turkish electricity market - naruc

21
Recent Regulatory Developments in Turkish Electricity Market Fatih Kölmek, MSc. Energy Expert / EMRA 5 April 2012, Kiev/Ukraine

Upload: others

Post on 27-Oct-2021

15 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TURKISH ELECTRICITY MARKET - NARUC

Recent Regulatory

Developments in Turkish

Electricity Market

Fatih Kölmek, MSc.

Energy Expert / EMRA

5 April 2012, Kiev/Ukraine

Page 2: TURKISH ELECTRICITY MARKET - NARUC

Outline

EMRA

Electiricity Market Reform

Market Structure and Figures

Targets in Electricity Supply

Interconnections, financial derivatives, renewable energy

New Electricity Market Law Draft

Wrap – Up

2

Page 3: TURKISH ELECTRICITY MARKET - NARUC

Sole regulator of Electricity, Gas, Petroleum

and LPG markets,

Autonomous authority

Monitors, supervises and audits markets &

market players

Approves tariffs

Main objectives are to provide;

• Financially viable, stable and competitive energy

market

• Sustainable energy at good quality and low cost,

in a reliable and environment friendly manner

Energy Market Regulatory Authority (EMRA)

3

Page 4: TURKISH ELECTRICITY MARKET - NARUC

1984 1994 2001 2006 1997 2003 2004

Law No: 3096

BOT Law (No: 3996)

BO Law (No :4283)

Electricity Market Law (No:4628)

Financial Settlement

Communique

Strategy Document

T-BSR

Start: T-BSR Application

TEK

TEAS TEDAS

EMRA

EUAS

TEIAS

TETAS

2009

Start: F-BSR Application

2011

Advanced Day Ahead Market,

Collateral Mechanism

2010

Start of 52 small HEPPs

Privatization

2013

100 % Fully Liberalization

2008

Start of Disco Privatizations

Private sector

is allowed to

operate in

generation,

transmission and distribution

REL Amendment (No: 6094)

Electricity Market Reform

2005

Renewable Energy Law (REL)

(No:5346)

4

Page 5: TURKISH ELECTRICITY MARKET - NARUC

TETAŞ

Wholesale Companies

(Private)

TEİAŞ (Transmission,

Market & System

Operation)

Disribution & Retail Sale Companies

Captive Customers

Eligible Customers

Import Import Export

Balancing and Settlement Mechanism IPPs

Autoproducers

EÜAŞ

BO-BOT-TOR

Market Structure

Generators Wholesalers System/Market

Operation

Distributors/

Retailers Consumers

• Market of bilateral contracts complemented by a power pool • 25 MWh/year eligibility threshold for 2012 (market opening: 78 %) • Retail unbundling in 2013

Page 6: TURKISH ELECTRICITY MARKET - NARUC

Day Ahead Market

Balancing Power Market

Hourly Settlement

Demand Side

Participation

Enables Market Splitting

Final Phase

Balancing

Mechanism

Monthly 3

Periods

Settlement

First Phase

Day Ahead Planning

Balancing Power

Market

Hourly Settlement

Second Phase

Aug 2006 – Nov 2009 Dec 2009 – Dec 2011 Dec 2011 – …..

Day Ahead Market provides;

Opportunity for the market participants to purchase/sell energy for the following

day in addition to their bilateral agreements

Balanced system to the system operator for the following day

Balancing Power Market is used for real-time balancing of demand and supply

Balancing&Settlement Mechanism

6

Page 7: TURKISH ELECTRICITY MARKET - NARUC

Market Figures

• Installed Capacity 53.6 GW

Renewable 36 %

Thermal 64 %

• Consumption (2011) 229.3 TWh

• Generation (2011) 228.4 TWh

Renewable 26 %

Thermal 74 %

• Peak Load (2011) 36.122 MW 34179.1, 64% 114.2, 0%

17359.3, 33%

1792.7, 3% 117.4, 0%

Installed Capacity (as of March 2012)

Thermal Geothermal Hydro Wind Other Renew.

0.0

5000.0

10000.0

15000.0

20000.0

25000.0

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011

RES-E Capacity (MW)

13,829

14,553

15,831

17,137

10000.0

11000.0

12000.0

13000.0

14000.0

15000.0

16000.0

17000.0

18000.0

2008 2009 2010 2011

Hydro Capacity (MW)

364

792

1,320

1,729

0.0

200.0

400.0

600.0

800.0

1000.0

1200.0

1400.0

1600.0

1800.0

2000.0

2008 2009 2010 2011

Wind Capacity (MW)

Page 8: TURKISH ELECTRICITY MARKET - NARUC

Ensure security of supply

Keep the costs & prices at a

level suitable to support

economical growth

Decrease the environmental

effects to the lowest

possible level

Exploitation of known lignite

and charcoal reserves

Decreasing share of gas in

generation mix

Introduction of nuclear energy

Achieving 30% share for

renewables in generation mix

Full utilization of

economically and

technically feasible

hydroelectric potential

Reaching 20.000 MW wind

capacity

Commissioning all of

geothermal potential

Utilization of solar and

other renewable sources

8

2023 Targets in Electricity Supply

Page 9: TURKISH ELECTRICITY MARKET - NARUC

BULGARIA 145 km 1510 MVA 136 km 995 MVA

GREECE 260 km 1510 MVA

SYRIA 124 km 1005 MVA

IRAN 73 km 204 MWA 100 km 581 MVA

NAKHCHIVAN 87 km 2x132 MVA

GEORGIA 28 km 287 MVA

ARMENIA 80,7 km 574 MVA

400 kV Exist 220 kV Exist 154 kV Exist

IRAQ 42 km 408 MVA

GREECE

GEORGIA 400 kV DC connection with 650 MW capacity (to be completed in 2012,

possible expansion to 1.000 MW) is under construction

Interconnections

ENTSO-E

9

The parallel operation with ENTSO-E has increased the quality and security electricity supply

through series of required improevements in the system, and is foreseen to eventually provide

full-access to the European Electricity Market.

Page 10: TURKISH ELECTRICITY MARKET - NARUC

Process Date

Isolated test at Maximum Load

Conditions

11-25 January 2010

Has been successfully completed.

Isolated test for Minimum Load

Conditions

22 March – 05 April 2010

Has been successfully completed.

Trial Parallel Operation • Stabilization Period (No exchange)

18 September 2010

• Non-commercial exchange

21 February 2011

• Commercial exchange (Limited)

1 June 2011

Planned to be completed by fall 2012

TIME TABLE

10

ENTSO-E Interconnection

Page 11: TURKISH ELECTRICITY MARKET - NARUC

Objectives:

Trading future electricity prices

Electricity price risk management

Reflection of expectations in future electricity prices

A benchmark for electricity prices

Contract Specifications :

Underlying Asset: Arithmetic average of the Day Ahead Market Prices announced by TSO

for each hour in the contract month.

Price Quotation: 1 MWh of electricity shall be quoted significant to two decimals.

Daily Price Limit: ± 10% of base price.

Contract Months: All calendar months.

Settlement Method: Cash settlement.

Last Settlement Price: Arithmetic average of the Day Ahead Market Prices announced by

TSO for each hour in the contract month.

Position Limits: Absolute position limit is 2000 and percentage position limit is 10%.

Initial Margin: TRY 12,000

Maintenance Margin: 75% of the initial margin.

Base Load Electricity Futures Contracts launched on

September 26, 2011 in Turkish Derivatives Exchange

Financial Derivatives

11

Page 12: TURKISH ELECTRICITY MARKET - NARUC

Incentive Scope Licensing fee Only 1% of the regular licensing fee is paid.

Exemption from the annual license fee for first 8 years Connection to the grid Priority by TEIAS and the distribution companies

% 85 reduction in system usage fees for 5 years (all plants to be commissioned prior to 31/12/2015 – extension possible)

Company establishment and licensing exemption

For the generators with a max capacity of 500 kW

Purchase obligation All of the suppliers have to procure renewable power in proportion with their share in total supply

Feed-in tariff For 10 years (all plants to be commissioned prior to 31/12/2015 – extension possible)

Different prices for each resource (also for domestically manufactured equipments)

Fees on land-use for PPs to be commissioned prior to 31/12/2015 (extension possible)

If the property in use is in possession of the Treasury, for first 10 years of operation,

85% deduction is applied to fees related to rent, right of access, and usage

permission.

85% deduction is applied to fees related to transporation and transmission

infrastructure invetments.

Exemption from the special fees like contribution to the development of the

woodland villages.

Free usage of state-owned estates located within the reservoir of HPPs holding a RES

certificate. 12

Renewable Incentives

Page 13: TURKISH ELECTRICITY MARKET - NARUC

Application

Project Assessment

Project Approval

Granting License

Required documents are published on EMRA’s webpage. All applications must include an initial collateral of “10.000 TRY x capacity MW”. Project assesment and auction (based on fee/kWh in case of multiple applications) for hydro by DSİ before license application

When the application phase is completed, the projects is assessed for approval: Conditions for grid connection are determined by DSO and/or

TSO and approved by EMRA Technical assessment of the project is done by YEGM for wind

solar. If there are multiple applications for the same site and/or

connection point (exceeding total available capacity) then TSO makes auctions (based on fee/kWh for wind and solar) and winning bidders are licensed.

If the assessment phase is finalized positively, then the projects is approved and some obligations are determined for being licensed: • Environmental impact assessment (EIA) • Contract with TSO if a tender was made • Increasing the amount of initial collateral (details on EMRA

webpage) • Required amendments in the main status of the company • Capital increase for the company (to 20 % of the total

investment for all projects that have been approved) (obligations must be fullfilled within 90 days. If a comprehensive EIA

is required then 300 days apply for EIA only)

If the obligations are fullfilled then the project is licensed 13

RES-E Licensing Procedure

Page 14: TURKISH ELECTRICITY MARKET - NARUC

Prices Applicable (USD ¢/kWh)*

Plant Type Schedule I ** Schedule II *** Total

a. Hydro 7,3 2,3 9,6

b. Wind 7,3 3,7 11

c. Geothermal 10,5 - 10,5

d. Biomass (including landfill gas) 13,3 - 13,3

e. Solar 13,3 6,7 20

* Before Law No: 6094, feed-in tariff was 5 - 5,5 €¢/kWh for all of the renewables (Law No:5346) ** 10 years for plants to be commissioned until 31/12/2015 *** Additional Incentive for Domestic Production - 5 years for plants to be commissioned until 31/12/2015

14

Renewable Feed-in-Tariffs

Page 15: TURKISH ELECTRICITY MARKET - NARUC

New Renewable Energy Support Mechanism (RESUM) is in

operation since 1 Dec. 2011.

Potential beneficiaries apply until 31 October EMRA to be listed in the RESUM

portfolio for the next year.

Mechanism starts in 1st calendar day (exc. 2011) of the next year and lasts for 1 year.

So, beneficiaries cannot leave/enter the mechanism until next year.

Beneficiaries are paid based on the unit prices indicated in Schedule I + applicable

portion of Schedule II.

Financial settlements are done in invoice periods (monthly) by Market Financial

Settlement Center (MFSC - market operator). MFSC calculates whole cost of the

RESUM portfolio and reflects this cost to the invoices of load serving suppliers in

proportion with their share in total consumption. Thus, all consumers goes GREEN!

28 generators were in RESUM for Dec. 2011. This number increased to 78 in 2012

implementation.

New RES-E Support Mechanism

15

Page 16: TURKISH ELECTRICITY MARKET - NARUC

RES-E generators up to 500 kW capacity, micro-cogenerators and

high-efficient cogenerators are exempt from licensing

EMRA has issued secondary legislation towards proper implementation

of the mechanism.

Distributed generation is encouraged towards better utilization of the

sources.

RES-E generators are integrated to RESUM portfolio and benefit from

FITs based on resource type.

Licensing Exemption

16

Page 17: TURKISH ELECTRICITY MARKET - NARUC

Auctions for intersecting (site or connection point) wind energy

applications have been completed. Fast wind penetration is

expected in the upcoming years.

Solar grid connection capacity was limited to 600 MW until 2014 by

law. Accordingly, capacities were announced on a substation basis.

Opening of applications is underway.

New license applications of wind or solar energy are required to

submit standardized measurement data

Data sets have to cover at least 1-year

Wind & Solar Projects

17

Page 18: TURKISH ELECTRICITY MARKET - NARUC

New law is expected to make siginificant changes:

Combining autoproduction and generation under a common

generation license

Issuance of a temporary license for generation that will cover the

pre-consruction period (siting, required permits, etc.)

Authorization of EMRA to extend the scope of licencing

exemption (e.g. increasing RES-E limit up to 1 MW from its

current level of 0.5 MW)

Unbundling of market and system operation activities carried out

by TSO and establishing an independent market operator

New Electricity Market Law Draft

18

Page 19: TURKISH ELECTRICITY MARKET - NARUC

New law is expected to make siginificant changes (cont):

Combining retail and whole sale activities under a supplier

license

Opening import/export to generators (also to retailers via the

supplier license)

Retail unbundling is stressed and supplier-of-last-resort is

defined

Price equalization mechanism (i.e. uniform retail price) will end

by 2016.

New Electricity Market Law Draft

19

Page 20: TURKISH ELECTRICITY MARKET - NARUC

Turkish electricity market is developing fast in terms of both size and

liberalization

Investors are very eager to enter the market as confirmed by the

developments in the installed capacity

Market structure is deepening with new mechanisms

Utilization of domestic sources, especially renewables, is a strategic

goal for energy supply in many aspects

New Electricity Market Law will make significant changes in the

market mechanism

20

Wrap - Up

Page 21: TURKISH ELECTRICITY MARKET - NARUC

Fatih Kölmek, MSc.

Energy Expert

Energy Market Regulatory Authority (EMRA)

Thank you for your attention.

E-mail : [email protected]

Tel : +90 312 201 46 20

Web : www.epdk.org.tr

Address : Muhsin Yazıcıoğlu Caddesi No:51/C

06530 Yüzüncüyıl, Ankara, Turkey

21