Tutorial 2 FORECASTING
OPERATIONS MANAGEMENT
![Page 2: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/2.jpg)
What is Forecasting?
► Process of predicting a future event
► Underlying basis of all business decisions
► Production► Inventory► Personnel► Facilities
??
![Page 3: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/3.jpg)
1. Short-range forecast► Up to 1 year, generally less than 3 months► Purchasing, job scheduling, workforce levels,
job assignments, production levels
2. Medium-range forecast► 3 months to 3 years► Sales and production planning, budgeting
3. Long-range forecast► 3+ years► New product planning, facility location,
research and development
Forecasting Time Horizons
![Page 4: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/4.jpg)
Distinguishing Differences
1. Medium/long range forecasts deal with more comprehensive issues and support management decisions regarding planning and products, plants and processes
2. Short-term forecasting usually employs different methodologies than longer-term forecasting
3. Short-term forecasts tend to be more accurate than longer-term forecasts
![Page 5: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/5.jpg)
Influence of Product Life Cycle
► Introduction and growth require longer forecasts than maturity and decline
► As product passes through life cycle, forecasts are useful in projecting
► Staffing levels► Inventory levels► Factory capacity
Introduction – Growth – Maturity – Decline
![Page 6: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/6.jpg)
Product Life Cycle
Best period to increase market share
R&D engineering is critical
Practical to change price or quality image
Strengthen niche
Poor time to change image, price, or quality
Competitive costs become criticalDefend market position
Cost control critical
Introduction Growth Maturity Decline
Com
pany
Str
ateg
y/Is
sues
Figure 2.5
Internet search engines
Sales
Drive-through
restaurantsDVDs
Analog TVs
Boeing 787
Electric vehicles
iPods
3-D game players
3D printers
Xbox 360
![Page 7: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/7.jpg)
Types of Forecasts
1. Economic forecasts► Address business cycle – inflation rate, money
supply, housing starts, etc.
2. Technological forecasts► Predict rate of technological progress► Impacts development of new products
3. Demand forecasts► Predict sales of existing products and services
![Page 8: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/8.jpg)
Forecasting Approaches
► Used when situation is vague and little data exist
► New products► New technology
► Involves intuition, experience► e.g., forecasting sales on
Internet
Qualitative Methods
![Page 9: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/9.jpg)
Forecasting Approaches
► Used when situation is ‘stable’ and historical data exist
► Existing products► Current technology
► Involves mathematical techniques
► e.g., forecasting sales of color televisions
Quantitative Methods
![Page 10: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/10.jpg)
Demand Management
A
B(4) C(2)
D(2) E(1) D(3) F(2)
Dependent Demand:Raw Materials, Component parts,Sub-assemblies, etc.
Independent Demand:Finished Goods
15-10
![Page 11: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/11.jpg)
Components of Demand
Average demand for a period of time
TrendSeasonal elementCyclical elementsRandom variationAutocorrelation
15-11
![Page 12: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/12.jpg)
Finding Components of Demand
1 2 3 4
x
x xx
xx
x xx
xx x x x
xxxxxx x x
xx
x x xx
xx
xx
x
xx
xx
xx
xx
xx
xx
x
x
Year
Sale
s
Seasonal variation
LinearTrend
15-12
![Page 13: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/13.jpg)
Types of Forecasts
Qualitative (Judgmental)
Quantitative Time Series Analysis Causal Relationships Simulation
15-13
![Page 14: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/14.jpg)
Qualitative Methods
Grass Roots
Market Research
Panel Consensus
Executive Judgment
Historical analogy
Delphi Method
QualitativeMethods
15-14
![Page 15: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/15.jpg)
Delphi Method
l. Choose the experts to participate representing a variety of knowledgeable people in different areas
2. Through a questionnaire (or E-mail), obtain forecasts (and any premises or qualifications for the forecasts) from all participants
3. Summarize the results and redistribute them to the participants along with appropriate new questions
4. Summarize again, refining forecasts and conditions, and again develop new questions
5. Repeat Step 4 as necessary and distribute the final results to all participants
15-15
![Page 16: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/16.jpg)
Time Series Analysis
Time series forecasting models try to predict the future based on past data
You can pick models based on:1. Time horizon to forecast2. Data availability3. Accuracy required4. Size of forecasting budget5. Availability of qualified personnel
15-16
![Page 17: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/17.jpg)
► MA is a series of arithmetic means ► Used if little or no trend► Used often for smoothing
► Provides overall impression of data over time
Moving Average Method
![Page 18: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/18.jpg)
Simple Moving Average Formula
F = A + A + A +...+Ant
t-1 t-2 t-3 t-n
The simple moving average model assumes an average is a good estimator of future behavior
The formula for the simple moving average is:
Ft = Forecast for the coming period N = Number of periods to be averagedA t-1 = Actual occurrence in the past period for up to “n”
periods
15-18
![Page 19: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/19.jpg)
Moving Average Example
MONTH ACTUAL SHED SALES 3-MONTH MOVING AVERAGEJanuary 10
February 12
March 13
April 16
May 19
June 23
July 26
August 30
September 28
October 18
November 16
December 14
(10 + 12 + 13)/3 = 11 2/3
(12 + 13 + 16)/3 = 13 2/3
(13 + 16 + 19)/3 = 16(16 + 19 + 23)/3 = 19 1/3
(19 + 23 + 26)/3 = 22 2/3
(23 + 26 + 30)/3 = 26 1/3
(29 + 30 + 28)/3 = 28
(30 + 28 + 18)/3 = 25 1/3
(28 + 18 + 16)/3 = 20 2/3
101213
![Page 20: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/20.jpg)
Simple Moving Average Problem (1)
Week Demand1 6502 6783 7204 7855 8596 9207 8508 7589 892
10 92011 78912 844
F = A + A + A +...+Ant
t-1 t-2 t-3 t-n
Question: What are the 3-week and 6-week moving average forecasts for demand?
Assume you only have 3 weeks and 6 weeks of actual demand data for the respective forecasts
15-20
![Page 21: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/21.jpg)
Week Demand 3-Week 6-Week1 6502 6783 7204 785 682.675 859 727.676 920 788.007 850 854.67 768.678 758 876.33 802.009 892 842.67 815.33
10 920 833.33 844.0011 789 856.67 866.5012 844 867.00 854.83
F4=(650+678+720)/3
=682.67F7=(650+678+720 +785+859+920)/6
=768.67
Calculating the moving averages gives us:
©The McGraw-Hill Companies, Inc., 2004
15-21
![Page 22: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/22.jpg)
500550600650700750800850900950
1 2 3 4 5 6 7 8 9 10 11 12
Dem
and
Week
De
Plotting the moving averages and comparing them shows how the lines smooth out to reveal the overall upward trend in this example
Note how the 3-Week is smoother than the Demand, and 6-Week is even smoother
15-22
![Page 23: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/23.jpg)
Simple Moving Average Problem (2) Data
Week Demand1 8202 7753 6804 6555 6206 6007 575
Question: What is the 3 week moving average forecast for this data?
Assume you only have 3 weeks and 5 weeks of actual demand data for the respective forecasts
15-23
![Page 24: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/24.jpg)
Simple Moving Average Problem (2) Solution
Week Demand 3-Week 5-Week1 8202 7753 6804 655 758.335 620 703.336 600 651.67 710.007 575 625.00 666.00
F4=(820+775+680)/3
=758.33F6=(820+775+680 +655+620)/5 =710.00
15-24
![Page 25: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/25.jpg)
► Increasing n smooths the forecast but makes it less sensitive to changes
► Does not forecast trends well► Requires extensive historical data
Potential Problems With Moving Average
![Page 26: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/26.jpg)
► Used when some trend might be present ► Older data usually less important
► Weights based on experience and intuition
Weighted Moving Average
Weighted moving average
![Page 27: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/27.jpg)
Weighted Moving Average
MONTH ACTUAL SHED SALES 3-MONTH WEIGHTED MOVING AVERAGEJanuary 10
February 12
March 13
April 16
May 19
June 23
July 26
August 30
September 28
October 18
November 16
December 14
WEIGHTS APPLIED PERIOD3 Last month
2 Two months ago
1 Three months ago
6 Sum of the weights
Forecast for this month =
3 x Sales last mo. + 2 x Sales 2 mos. ago + 1 x Sales 3 mos. ago
Sum of the weights
[(3 x 13) + (2 x 12) + (10)]/6 = 12 1/6
101213
![Page 28: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/28.jpg)
Weighted Moving Average
MONTH ACTUAL SHED SALES 3-MONTH WEIGHTED MOVING AVERAGEJanuary 10
February 12
March 13
April 16
May 19
June 23
July 26
August 30
September 28
October 18
November 16
December 14
[(3 x 13) + (2 x 12) + (10)]/6 = 12 1/6
101213
[(3 x 16) + (2 x 13) + (12)]/6 = 14 1/3
[(3 x 19) + (2 x 16) + (13)]/6 = 17
[(3 x 23) + (2 x 19) + (16)]/6 = 20 1/2
[(3 x 26) + (2 x 23) + (19)]/6 = 23 5/6
[(3 x 30) + (2 x 26) + (23)]/6 = 27 1/2
[(3 x 28) + (2 x 30) + (26)]/6 = 28 1/3
[(3 x 18) + (2 x 28) + (30)]/6 = 23 1/3
[(3 x 16) + (2 x 18) + (28)]/6 = 18 2/3
![Page 29: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/29.jpg)
Weighted Moving Average Formula
F = w A + w A + w A +...+w At 1 t-1 2 t-2 3 t-3 n t-n
w = 1ii=1
n
While the moving average formula implies an equal weight being placed on each value that is being averaged, the weighted moving average permits an unequal weighting on prior time periods
wt = weight given to time period “t” occurrence (weights must add to one)
The formula for the moving average is:
15-29
![Page 30: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/30.jpg)
Weighted Moving Average Problem (1) Data
Weights: t-1 .5t-2 .3t-3 .2
Week Demand1 6502 6783 7204
Question: Given the weekly demand and weights, what is the forecast for the 4th period or Week 4?
Note that the weights place more emphasis on the most recent data, that is time period “t-1”
15-30
![Page 31: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/31.jpg)
Weighted Moving Average Problem (1) Solution
Week Demand Forecast1 6502 6783 7204 693.4
F4 = 0.5(720)+0.3(678)+0.2(650)=693.4
15-31
![Page 32: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/32.jpg)
Weighted Moving Average Problem (2) Data
Weights: t-1 .7t-2 .2t-3 .1
Week Demand1 8202 7753 6804 655
Question: Given the weekly demand information and weights, what is the weighted moving average forecast of the 5th period or week?
15-32
![Page 33: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/33.jpg)
Weighted Moving Average Problem (2) Solution
Week Demand Forecast1 8202 7753 6804 6555 672
F5 = (0.1)(755)+(0.2)(680)+(0.7)(655)= 672
15-33
![Page 34: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/34.jpg)
Exponential Smoothing Model
Premise: The most recent observations might have the highest predictive value
Therefore, we should give more weight to the more recent time periods when forecasting
Ft = Ft-1 + a(At-1 - Ft-1)
constant smoothing Alphaperiod epast t tim in the occurance ActualA
period past time 1in alueForecast vFperiod t timecoming for the lueForcast vaF
:Where
1-t
1-t
t
a
15-34
![Page 35: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/35.jpg)
Exponential Smoothing Problem (1) Data
Week Demand1 8202 7753 6804 6555 7506 8027 7988 6899 775
10
Question: Given the weekly demand data, what are the exponential smoothing forecasts for periods 2-10 using a=0.10 and a=0.60?
Assume F1=D1
15-35
![Page 36: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/36.jpg)
Week Demand 0.1 0.61 820 820.00 820.002 775 820.00 820.003 680 815.50 793.004 655 801.95 725.205 750 787.26 683.086 802 783.53 723.237 798 785.38 770.498 689 786.64 787.009 775 776.88 728.20
10 776.69 756.28
Answer: The respective alphas columns denote the forecast values. Note that you can only forecast one time period into the future.
15-36
![Page 37: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/37.jpg)
Exponential Smoothing Problem (1) Plotting
500550600650700750800850
1 2 3 4 5 6 7 8 9 10
Dem
and
Week
Demand
0.1
0.6
Note how that the smaller alpha results in a smoother line in this example
15-37
![Page 38: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/38.jpg)
Exponential Smoothing Problem (2) Data
Question: What are the exponential smoothing forecasts for periods 2-5 using a =0.5?
Assume F1=D1
Week Demand1 8202 7753 6804 6555
15-38
![Page 39: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/39.jpg)
Exponential Smoothing Problem (2) Solution
Week Demand 0.51 820 820.002 775 820.003 680 797.504 655 738.755 696.88
F1=820+(0.5)(820-820)=820 F3=820+(0.5)(775-820)=797.75
15-39
![Page 40: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/40.jpg)
The MAD Statistic to Determine Forecasting Error
MAD = A - F
n
t tt=1
n
1 MAD 0.8 standard deviation1 standard deviation 1.25 MAD
The ideal MAD is zero which would mean there is no forecasting error
The larger the MAD, the less the accurate the resulting model
15-40
![Page 41: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/41.jpg)
MAD Problem Data
Month Sales Forecast1 220 n/a2 250 2553 210 2054 300 3205 325 315
Question: What is the MAD value given the forecast values in the table below?
15-41
![Page 42: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/42.jpg)
MAD Problem Solution
MAD = A - F
n=
404
= 10t t
t=1
n
Month Sales Forecast Abs Error1 220 n/a2 250 255 53 210 205 54 300 320 205 325 315 10
40
Note that by itself, the MAD only lets us know the mean error in a set of forecasts
15-42
![Page 43: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/43.jpg)
Tracking Signal Formula The Tracking Signal or TS is a measure
that indicates whether the forecast average is keeping pace with any genuine upward or downward changes in demand.
Depending on the number of MAD’s selected, the TS can be used like a quality control chart indicating when the model is generating too much error in its forecasts.
The TS formula is:
TS =RSFEMAD
=Running sum of forecast errors
Mean absolute deviation
15-43
![Page 44: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/44.jpg)
Simple Linear Regression Model
Yt = a + bx0 1 2 3 4 5 x (Time)
YThe simple linear regression model seeks to fit a line through various data over time
Is the linear regression model
a
Yt is the regressed forecast value or dependent variable in the model, a is the intercept value of the the regression line, and b is similar to the slope of the regression line. However, since it is calculated with the variability of the data in mind, its formulation is not as straight forward as our usual notion of slope.
15-44
![Page 45: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/45.jpg)
Simple Linear Regression Formulas for Calculating “a” and “b”
a = y - bx
b = xy - n(y)(x)x - n(x2 2
)
15-45
![Page 46: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/46.jpg)
Simple Linear Regression Problem Data
Week Sales1 1502 1573 1624 1665 177
Question: Given the data below, what is the simple linear regression model that can be used to predict sales in future weeks?
15-46
![Page 47: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/47.jpg)
15-47
Week Week*Week Sales Week*Sales1 1 150 1502 4 157 3143 9 162 4864 16 166 6645 25 177 8853 55 162.4 2499
Average Sum Average Sum
b =xy - n(y)(x)x - n(x
=2499 - 5(162.4)(3)
=
a = y - bx = 162.4 - (6.3)(3) =
2 2
) ( )55 5 9
6310
6.3
143.5
Answer: First, using the linear regression formulas, we can compute “a” and “b”
![Page 48: Tutorial 2 - forecasting.pptx](https://reader036.vdocuments.net/reader036/viewer/2022062501/5695cfc11a28ab9b028f64f6/html5/thumbnails/48.jpg)
15-48
Yt = 143.5 + 6.3x
180
Period
135140145150155160165170175
1 2 3 4 5
Sale
s SalesForecast
The resulting regression model is:Now if we plot the regression generated forecasts against the actual sales we obtain the following chart: