015-managing-monitoring-data 6/9
MONITORING
TUNNELLING JOURNAL 25
correlate it with the monitoring data isdifficult,” says Arup associate director MikeDevriendt. “Contractors were presenting
monitoring information to us in a ratherdisorganised way, and construction data was
not being represented alongside it. It was
taking our engineers as much time piecingtogether what construction event had causedthe movement as the time spent reviewing
the data and interpreting.”AIM presents ground and structural
monitoring results in a clear graphical waytogether with construction progress. But theclever bit is the analytics: looking for patterns
of data which can give early warnings or helpoptimise monitoring systems.
“If you have racing cars going round aFormula 1 circuit, you are trying to look at
data channels and spot problems with theengine or the tyre pressure, looking for trends
in the data,” says Devriendt. “Similarly withreviewing tunnelling-induced ground
movements, you need to spot trends whichare concerning and discern them fromanomalies in the data.”
The analytics in AIM can do three things:spot anomalies in the data and distinguish
between errors and concerning trends;continuously update mathematical models to
forecast an end result; and look at theinterdependence of points with respect to
space and time, and suggest where there maybe redundancy in the system.
“It has the potential to make monitoringinstrumentation design more efficient,” saysDevriendt.
For contractors, this could lead to morecost-effective procurement of monitoring
services. “For clients tendering monitoring
works, rather than opting for a lump sum
contract it may make sense to goremeasureable,” says Devriendt. ”Install a
robust amount of instrumentation then dialup or down the frequency of measurement.”
Setting the frequency would require
engineering judgement, considering whatconstruction activity was next and whatredundancy the analytics had identified.
”This could be one way to make savings,although such an approach needs to beagreed with third-party asset owners,” says
Devriendt. ”However, in speaking with manyasset owners in recent years, there is a
willingness to review these novel approachesif they offer greater visibility of data”
Interpreting monitoring and constructionprogress data is just one of numerous
potential applications for analytics in civilengineering. Others include processing data
gathered from the measurement trains whichsurvey railways or baggage handling systems.
No more middle man?What all these solutions have in common is
the ability to connect client, engineer andcontractor to the data more directly and more
effectively. The end result should be a moredynamic use of monitoring data to help
inform immediate and future decisions aboutdesign and sequencing.
Both BFK’s in-house approach and ArupAtkins QuantumBlack’s analytics solution
demonstrate contractors and designersattempting to take more ownership of howtheir monitoring data is served up. “Our
software has been designed by engineersinterpreting the data rather than monitoring
contractors, who are contracted to provide
the data,” says Devriendt.
The need to give the user more control issomething Soldata acknowledges too.
Bourdon expects that some organisations willchoose to buy Geoscope 7 without also
procuring Soldata’s services.
“It’s the first time that software gives thekeys to the client,” says Bourdon. “It’s a newstrategy. Until now, monitoring companieswanted to control the data. It was compulsory
to use a specialist contractor to manage thedata. Now you can employ people internally,
remanage the costs.”Mehdi Alhaddad, a PhD student at the
Cambridge Centre for Smart Infrastructure,reminds us of another strong force for change
in this area: generational differences.“Updating our current 'data interaction' tools
is a crucial task that our industry must takevery seriously, especially if we want to appeal
to the new generation of civil engineers whoare often disappointed when they comeacross our current tools,” says Alhaddad. For
him, tools such as AIM present data “in aform that is closer to what a modern brain is
trained to digest.”Those from Alhaddad’s Millennial
generation, aged between 20 and 34, havegrown up with mobile, smart technology and
– unlike some of their older counterparts –may not be able to work with columns ofdata listed in a spreadsheet. Of course, these
generational differences do not apply to every
individual but they do point to trends.It will be interesting to see what sort oftools the brains of Generation Z, those aged
20 and younger, will work best with. Expectsome exciting new developments in the not-
too-distant future.
Figure 6: Adaptive Instrumentation and Monitoring (AIM) application
7/18/2019 Tunnelling Journal Feb-Mar2015 Managing Monitoring Data
http://slidepdf.com/reader/full/tunnelling-journal-feb-mar2015-managing-monitoring-data 7/9
MONITORING
OVER THE LAST TWENTY YEARS Asia has
been home to some of the world’s largest andmost complex tunnelling projects. Many of
these have been delivered within challengingground conditions and ultra-competitive
markets. Whilst there have been commercial
and technical failures which have dominatedthe press there have also been many notable
successes. The region’s response to therequirements of the Joint Code of Practice
2004 has been laudable and in all Asiancountries formal risk management procedures
have been driven through by clients andconsultants and embraced by contractors.
Our ability to measure what we do is greaternow than ever before and as a result there has
been an explosion in the amount ofinformation which needs assimilating andcommunicating. This has raised a number of
challenges. The need to process and review all
this information puts a large strain onmanpower resources and as a result Engineersand geologists have become slaves to word
processors and spreadsheets. More time isoften spent handling information rather than
analysing it. Typically engineers are resourcefuland many develop their own systems to
manage this workload but this plethora ofpersonal systems limits the extent to whichdata can be communicated and collaborated.
Often projects and their data arecompartmentalised and run by different teams
each with differing focus and agenda. How
often have we been told “talk to Production”or “talk to Geotech” in response to a requestfor information? The goal must be to enable
Production to answer a geotech questionbecause they are themselves informed on
geotechnical issues.Maxwell Geosystems have been at the
forefront of a quiet revolution in Asia which
started in Hong Kong in 1997 with theStrategic Sewage Disposal Scheme. This was
the first project to implement a project wideinformation system to collect as much
structured data as possible about all aspects ofthe construction process. The initiative was
born out of client and engineer frustration atthe inconsistency in reporting across contract
teams on the same large project. The widelypublicised contractual difficulties focussedattention on data and how it would be
managed given that future arbitration wasinevitable. This buy in by the project top brass
gave the initiative impetus and by 1998 thesystem was managing all data on the three
replacement contracts and producingstandardised reports to government. This was
not without some difficulty. In 1997 theinternet was not so reliable and the system
had to rely on daily merging of multiple sitesdata into the central system. Whilst clunky thiswas effective and by the end of the project
every 15 minutes of time, every hole drilled,support installed and geology logged had
been loaded into one system which
comfortably sat on one CD. Accompanied by a
database of over twenty thousand fullyindexed photographs readily accessible inpaper and digital form the system was a key
component in the client’s successful arbitrationcase.
Overcoming inertiaSystems such as these always fight againstinertia to be established. We are told that data
is power and it is true that individuals seeownership of data as important and a way of
achieving competitive advantage. We all striveto have “better data” than the next guy.
However, once in place all but the moststubborn become advocates particularly if theycan get to their information and the
information of others quickly and easily andsafe in the knowledge that it has been audited
for quality and correctness.
The usefulness of the systems become most
apparent during the planning for the highlysensitive stage 2 around Hong Kong Island.The detailed data on production, in particular
the effect on poor ground and water inflowcombined with statistics for drilling and
grouting and the observed sensitivity ofoverlying deposits were instrumental in the
delivery of the project through feasibility todetailed design and construction. With greater
certainty on required quantities and risks theengineer was able to go to tender with a farmore equitable contract and a much lower risk
solution involving drill and blast. The tunnels
were completed in 2014 with no repeat of thecontractual or settlement issues which plaguedphase 1.
Formalised dataThe benefits of formalised data management
TUNNELLING JOURNAL 27
Figure 1: An early TDMS implementation on Hong Kong West Drainage Tunnel
Dr Angus Maxwell and Dr Andrew Ridley of the
GEOMAX Partnership describe how automated
risk management has been achieved using
integrated systems on some of Asia’s largest
tunnel infrastructure projects.
MISSIONPOSSIBLE
7/18/2019 Tunnelling Journal Feb-Mar2015 Managing Monitoring Data
http://slidepdf.com/reader/full/tunnelling-journal-feb-mar2015-managing-monitoring-data 8/9
MONITORING
28 TUNNELLING JOURNAL
have been embraced by the GeotechnicalEngineering Office and the requirements for
Tunnel Data Management Systems have nowbeen promulgated gradually through allgovernment departments. Initially the systems
were driven through conventional Engineer’sdesign contracts using standard ICE terms.
They were placed under the consultant’s
contract with the intention they be deliveredby the resident site staff and populated by theinspectors and engineers. Later this was
passed down to the main contractor’scontract. This led to some difficulty gaining
buy in since the systems were initially seen as anoose by which the Contractor could hangthemselves. As a result only the minimum
contractually obligated data was entered andstrictly to satisfy the contract rather than as an
integral part of the contractors daily methods.Over the past eight years of implementation
contractors have come to realise that thesesystems can be used to their benefit whilst also
satisfying the contractor’s requirements. Thesystems recently installed on the Klang Valley
Metro in Kuala Lumpur have replaced manualmethods of producing AAA response reportswith live reports generated on demand from a
secure blogging facility. Each alarm starts athread and the organised responses to the
thread follow the agreed procedure. Thecontractor saves time, the communication and
reaction time is quicker, engineers spend moretime on the solutions than on the reports and
we don’t cut down trees.Since the much publicised Nicol Highway
failure in 2004 the Land Transport Authority inSingapore have removed all responsibility forprotective instrumentation and monitoring
from the main contractor and put it under thegovernment body. Whilst this ensured
impartiality, the MTRC in Hong Kong adopted
a different approach driven by the desire toleave monitoring with the party best able tointerpret and respond to it. The MTRC put in
place a party whose responsibility it was toverify the data by independent measurement
and to publish the data to all parties so that allinformation could be seen. This was the
Independent Monitoring Consultant.
The Regional Express Line (XRL) monitoredover 30000 instruments along its 25km lengthand the IMC check measured approximately
15% of the contractor’s values and loaded alldata IMC and main contractor into a centralisedatabase. The physical checks were particularly
effective in raising the confidence in the dataquality and delivering information quickly to
the contractor but were only truly effective in adesign sense when parties were encouraged
to regularly provide groundinvestigation, design prediction and
construction progress data so thatcause, effect and expectation could
be monitored. This was particularlyapparent for the 400m x 250m x30m deep station excavation in
West Kowloon. Whilst successful,the motivation for contractors to
engage was uncertain still seeingthis as a client’s risk reduction tool
and an effective one at that with theIMC contract being a contributory
factor to a reduction in negotiatedproject insurance.
While all this was unfoldingAustralia were promoting the use of
Alliance forms of contracting onProjects such as the Inner NorthernBusway, Gateway Motorway and
Airport Link in Brisbane and theBallina Bypass in New South Wales
and the systems blossomed in this
hats off approach. Early systems weredelivered with engagement from designers toenable them to get feedback on their designs
in real time. The designers designed what theywanted the systems to do and the system
consultant made it happen. On the rapidlychanging sites the system became the focus
for the daily permit to tunnel risk assessments.Such collaborative risk management was
the key motivator behind Singapore Power’sdecision to implement their IDMS system in
2013. With two projects and 16 simultaneousTBM drives under very sensitive infrastructurethis is one of the largest tunnelling projects in
the world. Previous cable tunnel projectswhich had encountered significant settlements
during the construction stage triggered theneed for comprehensive instrumentation data
management systems. It was hoped thiswould allow all parties (client, consultants &
contractors) to access the basis of design data,
Figure 2: West Kowloon Station linking progress monitoring design andconstruction data
Figure 3: Keeping it simple.Singapore Power Cable Tunnels –16 consecutive TBM drives
monitored in one platform
Figure 4: No CAD bottleneck. Deep shafts andtunnel connections are best explained with
real time BIM programmatic constructions
7/18/2019 Tunnelling Journal Feb-Mar2015 Managing Monitoring Data
http://slidepdf.com/reader/full/tunnelling-journal-feb-mar2015-managing-monitoring-data 9/9
MONITORING
real-time and manual monitoring data as wellas the construction activities carried out at site
through a common platform that provideinteractive functions to generate graphical
plots linking the monitoring data and theconstruction activities. Based on the cause and
effect information, the system will allow the
project team to predict, forecast and use thesystem as the risk management tool for look-
ahead construction activities.In common with Singapore government
projects the instrumentation contracts weredirectly let under the owner and supervised by
the QPS. Centralised collection of these resultsand site observations from the QPS teams
would be straight forward but the collection oftunnelling information would need the
cooperation of the contractors.The Client negotiated with all six contractors
on the project to request them to contribute to
a centralised system for the management of
risk as part of the partnering process. The costof the system was equally shared by all sevenparties including client and contractors. Whilst
still seen by the contractors as an owner’sinitiative, the requirement to have a financial
stake motivated contractors to use the systemfor their benefit.
The system scope and delivery was managedby a steering committee with representativesfrom all the financial contributors. In addition
to providing the system the IDMS consultantalso provided staff to maintain the data and
provide a line of communication for users. The
team was managed by an experiencedinstrumentation and geotechnical engineer.The critical key to success was the presence of
director level drivers within all the teams whodemanded the use of the system across the
projects and weaned the staff away from theirspreadsheet and word zones of comfort into anew way of operating using open booked data
and effective media sharing andcommunication methods.
The systems now enable all the engineers toaccess any data and draw any map, section
graph or table for instruments TBM orproduction parameters ground investigation
and other digitised data sources such ashazards. The system embeds contractors
design predictions as they change through aproject enabling all parties to establish theexpectations of the works and identify early
areas of concern and trends. All of theseanalyses can be designed into custom canvases
where each user can tell their own story.
Allowing engineeringSystems will never replace engineers but they
will increase the proportion of time engineersspend doing engineering. They also enable
relationships to be observed which wouldotherwise be missed and this is the realbenefit. Above all engineers can now do in
real time the type of analysis that was normallyreserved for several weeks of forensic
investigation after a problem had occurred.
Figure 5 a to c. Engineers need the ability to undertake the kind of analysisnormally reserved for forensic investigations of failure….before the failure.