udot’s bim for bridges and structures initiative · udot’s bim for bridges and structures...

9
UDOT’s BIM for Bridges and Structures Initiative Carmen Swanwick, SE Utah Department of Transportation Deputy Project Development Director Chief Structural Engineer

Upload: others

Post on 26-Mar-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: UDOT’s BIM for Bridges and Structures Initiative · UDOT’s BIM for Bridges and Structures Initiative Carmen Swanwick, SE. Utah Department of Transportation. Deputy Project Development

UDOT’s BIM for Bridges andStructures Initiative

Carmen Swanwick, SEUtah Department of Transportation

Deputy Project Development DirectorChief Structural Engineer

Page 2: UDOT’s BIM for Bridges and Structures Initiative · UDOT’s BIM for Bridges and Structures Initiative Carmen Swanwick, SE. Utah Department of Transportation. Deputy Project Development

Project Overview

25 miles west of Salt Lake City Two bridge replacements

• I-80 EB and WB over UPRR at Blackrock• Tooele Interchange Bridge at Lakepoint

Delivery method• CMGC

A A S H T O S u b c o m m i t t e e o n B r i d g e s a n d S t r u c t u r e s – J u n e 2 0 1 7

Page 3: UDOT’s BIM for Bridges and Structures Initiative · UDOT’s BIM for Bridges and Structures Initiative Carmen Swanwick, SE. Utah Department of Transportation. Deputy Project Development

Project OverviewI-80 EB and WB over UPRR at Blackrock

A A S H T O S u b c o m m i t t e e o n B r i d g e s a n d S t r u c t u r e s – J u n e 2 0 1 7

Page 4: UDOT’s BIM for Bridges and Structures Initiative · UDOT’s BIM for Bridges and Structures Initiative Carmen Swanwick, SE. Utah Department of Transportation. Deputy Project Development

Project OverviewTooele Interchange Bridge at Lakepoint

A A S H T O S u b c o m m i t t e e o n B r i d g e s a n d S t r u c t u r e s – J u n e 2 0 1 7

Page 5: UDOT’s BIM for Bridges and Structures Initiative · UDOT’s BIM for Bridges and Structures Initiative Carmen Swanwick, SE. Utah Department of Transportation. Deputy Project Development

GoalsDepartment

Advance electronic delivery efforts Develop and advertise bridge designs within a Bridge

Information Modeling (BrIM) environment Implement 3D Engineered Models for construction by

utilizing 3D design tools in preconstruction Provide design files to contractors Develop processes and procedures to advertise projects with

the models as the legal document Focus on the development of the BrIM with the exchange of

structural analysis to the geomatic models A A S H T O S u b c o m m i t t e e o n B r i d g e s a n d S t r u c t u r e s – J u n e 2 0 1 7

Page 6: UDOT’s BIM for Bridges and Structures Initiative · UDOT’s BIM for Bridges and Structures Initiative Carmen Swanwick, SE. Utah Department of Transportation. Deputy Project Development

GoalsProject

Develop an integrated 3D model independent of specific software (geomatics, structures design, and construction planning) Deliver the project contract documents electronically and

eliminate the use of plan sheets Develop BrIM standards, workflow processes, and

procedures for construction to include sub-contractors and fabricators in the process Create a seamless electronic information transfer between

design, construction, and asset management

A A S H T O S u b c o m m i t t e e o n B r i d g e s a n d S t r u c t u r e s – J u n e 2 0 1 7

Page 7: UDOT’s BIM for Bridges and Structures Initiative · UDOT’s BIM for Bridges and Structures Initiative Carmen Swanwick, SE. Utah Department of Transportation. Deputy Project Development

Project Schedule

Design – in progress Construction – 2018

A A S H T O S u b c o m m i t t e e o n B r i d g e s a n d S t r u c t u r e s – J u n e 2 0 1 7

Page 8: UDOT’s BIM for Bridges and Structures Initiative · UDOT’s BIM for Bridges and Structures Initiative Carmen Swanwick, SE. Utah Department of Transportation. Deputy Project Development

Challenges

Data• Data Exchange• Data Accuracy and Accountability• Data Definition• Data Ownership and Management

Software

Hardware

People

Bridge Project Delivery

Roles and Responsibilities

Contractual Changes

Mindset and culture change• New project Development• Enhance value if different disciplines

Legal, liability and security

Insurance

Investment, cost and effort

A A S H T O S u b c o m m i t t e e o n B r i d g e s a n d S t r u c t u r e s – J u n e 2 0 1 7

Page 9: UDOT’s BIM for Bridges and Structures Initiative · UDOT’s BIM for Bridges and Structures Initiative Carmen Swanwick, SE. Utah Department of Transportation. Deputy Project Development

Lessons Learned and Recommendations

A A S H T O S u b c o m m i t t e e o n B r i d g e s a n d S t r u c t u r e s – J u n e 2 0 1 7