WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement Request for Proposals Unit Price Contract for Asbestos Abatement RFP #2018-12 Procurement Schedule Issue Date: August 22, 2017 Pre-Proposal Meeting: September 7, 2017 at 11:00 AM EST Washington County Public Schools Center for Education Services 10435 Downsville Pike Hagerstown, Maryland 21740 Deadline for Written Questions Submission: September 8, 2017 by 1:00 PM EST Proposal Due: September 19, 2017 by 11:00 AM EST Washington County Public Schools Center for Education Services 10435 Downsville Pike Hagerstown, Maryland 21740 Tentative Award Date: October 17, 2017 Dates and/or times are subject to change by the issuing of a written addendum. WCPS Contract Managers Procurement Officer Contract Administrator Scott Bachtell Mark Mills Supervisor of Purchasing Director of Maintenance and Operations 301-766-2842 301-766-2978 [email protected] [email protected] This RFP document is posted on the WCPS Purchasing website at www.wcpspurchasing.com. This is also the source for any/all addenda. Please register your company for notices about this RFP and similar projects on our web site. 1

Upload: others

Post on 13-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

Request for Proposals

Unit Price Contract for Asbestos Abatement

RFP #2018-12

Procurement Schedule

Issue Date: August 22, 2017

Pre-Proposal Meeting: September 7, 2017 at 11:00 AM EST

Washington County Public Schools

Center for Education Services

10435 Downsville Pike

Hagerstown, Maryland 21740

Deadline for Written Questions Submission: September 8, 2017 by 1:00 PM EST

Proposal Due: September 19, 2017 by 11:00 AM EST Washington County Public Schools

Center for Education Services

10435 Downsville Pike

Hagerstown, Maryland 21740

Tentative Award Date: October 17, 2017

Dates and/or times are subject to change by the issuing of a written addendum.

WCPS Contract Managers

Procurement Officer Contract Administrator Scott Bachtell Mark Mills

Supervisor of Purchasing Director of Maintenance and Operations

301-766-2842 301-766-2978

[email protected] [email protected]

This RFP document is posted on the WCPS Purchasing website at www.wcpspurchasing.com. This is also the source for

any/all addenda. Please register your company for notices about this RFP and similar projects on our web site.

1

Page 2: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

TABLE OF CONTENTS

Sections Page

I. General Terms & Conditions 3-14

II. Specific Terms & Conditions 15-19

III. Proposal Format and Submission 20-21

IV. Specifications 22-93

Required Attachments

A. Technical Proposal

Qualifications Proposal:

1. AIA A305 Form—1986—Contractor’s Qualification Statement.

2. Supplemental Questionnaire*

3. Employee Certification List*

4. Resume of AHERA certified Project Designer

5. Copy of State of Maryland Registration

6. Copy of State of Maryland license for Asbestos Removal/Encapsulation

7. Copy of Current Certificate of Insurance

B. Price Proposal Form*

C. Contract Affidavit

D. Mandatory Bid/Proposal Affidavit

E. Specification, Price, and Addenda Signature Acknowledgment

F. Electronic Copy of Technical Proposal

G. Electronic Copy of Price Proposal

*Included in the RFP package and available as separate fillable documents on the WCPS Purchasing website.

Sample Included:

Sample AIA Standard Form of Agreement A101-2007 – Asbestos

RFP 2018-12 Asbestos Abatement Project Form

2

Page 3: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

SECTION I - GENERAL TERMS AND CONDITIONS

1. Introduction

The intent of this invitation for bids (IFB) is to establish Unit Price Contract (UPC) for asbestos abatement services

for Washington County Public Schools (WCPS). The contractor shall provide all labor, materials, supplies,

equipment and incidentals needed to perform the timely and successful removal of materials containing asbestos,

from identified areas of a project.

The resulting Unit price contract (UPC) will be awarded to a minimum of two qualified and experienced companies

who will be invited to provide price quotations during the contract period. In the development of price quotations,

the maximum unit prices submitted and awarded under this UPC may not be exceeded, but can be reduced at the

discretion of the offeror on a competitive per project basis. Price quotations under the UPC contract will be fixed,

firm offers for services. WCPS will place task orders, including contract addendums, for services against this UPC

contract to the lowest cost responsive contractor on a per project basis. WCPS is not obligated to utilize the UPC

contract and may elect to solicit bids or quotes at its discretion.

The contractor awarded a project under the UPC will be responsible for the timely abatement of materials containing

asbestos as specified and directed by the responsible WCPS personnel. Work may be required to be performed at

any WCPS facility location. Work may be performed as a single project or part of a renovation project under

separate contract. All work must be performed in strict accordance with the specifications and general conditions of

the contract, as well as any specific project requirements, which will be communicated in advance to the Contractor.

The contractor(s) shall be responsible and liable for compliance with all applicable laws, regulations, industry

standards for compliance, licensing, patented systems, and requirements as pertain to asbestos abatement and

disposal.

All abatement work, starting from initial testing and design to the creation of a waste manifest and final report, must

comply with the Asbestos Hazard Emergency Response Act (AHERA) and the Asbestos School Hazard Abatement

Reauthorization Act (ASHARA).

2. Bidder Registration

Vendors are solely responsible for completing the vendor registration process online at wcpspurchasing.com.

Contact Beverly Bergan, Purchasing Associate, at 301-766-2841, or by email to: [email protected] if you

have any questions or to check the status of your registration. Once registered in the WCPS Vendor Database, you

will be able to view current solicitations and may automatically receive notification of certain bid solicitations.

Washington County Public Schools will not be held responsible for a company’s failure to become and remain a

registered Vendor, to identify appropriate commodity/service categories, to keep the self-service vendor account up

to date with current contact information, and to accomplish these things in a timely manner. Bidders with a repeated

history of not bidding in a specific category may be removed from the Vendor Database for that category at the

discretion of the Purchasing Supervisor.

3. Receipt of Bids

a. Bids received prior to the time of opening will be time stamped and securely kept unopened. No bid received

after the due date and time listed will be considered. WCPS will not be responsible for the premature opening of

bids received that are not properly addressed or identified. Any bid may be withdrawn before the scheduled time

for opening bids.

b. All inner and outer envelopes and packaging, used by Fed Ex, UPS and etc., are to be labeled with the following:

Bidder Name

Bid Number and Name

Due Date and Time

c. Bids received after the designated date and/or time will not be accepted, regardless of when they were mailed or

3

Page 4: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

given to a delivery carrier.

d. Bids not received by the date, time, and location designated on the solicitation cover sheet, due to improper

labeling, may be considered non-responsive.

In the event of inclement weather on the date when bids are scheduled to be opened and the WCPS offices are

closed, or operating under a modified schedule, bids will be opened on the next business day at the same time as

previously scheduled. Bids will be accepted until the scheduled time of opening on the next business day. Often

when schools are closed due to inclement weather, administrative offices remain open. When in doubt, call the

Purchasing Department (301-766-2840).

4. Addenda

a. All changes to the bid solicitation will be made through appropriate addenda issued from the Purchasing

Department.

b. Addenda will be available on the WCPS Purchasing Department webpage. Bidders should check the website

frequently while the Bid/RFP remains active and open to keep abreast of any posted addenda.

c. Addenda will be issued a minimum of five days prior to the bid opening date, unless the addenda issued extends

the due date.

d. Acknowledgement of each addenda shall be noted on the Signature and Addenda Acknowledgement form.

e. Each bidder shall ascertain, prior to submitting a bid that they have received all Addenda issued and the bidder

shall acknowledge receipt on the Signature Acknowledgement Form. Failure of any bidder to acknowledge the

receipt of addenda will not relieve that bidder from any obligations under this solicitation as amended by

addenda. All addenda so issued will become part of the award and contract documents.

5. Preparation of Bid

a. Should any bidder be in doubt as to the meaning of the specifications, or should they find any discrepancy or

omission, they shall notify the Contract Managers listed on the solicitation cover sheet. If required, bidders will

be notified of clarifications and/or additional information by means of addenda.

b. Each bid will be sealed, show the full business address and contact information of the bidder and be signed by

the person(s) legally authorized to sign contracts. All correspondence concerning the bid and contract, including

notice of award, copy of contract, and purchase order, will be emailed, or mailed, to the address shown on the bid

in the absence of written instructions from the bidder to the contrary.

c. Bidders shall be required under Article 56, Section 270(4), Annotated Code of Maryland, to provide proof of

Certificate of Registry and must be licensed to do business in the State of Maryland and must provide a tax

certification number. Visit the following website to ensure compliance:

https://certificate.dat.maryland.gov/Pages/default.aspx

d. By submitting a response to this solicitation, each Bidder represents that it is not in arrears in the payment of any

obligations due and owing the State of Maryland, including the payment of taxes and employee benefits, and that

it shall not become so in arrears during the term of the contract if selected for contract award.

e. Bids by partnerships must be signed with the partnership name, followed by the signature and designation of the

person having authority to sign. When requested, satisfactory evidence of authority of the person signing will be

furnished. Anyone signing the bid as an agent shall file satisfactory evidence of their authority to do so, if

requested.

f. Bids by corporations must be signed with the name of the corporation, followed by the signature and designation

of the person having authority to sign. When requested, satisfactory evidence of authority of the person signing

will be furnished. Anyone signing the bid as an agent shall file satisfactory evidence of their authority to do so, if

requested.

4

Page 5: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

g. Failure to sign the bid document will result in rejection of the bid as non-responsive.

h. WCPS will not be responsible for any costs incurred by a bidder in preparing and submitting a proposal in

response to this solicitation.

6. Errors in Bid Submissions

a. Bidders, or their authorized representatives, are expected to fully inform themselves as to the conditions and

requirements of the specifications before submitting bids. Failure to do so will be at the bidder's own risk.

b. If the bidder has made an error, the bidder may request, in writing, to have their bid withdrawn. Approval of a

bidder's request is not automatic and may be given only by the Supervisor of Purchasing. Requests for

withdrawal are usually denied, unless the bidder proves to the satisfaction of the Supervisor of Purchasing that

the mistake was either a scrivener's error or another type of clearly unintentional error so departing from

customary and reasonable business practices as to be obvious and to legitimately and substantially impair the

vendor's business.

Neither law nor regulations make allowance for errors either of omission or commission on the part of the bidders.

In case of error in multiplication of unit price when arriving at total price per line item, the unit price shall govern. If

there is a discrepancy between the price written in numbers and the price written in words, the words will govern.

7. Award or Rejection of Bids

a. The basis of award shall be the lowest responsible bidder submitting a responsive bid that conforms to the

specifications established in the solicitation with consideration given to the quantities involved, time required for

delivery, purpose for which required, competency and responsibility of bidder, the ability of the bidder to

perform satisfactory service, and the plan for utilization of minority contractors, if applicable.

b. WCPS reserves the right to cancel this RFP, to determine completeness and/or timeliness of bids, to reject any or

all bids in whole or in part, to make partial awards, to waive any informality in any quotation, to increase or

decrease quantities if quantities are listed in the bid, to reject any bid that shows any omissions, alterations of

form, additions not called for, conditions, or alternate proposals, to conduct discussions with any or all qualified

or potentially qualified Bidders in any manner necessary to serve the best interests of the WCPS, and to make

any such award as is deemed to be in its best interest.

c. Bidders may be required, before the awarding of a contract, to show to the complete satisfaction of WCPS, that

they have the necessary facilities, ability and financial resources to execute the contract in a satisfactory manner,

and within the time specified. Bidders may be required to demonstrate they have the necessary experience,

history and references to assure WCPS of their qualifications.

d. The Board of Education of Washington County reserves the right to award the bid within 90 days from the date

of the bid opening. This period may be extended at the Procurement Officer's request only with the Bidder's

written agreement.

e. Unless stated otherwise in Specific Terms & Conditions, the contract may be awarded by line item, group, or in

the aggregate, whichever is in the best interest of WCPS.

f. In the event of a tie, where all other factors, such as past performance, are considered comparable, the award

shall be made to the Washington County based bidder; the closest Maryland out-of-county based bidder; and the

closest out-of-state based bidder, in that order of preference.

g. WCPS does not have local, state or federal preference requirements except when mandated by a targeted funding

source.

h. If, after competitive sealed bids have been opened, the Supervisor of Purchasing determines that only one

responsible bidder has submitted a responsive bid, the procurement contract may be negotiated with that one

bidder as sole source procurement or the procurement may be re-bid. Whichever is deemed to be in the best

5

Page 6: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

interest of WCPS.

i. A recommendation for the award of a contract will be presented to the Board of Education of Washington

County for approval. Upon approval of the award of contract, the bidder(s) shall be notified of their award(s). If

applicable, a WCPS contract document shall also be issued.

j. The Board of Education of Washington County reserves the right to reject the bid of a bidder who has, in the

opinion of WCPS, failed to properly perform under previous contracts, or, who investigation shows, is not in a

position to perform the contract.

k. The Board of Education of Washington County retains the right to reject any and all bids, if it is deemed in the

best interest of WCPS to do so.

If, during the life of the contract, a product or service does not meet the solicitation terms and conditions, WCPS

retains the right to cancel the awarded item(s) and award to a new bidder, as long as that bidder mutually agrees to

the award.

8. Contract Assignment

a. The awarded vendor(s) will not assign or transfer any portion of their interest or obligation under this Agreement

to any third party, without the prior written consent of the Contract Managers. Nothing herein shall be construed

to create any personal or individual liability upon any employee, officer, elected official of the Board of

Education of Washington County, nor shall this Agreement be construed to create any rights hereunder in any

person or entity other than the parties to this Agreement.

b. The awarded vendor(s) will, when required, submit to the Contract Managers, in writing, the name of each

subcontractor they intend to employ, the portion of the material to be furnished, their place of business, and any

such information as may be required in order to know whether such subcontractor is reputable and reliable and

able to furnish satisfactorily the material as called for in the specifications.

c. WCPS reserves the right to approve or disapprove all subcontractors to be employed on a project. WCPS further

reserves the right to approve or disapprove a change of subcontractor once an initial subcontractor has been

approved. Any increased cost associated with the change of a subcontractor shall be the full obligation and

responsibility of the awarded vendor(s).

d. The awarded vendor(s) will not legally, or equitably, assign any of the funds payable under the contract, or its

claim thereto, unless by, and with, the consent of the Contract Managers.

e. The awarded vendor(s) will have the same provisions inserted in all subcontracts relative to the terms of the

general conditions and other contract documents. Nothing contained in this contract shall create any contractual

relations between any subcontractor and WCPS.

9. Insurance

The Contractor shall purchase and maintain (throughout the life of this contract) such insurance as will protect the

contractor, and the BOARD OF EDUCATION OF WASHINGTON COUNTY, from claims which may arise out of

or result from the Contractor's operations under the contract, whether such operations be by himself or by any

subcontractor, lower tier contractor or by anyone directly or indirectly employed by any of them, or by anyone for

whose acts any of them be liable.

This requested certificate of insurance will name the BOARD OF EDUCATION OF WASHINGTON COUNTY

as an additionally insured party for general liability, professional liability, workers' compensation, and

Contractor pollution liability insurance. The certificate will be submitted to the Purchasing Department (within

10 days of receiving an Award Letter) verifying that the indicated below will be maintained prior to

commencement of work.

6

Page 7: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

Coverage Required:

Worker's Compensation:

1. State

2. Employer’s Liability

Comprehensive General Liability (including Premises-Operations; Independent Contractor's Protective products

and Completed Operations; Board Form Property Damage);

1. Bodily Injury:

$1,000,000.00 - Each occurrence

$1,000,000.00 - Aggregate, Products and Completed Operations

2. Property Damage:

$1,000,000.00 - Each occurrence

$1,000,000.00 – Aggregate

Products and Completed Operations Insurance shall be maintained for a minimum period of two (2) years after final

payment, and contractor shall continue to provide evidence of such coverage to owner on an annual basis during

the aforementioned period.

Contractual Liability (Hold Harmless Coverage):

1. Bodily Injury:

$1,000,000.00 - Each occurrence

2. Property Damage:

$1,000,000.00 - Each occurrence

$1,000,000.00 - Aggregate

Personal injury, with employment exclusion deleted: $1,000,000.00.

Comprehensive Automobile Liability (Owned, non-owned, hired)

1. Bodily Injury:

$ 500,000.00 - each person

$2,000,000.00 - each occurrence

2. Property Damage:

$1,000,000.00 - each occurrence

Professional liability, errors and omissions insurance at a limit of not less than $1,000,000

Additional Required Insurance for this Asbestos Abatement RFP

Contractor pollution liability insurance or its equivalent for bodily injury, property damage, including loss of use,

and clean-up costs on and off the Project site, with minimum limits as follows:

$1,000,000 per each pollution incident;

$1,000,000 annual aggregate

This insurance shall include coverage for all of the following:

Liability arising from activities of the Contractor, or of others for which the Contractor is legally obligated, at the

Project site; and Contractual liability including protection for the Contractor from claims for bodily injury, property

damage and clean-up costs arising out of liability assumed under this Contract.

c. The contractor is responsible for the cost and terms of this insurance coverage.

10. Subcontractor’s Insurance

The Contractor shall either:

7

Page 8: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

1. Require each of his/her subcontractors to procure and to maintain during the life of the subcontracts

Liability Insurance of the type and in the same amounts as specified above, or 2. Insure the activities of the subcontractors in his/her own policies. It will be the responsibility of the

Contractor to insure that all subcontractors comply with this provision, and the Contractor will

indemnify and hold harmless the Board for the failure of the contractor or any subcontractor to

comply with these provisions.

11. Billing Procedure

a. Invoices for this contract shall be submitted to:

Washington County Public Schools

Attn: Andrea Knode

10435 Downsville Pike

Hagerstown, MD 21740

b. Invoices and packing slips must contain the following information:

i. Bid Number

ii. Brief Description of Item or Work Performed

iii. Quantity

iv. Unit Price Bid

v. Extended Total for Each Item

c. WCPS standard payment terms are Net 30

12. Taxes

No charge will be allowed for federal excise, state, and/or municipal sales and use taxes, from which the Board of

Education of Washington County is exempt. Pricing will be net and will not include the amount of any such tax.

Bidders will be required to pay the tax on all purchases and can recover it only as a part of their bid price.

Exemption certificates will be furnished upon request.

13. Subsidiaries

If a Bidder that seeks to perform or provide the services required by this RFP is the subsidiary of another entity, all

information submitted by the Bidder such as, but not limited to, proposed services, description of the Bidder's ability

to perform the scope of work, references and financial reports, shall pertain exclusively to the Bidder, unless the

parent organization will guarantee the performance of the subsidiary. If applicable, the Bidder's proposal must

contain an explicit statement that the parent organization will guarantee the performance of the subsidiary.

14. Multi-Year Contract

a. Contracts that require funding appropriation for more than one fiscal year automatically terminate if money

sufficient for the continued performance is not appropriated for any fiscal year. The date of termination is the

last day of the fiscal year for which money was last appropriated, or the date provided in the termination clause

of the procurement contract, whichever is earlier.

b. If the multi-year contract is terminated due to lack of funding, WCPS shall reimburse the vendor for the

reasonable value of any nonrecurring costs that were incurred as a result of the multi-year contract, but not

amortized in the price of the supplies or services delivered under the multi-year contract. The reasonable value

will be negotiated, and mutually agreed upon, by WCPS and the vendor.

c. The cost of termination may be paid from any appropriation available for that purpose.

15. Hold Harmless

It is understood that the awarded vendor(s) shall defend and hold harmless the Board of Education of Washington

County, and its representatives, from all suits, actions, or claims of any kind brought about as a result of any injuries

or damages sustained by person(s) or property during the performance of this contract.

8

Page 9: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

16. Termination for Default

a. When an awarded vendor has not performed or has unsatisfactorily performed the contract, payment shall be

withheld at the discretion of WCPS. WCPS may, by written notice of default to the vendor, terminate the whole

or any part of the contract in any of the following circumstances:

i. If the vendor fails to perform the services or provide the products within the time and manner specific

herein or any extension thereof, or:

ii. If the vendor fails to perform any of the provisions of this contact, or fails to make progress as to

endanger performance of this contract, in accordance with its terms and in either of these two

circumstances does not cure such failure within a period of ten calendar days (or longer as authorized

by the Supervisor of Purchasing) after receipt of written notice from the Supervisor of Purchasing of

such failure, or:

iii. If the vendor willfully attempts to perform the services other than specified as to coverage, limits,

protections, and quality or otherwise, without specified authorization in the form of contract

amendment, or:

iv. If a determination is made by WCPS that the obtaining of the contract was influenced by an employee

WCPS having received a gratuity, or a promise therefore, in any way or form.

b. In the event WCPS terminates the contract in whole or in part, WCPS may procure such products and services, in

a manner the Supervisor of Purchasing deems appropriate, and the vendor shall be liable to WCPS for any

additional cost(s) incurred.

c. If, after notice of termination of this contract under provisions of this clause, it is determined for any reason that

the vendor was not in default under the provisions of this clause, or that the default was excusable under the

provisions of this clause, the rights and obligations of the parties shall be the same as if the notice of termination

had been issued pursuant to a termination for convenience.

17. Termination for Convenience

The contract may be terminated by WCPS in accordance with this clause in whole, or in part, whenever WCPS

determines that such a termination is in the best interest of WCPS. Written notice shall be given a minimum of 60

days in advance. WCPS will pay for all services, in accordance with contract pricing, up to the date of the

termination. However, the awarded vendor(s) shall not be reimbursed for any anticipatory profits that have not been

earned up to the date of termination. Under this contract, the awarded vendor does not have a right to unilateral

termination for convenience.

18. Governing Law and Venue

The solicitation shall be construed in accordance with, and interpreted under, the laws of the State of Maryland. Any

lawsuits shall be filed in the appropriate State Court located in Washington County, Maryland.

19. Multi-Agency Participation

a. WCPS reserves the right to extend the terms and conditions of this solicitation to any and all other agencies

within the state of Maryland, as well as, any other federal, state, municipal, county, or local governmental agency

under the jurisdiction of the United States and its territories. This is conditioned upon mutual agreement of all

parties pursuant to special requirements, which may be appended thereto. The awarded vendor(s) agrees to

notify the issuing body of those entities that wish to use any contract resulting from this bid and will also provide

usage information, which may be requested.

b. By agreeing to extend the contract to other agencies, the vendor(s) reaffirms and warrants his original

commitment to WCPS so that afterwards all items and services shall continue to conform to the requirements and

conditions of the original agreement for its duration. Agencies who utilize the contract agree to notify WCPS

Purchasing Department of any significant experiences, problems or issues which may, or may have the potential

9

Page 10: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

to, affect our administration of this contract.

c. WCPS assumes no obligation on behalf of any other agency and shall be held harmless if either party is damaged

due to the agency or vendor’s failure to become informed of, or comply with, any provision or pricing under this

agreement. All purchase orders and billing will be transacted between the vendor and the public agency.

Each participating jurisdiction or agency shall enter into its own contract with the awarded vendor(s) and this

contract shall be binding only upon the principals signing such an agreement. Invoices shall be submitted in duplicate

“directly” to the ordering jurisdiction for each unit purchased. Disputes over the execution of any contract shall be

the responsibility of the participating jurisdiction or agency that entered into that contract. Disputes must be resolved

solely between the participating agency and the awarded vendor(s). The Lead Agency does not assume any

responsibility other than to obtain pricing for the specifications provided.

20. Compliance with Specifications

a. The awarded vendor(s) will abide by, and comply with, the true intent of the specifications and not take

advantage of any unintentional error or omission, but will fully complete every part as to the true intent and

meaning of the specifications and drawings.

b. Whenever mention is made of any article, material, or workmanship to be in accordance with laws, ordinances,

building codes, underwriter's code, A.S.M.E. regulations, or similar expressions, the requirements of these laws,

ordinances, etc., shall be construed as to the minimum requirements of these specifications.

c. Where the requirements of the specifications call for a higher grade and are not in conflict with the laws,

ordinances, etc., the specifications shall govern.

d. In the case of any apparent conflict between the specifications and such laws, ordinances, etc., the awarded

vendor(s) will contact the Contract Administrator and the Contract Manager for a decision before proceeding

with any work.

21. Safety Requirements

a. When applicable, all machinery/equipment must meet OSHA-MOSHA requirements as to the safety of the

operation of the equipment. All required safety devices shall be included in the price(s) bid.

b. When applicable, kitchen equipment and supplies must meet Maryland State Health Department, National

Sanitation Foundation (NSF) and Washington County Health Department requirements.

c. All construction activities must be conducted in strict compliance with OSHA/MOSHA requirements.

d. Equipment offered which fails to comply with any applicable section of the National Electrical Code, or is not

U.L. Listed (where U.L. Listings have been established for that type of device) shall be rejected.

e. The awarded vendor(s) shall submit Safety Data Sheets (SDS) for all items awarded to that vendor provided

under the terms of this proposal, if applicable.

f. The awarded vendor(s) and subcontractor(s) are required to comply with all provisions of the Access to

Information about Hazardous and Toxic Substances Act, a part of the Maryland Occupational Safety and Health

Law.

g. The awarded vendor(s) is responsible to report to WCPS any asbestos material or suspected material found or

uncovered that is not part of the scope of the project. In addition, they may not introduce new asbestos or

asbestos bearing materials into the site.

h. It is the responsibility of the awarded vendor(s) to comply with all Municipal, State, and Federal EPA regulations

and laws when handling or disposing of asbestos materials.

i. If the awarded vendor(s) intentionally endangers or jeopardizes the health of any building/school occupant(s)

through mishandling of hazardous material, the vendor(s) will be held liable for such action.

10

Page 11: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

22. Laws and Regulations

a. The vendor will comply with all Federal, State, and local laws, ordinances and regulations pertaining to work

under their charge. If the vendor performs any work which it knows or should know to be contrary to such laws,

ordinance, and regulations and without such notices to WCPS they shall bear all costs arising therefrom.

b. All vendors and subcontractors must abide by the Board of Education of Washington County policies and WCPS

regulations while working on school property.

c. The vendor certifies that their firm adheres to or follows non-discriminatory practices with respect to the

employment and promotion of personnel without regard to color, creed, race, sex, or national origin.

23. Employment of Child Sex Offenders and Persons with Uncontrolled Access to Students

a. Be advised that individuals who are registered sex offenders are not eligible to work on any WCPS’ project. The

awarded vendor(s) must initially check the Maryland Department of Public Safety & Correctional Services’

Maryland Sex Offender Registry and search for the name of any employee to be assigned to work on this project.

This applies to subcontractors and material/equipment suppliers as well. For projects lasting more than a few

months, the vendor will periodically re-check the names of workers against the registry to ensure ongoing

compliance. In the event that a registered sex offender is discovered to be working on a WCPS project, whether

through employment by the vendor, subcontractor or equipment or material supplier, WCPS will notify the site

superintendent to immediately remove the individual from the premises and permanently terminate his work

assignment. WCPS may terminate this contract at no additional costs, as a result if the vendor is unable to

demonstrate they have exercised care and diligence in the past in checking the Maryland registry.

b. Contracted service providers who have regular, direct and unsupervised access to children cannot begin service

without undergoing the same process as new employees per WCPS. If required, an awarded vendor(s) is

responsible for payment of the full cost of the criminal background check. If required, additional information

regarding this requirement will be found in Specific Terms & Conditions.

c. The awarded vendor(s), or subcontractor(s), may not knowingly assign an employee to work on WCPS school

premises with direct, unsupervised, and uncontrolled access to children, if the employee has been convicted of a

crime identified as a crime of violence.

d. The awarded vendor(s) will not assign employees who has been convicted of an offense under § 3-307 or § 3-

308 of the Criminal Law Article or an offense under the laws of another state that would constitute a violation of

§ 3-307 or § 3-308 of the Criminal Law Article if committed in the state.

e. An awarded vendor will not assign an employee who has been convicted of a crime of violence as defined in §

14-101 of the Criminal Law Article, or an offense under the laws of another state that would be a violation of §

14-101 of the Criminal Law Article if committed in this state.

24. Tobacco-Free Workplace

a. Maryland State Law (COMAR 13A.02.04) provides that each local school system is required to maintain a

tobacco-free school environment.

25. Weapon Possession on School Property

a. The criminal code of Maryland makes it illegal to possess a weapon on school property.

b. Any awarded vendor(s) whose employees violate this clause may be subject to the termination of the contract for

cause.

26. Illegal Immigrant Labor

The use of illegal immigrant labor to fulfill contracts solicited by WCPS is in violation of the law and is strictly

prohibited. Awarded vendor(s) and subcontractors must verify employment eligibility of workers in order to assure

that they are not violating federal/state/local laws regarding illegal immigration. A compliance audit may be

conducted.

11

Page 12: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

27. Student/Staff Confidentiality

a. Under no circumstances may any vendor/contractor/provider/consultant release, disclose, sell or otherwise use

names, addresses, or any other information related to students, or staff, of WCPS and may only use this

information for purposes required under any contract/agreement or memorandum of understanding.

b. The vendor/contractor/provider/consultant shall keep confidential, in accordance with federal and state laws, all

confidential and medical information that is obtained as the result of the performance of the services described in

this contract/agreement or memorandum of understanding.

28. Proprietary and Confidential Information

a. All submitted documents are subject to public disclosure.

b. Each offeror at its own expense shall submit a proprietary and confidential redacted electronic copy (on a

flash-drive or CD) of its proposal to be used in responding to Freedom of Information Act (FOIA)

requests. The offeror should clearly mark the electronic copy, and check the appropriate box on the

Signature Acknowledgment page. If the offerors submission does not have any proprietary and

confidential information, please check the appropriate box on the Signature Acknowledgment page.

c. Bidders should identify those portions of their solicitation, which they deem to be confidential, or to contain

proprietary commercial information or trade secrets. It is the responsibility of the offeror to clearly identify each

part of its proposal by marking the bottom right corner of each pertinent page with bold font letters stating the

words “confidential” or “proprietary”. Bidders should provide justification why such material, upon request,

should not be disclosed by WCPS under the Public Information Act, Title 4, General Provisions Article,

Annotated Code of Maryland.

d. The Offeror agrees that any portion of the proposal that is not stamped as propriety or confidential is not

proprietary or confidential. Unless portions of a proposal are identified as confidential, all records are

considered public. A person or governmental unit that wishes to inspect a public record, or receive copies of a

public record, shall submit a written or electronic request.

e. WCPS will notify the vendor if a Freedom of Information Act (FOIA) request is received in connection with a

Bid or RFP that has confidential information identified.

f. If litigation is instituted against the Board of Education or its agents, the party opposing the release must provide

representation to the Board or cover the cost of counsel and all other related ligation expenses. As a condition

for WCPS keeping the information confidential, the offeror must agree to defend and hold WCPS harmless if

any information is inadvertently released.

29. Force Majeure

Force Majeure is defined as an occurrence beyond the control of the affected party and not avoidable by reason of

diligence. It includes the acts of nature, war, riots, strikes, fire, floods, epidemics, terrorism, or other similar

occurrences. If either party is delayed by Force Majeure, said party shall provide written notification to the other

within 48 hours. Delays shall cease as soon as practicable and written notification of same provided. The time of

contract completion may be extended by contract modification, for a period of time equal to that delay caused under

this condition. WCPS may also consider requests for price increase for raw materials that are directly attributable to

the cause of delay. WCPS reserves the right to cancel the contract and/or purchase materials, equipment or services

from the best available source during the time of Force Majeure, and the vendor shall have no recourse against

WCPS. Further, except for payment of sums due, neither party shall be liable to the other or deemed in default under

this contract, if and to the extent that such party’s performance of this contract is prevented by reason of Force

Majeure as defined herein.

30. Non-Collusion

a. Bidder represents and certifies that prices for these services have been arrived at independently without

consultation, communication, or agreement for the purpose of restricting competition or any matter related to

such prices with any competitor or other bidder. Prices quoted in this bid have not been knowingly disclosed

12

Page 13: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

directly or indirectly to any competitor or other vendor prior to the opening of this bid.

b. Bidder represents and certifies that it has not employed or retained any other company or person (other than a

full-time bona fide employee working exclusively for the bidder) with the primary intent to solicit or secure the

contract.

31. Conflict Of Interest

The bidder will advise WCPS in writing as soon as possible, but not later than the date of the Bid/RFP opening, of

any known relationships with a third party, or WCPS employee or representative, which would present a significant

advantage to one bidder over another bidder or present a conflict of interest with the rendering of products and

services under this agreement.

32. False Statements

Bidders are advised that Section 11-205.1 of the State Finance and Procurement Article of the

Annotated Code of Maryland provides as follows:

a. In connection with a procurement contract a person may not willfully:

i. falsify, conceal, or suppress a material fact by any scheme or device;

ii. make a false or fraudulent statement or representation of a material fact; or

iii. use a false writing or document that contains a false or fraudulent statement or entry of a material fact.

b. A person may not aid or conspire with another person to commit an act under subsection (a) of this section.

c. A person who violates any provision of this section is guilty of a felony and on conviction is subject to a fine not

exceeding $20,000 or imprisonment not exceeding 5 years or both.

33. Maintenance of Records

The Vendor agrees to make available at the office of the Vendor at all reasonable times, and upon reasonable written

notice, during the term of this Contract and the period set forth below, any of the records for inspection, audit, or

reproduction by any authorized WCPS representative. The Vendor shall preserve and make available its records for

a period of three (3) years from the date of final payment under this Contract.

34. Warranty

Contractor shall warrant to WCPS that the materials, supplies and workmanship furnished under this contract will be

new, will conform to the requirements of this bid, be of good quality and shall be free from all defects and faults of

any kind.

All service shall be performed by qualified and competent personnel, in a proper and professional manner, without

disruption to school/staff or activities in the buildings.

35. Non-Conflict of Interest Statement

It is unlawful for any officer, employee or agent of the WCPS to participate personally in his/her official capacity

through decision, approval, disapproval, recommendation, advice or investigation in any contract or other matter in

which he/she, his/her spouse, parent, minor child, brother or sister, has a financial interest; or to which any firm,

corporation, association, or other organization in which he/she has a financial interest; or in which he/she is serving

as an officer, director, trustee, partner, or employee; or any person or organization with whom he/she is negotiating

or has any arrangement concerning prospective employment; is a party, unless such officer, employee, or agent has

previously complied with the provisions of Maryland Annotated Code, Article 40A, SS1-101 et. seq.

The successful bidder agrees that during the term of the Contract and for twenty-four (24) months following the exit

conference, the successful bidder, its employees, agents and representatives, shall not, with or without compensation,

on behalf of the successful bidder, or another person, entity, or corporation, take any action in connection or receive

any benefit with any specific matter, finding or recommendation associated in any way with this project, except with

the express written consent of the WCPS.

13

Page 14: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

36. eMaryland Marketplace Registration

Contractors are required to register with eMaryland Marketplace (https://emaryland.buyspeed.com/bso/) within

five (5) days following notice of award. Maryland law requires local and state agencies to post award notices on

eMaryland Marketplace. This cannot be done without the contractor’s self-registration in the system. Registration is

free. Failure to comply with this requirement may be considered grounds for default. It is recommended that any

interested bidder register with eMaryland Marketplace regardless of the award outcome for this procurement as it is a

valuable resource for bid notification for municipalities through Maryland.

14

Page 15: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

SECTION II - SPECIFIC TERMS AND CONDITIONS

1. Sponsoring Departments

The Purchasing Office has issued this UPC for the Facilities Maintenance and Operations Department and the

Facilities Planning and Development Department, which are responsible for the technical specifications and service

requirements outlined herein. After award, representatives from these departments will administer the contract.

2. Questions and Inquiries

Questions and inquiries should be emailed to Scott Bachtell ([email protected]) with a copy to Mark Mills

([email protected]). Please put the following in the subject line “2018-12 – Unit Price Contract for

Asbestos Abatement”.

3. Contract Period

The initial contract shall be for a period of three (3) years, beginning November 1, 2017 and ending October 31,

2020.

WCPS reserves the option to renew this contract for one (1) additional two (2) year period, subject to acceptable

performance. Prior to a contract renewal, WCPS and the award firm will communicate regarding performance,

pricing, revisions and modifications to this contract. All terms and conditions of the bid will apply to any renewal of

this contract.

4. Contract Form

a. This UPC contract will utilize the American Institute of Architects AIA Document A101- 2007, Standard Form

of Agreement between Owner and Contractor, as the form of agreement between the parties. The contract will

be governed by AIA Document A201 – 1997, General Conditions of the Contract for Construction.

b. This is an open requirements contract with no guarantee of any work is expressed or implied. Orders will be

placed only as needs arise throughout the contract period.

5. Pricing

a. All prices shall remain firm through the first year of the contract. Pricing shall include all delivery costs and shall

be the final cost to Washington County Public Schools. No bid shall be considered which contains an escalator

clause, packaging or delivery charges, or any add-on or irregular figures.

b. Price decreases are acceptable at any time, need not be verifiable, and are required should the

contractor/producer/processor/manufacturer experience a decrease in costs associated with the execution of the

contract.

c. Price adjustments from the contractor/producer/processor/manufacturer for any/all items may be considered

yearly. The request is subject to approval by the Procurement Officer. The request must be submitted in writing

at least sixty (60) prior to the renewal term and shall be accompanied by supporting documentation. It is the

contractor / producer / processor / manufacturer’s responsibility to submit a letter requesting price changes, as

well as documentation from the manufacturer to support the change.

d. Should the awarded vendor, at any time during the life of the contract, sell materials of similar quality to another

customer, or advertise special discounts or sales, at a price below those quoted within the contract, the lowest

discounted prices shall be offered to Washington County Public Schools.

6. Offeror Investigation

Before submitting a proposal, each offeror shall make all investigations and examinations necessary to ascertain all

conditions and requirements affecting the full performance of the contract, and to verify any representations made by

WCPS that the offeror will rely upon. No pleas of ignorance of such conditions and requirements resulting from

failure to make such investigations and examinations will relieve the successful offeror from its obligations to

comply in every detail with all the provisions and requirements of the contract documents, or will be accepted as a

basis for any claim whatsoever for any monetary consideration on the part of the successful bidder.

15

Page 16: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

7. Contractor’s Employees

a. The awarded contractor(s) has the right to remove or replace individuals from the "Employee Certification Form” throughout

the term of contract by notifying the WCPS contract administer in writing. WCPS reserves the right to review the

employee’s work record to verify that they are properly trained and experienced. WCPS maintains the right to request

substitution of an employee utilized on a specific project.

b. For all new employees, the awarded contractor shall:

1. Submit the employee name and their last two years of work history to WCPS for review. Work history must

include previous employer’s contact information.

2. Provide a copy of ALL related certifications and licenses for each employee.

c. WCPS must be notified of an awarded contractor’s intent to replace a worker on a scheduled project within one business

day of original worker’s departure and shall provide proof of required certifications for the new worker.

d. Utilizing any employee not previously approved by WCPS is reason for immediate termination of the contract for cause.

8. Qualifications

a. Maintain a permanent place of business and shall be certified to do business in Maryland as evidenced by a State

of Maryland License;

b. Have been in the asbestos abatement business for at least three years;

c. Be bondable before and during this contract;

d. Maintain appropriate levels of liability and specialized abatement and pollution insurance at all times as specified

during this contract;

e. Have preferred experience with WCPS, federal or state agencies, or with other public schools;

f. Have preferred experience with the Indefinite Quantities (IDQ) contract format;

g. Provide evidence of appropriate licenses necessary to perform this work;

h. Demonstrate to the satisfaction of WCPS that employees who will be used on any WCPS project are properly

trained, certified and experienced in asbestos abatement services;

i. Be an approved WCPS vendor;

j. Submit all required documentation, including the AIA A305 Contractor’s Qualification Statement and WCPS

Supplemental Questionnaire.

WCPS may make such investigations as deemed necessary to determine the ability of the bidder to perform the work

contemplated herein. The bidder shall furnish to WCPS any data and information requested to assist in

determination of the bidder's ability and qualifications to perform under this contract. WCPS may reject a bid or not

accept a cost proposal if the evidence submitted by, or investigation of such bidder fails to satisfy the WCPS that,

such bidder is sufficiently qualified to carry out the obligations of the contract.

9. Project Ordering Procedure

This contract may be used for emergency and scheduled response projects. Emergency response may be required in

order to maintain progress of work during a construction project or to expedite occupancy of the premises.

16

Page 17: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

Emergency Projects

The sponsoring department will contact an awarded vendor to determine if they can meet the timeline required.

The vendor will provide a quote based on the unit prices submitted and awarded under this UPC. A purchase

order will be issued after which work may commence.

Scheduled Projects

The minimum order for services under this contract will be approximately $500. All awarded contractors will be

solicited to submit a quote proposal for projects estimated to exceed $10,000.

The sponsoring department designee will:

Notify the awarded vendor(s) by telephone, or email, of a planned project(s).

Set a pre-quote meeting date (with at least 48 hours’ notice) for a site visit for the project. During the

visit, staff will define the scope of work, the project schedule (including start and finish dates), and

answer any project specific questions. If available, the designee will furnish plans showing locations of

work.

Provide a due date and time for price quotes (giving at least 48 hours) for that specific project.

Award the specific project to the lowest responsive, responsible bidder for the project with consideration

given to the contractor’s ability to meet the completion schedule. The designee will Issue a purchase

order, after which work may commence.

The Contractor will:

Be responsible to take all of their own measurements.

If interested, the contractor(s) will be required to submit (in hard copy or via email, as determined by the

contract administer) the following, referencing “Bid #2018-12 – Project Location” by the date and time

specified by the sponsoring department designee at the pre-quote meeting:

A proposed written schedule

A cost estimate

The method of abatement

The contractor must provide the name(s) and current AHERA certificates for the project designer

and other authorized individuals for each project submission unless they are already on file.

For a given project, the appropriate units of labor and/or materials from this bid and the estimated

quantity of each will be identified by the contractor. Pricing for units of labor, materials, or equipment,

which are not specifically listed herein, will be list by line with detail. The unit total of all lines,

including additional items, will be added together to establish an estimated total project cost.

Obtain all required permits from the local and State authorities if applicable and required. Contractor

must provide evidence of all permits and approvals to WCPS prior to beginning any removal activities.

If awarded, confine its apparatus, storage of materials and operations of workmen to the limits indicated

by WCPS.

If awarded, the contractor is required by State law and Board policy to report to the main office of the

school building and register as a visitor to that building each day

If awarded, the contractor must keep the premises free from accumulations of work material and rubbish.

Respond to every RFQ, if the contractor is unable to provide a quote for any reason, the contract must

submit a “No Quote” response. An awarded vendor that does not respond to request for proposals on

more than three occasions may be subject to contract termination and/or non-renewal.

a. In the development of price quotations, the maximum unit prices submitted and awarded under this

UPC may not be exceeded, but can be reduced at the discretion of the offeror on a competitive per

project basis. The sum total of all units extended will be the total price quote for each project.

b. In cases of non-performance, liquidated damages may be deducted from the final invoice. Extensions

may be granted if the delay in completing the project were not the fault of the contractor.

17

Page 18: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

10. Bonds

Bid bids are not required. For some projects, WCPS may request a performance bond and/or payment bond in 100%

of the contract amount. In such case, WCPS would reimburse up to 2% of the contract amount for the provision of

bonds. Failure to provide bonds where required by WCPS may be cause for cancellation of the contract.

11. Evaluation

Bids will be evaluated by staff in the Purchasing, Facilities Maintenance and Operations, and Facilities Planning and

Development departments. Unit prices will be evaluated using a variety of past and/or hypothetical project(s) to

determine project totals. The determination of ranking of the bids according to these criteria rests with the

Supervisor of Purchasing whose final judgment will not be grounds for appealing the contract award.

Technical Proposal 60 Points

Registered in State of Maryland

Length of time the business has done asbestos abatement work

Experience with WCPS and Maryland schools

Experience with Unit Price contracts

Insurance Coverage

Bonding capability

Firm’s permanent staffing levels

Employees certification(s), experience

Experience of in-house project designer

Absence of Citations

References

Pricing Proposal

Pricing 40 Points

Total: 100 Points

12. Award

a. The contract shall be awarded based on the evaluation of the Technical and Cost proposals. Final ranking will

be made on the basis of the criteria and rubric listed above. It is the intent of WCPS to award the bid to multiple

contractors. Complete discretion is reserved by WCPS in determining completeness and/or timeliness of

proposals, advantages attributable to acceptance of higher prices, allowance of submission of additional data or

information and any other procedures determined by the WCPS to suit its best interest.

b. The Board reserves the right to reject any/or all proposals in whole or in part without explanations, to waive any

informalities in the bids, to make partial awards, to waive any irregularity in any quotation and may reject any

proposal that shows an omissions or alterations of form, additions not called for, and conditions or alternate

proposals. The Board may award the Contract to the bidder who proves to be qualified as to financial

responsibility, reputation and ability to carry out the obligations of the Contract and is deemed to be in the best

interest of the Board. Bid forms, which are not complete in accordance with instructions, may be considered

non-responsive.

13. Objection to Award

Any company objecting to the bid procedure or the recommendation for award has five (5) business days following

the date of award by the WCBOE to file a written protest with the Superintendent of Schools. It is the company’s

responsibility to ascertain and confirm the date/time of the pertinent Board Meeting. The written appeal must be

submitted on company letterhead, dated and signed by the senior officer in the company. The protest letter must

include a request for review and ruling by WCPS, a detailed statement of the legal and factual grounds for the

protest, including the resulting prejudice to the company, copies of relevant documents, and a statement of the form

of relief being requested. Failure to comply with these instructions may result in the protest being deemed “not

filed.” Bid protests received later than five (5) days after the pertinent Board Meeting will result in the

protest being deemed “not timely.” The WCPS will not respond or address bid protests that do not conform to

these instructions.

18

Page 19: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

14. Bid Tabulations

Bid summaries are posted on the WCPS website: http://wcpspurchasing.com/bids/results.

15. Liquidated Damages

a. A date for delivery and/or installation/assembly shall be stated for each project under this contract. Requests for

extension of completion time due to strikes, lack of materials, or any other causes over which the awarded

vendor(s) has no control must be submitted, in writing, with supporting documentation, to the Contract

Managers. Requests must occur immediately upon occurrence of conditions for a time extension to be granted.

Extensions are not guaranteed.

b. If the awarded vendor(s) fails to provide the services, equipment, or other items required within the prescribed

time limits, the Contract Managers may elect to obtain services, equipment, or other items necessary from an

alternate source.

c. The awarded vendor(s) will pay any additional cost(s) incurred by WCPS for obtaining replacement services,

equipment, and other necessary items.

d. WCPS shall have the unilateral right of alternate source selection to perform the work when the awarded

vendor(s) does not perform the required work.

e. In addition to, or in lieu of, paying for any incurred replacement costs(s), the awarded vendor(s) may pay

liquidated damages, in the amount of $500 per day, for any delay or failure in performance, as well as any related

damages sustained by WCPS.

f. The assessment of liquidated damages by WCPS against the awarded vendor(s) does not supersede or affect the

right of WCPS to impose other remedies that may be available.

16. Subcontractors

With each project an awarded vendor will submit (in writing) a list of subcontractors that will be utilized on that

specific project. The contractor shall remain at all times fully responsible for all services and deliverables required

under this contract including any portion of the work assigned to a subcontractor. Nothing contained in this contract

shall create any contractual relations between any subcontractor and the Washington County Board of Education.

WCPS reserves the right to approve or disapprove any/all subcontractors on a project by project basis.

17. Professional And Trade Licenses

In the event the services to be provided by Contractor must by law be provided by individuals who are licensed

and/or certified, only individuals who are licensed and/or certified in accordance with the law shall provide the

required services. All such individuals assigned by Contractor to provide services shall maintain their license and/or

certification in good standing (not under review or subject to suspension, credentials current) during the entire term

of this Agreement. Contractor shall, prior to providing services, submit documentation that the individuals assigned

to provide services are properly credentialed and are licensed.

19

Page 20: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

SECTION III – PROPOSAL FORMAT AND SUBMISSION

1. Proposal Format

The format outlined in the RFP must be adhered to in your proposal. A responsive proposal will consist of the

following documents completed:

Technical Proposal

a. Introductory Cover Letter

b. Qualifications Proposal:

c. AIA A305 Form—1986—Contractor’s Qualification Statement.

d. Supplemental Questionnaire

e. Employee Certification List

f. Resume of AHERA certified Project Designer

g. Copy of State of Maryland Registration

h. Copy of State of Maryland license for Asbestos Removal/Encapsulation

i. Copy of Current Certificate of Insurance

j. Contract Affidavit (signed)

k. Mandatory Proposal Affidavit (signed)

l. Specification, Price, and Addenda Signature Acknowledgment (signed)

Pricing Proposal

a. Price Form

2. Proposal Submission

a. The Technical and Price Proposal Proposals must be submitted separately in sealed envelopes clearly

marked “Technical Proposal” and “Price Proposal” (The envelopes may be sent in the same box or

package). The Price Proposal will remain sealed until WCPS determines if your firm’s submission is

satisfactory according to the technical evaluation criteria of this RFP document. For this reason, a

Proposal that is not organized and submitted as separate and distinct “Technical” and “Price” proposal

sections will result in disqualification. A technical proposal that includes any pricing information will be

disqualified.

b. Proposal shall be submitted or hand delivered by the time and date listed on the coversheet to Washington

County Public Schools, 10435 Downsville Pike, Hagerstown, MD 21740, Attn: Purchasing Department.

Proposals submitted after that time and date will be returned unopened.

c. Electronic copies must be submitted in the format they were sent in.

1. The Sealed Technical Proposal (including all Signature pages) must include the following:

Quantity

Original: One (1)

Electronic Version (CD-ROM or USB Flash Drive) One (1)

2. The Sealed Cost Proposal must include the following:

Quantity

Original: One (1)

Electronic Version (CD-ROM or USB Flash Drive) One (1)

d. Due to possible changes and/or additions to the specifications, proposals should not be mailed until after

the question period ends. All changes will be processed through addenda to this solicitation package.

20

Page 21: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

e. All inner and outer envelopes and packaging, used by Fed Ex, UPS and etc., should be labeled with

the bid name, bid number, and due date/time. This will help assure timely receipt of bids in the

Purchasing Department. Bids not received in time due to improper labeling will be considered non-

responsive.

f. All forms must be properly completed and where applicable signed by an officer or principal of the

company.

g. If the qualifications proposal is deemed incomplete or indicates unacceptable staffing, experience or

skills, WCPS will not open the price proposal; the price proposal would be returned unopened to the

bidder.

h. The time/date for opening of Price Proposals will not be publicly announced. Information contained in the

qualifications proposals will not be released to the public until a final decision is made by the Board of

Education.

21

Page 22: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement

SECTION IV – SPECIFICAITONS

Section 01013

Summary of the Work

Asbestos Abatement Services

Part 1 – General

Project Intent:

1.1 The Intent of this contract is to establish an on call unit cost contract for asbestos

abatement services. Asbestos abatement services may be required in the routine

maintenance or replacement of Heating & Ventilation building components and in

the overall building renovation, window replacement or cosmetic upgrade of a

facility.

1.2. Work shall include, but may not be limited to the following:

i. Removal of specified quantities of asbestos-containing building materials including

paint covered surfaces.

ii. Repair and/or encapsulation of asbestos-containing building materials.

iii. Cleaning of areas contaminated with asbestos.

1.2.1 Authority to Stop Work: The Owner has the authority to stop the abatement work, at the

time the Owner determines either personally or through the services of the Industrial

Hygienist (IH) that conditions are not within the specifications and applicable regulations.

The stoppage of work shall continue until conditions have been corrected and corrective

steps have been taken to the satisfaction of the Owner. Standby time required to resolve

violations shall be at the Contractor’s expense.

1.2.2 Contractor work within a containment area (including but not limited to preparation or final

cleaning of containment area) shall not take place until the IH has inspected the

containment area.

1.2.3 Responsibility for Damages: Any damages to the finishes, floors, walls, or any other items

or fixtures that are to remain or be salvaged, that has been a result of actions by this phase of

the work shall be repaired to their original condition without any additional cost to the

Owner. A comparison of the pre-demolition inspection report shall be the basis for the

assessment of damages to be addressed.

1.3 Work to Be Done

1.3.1 The work to be done consists of the furnishing of all labor, materials, equipment and

performing the work required for Asbestos Abatement Services on a unit cost, on call basis,

in accordance with the specifications and drawings forming a part hereof and comprising

general interior building demolition, asbestos abatement and such work as may be required

for the completion of the contract within the intent and scope of the drawings and

specifications.

22

Page 23: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.3.2 The general administrative requirements of the Contract are set forth in the following

specification sections:

01013 Summary of the work – Asbestos Abatement

01043 Project Coordination – Asbestos Abatement

01091 Definitions and Standards– Asbestos Abatement

01313 Schedules, Reports, Meetings – Asbestos Abatement

01313 Products and Substitutions– Asbestos Abatement

01092 Applicable Codes– Asbestos Abatement

01503 Temporary Facilities– Asbestos Abatement

01526 Temporary Enclosures

01410 Test Laboratory Systems

01563 Decontamination Units

01513 Pressure Differential System

01560 Worker Protection– Asbestos Abatement

01562 Respiratory Protection

01046 Cutting and Patching - Asbestos Containing Materials

02081 Removal of Asbestos Containing Materials

02082 Removal of Asbestos Contaminated Soil

02084 Disposal of Asbestos Containing Waste Material

01710 Cleaning and Decontamination Procedures

01711 Project Decontamination

01714 Work Area Clearance

01701 Project Closeout

01526 Local Area Preparation

01561 Worker Protection- Repair and Maintenance

01562 Respiratory Protection

01528 Entry into Controlled Areas

02083 Disturbance of Small Areas of Asbestos Containing Materials

1.4 Potential Asbestos Hazard

The disturbances or dislocation of asbestos-containing materials may cause asbestos fibers to be

released into the building’s atmosphere, thereby creating a potential health hazard to workmen and

building occupants. Apprise all workers, supervisory personnel, subcontractors and consultants who

will be at the job site, of the seriousness of the hazard and of proper work procedures which must be

followed. Where in the performance of the work, workers, supervisory personnel, subcontractors, or

consultants may encounter, disturb, or otherwise function in the immediate vicinity of any identified

asbestos-containing materials, take appropriate continuous measures as necessary to protect all

building occupants from the potential hazard of exposure. Such measures shall include the

procedures and methods described herein, and compliance with regulations of applicable federal,

state and local agencies.

1.5 Stop Work:

If the Owner or the Project Administrator presents a written stop work order, immediately and

automatically stop all work. Do not commence work until authorized in writing by Owner.

23

Page 24: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Any surface areas of ACM (Asbestos Containing Materials) contamination, material delaminating

or associated debris are to be thoroughly cleaned, and the surface area rendered free from hazardous

material.

1.6 Project Air Monitoring and IH Services

1.6.1 The provision of Project Air Monitoring and industrial hygiene services are not within the

Contractor’s scope of work. A representative of the IH firm is to be on-site during all critical

periods of the project, (i.e. pre-abatement inspection, background air or surface sampling,

asbestos removal, encapsulation, final cleaning, tear down, etc.). This representative is to be

responsible for documenting the quality of work practices being employed by the

Contractor, and to immediately notify the Washington County Public Schools Contract

Administrator of any potential risk to the building or its occupants. Observations are to be

recorded in a written format in accordance with these specifications and submitted daily for

review to a Washington County Public Schools Representative. A mutually convenient

location will be designated for the submission of the documents. (Not sure what to do with

this paragraph)

1.7 Contractor Use of Premises

1.7.1 The Contractor shall limit his use of the premises to the work indicated so as to allow for

Owner occupancy and use by the public.

1.7.2 Confine operations at the site to the areas permitted under the Contract. Portions of the site

beyond areas on which work is indicated are not to be disturbed. Conform to site rules and

regulations affecting the work while engaged in project construction.

1.7.3 Keep existing driveways and entrances serving the premises clear and available to the

Owner and his/her employees at all times. Do not use these areas for parking or storage of

materials.

1.7.4 Do not unreasonably encumber the site with materials or equipment. Confine stockpiling of

materials and location of storage sheds to the areas indicated. If additional storage is

necessary, obtain and pay for such storage off site.

1.7.5 Existing toilet facilities, if used, must be maintained in the order that they were received by

the Contractor. Toilet facilities allowed to be used will be marked on the drawings if

applicable. Upon completion of the work, the facilities will be cleaned.

1.7.6 Maintain existing building in a safe and weather tight condition throughout the construction

period. Repair damage caused by construction operations. Take all precautions necessary to

protect the building and its occupants during the construction period.

1.7.7 Keep public areas such as hallways, stairs, elevator lobbies and toilet rooms free of waste,

rubbish or construction debris.

1.7.8 Take all proper precautions to protect persons from injury and unnecessary interference or

inconvenience, leave an unobstructed way along paths and private places for pedestrians and

vehicles and for access to hydrants. Walks and other surfaces outside of the Contract which

by reason of this construction becomes littered with earth and other debris are to be cleaned

at the end of each working day. Permanent walks shall be kept open at all times.

24

Page 25: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.7.9 Replace and put in good condition every public way and private way, catch basin, conduit,

trees, fence or things injured in carrying out the contract, unless the same shall be

permanently done away with by order of the owner as being unnecessary for the proper

carrying out of the Contract. Permission from the owner must be obtained.

1.7.10 The types of temporary security and protection provisions required include, but not by way

of limitation, fire protection, barricades, warning signs, lights, site enclosure fences,

sidewalk bridges, building enclosure/lockup, watchman service, environmental protection,

and similar provisions intended to minimize property losses, personal injuries and claims for

damages at project site.

1.7.11 The Owner reserves the right to place and install equipment as necessary in areas of the

building in which all asbestos abatement and project decontamination procedures have been

completed, and to occupy such completed areas prior to substantial completion, provided

that such occupancy does not substantially interfere with completion of the work. Such

placing of equipment and partial occupancy shall not constitute acceptance of the work or

any part of the work.

1.7.12 Tobacco Products - Are not permitted on WCPS property.

End of Section 01013

25

Page 26: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01043

Project Coordination – Asbestos Abatement

Part 1 – General

1.1 Related Documents:

Drawings and general provisions of Contract apply to work of this section.

1.2 Special Reports

Except as otherwise indicated, submit special reports directly to Owner within

one day of occurrence requiring special report.

1.2.1 When an event of unusual and significant nature occurs at site (i.e. failure of negative

pressure system, rupture of temporary enclosures), prepare and submit a special report

listing chain of events, persons participating, response by Contractor’s personnel, evaluation

of results or effects, and similar pertinent information. When such events are known or

predictable in advance, advise Owner in advance at earliest possible date.

1.2.2 Prepare and submit reports of significant accidents, at site and anywhere else work is in

progress. Record and document data and actions; comply with industry standards. For this

purpose, a significant accident is defined to include events where personal injury is

sustained, or property loss of substance is sustained, or where the event posed a significant

threat of loss or personal injury.

1.3 Submittals During The Work: Final payment will be withheld until the Contractor has

provided the following documents.

Submit copies of the following items to the IH within 30 days of completion.

1.3.1 Security and safety logs showing names of persons entering the work space, date and time of

entry and exit, record of any accident, emergency evacuation, and any other safety and/or

health incident.

1.3.2 Copies of disposal certificates shall be submitted to the Owner and IH within 24 hours after

each disposal of asbestos material.

1.3.3 All required permits, clearances, licenses, including certificates for Project Designer, Project

Supervisor and all workers.

1.4 Notifications, Permits, Warning Signs, Labels and Posters:

1.4.1 Provide required NESHAP or other project notification to (within the required time frame)

regional, state, and local authority having jurisdiction on the project. Secure all permits

required for work, including of asbestos in an approved landfill.

1.4.2 Provide copies of any notifications to the Owner and IH before commencement of the work.

26

Page 27: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.4.3 Erect warning signs around the work space and at every point of potential entry from the

outside. The warning signs shall meet the requirements of OSHA and AHERA.

1.4.4 Provide the required labels for all plastic bags and all drums utilized to transport

contaminated material to the landfill. License number and date shall also be

placed on all the waste containers/bags.

1.4.5 Provide any other signs, labels, warnings, and posted instructions that are necessary to

protect, inform, and warn people of the hazard from asbestos exposure. Post in a prominent

and convenient place for the workers, a copy of the latest applicable regulations from

OSHA, EPA, NIOSH, and COMAR.

1.5 Submittals

1.5.1 Before the start date of work, submit the following to the Owner. No work shall begin until

these submittals are approved by written documentation for unrestricted use or final-but-

restricted use.

Submittals Checklist

Required in accordance with Washington County Public Schools specifications inclusive of but limited to:

Prior to Start of Work

Section Page Description

____ 01013 23 Assessment of pre-existing damage and/or conditions

____ 01043 28 Copies of licenses and permits

____ 01340 57 MSDS Product information on encapsulant

____ 01513 75 Negative Pressure Patent Infringement

____ 01092 53 Copies of notifications to EPA and State of MD

____ 01313 55 Detailed schedule of work

____ 01340 58 MSDS Full product information on all

replacement/reinsulation materials (if applicable)

____ 01560 88 Training Certifications

____ 89 Medical Examination Statements

____ 01562 95 Respiratory protection product data, operating manual,

respiratory protection program, and history of past airborne

fiber levels to justify level of protection selected.

The following documentation must be maintained daily at the site.

____ 01562 95 Record of most recent fit testing

____ 01563 109 Documentation of water filtration (manufacturers data)

27

Page 28: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

____ 02081 145 Product information on surfactants, encapsulant, (inclusive of

NESHAPS data and MSDS sheets)

____ 01043 27 Special reports (as needed)

____ 27 Employee/Visitor Log-in sheets to restrict areas

____ 01043 28 Disposal Manifests

____ 01313 55 Daily Logs

____ 01410 66 Air sampling results (within 24 hours)

____ 01513 75 Pressure differential readings

____ 01513 75 Record of last HEPA unit inspection/certification

____ 01711 129 Documentation of final inspection by IH

____ 01714 142 Laboratory analysis results

Following the Performance of the Work

____ 01701 124 Prerequisites to final acceptance

____ 01701 124 Submission of two copies of the final report, with completed

waste manifests, diagrams of work areas sampling and all air

sampling results

Part 2-- Products

2.1 Materials

2.1.1 Encapsulant: The encapsulating agents shall be penetrating sealants and shall meet the

following criteria:

2.1.1.1 They shall withstand most impact or abrasion and protect the encapsulant surface.

2.1.1.2 Encapsulant selected for use by the Asbestos Abatement Contractor shall be one of

those demonstrating probable effective performance under the tests conducted by

an independent testing laboratory and are approved by the IH.

2.1.1.3 They shall have high flame retardant characteristics and a low toxic fume and

smoke emission rating

2.1.14 They shall not be noxious or toxic to application workers, or subsequent users of

the building

2.1.1.5 They shall have some permeability to water vapor to prevent condensation

accumulation, and resist solution by common cleaning agents.

2.1.1.6 They shall have acceptable weathering and aging characteristics

28

Page 29: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

2.1.1.7 They shall be acceptable by architectural standards

2.1.1.8 They shall be compatible with substrate material and any remaining non-asbestos

insulation materials

2.1.1.9 They shall be demonstrably capable of adhering to the surfaces of the substrate.

2.2 Tools and Equipment

2.2.1 Airless Sprayer: An airless sprayer, suitable for application of encapsulating material, shall

be used

2.2.2 Asbestos Filtration Device (AFD): Asbestos filtration devices shall utilize High Efficiency

Particulate Absolute (HEPA) filtration systems

2.2.3 Scaffolding: Scaffolding, as required to accomplish the specified work, shall meet all

applicable safety regulations

2.2.4 Transportation Equipment: Transportation equipment, shall be suitable for loading,

temporary storage, transmit, and unloading of contaminated waste without exposure to

persons or property

2.2.5 Vacuum Equipment: All vacuum equipment utilized in the work area shall utilize HEPA

filtration systems. All HEPA equipment may be tested at the direction of the Owner to

determine if HEPA filtration is being achieved.

2.2.6 Water Sprayer: The water sprayer shall be an airless or other low pressure sprayer for

amended water application

2.2.7 Negative Pressure System: The use of a negative air pressure system as described in Section

01513 shall not be used for all containment areas unless otherwise noted in the application

2.2.8 Other Tools and Equipment: The Asbestos Abatement Contractor shall provide other

suitable tools for stripping, removal, encapsulation and disposal activities including, but not

limited to: hand held scrapers, wire brushes, sponges, rounded edge shovels, brooms, and

carts

End of Section -01043

29

Page 30: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01091

Definitions and Standards – Asbestos Abatement

Part 1 – General

1. Related Documents

1.1. Drawings and general provisions of Contract and other Division-1 Specification sections, apply to

work of this section

1.2 Definitions

1.2.1 General Explanation: A substantial amount of specifications language constitutes definitions

for terms found in other contract documents, including the drawings. (Drawings must be

recognized as diagrammatic in nature and not completely descriptive of the requirements

indicated thereon.). Certain terms used in contract documents are defined in this article.

Definitions and explanations of this section are not necessarily either complete nor

exclusive, but are general for the work to the extent they are not stated more explicitly in

another element of contract documents

1.2.2 Project Site: The term “Project Site” is defined as the space available to the

Contractor for performance of the work, either exclusively or in conjunction with

others performing other work as part of the project. The extent of the project site

is shown on the drawings, and may or may not be identical with the description of

land upon which the project is to be built

1.2.3 Furnish: Expect as otherwise defined in great detail, the term “furnish” is used to

mean supply and deliver to the project site, ready for unloading, unpacking,

assembly, installation, etc., as applicable in each instance

1.2.4 Install: Except as otherwise defined in greater detail, the term “install” is used to

describe operations at the project site including unloading, unpacking, assembly,

erection, placing, anchoring, applying, working to dimension, finishing, curing,

protecting, cleaning and similar operations, as applicable in each instance

1.2.5 Provide: Except as otherwise defined in greater detail, the term “provide” means

furnish and install, complete and ready for intended use, as applicable in each

instance

1.2.6 Installed: The term “installed” is defined as the entity (person or firm) engaged by

the Contractor, or its subcontractor or sub-subcontractor for performance of a

particular unit of work at the project site, including installation, erection,

application and similar required operations. It is a general requirement that such

entities (Installers) be expert in operations they are engaged to perform.

1.2.7 Testing Laboratory: The term “testing laboratory” is defined as an independent

entity engaged to perform specific inspections or tests of the work, either at the

project site or elsewhere; and to report and (if required) interpret results of those

inspections or tests

30

Page 31: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.3 Definitions Relative to Asbestos Abatement

1.3.1 Aerosol: A system consisting of particles, solid or liquid, suspended in air

1.3.2 Air Cell: Insulation normally used on pipes and duct work that is comprised of corrugated

cardboard which is frequently comprised of asbestos combined with cellulose or refractory

binders

1.3.3 Air Monitoring: The process of measuring the fiber content of a specific volume of air

1.3.4 Amended Water: Water to which a surfactant has been added

1.3.5 Asbestos: The asbestiform varieties of serpentinite (chrysotile), riebeckiet (crocidolite),

cummingtonite-grunerite, anthophyllite, and actinolite-tremolite. For purposes of

determining respiratory and worker protection both the asbestiform and non-asbestiform

varieties of the above minerals and any of these materials that have been chemically treated

and/or altered shall be considered as asbestos

1.3.6 Asbestos-Containing Material (ACM): Any material containing more than 1 % by volume

of asbestos of any type or mixture of types

1.3.7 Asbestos-Containing Waste Material: Any material which is or is suspected of being or any

material contaminated with an asbestos containing material which is to be removed from a

work area for disposal

1.3.8 Authorized Visitor: The Owner, the Owner’s Representative, testing lab personnel, the

Architect/Engineer or a representative of any federal, state and local regulatory or other

agency having authority over the project

1.3.9 Barrier: Any surface that seals off the work area to inhibit the movement of fibers

1.3.10 Breathing Zone: A hemisphere forward of the shoulders with a radius of approximately 6-9

inches

1.3.11 Ceiling Concentration: The concentration of an airborne substance that shall not be

exceeded

1.3.12 Certified Industrial Hygienist (CIH): An industrial hygienist certified in Comprehensive

Practice by the American Board of Industrial Hygienist

1.3.13 Demolition: The wrecking or taking out of any building component, system, finish or

assembly of a facility together with any related handling operations

1.3.14 Disposal Bag

1.3.14.1 The initial or internal disposal bag is to be reinforced or woven plastic that is

resistant to punctures or tears by sharp objects. This is to be used in addition to the

external disposable bag

31

Page 32: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.3.14.2 The external disposal bag is to be 6 mil thick leak tight plastic bags used for

transporting asbestos waste from work and to disposal site. Each is labeled as

follows:

DANGER

CONTAINS ASBESTOS FIBERS

AVOID CREATING DUST

CANCER AND LUNG DISEASE HAZARD

And

CAUTION

Contains Asbestos Fibers

Avoid opening or breaking container

Breathing asbestos is hazardous to your health

1.3.14.3 All materials are to be contained within a minimum of two completed sealed

disposal bags. No leakage of any kind shall occur.

1.3.15 Encapsulant: A material that surrounds or embeds asbestos fibers in an adhesive

matrix, to prevent release of fibers Bridging Encapsulant: An encapsulant that

forms a discrete layer on the surface of an in situ asbestos matrix

Penetrating Encapsulant: An encapsulant that is absorbed by the in situ asbestos

matrix without leaving a discrete surface layer

Removal Encapsulant: A penetrating encapsulant specifically designed for removal

of asbestos-containing materials rather than for in situ encapsulation

1.3.16 Encapsulation: Treatment of asbestos-containing materials, with an encapsulant

1.3.17 Enclosure: The construction of an air-tight, impermeable, permanent barrier around

asbestos-containing material to control the release of asbestos fibers into the air

1.3.18 Filter: A media component used in respirators to remove solid or liquid particles

from the inspired air.

1.3.19 Friable Asbestos Material: Material that contains more than 1.0% asbestos by

volume, and that can be crumbled, pulverized, or reduced to powder by hand

pressure when dry.

1.3.20 Glove bag: A sack (typically constructed of 6 mil transparent polyethylene or

polyvinylchloride plastic) with two inward projecting long sleeve gloves which are

designed to enclose an object from which an asbestos-containing material is to be

removed.

1.3.21 HEPA Filter: A High Efficiency Particulate Absolute (HEPA) filter capable of

trapping and retaining 99.97 % of asbestos fibers greater than 0.3 microns in

length.

32

Page 33: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.3.22 HEPA Filter Vacuum Collection Equipment (or vacuum cleaner): High fficiency

Particulate Air (absolute) filtered vacuum collection equipment with a filter system

capable of collecting and retaining asbestos fibers.

1.3.23 High-Efficiency Filter: A filter which removes from air 99.97% or more of

monodisperse dioctyl phthalate (DOP) particles having a mean particle diameter of

0.3 micrometers

1.3.24 Negative Pressure Respirator: A respirator in which the air pressure inside the

respiratory-inlet covering is positive during exhalation in relation to the air

pressure of the outside atmosphere and negative during inhalation in relation to the

air pressure of the outside atmosphere

1.3.25 Negative Pressure Ventilation System: A local exhaust system, utilizing HEPA

filtration capable of maintaining a negative pressure inside the work area and a

constant air flow from adjacent areas into the work area and exhausting that air

outside the work area

1.3.26 Differential Pressure: Air pressure lower than surrounding areas, generally caused

by exhausting air from a sealed space (work area)

1.3.27 Personal Monitoring: Sampling of the asbestos fiber concentrations within the

breathing zone of an employee

1.3.28 Protection Factor: The ration of the ambient concentration of an airborne substance

to the concentration of the substance inside the respirator at the breathing zone of

the wearer. The protection factor is a measure of the degree of protection provided

by a respirator to the wearer

1.3.29 Respirator: A device designed to protect the wearer from the inhalation of harmful

atmospheres

1.3.30 Surfactant: A chemical wetting agent added to water to improve penetration, thus

reducing the quantity of water required for a given operation of area

1.3.31 Time Weighted Average (TWA): The average concentration of a contaminant in

air during a specific time period (usually 8 hours)

1.3.32 Visible Emissions: any emissions containing particulate asbestos material that are

visually detectable without the aid of instruments. This does not include condensed

uncombined water vapor

1.3.33 Wet Cleaning: The process of eliminating asbestos contamination from building

surfaces and objects by using cloths, mops or other cleaning utensils which have

been dampened with amended water and afterwards thoroughly decontaminated or

disposed of as asbestos contaminated waste

1.3.34 Work Area: The area where asbestos related work or removal operations are

performed which is defined and/or isolated to prevent the spread of asbestos dust,

fibers or debris, and entry by unauthorized personnel. Work area is a Regulated

Area as defined by 29 CFR 1926

33

Page 34: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.3.35 Excursion Limit: Personal air samples taken for 30 minute intervals to determine

that exposed airborne concentrations of asbestos are not in excess of 1.0 Fiber per

cubic centimeter of air (1.0 f/cc)

.

1.4 Abbreviations and Names

1.4.1 Abbreviations and names: Where acronyms or abbreviations are used but not identified in

specifications or other contract documents they are defined to mean the industry recognized

name of trade association, standards generating organization, governing authority or other

entity applicable to context of text provision. Refer to “Encyclopedia of Associations”,

published by Gale Research Co., available in large libraries

1.4.2 Abbreviation and Names: the following acronyms or abbreviations as referenced in contract

documents are defined to mean the associated names. Both names and addresses are subject

to change, and are believed to be, but are not assured to be, accurate and up to date as of date

of contract documents:

AIA American Institute of Architects

1735 New York Avenue, NW

Washington, DC 20006

(202) 626-7474

ANSI American National Standards Institute

1430 Broadway

New York, NY 10018

(212) 354-3300

ASHRAE American Society for Heating, Refrigerating, and Air

Conditioning Engineers

1791 Tullie Circle, NE

Atlanta, GA 30329

(404) 636-8400

ASTM American Standard for Testing and Materials

1916 Race Street

Philadelphia, PA 19103

(215) 299-5400

CFR Code of Federal Regulations

Available from Government Printing Office

Washington, DC 20402

(Usually first published in the Federal Register)

CGA Compressed Gas Association

1235 Jefferson Davis Highway

Arlington, VA 22202

(703) 979-0900

CS Commercial Standard of NBS

34

Page 35: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

(U.S. Department of Commerce)

Government Printing Office

Washington, DC 20402

DOT Department of Transportation

400 Seventh St, NW

Washington, DC 20406

(202) 426-0677

EPA Environmental Protection Agency

401 M St, SW

Washington, DC 20406

(202) 382-3949

FS Federal Specifications

(General Services Administration)

Obtain from your Regional GSA office, or purchase from

GSA Specification Unit (WFSIS)

7th and D Streets

Washington, DC 20406

(202) 472-2205 or 2140

GA Gyspum Association

1603 Orrington Ave

Evanston, IL 60201

(312) 491-1744

GSA General Services Administration

F ST and 18th ST, NW

Washington, DC 20405

(202) 655-4000

MIL Military Standardization Documents

(US Department of Defense)

Naval Publications and Forms Center

5801 Tabor Ave

Philadelphia, PA 19120

NIST National Institute of Standards and Technology

(US Department of Commerce)

100 Bureau Drive

Gaithersburg, MD 20899

(301) 975-1000

NEC National Electrical Code (by NFPA)

NFPA National Fire Protection Association

Batterymarch Park

Quincy, MA 02269

(617) 770-3000

35

Page 36: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

OSHA Occupational Safety and Health Administration

(US Department of Labor)

Government Printing Office

Washington, DC 20402

PS Product Standard of NIST

(U.S Department of Commerce)

Government Printing Office

Washington, DC 20402

UL Underwriters Laboratories

333 Pfingsten Road

Northbrook, IL 60062

(312) 272-8800

End of Section 01091

36

Page 37: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01092

Codes and Regulations – Asbestos Abatement

Part 1-General

1.1 Related Documents

Drawings and general provisions of contract, including General and Supplementary

Conditions and other Division-1 Specification section, apply to work of this section

1.2 Description of the Work

This section sets forth governmental regulations and industry standards which are included and

incorporated herein by reference and a made a part of the specification. This section also sets forth

those notices and permits which are known to the Owner and which either must be applied for and

received, or which must be given to governmental agencies before start of work

1.3 Codes and Regulations

1.3.1 General Applicability of Codes, Regulations, and Standards: Except to the extent that more

explicit or more stringent requirements are written directly into the contract documents all

applicable codes, regulations, and standards have the same force and effect (and are made a

part of the contract documents by reference) as if copied directly into the contract

documents, or as if published copes are bound herewith.

1.3.2 Contractor Responsibility: The Contract shall assume full responsibility and liability for the

compliance with all applicable Federal, State, local regulations pertaining to work practices,

hauling, disposal, and protection of workers, visitors to the site, and person occupying areas

adjacent to the site. The Contract is responsible for providing medical examinations and

maintaining medical records of personnel as required by the applicable Federal, State, and

local regulations. The Contractor shall hold the Owner harmless for failure to comply with

any applicable work, hauling, disposal, safety, health or other regulation on the part of

himself, his employees, or his subcontractors

1.3.3 Federal Requirements: Which govern asbestos abatement work or hauling and disposal of

asbestos waste materials include but are not limited to the following:

U.S. Department of Labor, Occupational Safety and Health Administration, (OSHA),

including but not limited to:

Occupational Exposure to Asbestos, Tremolite, Anthophyllite, and Actinolite; Final

Rules Title 29, Part 1910, Section 1001 and Part 1926, Section 58 of the Code of Federal

Regulations

Respiratory Protection

Title 29, Part 1910, Section 134 of the Code of Federal Regulations

Construction Industry

Title 29, Part 1926, of the Code of Federal Regulations

Access to Employee Exposure and Medical Records

37

Page 38: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Title 29, 1910, Section 2 of the Code of Federal Regulations

Hazard Communications

Title 29, Part 1910, Section 1200 of the Code of Federal Regulations

Specifications for Accident Prevention Signs and Tags, Title 29, Part 1910,

Section 145 of the Code of Federal Regulations

U.S. Environmental Protection Agency (EPA) including but not limited to:

Asbestos Abatement Projects Rule

40 CFR Part 762

CPTS 62044, FRL 2843-9

Federal Register, Vol 50, No. 134, July 12, 1985

P28530-28540

Regulation for Asbestos

Title 40, Part 61, Subpart A of the Code of Federal Regulations

National Emission Standard for Asbestos

Title 40, Part 61, Subpart M (Revised Subpart B) of the Code of

Federal Regulations

Asbestos Containing Materials for Schools

40 CFT Part 763

Federal Register, Volume 52, No. 210,

October 30, 1987

1.3.4 State Requirements: Which govern asbestos abatement work or hauling and disposal of

asbestos waste materials include but are not limited to the following:

State of Maryland

Office of Environmental Programs

Air Management Administration

COMAR Regulations 10.18.23

License to Remove and Encapsulate Asbestos

Maryland Occupational Safety and Health

Department of Licensing and Regulations

Division of Labor and Industry

1.4 Standards

Which govern asbestos abatement work or hauling and disposal of asbestos waste materials include

but are not limited to the following;

1.4.1 American National Standards Institute (ANSI)

1430 Broadway

New York, NY 10018

(212) 354-3300

38

Page 39: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.4.2 Fundamental Governing the Design and Operation of Local Exhaust Systems

Publication Z9.2-79

1.4.3 Practices for Respirator Protection Publication Z288.2-80

1.4.4 American Society for Testing and Materials (ASTM)

1916 Race Street

Philadelphia, PA 19103

(215) 299-5400

Specification for Encapsulants for Friable Asbestos Containing Building Materials Proposal P-189

Safety and Health Requirements relating to Occupational Exposure to Asbestos. E849-82

1.5 Federal Notices

Send written notification as required by US EPA National Standards for Hazardous Air Pollutants

(NESHAPS) Asbestos Regulation (40 CFR 61, SubPart M) to the regional Asbestos NESHAPS

contact at least 10 days prior to beginning any work on asbestos containing materials. Send

notifications to the following address:

Region 3

Asbestos NESHAPS Contact

Air and Waste Management Division

841 Chestnut Street

Philadelphia, PA 19107

1.5.1 Notification: Include the following information in the notification sent to the NESHAP’s

contact:

1.5.1.1 Name and Address of Owner and Operator

1.5.1.2 Description of the facility being demolished or renovated, including the size, age,

and prior use of the facility

1.5.1.3 Estimate of the approximate amount of friable asbestos material present in the

facility in terms of linear feet of pipe, and surface area on other facility

components. For facilities in which the amount of friable asbestos materials is less

than 80 linear meters (260 linear square feet) on pipes and less than 15 square

meters (160 square feet) on other facility components, explain techniques of

estimation

1.5.1.4 Location of the facility being demolished or renovated

1.5.1.5 Scheduled starting and completion dates of demolition or renovation

1.5.1.6 Nature of planned demolition or renovation and method(s) to be used

1.5.1.7 Procedures to be used to comply with the requirements of EPA National Emission

Standards for Hazardous Air Pollutants (NESHAPS) Asbestos Regulations (40

CFR60 SubPart M)

39

Page 40: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.5.1.8 Name and location of the waste disposal site where the friable asbestos waste

material will be deposited

1.6 State Notification and Licenses

Maintain current licenses as required by State of Maryland COMAR Regulations 10.18.23. Send

written notification within 10 days prior to beginning any work on asbestos-containing materials.

Send notifications to the following address:

Maryland Air Management Administration

1800 Washington Blvd

Baltimore, MD 21230

1.7 Submittals

Before beginning any work on the Contract, submit all notices sent to the US EPA and State to

the Owner for his approval. No work shall begin until these submittals are approved by the Owner.

The Contractor will submit to the Owner, before beginning the work, a copy of his current licenses

required by Federal and State to carry out the work of this Contract.

End of Section 01092

40

Page 41: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01313

Schedules, Reports, Meetings

Part 1-General

1.1 Related Documents

Drawings and general provisions of Contract, including General and Supplementary Conditions and

other Division 1 Specifications sections, apply to work of this section.

1.2 Schedules

Provide proposed detailed schedule including work dates, work shift time, number of employees,

dates of start and completion including dates of preparation work, removals and final inspection

dates.

1.3 Reports

Daily Log: Maintain within the Decontamination Unit a daily log documenting the dates and time of

but not limited to the following items:

1.3.1 Meetings; purpose, attendees, discussion (brief)

1.3.2 Visitations; authorized and unauthorized

1.3.3 Personnel, by name, entering and leaving the work area

1.3.4 Special or unusual event, i.e. barrier breaching, equipment failures

1.3.5 Air monitoring tests (24 hour turnaround time)

End of Section 01313

41

Page 42: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01340

Drawings, Product Data and Samples

Part 1-General

1.1 Related Documents

Drawings and general provisions of Contract, including General and Supplementary Conditions and

other Divisions 1 Specifications sections, apply to work of this section

1.2 Description of Requirements

1.2.1 This section specifies procedural requirements for non-administrative submittals including

shop drawings, product data, samples and other miscellaneous work related submittals.

1.2.2 Shop drawings are technical drawings and data that have been specifically prepared by or on

behalf of the Contractor for this project. The Contractor shall add in red ink all addenda and

supplemental items on all drawings and specifications which are to be used at the job site

1.2.3 Samples are physical examples of work, including but not limited to the following items:

Partial sections of manufactured or fabricated work

Small cuts or containers of materials

Complete units of repetitively used materials

Swatches showing color, texture, and pattern

Color range sets

Units of work to be used for independent inspection and testing

1.2.4 Miscellaneous submittals are work related, non-administrative submittals that do not fit in

the three previous categories, including, but not limited to the following:

Specially prepared and standard printed warranties

Maintenance agreements

Workmanship bonds

Survey data and reports

Project photographs

Testing and certification reports

Record drawings

Operating and maintenance manuals

Keys and other security protection devices

Maintenance tools and spare parts

Overrun stock

1.2.5 Product Data: General information required specifically as product data includes

manufacturer’s standard printed recommendations for application and use, compliance with

recognized standards of trade associations and testing agencies, and the application of their

labels and seals (if an), special notation of dimensions which have been verified by way of

field measurement, and special coordination requirements for interfacing the material,

produce or system with other work.

End of Section 01340

42

Page 43: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01410

Air Monitoring Test Laboratory Services

Part 1-Description of the Work

1.1 This section describes air monitoring carried out by the Industrial Hygiene Firm to verify that the

building beyond the work area and the outside environment remain uncontaminated.

Air monitoring required by OSHA is the work of the Contractor and is not covered in this section

1.2 Related Documents

Drawings and general provisions of the Contract, including General and Supplementary Conditions

and other Division 1 Specification sections, apply to the work of this section

1.3 Air Monitoring

Air monitoring during work area clearance is described in Section 01714 Work Area Clearance

1.4 Industrial Hygienist

The term “IH” where used in this section of the specifications shall mean the “Industrial Hygienist”

employed by WCPS. The IH may delegate his/her representative to conduct the actual contract

monitoring, to be under the IH’s guidance and supervision

1.4.1 The performance and execution of the work shall be monitored periodically by the IH or his

designated representative. The monitoring shall be inside the work area and the

surroundings to ensure full compliance with these specifications and all applicable

regulations

1.4.2 The continuous monitoring and checking shall include air samples in the workplace,

personnel samples at breathing levels for a number of workers to be determined by the IH,

air samples in the areas surrounding the work area and the outside, checking of the Standard

Operating Procedures, Engineering Control System, Respiratory Protection System,

Packing, Parking, Transporting and Disposal of Asbestos, Decontamination Facilities and

Procedures and any other aspects of the abatement process that may impact the health and

safety of the people and the pollution of the environment

1.4.3 Inspection of work area and decontamination enclosures. Prior to any removal of asbestos

containing material, notify the owner for inspection

1.4.4 All cost in connection with the laboratory work required in Paragraph 1.4.2 above for the

initial analysis, and the costs of all subsequent laboratory analyses taken because the limits

specified were exceeded on the initial tests, shall be borne by the Asbestos Abatement

Contractor

1.4.5 The Asbestos Abatement Contractor must notify the IH at least two weeks prior to the

planned start of the asbestos removal. The IH will take required air samplings after the

contract work, and be present to monitor the asbestos removal, including adequacy of seals

prior to work start and periodically throughout the removal

43

Page 44: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.4.6 All daily monitoring results will be available to the Owner and IH within 24 hours for their

evaluation of the progress of the project

End of Section 01410

44

Page 45: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01503

Temporary Facilities - Asbestos Abatement

Part 1 –General

1.1 Related Documents

Drawings and general provisions of the Contract, including General and Supplementary conditions

and other Division 1 Specifications sections, apply to the work of this section

1.2 Description Requirements

Provide temporary connection to existing building utilities or provide temporary facilities as

required herein or as necessary to carry out the work

Part 2-Products

2.1 Materials and Equipment

Provide new or used materials and equipment that are undamaged and in serviceable condition.

Provide only materials and equipment that are recognized as being suitable for the intended use, by

compliance with appropriate standards

2.2 Scaffolds, Ways, Apparatus, Etc.

2.2.1 Contractor shall furnish and maintain all necessary derricks, hoisting machinery,

scaffolding, ladders and/or staging, etc. required for the execution of the work

2.2.2 Scaffolding may be of suspension type, or standing type such as metal tube and coupler,

tubular welded frame, pole or outrigger type or cantilever type. The type, erection and use of

all scaffolding shall comply with all applicable OSHA provisions

2.2.3 During the erection and/or moving of scaffolding, care must be exercised so that the

polyethylene floor covering is not damaged

2.3 Temporary Water Supply and Temporary Electric Services

2.3.1 The Contractor will be permitted to use existing sources for utilities during this contract.

These shall include water and electric. The Contractor shall make his own connections in a

manner complying with all applicable codes. No charge will be made for the use of these

utilities as long as the Contractor does not waste these utilities. Should waste be established

then the privilege of free use of these utilities will be withdrawn and the Contractor will be

required to install meters at his own expense and reimburse the Owner for their cost in

connection with these utilities. The Contractor will also be responsible for his subcontractors

in connection with the waste of these utilities

2.3.2 These provisions will be strictly enforced

45

Page 46: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

2.3.3 If existing water supply does not exist during the duration of this Contract, the Contractor

will be responsible for supplying water to the site. The Contractor will be responsible for the

cost of the water needed on site.

2.3.4 The Contractor will provide receptacle outlets equipped with ground fault circuit

interrupters, reset button and pilot light, for plug in connection of power tools and

equipment

2.3.5 Use only grounded extensions cords, use “hard-service” cords where exposed to abrasion

and traffic. Use single lengths or use waterproof connector to connect separate lengths of

electric cords, if single lengths will not reach are of work

2.3.6 The Contractor will provide general service incandescent lamps of wattage indicated or

required for adequate illumination. Protects lamps with guard cages or tempered glass

enclosures, where fixtures are exposed to breakage by construction operation. Provide

exterior fixtures where fixtures are exposed to the weather or moisture

2.4 First Aid Supplies

Comply with governing regulations and recognized recommendation within the construction

industry. First aid supplies must be on site during all phases of the work

2.5 Fire Extinguishers

Provide Type “A” fire extinguishers for temporary offices and similar spaces where there is

minimal danger of electrical or grease oil flammable liquid fires. In other locations provide type

“ABC” dry chemical extinguishers, or a combination of several extinguishers of NFPA

recommended types for the exposures in each case

Part 3- Execution

3.1 Scaffolding

3.1.1 During the erection and/or moving of scaffolding, care must be exercised so that the

polyethylene floor cover is not damaged

3.1.2 Clean as necessary debris from slip surfaces

3.1.3 At the completion of abatement work, clean all construction aids within the work area, wrap

in one layer of 6 mil polyethylene sheet and seal before removal from the work area

3.2 Installation

Use qualified tradesmen for installation of temporary services and facilities. Locate temporary

services and facilities where they will service the entire project adequately and result in minimum

interference with the performances of the work Relocate, modify, and extend services and facilities

as required during the course of work so as to accommodate the entire work of the project

3.3 Water Service

46

Page 47: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Water connection (without charge) to Owner’s existing potable water system is limited to one ¾”

pipe size connection, and a maximum flow of 10 gpm each to hot and cold water supply. Supply hot

and cold water to the Decontamination Unit in accordance with Section 01515. In addition, water

shall be supplied for the following uses:

3.3.1 Maintain hose connections and outlet valves in leak proof condition. Where finish work

below and outlet might be damaged by spillage or leakage, provide a drip pan of suitable

size to minimize the possibility of water damage. Drain water promptly from pans as it

accumulates

3.4 Electrical Service

Provide a weather proof, grounded temporary electric power service and distribution system of

sufficient size, capacity, and power characteristics to accommodate performance of work during the

construction period. Install temporary lighting adequate to provide sufficient illumination for

safe work and traffic conditions in every area of work.

3.4.1 Power Distribution System: Provide circuits of adequate size and proper characteristics for

each use. In general, run wiring overhead, and fuse vertically where wiring will be at least

exposed to damage from construction operations

3.4.2 Temporary Wiring: Temporary wiring in the work area should be type UF nonmetallic

sheathed cable located overhead and exposed for surveillance. Do not wire temporary

lighting with plain, exposed (insulated) electrical conductors. Provide liquid tight

enclosures or boxes for wiring devices

3.4.2.1 Provide overload protected disconnect switch for each temporary circuit located

at the power distribution center

3.4.2.2 For power hand tools and task lighting, provided a temporary 4 gang outlet at

each decontamination unit, located in the equipment room. Provide a separate

110-120 Volt, 20 Amp circuit for each 4 gang outlet (4 outlets per circuit)

3.4.3 Temporary Lighting: Provide the following where natural lighting or existing building

lighting does not meet the required light level:

3.4.3.1 Provide sufficient temporary lighting to ensure proper workmanship everywhere;

by combined use of daylight, general lighting, and portable plug in task lighting

3.4.3.2 Provide lighting in the Decontamination Unit as required to supply sufficient

temporary light levels.

End of Section 01503

47

Page 48: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01513

Differential Pressure System

Part 1 General

1.1 Related Documents

Drawings and general provisions of Contract, including General and Supplementary Conditions and

other Division 1 Specification sections, apply to work of this section

1.2 Quality Assurance

1.2.1 Provide an automatic recording instrument to monitor the pressure differential in a

representative location. The instrument shall continuously generate a permanent record for

the entire period of removal and clean-up of the area. Manual readings from a recording

device may be substituted if written documentation is made every 15 minutes

Part 2 Products

2.1 Pressure Differential System

The pressure differential system should be constructed of steel or other durable materials able to

withstand damage from rough handling and transportation. The cabinet shall be factory sealed to

prevent asbestos containing dust from being released during use, transport, or maintenance. Access

to and replacement of all air filters shall be from intake end

2.2 Filter

The final filter shall be the HEPA type. The filter media must be completely sealed on all edges

with a structurally rigid frame. A continuous rubber gasket shall be located between the filter and

the filter housing to form a tight seal. Each filter shall be marked with the name of the

manufacturer, serial number, air flow rating, efficiency and resistance, and the direction of test air

flow

2.3 Prefilters

Prefilters, which protect the final filter by removing the large particles, are required to prolong the

operating life of the HEPA filter. Two stages of prefiltration are required. The first stage prefilter

shall be a low efficiency type (i.e. for particle 10 um and larger). The second stage (or

intermediate) filter shall have a medium efficient (i.e. effective for particle down to 5 um). Prefilters

and intermediate filters shall be installed either on or in the intake grid of the unit and held in place

with specials housing or clamps

2.4 Magnahelic Gauge

Each unit shall be equipped with a Magnahelic gauge or manometer to measure the pressure drop

across filters and indicate when filters have become loaded and need to be changed

48

Page 49: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

2.5 The unit shall have an electrical or mechanical lockout to prevent the fan from operating without a

HEPA filter. The units shall be equipped with automatic shutdown systems to stop the fan in the

event of a major rupture in the HEPA filter or blocked air discharge

2.6 The electrical components shall be approved by the National Electrical Manufacturers Association

(NEMA) and Underwriters Laboratory (UL). Each unit shall be equipped with overload protection

sized for the equipment. The motor, fan, fan housing, and cabinet shall be grounded.

2.7 The exhaust of the pressure differential system machine should be ducted into the indoor air. The

plastic around the unit or duct should be sealed with tape.

2.8 The Contractor shall pay all royalties and license fees. He shall defend all units or claims for

infringement of any patent rights and shall save the Owner harmless from loss on account thereof.

A letter of assurance to the Washington County Public Schools from the Contractor to this effect

will be required.

Part 3 Execution

3.1 Pressure Differential

Provide a fully operational pressure differential system within the work area maintaining

continuously a pressure differential across work area enclosures of 0.02 inches of water.

Demonstrate to the Owner the pressure differential by use of a pressure differential meter or

manometer, before disturbance of any asbestos containing materials

3.2 Monitoring

Continuously monitor and record the pressure differential between the work area and the building

outside of the work area with a monitoring device incorporating a strip charge recorder or a

constant written reading every fifteen (15) minutes

3.3 Venting

The exhaust system will be to the outside of the building unless authorized in writing by the Owner

3.4 Use of the Pressure Differential System

3.4.1 General: Each unit shall be serviced by a dedicated minimum 115V-20A circuit with

overload device tied into an existing building electrical panel which has sufficient spare

capacity to accommodate the load of all pressure units connected. Dedication of an existing

circuit may be accomplished by shutting down existing loads on the circuit

3.4.2 Testing the System: Test pressure differential system before any asbestos containing

material is wetted or removed. After the work area has been prepared, the decontamination

facility set up, and the exhaust unit(s) installed, start the unit(s), (one at a time).

3.4.3 Demonstrate operation of the pressure differential system to the Owner will include, but not

be limited to, the following:

3.4.3.1 Plastic barriers and sheeting moved lightly in toward work area

49

Page 50: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.4.3.2 Curtain of decontamination units moved lightly in toward work area

3.4.3.3 There is a noticeable movement of air through the decontamination unit. Use

smoke tube to demonstrate air movement from Clean Room to Shower Room,

from Shower Room to Equipment Room, and from Equipment Room to Work

Area

3.4.3.5 Use a differential pressure meter or manometer to demonstrate a pressure

difference of at least 0.02 inches of water across every barrier separating the

Work Area from the balance of the building or outside

3.4.4 Modify the pressure differential system as necessary to successfully demonstrate

the above

3.4.5 Use of system during abatement operations:

Start exhaust units before beginning work (before any asbestos containing material is

disturbed). After abatement work has begun, run units continuously to maintain a

constant negative pressure until decontamination of the work area is complete.

Do not turn off units at the end of the work shift or when abatement operations

temporarily stop

Do not shut down the pressure differential system during encapsulating procedures,

unless authorized by the Owner in writing

Start abatement work at a location farthest from exhaust units and proceed toward

them. If an electric power failure occurs, immediately stop all abatement work and

do not resume until power is restored and exhaust units are operating again.

At completion of abatement work, allow exhaust units to run as specified under

Section 01711, to remove airborne fibers that may have been generated during

abatement work and cleanup and to purge the work area with clean makeup air. The

units may be required to run for a longer time after decontamination, if dry or only

partially wetted asbestos material was encountered during any abatement work.

3.4.6 Dismantling the system:

When final inspection and the results of final air tests indicate that the area has

been decontaminated, exhaust units may be removed from the work area. Before

removal from the work area, remove and properly dispose of pre-filter, and seal

intake to the machine with 6 mil polyethylene to prevent environmental

contamination from the filters

End of Section 01513

50

Page 51: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01526

Temporary Enclosures

Part 1 General

1.1 Related Documents

Drawings and general provisions of Contract, including General and Supplementary Conditions and

other Division 1 Specification sections, apply to work of this section

1.2 Submittals

Submit Contingency Plans for safe evacuation of the work area in case of fire or injury

1.3 Safety

Contact fire control agencies to review procedures prior to start of work

Part 2 Products

2.1 Polyethylene Sheet

A single polyethylene film in the largest sheet size possible to minimize seams 6 mils thick as

indicated, clear, frosted or black as indicated

2.2 Polyethylene Sheet

In areas where there is hot equipment or a potential for fire, such as in a boiler room provide flame

resistant polyethylene film that conforms to requirements set forth by the National Fire Protection

Association Standard 701, Small scale Fire Test for Flame Resistant Textiles and Films. Provide

largest size possible to minimize seams, 6 mils thick as indicated, frosted or black as indicated.

2.3 Spray Plastic

Provide spray plastic in aerosol cans or premixed for spray application which is formulated to

adhere gently to surfaces and remove cleanly by pulling off at the completion of the work

2.4 Duct Tape

Provide duct tape in 2” or 3” widths as indicated, with an adhesive which is formulated to

aggressively stick to sheet polyethylene

2.5 Spray Cement

Provide spray adhesive in aerosol cans which is specifically formulated to stick tenaciously to sheet

polyethylene

Part 3- Execution

3.1 Sequence of Work

51

Page 52: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Carry out work of this section sequentially. Complete each activity before proceeding to the next.

3.2 General

3.2.1 Work area is the location where asbestos abatement work occurs. It is a variable of the

extent of work of the Contract. It may be a portion of a room, a single room, or a complex of

rooms. A “work area” is considered contaminated during the work, and must be solated

from the balance of the building, and decontaminated at the completion of the asbestos

control work

3.2.2 Completely insulate the work area from other parts of the building so as to prevent asbestos

containing dust or debris from passing beyond the isolated area. Should the area beyond the

work area(s) become contaminated with asbestos containing dust or debris as a consequence

of the work, clean those areas in accordance with the procedures indicated in Section 01711.

Perform all such required cleaning or decontamination at no additional cost to the Owner

3.2.3 Place all tools, scaffolding, staging, etc., necessary for the work in the area to be isolated

prior to erection of plastic sheeting temporary enclosure

3.2.4 Remove all uncontaminated removable furniture, equipment, and/or supplies from the work

area before commencing work, or completely cover with two (2) layers of polyethylene

sheeting, at least 6 mil in thickness securely taped in place with duct tape. Such furniture

and equipment shall be considered outside the work area unless covering plastic or seal is

broached

3.2.5 Disable ventilating systems or any other system bringing air into our out of the work area.

Disable system by disconnecting wires, removing circuit breakers, by lockable switch or

other positive means that will prevent accidental premature restarting of equipment

3.2.6 In areas of asbestos abatement disassemble all removable items from the work area, such as

lights, grilles, registers, etc. Thoroughly decontaminate through wet cleaning and/or HEPA

vacuum, all furniture carpets, lighting fixtures, and other removables. Store the

decontaminated removables for retrieval by the Owner

3.3 Control Access

3.3.1 Permit access to the work area only through the decontamination unit. All other means of

access shall be closed off and sealed and warning signs displayed on the clean side of the

sealed access

3.3.2 Visual Barrier: Where the work areas is immediately adjacent to, or within view of occupied

areas, provide a visual barrier of opaque polyethylene sheet at least 6 mil in thickness so that

the work procedures are not visible to building occupants. Where this visual barrier would

block natural light, substitute frosted sheet plastic in locations approved by the Owner

3.3.3 Physical Barrier: Where the area adjacent to the work area is accessible to the public,

construct a solid barrier on the public side of the sheeting to protect the sheeting. Construct

the barrier with nominal 2” x 4” wood or metal studs 16” on center, securely anchored to

prevent movement, covered with a minimum ¼ inch thick hardboard, ½” gypsum wall

board, ½” plywood, or ½” thick rigid foam board

52

Page 53: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.3.4 Provide warning signs at each visual and physical barriers reading as follows in English:

DANGER, ASBESTOS HAZARD, DO NOT ENTER

The warning signs should be a bright color so that they will be easily noticeable. The size of

the sign and the size of the lettering shall be not less than OSHA requirements

3.3.5 Provide any other signs, labels, warnings, and posted instructions that are necessary to

protect, inform, and warn people of the hazard from asbestos exposure. Post in a prominent

and convenient place for the workers, a copy of the latest applicable regulations from

OSHA, EPA, NIOSH and COMAR.

3.4 Alternate Methods of Enclosure

Alternate methods of containing the work area may be submitted to the Owner for approval.

Do not proceed with any such method(s) without prior written approval of the Owner.

3.5 Respiratory and Worker Protection

Before proceeding beyond this point in providing Temporary Enclosures:

Provide Respiratory Protection per Section 01562

Provide Worker Protection per Section 01560

3.6 Critical Barriers

3.6.1 Completely separate the work area from other portions of the building, and the outside by

sheet plastic barriers at least 6 mil in thickness, or by sealing with duct tape

3.6.2 Individually seal all ventilation openings (supply and exhaust), lighting fixtures, clocks,

doorways, windows, convectors, speakers, and other openings into the work area with duct

tape alone or with polyethylene sheeting at least 6 mil in thickness, taped securely in place

with duct tape. Maintain seal until all work including Project Decontamination is completed.

Take care in sealing off lighting fixtures to avoid melting or burning of sheeting

3.6.3 Provide sheer plastic barriers at least 6 mil in thickness as required to completely seal

openings from the work area into adjacent areas. Seal the perimeter of all sheet plastic

barriers with duct tape or spray cement

3.6.4 Mechanically support sheet plastic independently of duct tape or spray cement seals so that

seals do not support the weight of the plastic. Following are acceptable methods of

supporting sheet plastic barriers. Alternative support methods may be used if approved by

the Owner or designated IH representative

3.6.4.1 Plywood squares 6” x 6” x 3/8” held in place with one 6” smooth masonry nail or

electro-galvanized common nail driven through center of the plywood and duct

tape on plastic so that plywood clamps plastic to the wall. Locate plywood

squares at each end, corner and at maximum 4” on centers

53

Page 54: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.6.4.2 Nylon or polypropylene rope minimum ¼” in diameter suspended between

supports securely fastened on either side of opening at maximum 1’ below

ceiling. Tighten rope so that is has 2” maximum dip. Drape plastic over rope

from outside work area so that a 2” flap of plastic extends over rope into work

area. Staple or wire plastic to itself 1” below rope at a maximum 6” on centers to

form a sheath over rope. Lift flap and seal to ceiling with duct tape or spray

cement. Seal loop at bottom of flap with duct tape. Erect entire assembly so that

it hangs vertically without a “shelf” upon which debris could collect

3.6.5 Provide decontamination units per section 01563

3.6.6 Provide pressure differential system per section 01513

3.6.7 Clean housing and ducts of all overspray materials prior to erection of the critical barrier

polyethylene sheeting

3.7 Primary Barrier

3.7.1 Clean all contaminated furniture, equipment, and or supplies with HEPA filtered vacuum

cleaner or by wet cleaning, as specified in Section 01712, prior to being moved or covered.

All equipment furniture, etc., is to be deemed contaminated unless specifically declared as

uncontaminated on the drawings or in writing by the Owner

3.7.2 Clean all surfaces in work area with HEPA filtered vacuum or by wet wiping prior to the

installation of any sheet plastic

3.7.3 Enclose work areas with two (2) layers of plastic sheeting on floor and one (1) layer on

walls, or as otherwise directed on the contract drawings or in writing by the Owner

3.7.4 Remove all electrical and mechanical items, such as lighting fixture, clocks, diffusers,

registers, escutcheon plates, etc., which cover any part of the surface to be worked on with

the work

3.7.5 Remove all general construction items such as cabinets, casework, doors, and window trim,

moldings, ceiling, trim, etc. which cover the surface of the work as required to prevent

interference with the work. Clean, decontaminate and reinstall all such materials, upon

completion of all removal work with materials, finishes, and workmanship to match existing

installations before start of work

3.7.6 Cover all walls in work area including “Critical Barrier” sheet plastic barriers with one layer

of polyethylene sheeting, at least 6 mil in thickness, mechanically supported and sealed with

duct tape or spray glue in the same manner as “Critical Barrier” sheet plastic barriers. Tape

all joints including the joining with the floor covering with duct tape or as otherwise

indicated on the contract documents or in writing by the Owner

3.7.7 Elevator: If there are elevators in the area where the Contract work is to occur, cover walls,

floor and ceiling of elevator with 2 layers of 6 mil polyethylene. Arrange entry to work area

so that elevator door is in a positively pressurized space outside the clean room of the

decontamination unit. At completion of work, elevator shall be cleaned as set forth in

Section 01711. Refer to section 01013 summary of work for additional requirements for

protection of elevator

54

Page 55: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.7.8 Stairs and Ramps: Do not cover stairs or ramps with unsecured sheet plastic. Where stairs

or ramps are covered with plastic, provide ¾” exterior grade plywood treads securely held in

place, over plastic. Do not cover rungs or rails with any type of protective materials. Stairs

may be left uncovered, but the Contractor must clean the stairs thoroughly after work is

completed

3.8 Extension of Work Area

3.8.1 Extension of Work Area: If the enclosure barrier is breeched in any manner that could allow

the passage of asbestos debris or airborne fibers, then add affected area to the work area,

enclose it as required by this section of the specifications and decontaminate it as described

in section 01711

3.9 Secondary Barrier

3.9.1 Secondary layer of plastic as a drop cloth to protect the primary layer from debris generated

by the asbestos abatement work is specified in the appropriate work sections

End of Section 01526

55

Page 56: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01528

Entry into Controlled Areas

Part 1 General

1.1 Related Documents

Drawings and general provisions of the Contract, including General and Supplementary Conditions

and other Division 1 Specifications sections, apply to work of this section

1.2 Description of Work

The provisions of this section apply when entry is required into an area where such entry could

cause contamination of portions of the building and/or where respiratory or other worker protection

measures are required

Unless authorized in writing by the Owner, the provisions of this section apply to only the

following situations:

1.2.1 Entry into the space above a suspended ceiling where there is asbestos containing fire

proofing or other friable asbestos containing material when the ceiling tiles in an area no

greater than 6 feet by 12 feet are to be removed

1.2.2 Entry through sealed access (access door, hatchway, locked door) into an area with friable

asbestos containing materials

Part 2 Products (Not Applicable)

Part 3 Execution

3.1 Access through Suspended Ceilings

3.1.1 Follow worker protection procedures including disposable coveralls and respirators required

by Section 01561, and Section 01562

3.1.2 Follow local area protection procedures of Section 01528. Spread layer of 6 mil

polyethylene sheets on floor 6 feet further in extent than the size of the ceiling opening to be

made

3.1.3 HEPA vacuum around edges of all panels to be removed

3.1.4 While holding nozzle of HEPA vacuum in vicinity slowly lift one edge of center ceiling

panel. Immediately HEPA vacuum space at lift edge. Lift entire panel straight up and HEPA

all four sides

3.1.5 Place panel on top of adjacent ceiling

3.2 Entry into Controlled Area

Use same procedure as above except that that ceiling tiles do not need to be removed

56

Page 57: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.2.1 If access is through a wall hatch or door, duct tape floor sheet to wall or threshold

3.2.2 If access is into large area such as crawl tunnel, comply with worker protection requirements

but use HEPA vacuum only for work procedures in the area

End of Section 01528

57

Page 58: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01560

Worker Protection-Asbestos Abatement

Part 1 General

1.1 Related Documents

Drawings and general provisions of the Contract, including General and Supplementary Conditions

and other Division 1 Specifications sections, apply to work of this section

1.2 Description of Work

This section describes the equipment and procedures required for protecting workers against

asbestos contamination and other workplace hazards except for respiratory protection

1.3 Related Work Specified Elsewhere

1.3.1 Respiratory Protection is specified in Section 01562

1.4 Worker Training

1.4.1 Train in accordance with 29 CFR 1926 and 40 CFR 763, all workers in the dangers inherent

in handling asbestos and breathing asbestos dust and in proper work procedures and personal

and area protective measures. Include but do not limit the topics covered in the course to the

following:

Methods of recognizing asbestos

Health effects associated with asbestos

Relationship between smoking and asbestos in producing lung cancer

Nature of operations that could result in exposure to asbestos

Importance of and instruction in the use of necessary protective controls, practices and

procedures to minimize exposure including:

Engineering controls

Work practices

Respirators

Housekeeping procedures

Hygiene facilities

Protective clothing

Decontamination procedures

Emergency procedures

Waste disposal procedures

Purpose, proper use, fitting, instructions, and limitations of respirators as

required by 29 CRF 1910.134

58

Page 59: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Appropriate work practices for the work

Requirements of medical surveillance program

Review of 29 CFR 1926 and 40 CFR 763

Negative air systems

Work practices including bands on or on job training

Air monitoring; personal and area

1.5 Medical Examinations

1.5.1 Provide medical examinations for all workers who may encounter an airborne fiber level of

0.1 f/cc or greater for an 8 hour time weighted average. In the absence of specific airborne

fiber data provided medical examination for all workers who will enter the work area for

any reason. Examinations shall, as a minimum, meet OSHA requirements as set forth in 29

CFR 1926. In addition, provide an evaluation of the individual’s ability to work in

environments capable of producing heat stress in the worker

Part 2-Equipment

2.1 Protective Clothing

2.1.1 Coveralls: Provide disposable full body coveralls and disposable head covers, and require

that they be worn by all workers in the area. Provide a sufficient number for all required

changes, for all workers in the area

2.1.2 Boots: Provide work boots with non-skid soles, and where required by OSHA foot

protective covers, for all workers. Provide boots at no cost to workers. Paint uppers of all

boots red with water proof enamel. Do not allow boots to be removed from the work area

for any reason after being contaminated with asbestos containing materials. Dispose of

boots as asbestos contaminated waste at the end of the work

2.1.3 Goggles: Provide eye protection (goggles) as required by OSHA for all workers involved in

scraping, spraying, or any other activity which may potentially cause eye injury

2.1.4 Gloves: Provide work gloves to all workers and require that they be worn at all times in the

work area. Do not remove gloves from work area and dispose of as asbestos contaminated

waste at the end of the work

2.1.5 Provide hard hats as required by job conditions and safety regulations

2.1.6 Reusable footwear, hardhats, and eye protection devices shall be left in the “Contaminated

Equipment Room” until the end of the asbestos abatement work

59

Page 60: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

2.1.7 All disposable protective clothing shall be discarded and disposed of as asbestos waste

every time wearer exits from the workspace to the outside through the decontamination

facility

2.2 Additional Protective Equipment

Respirators, disposable coveralls, head covers, and footwear covers shall be provided by the

Contractor for the Owner, Project Administrator, IH and other authorized representatives who may

inspect the job site

Part 3-Execution

3.1 General

Provide worker protection as required by the most stringent OSHA and /or EPA standards

applicable to the work. The following procedures are minimums to be adhered to regardless of fiber

count in the work area:

3.1.1 Each time work area is entered put on new disposable coverall, new head cover, and a clean

respirator

3.2 Decontamination Procedures

3.2.1 Require all workers to adhere to the following personal decontamination procedures

whenever they leave the work area:

3.2.2 Type C Supplied Air or Powered Air Purifying Respirators: Require that all workers use the

following decontamination procedures as a minimum requirement whenever leaving the

work area:

3.2.2.1 When exiting area, remove disposable coveralls, disposable head covers, and

disposable footwear covers or boots in the equipment room

3.2.2.2 Still wearing respirators, proceed to showers. Showering is mandatory.

3.2.3 Air Purifying Negative Pressure Respirators: Require that all workers use the following

decontamination procedures as a minimum requirement whenever leaving the work area

with a half or full face cartridge type respirator:

3.2.3.1 When exiting area, remove disposable coveralls, disposable head covers, and

disposable footwear covers or boots in the equipment room

3.2.3.2 Still wearing respirators, proceed to showers. Showering is mandatory

3.2.4 Proceed from shower to changing room and change into street clothes or into new

disposable work items

3.3 Within Work Area

60

Page 61: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Require that workers NOT eat, drink, smoke, chew gum or tobacco in the work area. To eat, chew,

drink, or smoke, workers shall follow the procedures listed above, and then dress in street clothes

before entering the non-work areas of the building. Smoking is prohibited on school property.

End of Section 01560

61

Page 62: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01562

Respiratory Protection

Part 1 General

1.1 Related Documents

Where applicable, drawings and general provisions of the Contract, including General and

Supplementary Conditions and other Division 1 Specifications sections, apply to work of this

section.

1.2 Description of Work

Instruct and train each worker involved in asbestos abatement or maintenance and repair of friable

asbestos containing materials in proper respiratory use and require that each worker always wear a

respirator, properly fitted on the face in the work area from the start of any operation which may

cause airborne asbestos fibers until the work area is completely decontaminated. Use respiratory

protection appropriate for the fiber level encountered in the work place or as required for other toxic

or oxygen deficient situations encountered. All respiratory equipment shall be inspected by the

Contractor’s project supervisory personnel at the beginning of each work period, including breaks

and lunch periods

1.3 Standards

Except to the extent that more stringent requirements are written directly into the Contract

Documents, the following regulations and standards have the same force and effect (and are made a

part of the Contract Documents by reference) as if copied directly into the Contract Documents, or

as if published copies were bound herewith. Where there is a conflict in requirements set forth in

these regulations and standards, meet the more stringent requirement.

1.3.1 OSHA- US Department of Labor Occupational Safety and Health Administration Safety and

Health Standards 29 CFR 1910, Section 1001 and Section 1910.134.29 CFR 1926

1.3.2 CGA-Compressed Gas Association, Inc. New York, Pamphlet G-7, “Compressed

Air for Human Respiration”, and specification G-7.1 “Commodity Specification

for Air”.

1.3.3 CSA-Canadian Standard Association, Rexdal, Ontario, Standard Z180.1-1978,

“Compressed Breathing Air”

1.3.4 ANSI-American National Standard Practices for Respiratory Protection ANSI

A88.2-1980

1.3.5 NIOSH-National Institute for Occupational Safety and Health

1.3.6 MSHA-Mine Safety and Health Administration

1.4 Submittals

62

Page 63: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Before start of work, submit the following to the Owners Representative for review. Do not begin

work until these submittals are returned with the Owners approval indicating that the submittal is

returned for unrestricted use:

1.4.1 Product Data: Submit manufacturer’s product information for each component used,

including NIOSH and MSHA Certifications for each component in an assembly and/or for

entire assembly

1.4.2 System Diagram: When a Type “C” supplied air respiratory system is required by the work,

submit drawing showing assembly of components into a complete supplied air respiratory

system. Include diagram showing location of compressor, filter banks, backup air supply

tasks, hose line connections in work area(s), routing of air lines to work area(s) from

compressor

1.4.3 Operation Instruction: Submit complete operating and maintenance instructions for all

components and systems as a whole. Submittal is to be in bound manual form suitable for

field use.

1.4.4 Respiratory Protection Program: Submit level of respiratory protection intended for each

operation required by the project. Submit this information on the “Respiratory Protection

Program” form at the end of this section

1.4.5 Historic Airborne Fiber Data: Submit airborne asbestos fiber count data from an

independent air monitoring firm to substantiate selection of respiratory protection proposed.

Data submitted shall include, at a minimum, the following for each procedure required by

the work:

Data of Measurements

Operation Monitored

Sampling and analytical methods used and evidence of their accuracy

Number, duration, and results of samples taken

1.4.6 Resume Information: Submit resume and information on training for individual

monitoring the operation of supplied air respiratory systems. Submit training

certifications where applicable

1.5 Air Quality for Supplied Air Respiratory Systems

Provide air used for breathing in Type “C” supplied air respiratory systems that meets or exceeds

standards set for CGA type 1 (Gaseous Air) Grade H or CSA Z180.1, whichever presents the more

stringent quality standard

Indicate that the standard shows no limiting characteristics

The CGA standards do not call out a specific moisture limit when the ambient temperature

is above freezing. However, since a moisture content no greater than a -50 Degrees

Fahrenheit dew point (66 PPMv) is necessary for carbon monoxide elimination, the CO

63

Page 64: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

limits could not be met unless the air were dried to a -50 Degrees Fahrenheit dew point or

better

Maximum allowable content of tricholotrifluorenthane, dichlorodifluoromethane, and

chlorodifluoromethane is 2 PPMv for each. Unlisted contaminants shall not exceed one

tenth of the Threshold Limit Values (TLV’s) for Chemical Substances in Workroom air

adopted by the American Conference of Governmental Industrial Hygienists (ACGIH)

1.7 Delivery

Deliver replacement parts, etc. not otherwise labeled by NIOSH or MSHA to job site in

manufacturer’s containers

Part 2 Equipment

OSHA regulations allow respiratory protection to be selected based upon the airborne fiber counts

encountered in the work place

2.1 EPA has not promulgated any regulations more stringent than those of OSHA, but, EPA and

NIOSH have issued a recommendation that far exceeds the OSHA regulation. EPA and NISOH

recommend that air purifying respirators be used only in situations where measureable quantities

of airborne asbestos are not detectable, and the use of the respirator is a precaution against

accidental disturbance of asbestos containing materials. Situations identified by the

recommendation are those such as pre-abatement inspections, preparation of abatement areas, final

cleaning, removal of the last layer of plastic, glove bag removals, etc.

2.2 Strict adherence to this recommendation may in many instances be impractical and even unsafe for

the worker. Supplied air respiratory protection should be used only where it is properly setup,

maintained and continuously monitored by trained personnel. If this is not done, workers could be

subjected to a very real life hazard from the system that is supposed to be protecting them

Provide sufficient capacity in the back up air supply to allow a minimum escape time of one half

hour times the number of connections available to the work area. Air requirements at each

connection is the air requirement of the respirators in use plus the air requirement of an average size

adult male engaged in moderately strenuous activity

2.3 Air Purifying Respirators

2.3.1 Respirator Bodies: Provide half face or full face type respirators. Equip full face respirators

with a nose cup or other anti-fogging device as would be appropriate for use in air

temperature less than 32 Degrees Fahrenheit

2.3.2 Filter Cartridges: Provide, at a minimum, HEPA type filters labeled with NIOSH and

MSHA Certification. OSHA Respiratory Standard 1910.134

Part 3 Execution

Conform to the standards of OSHA Respiratory Standard 1910.134

End of Section 01562

64

Page 65: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01563

Decontamination Units

Part 1 General

1.1 Related Documents

Drawings and general provisions of the Contract, including General and Supplementary Conditions

and other Division 1 Specifications sections, apply to work of this section

1.2 Description of Work

Provide a separate personnel and equipment decontamination facilities for each abatement area.

Require that the Personnel Decontamination Unit be the only means of ingress and egress for the

work area. Require that all materials exit the work area through the Equipment Decontamination

Unit

1.3 Related Work Specified Elsewhere

Refer to Section 01503 Temporary Facilities-Asbestos Abatement for electrical requirements and

requirements relative to connection of decontamination facilities to building systems such as water,

sewer, and electrical

Part 2-Products

2.1 Polyethylene Sheet

A double layer of polyethylene film in the largest sheet size possible to minimize seams, 6.0 mils

thick as indicated, clear, frosted, or black as indicated

2.2 Reinforced Polyethylene Sheet

Where plastic sheet is the only separation between the work area and building exterior, provide

translucent, nylon reinforced, laminated, flame resistant, polyethylene film that conforms to

requirements set forth by the National Fire Protection Association Standard 701, Small scale Fire

Test for Flame resistant Textiles and Films. Provide indicated, frosted or black as indicated

2.3 Duct Tape

Provide duct tape in 2” or 3” widths as indicated, with an adhesive which is formulated to

aggressively stick to sheet polyethylene

2.4 Spray Cement

Provide spray adhesive in aerosol cans which is specifically formulated to stick tenaciously to sheet

polyethylene

2.5 Shower Pan

65

Page 66: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Provide one piece waterproof shower pan 4’ x 8’ x 6’ deep. Fabricate from seamless fiberglass

minimum 1/16” thick reinforced with wood, 18 ga. Stainless steel with welded seems, or a

seamless liner of minimum 60 mil thick rubber roofing

2.6 Shower Walls

Provide 8’ long by approximately 7’ high walls fabricated from rigid, impervious, waterproof

material, either corrugated fiberglass roofing or equivalent. Structurally support as necessary for

stability

2.7 Shower Head and Controls

Provide a factory made shower head producing a spray of water which can be adjusted for spray

size and intensity. Feed shower with water mixed from hot and cold supply lines. Arrange sot that

control of water temperature, flow rate, and shut off is from inside shower without outside aid.

2.8 Filters

Provide cascaded filter units on drain lines from showers or any other water source carrying

asbestos contaminated water from the work area. Provide units with disposable filter elements as

indicate below. Connect so that discharged water passes primary filter and output primary filter

passes through secondary filter.

Primary Filter-Pass particles 20 microns and smaller

Secondary Filter-Pass particles 5 microns and smaller

2.9 Hose Bib

Provide heavy bronze angle type with wheel handle, vacuum breaker, and ¾” National Standard

male hose outlet

2.10 Shower Stall

For Wash Down Station provide leak tight shower enclosure with integrated rain pan fabricated

from fiberglass or other durable waterproof material, approximately 3’ x 3’ square with minimum 6’

high sides and back. Structurally support as necessary for stability. Equip with hose bib, as specified

in this section, mounted at approximately 4’-0” above drain pan. Connect drain to a reservoir, pump

water from reservoir filters inside shower stall on back wall beneath hose bib

2.11 Rubber Roofing

Provide uniform flat sheets of flexible sheet roofing material fabricated from EPDM (Ethylene

propylene diene monomers) or Neoprene (polychloroprene), in a nominal thickness of 45 mils

2.12 Lumber

Provide kiln dried lumber of any grade or species

2.13 Sump Pump

66

Page 67: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Provide totally submersible waterproof sump pump with integral float switch. Provide unit sized to

pump 2 times the flow of capacity of all showers or hoses supplying water to the sump, through the

filters specified herein when they are loaded to the extent that replacement is required. Provide

unit capable of pumping debris, sand, plaster or other materials washed off during decontamination

procedures without damage to mechanism of pump. Adjust float switch so that a minimum of 3”

remains between top of liquid and top of sump pan

Part 3 Execution

3.1 Personnel Decontamination Unit

Provide a Personnel Decontamination Unit consisting of a serial arrangement of 3 connected rooms

or spaces, Changing Room, Shower Room, and Equipment Room. Require all persons without

exception to pass through this decontamination unit for entry into and exiting from the work area

for any purpose. Do not allow parallel routes for entry or exit. Do not remove equipment or

materials through.

Personnel Decontamination Unit: Provide temporary lighting within decontamination units as

necessary to reach a lighting level of 100 foot candles. The Decontamination Unit should be cleaned

several times during abatement activities, to ensure no contamination occurs outside of the work

area.

3.1.1 The Decontamination Unit for workers and visitors shall consist of three rooms that serve as

three air locks as follows: Clean room at entrance followed by Shower Room followed by an

Equipment Room leading to the work area

3.1.2 Changing Room (clean room): Provide a room that is physically and visually separated from

the rest of the building for the purpose of changing into protective clothing. Construct using

polyethylene sheeting, at least 6 mil in thickness, to provide an airtight seal for changing

into protective clothing. Construct using polyethylene sheeting, at least 6 mil in thickness, to

provide an airtight seal between the Changing Room and the rest of the building. Locate so

that access to work area from the Changing Room is through the Shower Room. Separate

Changing Room from the building by a sheet polyethylene flapped doorway.

3.1.2.1 Require workers to remove all street clothes in this room, dress in clean, disposable

overalls, and don respiratory protection equipment. Do not allow asbestos

contaminated items to enter this room. Require workers to enter this room either

from outside the structure dressed street clothes, or naked from the shower room

3.1.2.2 An existing room may be utilized as the Changing Room if it is suitably located and

of a configuration whereby workmen may enter the Changing Room directly from

the Shower Room. Protect all surfaces of room with sheet plastic as set forth in

Section 01526, Temporary Enclosures. Authorization for this must be obtained from

the Owner in writing prior to start of construction. Submit written request in

accordance with Section 01632 Products and Substitutions detailing layout and

protective measures proposed

3.1.2.3 Maintain floor of changing room, to be dry and clean at all times. Do not allow

overflow water from shower to wet floor in changing room

3.1.2.4 Damp wipe all surfaces twice after each shift change with a disinfectant solutions

67

Page 68: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.1.2.5 Provide a continuously adequate supply of disposable bath towels

3.1.2.6 Provide posted information for all emergency phone numbers and procedures

3.1.2.7 Provide 1 storage locker per employee

3.1.3 Shower Room: Provide a completely water tight operational shower to be used for transit by

cleanly dressed workers heading for the work area from the Changing Room, or for

showering by workers headed out of the Work Area after undressing in the Equipment

Room

3.1.3.1 Construct room by providing a shower pan and 2 shower walls in a configuration

that will cause water running down walls to drip into pan. Install a freely draining

wooden floor in shower pan at elevation of top of pan

3.1.3.2 Separate this room from the rest of the building with air tight walls fabricated of 6

mil polyethylene

3.1.3.3 Separate this room from the Changing and Equipment Rooms with air tight walls

fabricated of 6 mil polyethylene

3.1.3.4 Provide splash proof entrances to Changing and Equipment Rooms with 2 doors

arranged in the following configuration:

At each entrance to the Shower Room, construct a door frame out of 2” x 4” lumber

with 1-1/2 jambs (sides) and 1-1/2” head (top) and sill bottom 1-1/2” PVC tubing

may be substituted for the lumber frames

3.1.3.5 Provide shower head and controls

3.1.3.6 Provide temporary extensions of existing hot and cold water and drainage, as

necessary for a complete and operable shower

3.1.3.7 Provide a soap dish and a continuously adequate supply of soap and maintain in a

sanitary condition

3.1.3.8 Arrange so that water from showering does not splash into the Changing or

Equipment Room

3.1.3.9 Arrange water shut off and drain pump operation controls so that a single individual

can shower without assistance from either inside or outside of the work

area

3.1.3.10 Provide a flexible hose shower head

3.1.3.11 Pump waste water to drain or to storage for use in amended water. If pumped to

drain, provide 20 micron and 5 micron waste water filters in line to drain or waste

storage. Change filters daily or more often if necessary. Locate filters inside shower

unit so that water lost during filter changes is caught by a shower pan

68

Page 69: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.1.3.12 Provide hose bib

3.1.3.13 Provide all other items indicated on contract drawings

3.1.4 Equipment Room (Contaminated Area): Require work equipment, footwear and additional

contaminated work clothing to be left here. This is a change and transit area for workers.

Separate this room from the work area by an air lock system

Separate this room from the rest of the building with air tight walls fabricated of 6 mil

polyethylene

Separate this room from the Shower Room and Work Area with air tight walls fabricated of

6 mil polyethylene

3.1.5 Work Area: Separate Work Area from the Equipment Room by polyethylene barriers. If the

airborne asbestos level in the Work Area is expected to be high, as in dry removal, add an

intermediate cleaning space between the equipment Room and the Work Area. Damp wipe

clean all surfaces after each shift change. Provide one additional floor layer of 6 mil

polyethylene per shift change and remove contaminated layer after each shift

3.2 Construction

3.2.1 Walls and Ceilings: Construct air tight walls and ceiling using 2 layers of polyethylene

sheeting, at least 6 mil thick. Attach to existing building components or a temporary

framework

3.2.2 Floors: Use 2 layers (minimum) of 6 mil. Polyethylene sheeting to cover floors in the

Equipment, Shower (underneath shower pan), and Changing Rooms. Provide an additional

layer in the Equipment Room for every shift change expected. Roll one layer of plastic from

Equipment Room to Work Area after each shift change. Provide a minimum of two (2)

layers of plastic at all times. Use only clear plastic to cover floors.

3.2.3 Doors: an air lock is a system permitting ingress and egress without permitting air

movement. It consists of four curtained doorways at least six feet apart. Each curtained

doorway shall be constructed by placing three overlapping sheets of 6 mil plastic over a

framed doorway, securing each along the top of the doorway. The first and third sheet shall

be secured on the one side of the doorway. The second sheet shall be secured on the other

side of the doorway. Provide a minimum of six feet (6’) between entrance and exit of any

room.

3.3 Alternate methods of providing decontamination facilities may be submitted to the Owner for

approval. Do not proceed with any such method(s) without written authorization of the Owner

3.4 Electrical

Provide subpanel at Changing Room to accommodate all removal equipment. Power the subpanel

directly from a building electrical panel. Connect all electrical branch circuits in decontamination

unit and particularly any pumps in shower room to a ground fault circuit protection device

3.5 Decontamination Sequence

69

Page 70: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.5.1 Entering Work Area: Worker enters Changing Room and removes street clothing, puts on

clean disposable overalls and respirator, and passes through the Shower Room in to the

Equipment Room

Any additional clothing and equipment left in Equipment Room needed by the worker are

put on in the Equipment Room

Worker proceeds to Work Area

3.5.2 Existing Work Area: Before leaving the work area, require the worker to remove all gross

contamination and debris from overalls and feet. The worker then proceeds to the

Equipment Room and removes all clothing except respiratory protection equipment. Extra

work clothing may be stored in contaminated end of the Equipment Room. Disposable

coveralls are placed in a bag for disposal with other material. Decontamination procedures

found in Section 01560 shall be followed by all individuals leaving the work area

3.6 Cleaning of Decontamination Units

Clean debris and residue from inside of Decontamination Units on a daily basis or as otherwise

indicated on contract drawings. Damp wipe or hose down all surfaces after each shift change. Clean

debris from shower pans on a daily basis

If the Changing Room of the Personnel Decontamination Unit becomes contaminated with asbestos

containing debris, abandon the entire decontamination unit and erect a new decontamination unit.

Use the form Changing Room as an inner section of the new Equipment Room

3.7 Signs

3.7.1 Required work area/notification signs shall be posted in accordance with AHERA and other

applicable regulations

3.7.2 Post an approximately 10” x 14” manufactured sign at each entrance to each work area

displaying the following legend with letter sizes and styles of a visibility at least equal to the

following:

Legend Notation No Food, Beverages or Tobacco Permitted ¾” Block

All persons shall don protective ¾” Block

Clothing (coverings) before

Entering the work area

All persons shall shower immediately ¾” Block

after leaving work area and before

enter the Changing Room

3.8 Repair immediately any tears or leaks to the decontaminating enclosure or work area. Visually

inspect the enclosures and plastic barriers at each work period and during non-work periods by the

supervisory team

End of Section 01563

70

Page 71: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01701

Project Closeout – Asbestos Abatement

Part 1 General

1.1 Related Documents

Drawings and general provisions of the Contract, including General and Supplementary Conditions

and other Division 1 Specifications sections, apply to work of this section

1.2 Description of Requirements

1.2.1 Definition: Project closeout is the term used to describe certain collective project

requirements, indicating completion of the work, that are to be fulfilled near the end of the

Contract time in preparation for final acceptance and occupancy of the work by the Owner,

as well as final payment to the Contract and the normal termination of the Contract.

1.2.2 Specific requirements for individual units of work are included in the appropriate sections in

Division 2 through 16

1.2.3 Time of closeout is directly related to “Substantial Completion”; therefore, the time of

closeout may be either a single time period for the entire work or a series of time periods for

individual elements of the work that have been certified as substantially complete at

different dates. This time variation, if any, shall be applicable to the other provisions of this

section

1.3 Prerequisites to Substantial Completion

Complete the following before requesting the Owner inspect the certification of substantial

completion, either for the entire work or for portions of work. Include list of known exceptions:

1.3.1 In the progress payment request that coincides with, or is the first request following, the date

substantial completion is claimed, show either 100 percent completion for the portion of the

work claimed as “substantially complete”, or list incomplete items, the value of incomplete

work, and reason for the work being incomplete

1.3.2 Include supporting documentation for completion as indicated in these contract documents

1.3.3 Submit a statement showing an accounting of changes to the Contract Sum.

1.3.4 Advise owner of pending insurance change over requirements

1.3.5 Submit specific warranties, workmanship/maintenance bonds, maintenance agreements,

final certifications and similar documents

1.3.6 Obtain and submit releases enabling Owners full, unrestricted use of the work and access to

services and utilities. Where required, include occupancy permits, operating certificates and

similar releases

1.3.7 Complete final cleaning up requirements, including touch up painting of marred surfaces

71

Page 72: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.3.8 Touch up and otherwise repair and restore marred exposed finishes

1.4 Inspection Procedures

Upon receipt of the Contractor’s request for inspection, the Owner will either proceed with

inspection or advise the Contractor of unfulfilled prerequisites

Results of the completed inspection will form the initial “punch list’ for final acceptance

1.5 Prerequisites to Final Acceptance

Submit the final payment request with final releases and supporting documentation not previously

submitted and accepted. Include certificates of insurance for products and completed operations

where required

1.6 Reinspection Procedure

The Owner will reinspect the work upon receipt of the Contractor’s notice that the work, including

punch list items resulting from earlier inspections, has been completed, except for these items

whose completion has been delayed because of circumstances that are acceptable to the Owner

Upon completion of inspection, the Owner will either accept the final clearance or will advise the

Contractor of work that is incomplete or of obligations that have not been fulfilled, but are required

for final acceptance. If necessary, the reinspection procedure will be repeated

1.7 Record Drawings

Maintain a record set of blue or black line white prints of contract drawings and shop drawings in a

clean, undamaged condition. Mark up the set of record documents to show the actual installation

where the installed work varies substantially from the work as originally shown. Mark whichever

drawings in most capable of showing the actual field condition fully and accurately; however,

where shop drawings are used for mark up, record a cross reference at the corresponding location on

the working drawings. Give particular attention to concealed work that would be difficult to

measure and record at a later date

1.8.1 Mark record sets with red erasable pencil and, where feasible, use other colors to distinguish

between variations in separate categories of work

1.8.2 Mark up new information which is known to be important to the Owner, but for some

reasons was not shown on either contract drawings or shop drawings

1.8.3 Note related change order number where applicable

1.8.4 Organize record drawing sheets into manageable sets, bind with durable paper cover sheets,

and print suitable titles, dates and other identification on cover of each set

1.9 Record Product Data

Maintain one copy of each product data submittal. Mark these documents to show significant

variations in the actual work performed in comparison with the submitted information. Include both

72

Page 73: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

variations in the products as delivered to the site, and variations from the manufacturer’s

instructions and recommendations for installation. Give particular attention to concealed products

and portions of the work which cannot otherwise be readily discerned at a later date by direct

observation. Note related change orders and mark up of record drawings and specifications

Upon completion of mark up, submit complete set of record product data to the Owner’s

representative for the Owner’s records

1.10 Miscellaneous Record Submittals

Refer to other sections of these specifications for requirements of miscellaneous record keeping and

submittals in connection with the actual performance of the work. Immediately prior to the date or

dates of substantial completion, complete miscellaneous records and place in good order, properly

identified and bound or filed, ready for continued use and reference. Submit to the Owner for the

Owner’s records

Part 2 Products (Not Applicable)

Part 3 Execution

3.1 Final Cleaning

3.1.1 General: Special cleaning requirements for specific units of work are included in the

appropriate sections of Division 2 through 49. General cleaning during the regular progress

of the work is required by the General Conditions and is included under section “Temporary

Facilities”

3.1.2 Cleaning: Provide final cleaning of the work at the time indicated. Employ experienced

workers or professional cleaners for final cleaning. Clean each surface or unit of work to the

condition expected from a normal commercial building cleaning and maintenance program.

Comply with the manufacturer’s instructions for operations. Complete the following

cleaning operations before requesting the Owner’s inspection for substantial completion

3.1.2.1 Remove exposed labels in finished spaces which are not required as permanent

labels on materials supplied as part of the work, except for “Asbestos”, “Asbestos

Free”, or Thermal Insulation labels specified elsewhere

3.1.2.2 Clean transparent materials, affected by the work including mirrors and window/door

glass, to a polished condition, removing substances which are noticeable vision

obscuring materials. Replace broken glass and damaged transparent materials

3.1.2.3 Clean exposed hard surfaced finishes affected by the work, to a dirt free condition,

free of dust, stains, films and similar distracting substances. Except as otherwise

indicated, avoid disturbances of natural weathering of exterior surfaces. Restore

reflective surfaces to original reflective condition

3.1.2.4 Vacuum clean with HEPA vacuum carpeted surfaces and similar soft surfaces and/or

professionally clean to remove staining caused by work of this contract

3.1.2.5 Clean plumbing fixtures affected by the work to a sanitary condition, free of stains

including those resulting from water exposure

73

Page 74: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.1.2.6 Clean project site (yard and grounds), including landscaped areas, of litter and

foreign substances left during the course of the work. Sweep paved areas which have

been affected by the work to a broom clean condition; remove stains, petrochemical

spills and other foreign deposits left by the work. Rake grounds which are neither

planted nor paved, to a smooth, even textured surface where they have been

disturbed by the work

3.1.3 Removal of Protection: Except as otherwise indicated or requested by the Owner, remove

temporary protection devices and facilities which were installed during the course of the

work to protect previously completed work during the remainder of the construction period

3.1.4 Compliance: Comply with safety standards and governing regulations for cleaning

operations. Do not burn waste materials at this site. Do not bury debris or excess materials

on the Owner’s property. Do not discharge volatile or other harmful or dangerous materials

into drainage system. Remove waste materials from the site and dispose of in a lawful

manner. Where extra materials of value remaining after completion of associated work have

become the Owner’s property, dispose of these to the Owner’s best advantage as directed

3.2 Submittals

A final written report shall be submitted to the Owner that includes; all monitoring data, daily

reports, special or incident reports, transportation manifests, and disposal receipts. This report shall

be bound and three bound copies shall be submitted to the Owner.

End of Section 01701

74

Page 75: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01711

Project Decontamination

Part 1 General

1.1 Related Documents

Drawings and general provisions of Contract, including General and Supplementary Conditions and

other Division 1 Specification sections, apply to work of this section

1.2 Description of Requirements

General: Decontamination of the work area following asbestos abatement.

1.2.1 If the asbestos abatement work is on undamaged and non-friable materials, then the building

space is deemed uncontaminated before the start of work. The decontamination procedure in

this case is a two-step procedure with two cleanings of the primary barrier plastic to remove

contamination, thus preventing contamination of the building when the work area isolation

barriers are removed.

1.3 Related Work Specified Elsewhere

Removal of gross debris is integral with the performance of abatement work and as such is specified

in the appropriate work section(s) of these specifications.

1.3.1 Section 02081 Removal of Asbestos Containing Materials

1.3.2 Section 15250 Removal of Asbestos Containing Mechanical Insulation

1.4 Work Area Clearance

Air testing and other requirements which must be met before release of Contractor and reoccupancy

of the work area are specified in Section 01714

Part 2 Products (Not Applicable)

Part 3 Execution

3.1 General

3.1.1 Work of this section includes the decontamination of air to the work area which has been, or

may have been contaminated by the elevated airborne asbestos fiber levels generated during

abatement activities, or which may previously had elevated fiber levels due to friable

asbestos containing materials in the space

3.1.2 Work of this section includes the cleaning, decontamination, and removal of temporary

facilities installed prior to abatement work, including:

Primary and critical barriers erected by work of Section 01526

75

Page 76: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Decontamination Unit erected by work of Section 01563

Pressure Differential System installed by work of Section 01513

3.1.3 Work of this section includes the cleaning and decontamination of all surfaces

(ceiling, walls, floor) of the work area and all furniture or equipment the work area

3.2 Start of Work

3.2.1 Previous Work: During the completion of the asbestos work specified in other sections, the

Secondary Barrier of polyethylene sheeting will have been removed and disposed of along

with any gross debris generated by the asbestos abatement work

3.2.2 Start of Work: Work of this section begins with the cleaning of the Primary Barrier. At start

of work the following will be in place:

3.2.2.1 Primary Barrier: Two layers of polyethylene sheeting on floor and one layer on the

walls

3.2.2.2 Critical Barrier which forms the sole barrier between the work area and other

portions of the building or the outside

3.2.2.3 Critical Barrier Sheeting over lighting fixtures and clocks, ventilation openings,

doorway, convectors, speakers and other openings

3.2.2.4 Decontamination Units for personnel and equipment in operating condition

3.2.2.5 Pressure Differential System in operation

3.3 First Cleaning

3.3.1 First Cleaning: Carry out a first cleaning of all surfaces of the work area including items of

remaining sheeting, tools, scaffolding and/or staging by use of damp cleaning and mopping

and/or a High Efficiency Particulate Absolute (HEPA) filtered vacuum. (Note: A HEPA

vacuum will fail if use with wet material). Do not perform dry dusting or dry sweeping. Use

each surface of a cleaning cloth one time only and then dispose of as contaminated waste.

Continue this cleaning until there is no visible debris from removed materials or residue on

plastic sheeting or other surfaces.

3.3.2 Remove all filters and air handling system(s) and dispose of as asbestos containing waste in

accordance with requirements of Section 02084

3.3.3 Wait 24 hours to allow negative air machines to clean air of airborne asbestos fibers. Use

oscillating fans as necessary to assure circulation of air in all parts of work areas during the

period. Maintain negative pressure system in operation for the entire 24 hour period

3.3.4 If abatement work is on “undamaged and non-friable” materials, skip section on second and

third cleaning

3.4 Second Cleaning

76

Page 77: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Second Cleaning: Carry out a second cleaning of all surfaces in the work area in the same manner

as the first cleaning:

3.4.1 Immediately following the second cleaning of the primary plastic, remove all Primary

Barrier sheeting and Material Decontamination Unit, if there is one, leaving only:

3.4.2 Critical Barrier which forms the sole barrier between the work area and other portions of the

building or the outside

3.4.3 Critical Barrier Sheeting over lighting fixtures and clocks, ventilation openings, doorway,

convectors, speakers and other openings

3.4.4 Decontamination Units for personnel and equipment in operating condition

3.4.5 Pressure Differential System in operation

3.5 Third Cleaning

Carry out a third cleaning of all surfaces in the work area in the same manner as the first cleaning

immediately after removal of primary plastic. This cleaning is now being applied to existing room

surfaces. Take care to avoid water marks or other damage to surface.

3.5.1 Wait 24 hours to allow negative air machines to clean air of airborne asbestos fibers. Use

oscillating fans as necessary to assure circulation of air in all parts of work areas during the

period. Maintain negative pressure system in operation for the entire 24 hour period.

3.6 Final Cleaning

3.6.1 Final Cleaning: Carry out a final cleaning of all surfaces in the work area in the same

manner as the previous cleaning:

3.6.2 Wait 24 hours to allow negative air machines to clean air of airborne asbestos fibers. Use

oscillating fans as necessary to assure circulation of air in all parts of work areas during the

period. Maintain negative pressure system in operation for the entire 24 hour period

3.7 Visual Inspection

3.7.1 After 24 hours, the IH will perform a complete visual inspection of the entire work area

including: decontamination unit, all plastic sheeting, seals over ventilation openings,

doorways, windows, and other openings; look for debris from any sources, residue on

surfaces, dust or other matter. If any such debris, residue, dust or other matter is found,

repeat final cleaning and continue decontamination procedure from that point

3.7.2 If the visual inspection does not reveal any dust or other signs of contamination, the final air

monitoring will take place

3.8 Final Air Sampling

The final testing shall take place using aggressive air sampling in the work space. Leaf blowers

shall be used initially on all work surfaces to dislodge any debris. Circulation fans shall be run

during the entire air sampling period to insure the movement of air inside the work space. Air

77

Page 78: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

samples shall have a minimum volume of 1,200 liters per sample, the volume of air run through the

air filter shall range between 2 to 10 liters per minute.

3.8.1 Phase Contract Microscopy (PCM): After the work area is found to be visually clean, air

samples will be taken and analyzed in accordance with the procedure for phase contrast

microscopy set forth in Section 01714:

If release criteria are not met, repeat Final Cleaning and continue decontamination procedure

from that point

If release criteria is met, remove the interior of the decontamination unit leaving in place

only the Critical Barriers separating the work area from the rest of the building and the

operating negative pressure systems.

Any small quantities of residual material found upon removal of the plastic sheeting shall be

removed with a HEPA filtered vacuum cleaner and local area protection. If significant

quantities, as determined by the Owner are found, then the entire area affected shall be

decontaminated as specified herein for the Final Cleaning.

3.8.2 Transmission Electron Microscopy (TEM): After the work area is found to be

visually clean, air samples will be taken and analyzed in accordance with the

procedure for transmissions electron microscopy set for in Section 01714

If release criteria are not met, repeat Final Cleaning and continue decontamination

procedure from that point

If the release criteria are met, remove the Critical Barriers separating the work

area from the rest of the building and shut down and remove the negative pressure

systems.

3.9 Completion of Abatement Work

3.9.1 Seal negative air machines with 6 mil polyethylene sheet and duct tape to form a tight seal at

intake and before being moved from work area.

3.9.2 Asbestos Abatement work is complete upon meeting the work area clearance criteria and

fulfilling the following:

Remove all equipment, materials, debris from the work area

Dispose of all asbestos containing waste material as specified in Section

02084

Repair or replace all interior finishes damaged during the course of asbestos

abatement work

Fulfill project closeout requirements of Section 01701

End of Section 01711

78

Page 79: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01712

Cleaning and Decontamination Procedures

1.1 Related Documents

Drawings and general provisions of Contract, including General and Supplementary Conditions and

other Division 1 Specification sections, apply to work of this section

1.2 Description of Work

1.2.1 The extent of cleaning and decontamination work is shown on the drawings

1.2.2 The work includes decontamination of the areas indicated in the “Schedule of

Decontamination Work”, found at the end of this section

1.3 Related Work Specified Elsewhere

Work Area Clearance: Specified in Section 01714

Part 2 Products (Not Applicable)

Part 3 Execution

3.1 General

Complete the following before start of work of this section:

01527 Local Area Protection

01562 Respiratory Protection

01561 Worker Protection Repair and Maintenance

3.2 Wet Cleaning

Accomplish wet cleaning during decontamination with paper towels or disposable rags:

3.2.1 Immerse paper towel or rage in bucket of water with surfactant

3.2.2 Wring Out

3.2.3 Wipe surface one and refold to a fresh face of cloth. Proceed in this manner until all

available faces of paper towel or rage have been used

3.2.4 Dispose of paper towel or rage

3.2.5 Do not place rag back in bucket to rinse out for any other purpose. If a used towel or rag

comes in contact with water, empty bucket and refill.

3.2.6 Material adhered to a surface with removal encapsulant to facilitate cleaning may require the

application of additional removal encapsulant to facilitate cleaning

79

Page 80: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.2.7 A tacky or stick type of disposal cloth designed for cleaning dust surfaces may be used for

final cleaning. The cloth should be used as described using towel or rag immersed in bucket

of water with surfactant

3.2.8 A cloth sprayed with a dust suppressant such as Endust may be used for the final cleaning.

The cloth should be used as described using towel or rag immersed in a bucket of water with

surfactant.

3.3 Removal of Asbestos Containing Debris

3.3.1 Work of this section is limited to the cleanup of a small quantity of massed debris which has

fallen from an architectural finish, fire proofing, or thermal insulation on pipes, boilers and

other thermal equipment

3.3.1.1 Shut down all ventilation into contaminated area

3.3.1.2 Seal entry to work area with 6 mil polyethylene. Slit polyethylene for entry. Install a

flap to automatically cover the slit; tape slit closed after entry

3.3.1.3 Start HEPA vacuum before entering area

Remove all small debris with the HEPA vacuum

3.3.1.4 HEPA vacuum surfaces of all pieces too large to be removed by the suction of the

HEPA vacuum

3.3.15 Pick up such pieces and place in the bottom of a 6 mil polyethylene disposal bag

conforming to the requirements of Section 02084 of the specifications. Place pieces

in the bag without dropping, avoiding unnecessary disturbance and release of

material

3.3.1.6 Remove all remaining visible debris with HEPA vacuum

3.3.1.7 HEPA vacuum an area 3’ feet beyond the location in which any visible debris was

found in two directions each at right angles to the other

3.3.1.8 Place a 6 mil polyethylene drop cloth in accordance with Section 01627 immediately

on top of the HEPA vacuumed area before performing any repair work on site from

which fall out occurred

3.3.1.9 HEPA vacuum the site from which material fell removing all loose material which

can be removed by the vacuum’s suction

3.3.10 Repair or remove remaining material

3.3.11 HEPA vacuum ladder and/or any tools used and pass out the work area

3.3.12 If the debris is extensive then HEPA vacuum all surfaces in the room starting at the

top of wall and working downward to the floor. Then start at corner of floor farthest

from work area entrance and work towards entrance

80

Page 81: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.3.13 HEPA vacuum the floor using a floor attachment with rubber floor seals and

adjustable floor to attachment height. Adjust the height so that the rubber seals just

touch the floor if carpeted and within 1/16” of hard surface floors. Vacuum the floor

in parallel passes with each pass overlapping the previous by one half the width of

the floor attachment. At the completion of one cleaning vacuum the floor a second

time at right angles to the first

3.3.14 Secure the area from occupancy until air monitoring results per Section 01714

indicate the area is safe for reoccupancy

3.4 Cleaning and Decontamination of Objects

Perform all work of decontaminating objects wherever possible on a plastic drop street installed:

3.4.1 HEPA vacuum all surfaces of object and immediate area before moving the object

3.4.2 Pick up object, if possible, and HEPA vacuum all surfaces

3.4.3 Hand to off sheet worker who will wet clean object, if possible, and place in storage location

3.4.4 Decontamination area where object was located by HEPA vacuuming twice, in two

perpendicular directions

3.4.5 Return object to its original location

3.5 Guidelines for Decontamination of Rooms

Following is an example of procedures for cleaning spaces adjacent to a work area which have been

contaminated by fiber migration, or which have been contaminated by gross debris. As

written, this section requires worker decontamination by showering.

3.5.1 Shut down all ventilation into space

3.5.2 Seal entry to work area with 6 mil polyethylene. Slit polyethylene for entry. Install a flap to

automatically cover the slit; tape slit closed after entry

3.5.3 Install pressure differential system in accordance with Section 01513

3.5.4 If it is feasible to exhaust the air handling machine outside the workspace, then place the

machine by operating it such that discharge from machine is into the space. Use one air

handling machine for each 2,500 cubic feet

3.5.5 HEPA vacuum all surfaces in the room starting at the ceiling, then top of the wall and

working downward toward the floor

3.5.6 HEPA vacuum the floor using a floor attachment with rubber floor seals and adjustable floor

to attachment height. Adjust the height so that the rubber seals are within 1/16” of hard

surface floors. Vacuum the floor in parallel passes with each pass overlapping the previous

by one half the width of the floor attachment. At the completion of one cleaning, vacuum the

floor a second time at right angles to the first

81

Page 82: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.5.7 If the floor is carpeted, discard the carpet as asbestos containing materials waste in

accordance with Section 02084

3.5.8 Operate pressure differential system machine in space for 24 hours minimum

3.5.9 At completion of decontamination work, workers decontaminate in accordance with Section

01561.k

3.5.10 Secure area from occupancy air monitoring results per Section 01714 and indicate area is

safe for reoccupancy

End of Section 01712

82

Page 83: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 01714

Work Area Clearance

Part 1 General

1.1 Related Documents

Drawing and general provisions of contract, including General and Supplemental Conditions and

other Division 1 Specification sections, apply to work of this section

1.2 Contractor Release Criteria

The work is complete when the work area is visually clean and airborne fiber levels have been

reduced to the level specified below

1.3 Air Monitoring

To determine if the elevated airborne fiber counts encountered during abatement operations have

been reduced to the specified level, the IH still take samples and analyze them according to the

following procedures:

Fibers Counted: “Fibers” referred to in this section shall be either fibers regardless of composition

as counted in the NIOSH 7400, Procedures or asbestos fibers of any size as counted using

Transmission Electron Microscope as described in the RPA AHERA Regulation d(40 CFR 763).

1.4 Aggressive Sampling

All air samples will be taken using aggressive sampling techniques

1.5 Schedule of Air Samples

The number and volume of air samples taken and analytical methods used will be in accordance

with AHERA and other applicable regulatory protocol and the recommendations of the IH.

1.5.1 Analysis: Asbestos fibers on each filter will be measured using the EPA AHERA (40 CFR

763) mandatory or non-mandatory protocols in Appendix A

1.5.2 The method of sample preparation shall be used as described in the EPA AHERA (40 CFR

763) Regulations

1.5.3 Release Criteria: Decontamination of the work site is complete if the average fiber

concentration of the work area is not statically larger than the average of outside samples for

each homogenous work area. If the average of the work area samples is statistically larger

than the average of the outside samples then the decontamination is incomplete and the

cleaning procedures of Section 01710 shall be repeated

Part 2 Products (Not Applicable)

Part 3 Execution (Not Applicable)

End of Section 01714

83

Page 84: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 02081

Removal of Asbestos Containing Materials

Part 1 General

1.1 Related Documents

Drawings and general provisions of the Contract, including General and Supplementary Conditions

and other Division 1 Specifications sections, apply to work of this section

1.2 Related Work Specified Elsewhere

1.2.1 Installation of Critical and Primary Barriers, and work area isolation procedures are set forth

in Section 01562

1.2.2 Project decontamination procedures after removal of the secondary barrier are specified in

Section 01711

1.2.3 Disposal of asbestos containing waste is specified in Section 02084

1.3 Submittals

1.3.1 Before start of work, submit the following to the Owner for review. Does not start work

until these submittals are approved by the Owner:

1.3.2 Surfactant: Submit product data, use instructions and recommendations from the

manufacturer of surfactant intended for use. Include data substantiating that material

complies with requirements

1.3.3 Removal Encapsulant: Submit product data, use instructions and recommendations from the

manufacturer of encapsulant intended for use. Include data substantiating that material

complies with requirements

1.3.4 NESHAPS Certification: Submit certification from manufacturer of surfactant or removal

encapsulant that, to the extent required by this specification, the material, if used in

accordance with the manufacturer’s instructions, will wet asbestos containing materials to

which it is applied as required by the National Emission Standard for Hazardous Pollutants

(NESHAPS) Asbestos Regulations (40 CFR `651, Subpart M)

1.3.5 Material Safety Data Sheet: Submit the Material Safety Data Sheet, or equivalent, in

accordance with the OSHA Hazard Communication Standard (29 CFR 1910, 100) for each

surfactant and encapsulating material proposed for use on the work. Include a separate

attachment for each sheet indicating the specific worker protective equipment proposed for

use with the material indicated

Part 2 Products

Following allows the contractor to use either a surfactant in water or a removal encapsulant,

providing that it is able to perform as well as the generic mixture of 50% polyoxyethylene ester and

50% polyoxyethylene ether

2.1 Wetting Materials:

84

Page 85: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

For wetting prior to disturbance of asbestos containing materials, use amended water. Provide

water to which a surfactant has been added. Use a mixture of surfactant and water which results in

wetting of the asbestos containing material and retardation of fiber release during disturbance of the

material equal to or greater than that provided by the use of one ounce of a surfactant consisting of

50% polyoxyethylene ester and 50% polyexyethylene mixed with five gallons of water

2.2 Disposable Bags

Provide 6 or 10 mil thick leak tight polyethylene bags labeled with text as follows:

Danger

Contains Asbestos Fibers

Avoid Creating Dust

Cancer and Lung Disease Hazard

Breathing Airborne Asbestos, Tremolite, Anthophyllite, or Actinolite Fibers is

Hazardous to Your Health

2.3 Woven Disposal Bags

A woven material bag made of plastic fibers that is composed of threads woven in a weave pattern

similar to burlap or grain sacks is to be used as the first bag in asbestos waste disposal as necessary.

Reinforced plastic bags that are puncture and tear resistant may be substituted

Part 3-Execution

3.1 Secondary Barrier

3.1.1 Secondary Barrier: Over the Primary Barrier, install as a drop cloth, a clear 6 mil sheet

plastic in all areas where asbestos removal work is to be carried out. Completely cover the

floor with sheet plastic. Where the work is within 10’ 0” of a wall extend the Secondary

Barrier up wall to ceiling. Support sheet plastic on wall with duct tape, seal top of secondary

plastic to Primary Barrier with duct tape so that debris is unable to get behind it. Provide

cross strips of duct tape at wall support as necessary to support sheet plastic and prevent its

falling during removal operation

3.1.2 Install secondary barrier at the beginning of each work shift. Install only sufficient plastic

for work of that shift

3.1.3 Remove secondary barrier at end of each work shift or as work in an area is completed. Fold

plastic toward center of sheet and pack in disposal bags. Keep material on sheet

continuously wet until bagged.

3.2 Worker Protection

Before beginning work with any material for which a Material Safety Data Sheet has been

submitted, provide workers with the required protective equipment. Require that appropriate

protective equipment be used at all times

3.3 Wet Removal

85

Page 86: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.3.1 Thoroughly wet to satisfaction of Owners asbestos containing materials to be removed prior

to stripping and/or tooling to reduce fiber dispersal into the air. Accomplish wetting with a

fine spray (mist) of amended water. Saturate material sufficiently to wet the substrate

without causing excess dripping. Allow time for water to penetrate material thoroughly.

Spray material repeatedly during the work process to maintain a continuously wet condition

3.3.2 Mist work area continuously with amended water whenever necessary to reduce airborne

fiber levels. An airless sprayer should be used to mist the work are continuously

3.3.3 As the material is removed, simultaneously pack material while still wet into woven disposal

bags. Twist pack of bags, bend over and seal with minimum three wraps of duct tape. Clean

outside and move to wash down station adjacent to material decontamination unit

3.3.4 Remove the materials in manageable quantities and control the descent to the ground below

3.4 Airborne Fiber Counts

General: Use work procedures that result in an 8 hour time Weighted Average (TWA) airborne fiber

count less than that indicated in the section of these specifications on “Air Monitoring-Test

Laboratory Services Section”. If airborne fiber counts exceed this level immediately mist the area

with amended water to lower fiber counts and revise work procedures to maintain airborne fiber

levels within the required limit

End of Section 02081

86

Page 87: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 02082

Removal of Asbestos Contaminated Soil

Part 1 General

1.1 Related Documents

Drawings and general provisions of the Contract, including General and Supplementary Conditions

and other Division 1 Specifications sections, apply to work of this section

Part 2-Products

2.1 Amended Water

Amended water and removal encapsulant are specified under Section 02081

Part 3-Execution

3.1 Wet Soils

After removal of Secondary Barrier and floor layer of Primary Barrier, remove the top one inch (1”)

of soils which are damp or wet and place in disposal bags. Start removal at the point of work

farthest from the entrance to the soil floor area and proceed toward the entrance. Do not permit

traffic into the fresh soil surface. Arrange negative air system so that air flow is the starting point of

work toward the entrance. After the entire first layer of soil is removed completely change coveralls

and at the entrance to the soil removal area don clean boot covers. Remove the second one inch (1”)

of soil in the same manner as the first. Carry out the decontamination procedures set forth in the

“Project Decontamination” section of this specification at this time. At the end of the project

decontamination remove the third one inch (1”) of soil in the same manner as the previous two

inches (2”).

3.2 Dry Soils

Use the same procedure for dry soils, except saturate soils with amended water or a removal

encapsulant as specified in the other Division 2 sections of the specification. If a removal

encapsulant is used, use in accordance with manufacturer’s instructions. Saturate soil beyond the

inch of soil currently being removed. If amended water is used, keep the surface of the soil

continuously wet throughout the removal and decontamination

3.3 If it can be demonstrated that the asbestos containing materials have not penetrated below 3 inches

or below the hard surface of the soil layer, then the soils are considered free of asbestos debris. If

not, the soil removal process shall continue until no visible asbestos containing materials remain.

End of Section 02082

87

Page 88: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 02084

Removal of Asbestos Containing Built Up Roof System and Flashing

1.1 Related Documents

Drawings and general provisions of the Contract, including General and Supplementary Conditions

and other Division 1 Specifications sections, apply to work of this section

1.2 Description of Work

1.2.1 All respiratory and personal protection as described in Sections 01560 and 01562 will be

worn at all times during the removal and clean-up of the asbestos containing roofing

materials

1.2.2 The asbestos containing roofing materials will be continually misted with an airless sprayer

while the materials are being cut and removed from the building. No hose bibs will be used.

1.2.3 Amended water will be used to control dust emission during the asbestos containing roof

materials removal. Water from a hose without the addition of a surfactant WILL NOT be

acceptable. Work performed in a manner other than that specified will be shut down until

written approval by the Owner is made to restart the work

1.2.4 Water from a standard hose bib will not be acceptable to mist the asbestos containing roof

materials during the removal process. Too much water can cause damage to the interior of

the building, which the Contractor will be held responsible for, decontamination and repair

at no extra expense to the Contractor

1.2.5 A standard roofing cutter with a modified shroud is to be used in cutting the roofing felts,

mastics, and identified insulation. The modified shroud will have a hose connection to a

HEPA filtered vacuum. Removal shall be to the point that the entire structural desk is

exposed

1.2.6 The HEPA filtered vacuum is to be cleaned at least once daily before cutting operations or

more if the efficiency of the vacuum decreases so as to increase dust emissions from the

cutting action

1.2.7 The area to be cut will be misted before cutting to control ambient dust

1.2.8 The roofing material will be cut into 2 foot by 2 foot squares and bagged in a woven

material bag. The bag will then be bagged again in 6 mil plastic bag so as to have double

bagging of the asbestos waste. The asbestos waste material may be “Christmas” wrapped

instead of bagging. The waste materials are gently laid on a sheet of at least 6 mil

polyethylene sheets and wrapped so that the waste materials have at least 2 wraps of

polyethylene.

1.2.9 Any areas of the roof that need to be removed but can’t be cut with a roofing cutter may be

cut with axes. The surfaces to be cut are to be misted before cutting and during the cutting

action if visible dust emissions are seen. Removal shall be to the point that the entire

structural deck is exposed

88

Page 89: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1.2.10 The structural deck surface will be vacuumed with a HEPA filtered vacuum after the

material has been removed and before a new membrane is placed

1.2.11 Wipe samples will be taken of the structural deck after the asbestos material is removed.

This will occur until it is assured that asbestos fibers are completely removed before

placement of the new membrane within the described procedures of this protocol

1.2.12 The bagged asbestos waste materials will be lowered to the ground gently so that the bag

will not break or tear

1.2.13 All dust and water runoff from the removal process will be caught in a catchment basin and

filtered to prevent contamination of the environment surrounding the building. The filters

will be prefilters used for the pressure differential air handling services as described in

Section 01513, or the asbestos water filtering device using a five (5) micrometer filter. The

water may then drain onto the ground or into the storm sewer system

1.2.14 During the removal of the asbestos containing built up roof system and flashings, bagging

the asbestos waste materials, and clean-up of the work surface, air monitoring as described

in Section 01410 will be followed

1.2.15 If the fiber counts cannot be maintained below 0.05 fibers per cubic centimeter of air or if

the excursion limit is excluded, the use of the pressure differential system will be

implemented immediately by the Contractor at the Contractor’s sole cost and expense. The

pressure differential system will be invoked at the determination of the Owner. A significant

fiber count (double the allowable count) exceeding the allowable fiber count or two

violations of the fiber count are grounds for the Owner to require the use of full

containments with pressure differential systems. The Owner reserves the right to require

full containment if it is deemed necessary due to Contractor neglect or malfeasance.

Part 2 Products

1.2 All products to be used during this process will conform to the sections of this Contract

Part 3 Execution

3.1 The execution of this work will conform to the sections of this Contract

End of Section 02084

89

Page 90: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 15250

Mechanical Systems Insulation

Part 1 General

1.1 Reference Standards

1.1.1 American Society for Testing and Materials, ASTM

1.1.2 National Fire Protection Association, NFPA

1.1.3 Underwriters Laboratory, Inc., UL

1.2 Regulatory Requirements

All insulating and accessory materials shall meet NFPA noncombustible requirement of flame

spread not to exceed 25 and smoke developed not to exceed 50 as listed by procedure ASTME 84,

NFPA 255, or UL 723

1.3 Submittals

1.3.1 Submit product data for all insulation and materials

1.3.2 Where compliance with any government specification is required, manufacturer shall issue

certificate of compliance before shipment of materials

Part 2-Products

2.1 Insulation

Replacement insulation on the boilers and breechings, where specified, is to consist of a 2 ½” thick

rigid high temperature mineral wool board material, and shall be treated to withstand temperatures

of 1200 Degrees Fahrenheit. Acceptable products include “Ther-Fiber”, manufactured by U.S.

Gypsum, Inc., or approved equivalent

2.1.1 Insulation materials will be required to have a factory applied foil skim Kraft paper service

jacket vapor barrier. Final coating shall be on eight (8) ounce canvas jacket, with a filed

applied fire retardant lagging adhesive

2.1.2 The heat and domestic water pipes are to be reinsulated with 1-1/2” thick fiberglass or

mineral fiber with an all service jacket (ASJ)

2.1.3 The fittings and valves are to be reinsulated in an equal thickness and density fiberglass or

mineral fiber that covers the heat pipes. This insulation is to adjoin the pipe insulation. The

elbows are to be covered with a PVC cover over the insulation

2.1.4 The expansion joint in the duct work shall be replaced by a non-asbestos material

Part 3 Execution

90

Page 91: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.1 General

3.1.1 Install insulation for each service as recommended by the manufacturer

3.1.2 Do not apply pipe covering or insulation materials to piping, or item of equipment until after

the tests have been completed and work is proved sound and far from defects

3.1.3 Clean piping, fittings, and equipment according to recommendations of insulation

manufacturer before installation is applied

3.1.4 Provide drop cloths or other means of protective equipment from drippings or spattering

which may be caused by application of insulation materials

3.1.5 Wherever insulated pipes pass through sleeves or openings, full specified thickness of

insulation shall pass through sleeves or openings

3.1.6 Do not use staples or pressure sensitive tape for securement and sealing unless specifically

allowed in specifications

End of Section 15250

91

Page 92: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Section 15254

Repair of Insulation and Lagging

Part 1 General

1.1 Related Documents

Drawings and general provisions of Contract, including General and Supplementary Conditions and

Division 1 Specification Sections apply to work of this Section

2.1 Description of Work

Repair of insulation on all piping upon which asbestos containing insulation is to remain

3.1 Reference Standards

3.1.1 American Society for Testing and Materials, ASTM

3.1.2 National Fire Protection Association, NFPA

3.1.3 Underwriters Laboratory, Inc., UL

4.1 Regulatory Requirements

All insulating and accessory materials shall meet NFPA noncombustible requirement of flame

spread not to exceed 25 and smoke developed not to exceed 50 as listed by procedure ASTME 84,

NFPA 255, or UL 723

5.1 Submittals

5.1.1 Submit product data for all insulation and materials

5.1.2 Where compliance with any government specification is required, manufacturer shall issue

certificate of compliance before shipment of materials

Part 2 Products (Not Applicable)

Part 3 Execution

3.1.1 Install insulation for each service as recommended by the manufacturer

3.1.2 Do not apply pipe covering or insulation materials to piping, or item of equipment until after

the tests have been completed and work is proved sound and far from defects

3.1.3 Clean piping, fittings, and equipment according to recommendations of insulation

manufacturer before installation is applied

3.1.4 Provide drop cloths or other means of protective equipment from drippings or spattering

which may be caused by application of insulation materials

92

Page 93: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.1.5 Wherever insulated pipes pass through sleeves or openings, full specified thickness of

insulation shall pass through sleeves or openings

3.1.6 Do not use staples or pressure sensitive tape for securement and sealing unless specifically

allowed in specifications

End of Section 15254

93

Page 94: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Document A30S™ -1986 Contractor's Qualification Statement

The Undersigned certifies under oath that the information provided herein is true and sufficiently complete so as not to be misleading.

SUBMITTED TO:

ADDRESS:

SUBMITTED BY:

NAME:

ADDRESS:

PRINCIPAL OFFICE:

] Corporation

] Partnership

]Individual

]Joint Venture

Other

NAME OF PROJECT: (if applicable) II

TYPE OF WORK: (file separate form for each Classification of Work)

] General Construction

]HVAC

] Electrical

] Plumbing

] Other: (Specify)

§ 1 ORGANIZATION § 1.1 How many years has your organization been in business as a Contractor?

§ 1.2 How many years has your organization been in business under its present business name?

§ 1.2.1 Under what other or former names has your organization operated?

§ 1.3 If your organization is a corporation, answer the following: § 1.3.1 Dateofincorporation : § 1.3.2 State of incorporation : § 1.3.3 President's name:

ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AlA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed . A vertical line in the left margin of this document indicates where the author has added necessary information and where the author has added to or deleted from the original AlA text.

This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

This form is approved and recommended by the American Institute of Architects (AlA) and The Associated General Contractors of America (AGC) for use in evaluating the qualifications of contractors . No endorsement of the submitting party or verification of the information is made by AlA or AGC.

AlA Document A305 TM -1986. Copyright C1:> 1964. 1969. 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING : This AJAC Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AlAe Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AlA software at 09:00:15 on 10/30/2015 under Order No. 998103204 7 _1 which expires on 05/17/2016. and is not for resale. User Notes: (1701539959)

94

Page 95: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

§ 1.3.4 Vice-president 's name(s)

§ 1.3.5 Secretary' s name: § 1.3.6 Treasurer ' s name:

§ 1.4 If your organization is a partnership, answer the following: § 1.4.1 Date of organization: § 1.4.2 Type of partnership (if applicable): § 1.4.3 Name(s) of general partner(s)

§ 1.5 If your organization is individuall y owned, answer the following: § 1.5.1 Date of organization: § 1.5.2 Name of owner:

§ 1.6 Ifthe form of your organization is other than those li sted above, describe it and name the principals :

§ 2 LICENSING § 2.1 List jurisdictions and trade categories in which your organization is legally qualified to do business, and indicate registration or license numbers, if applicable.

§ 2.2 List jurisdictions in which your organization ' s partnership or trade name is fil ed.

§ 3 EXPERIENCE § 3.1 List the categories of work that your organization normall y performs with its own forces.

§ 3.2 Claims and Suits. (If the answer to any of the questions below is yes, please attach detai ls.) § 3.2.1 Has your organization ever failed to complete any work awarded to it?

§ 3.2.2 Are there any judgments, claims, arbitration proceedin gs or suits pending or outstanding against your organization or its officers?

§ 3.2.3 Has your organization filed any law suits or requested arbitrati on with regard to construction contracts within the last five years?

§ 3.3 Within the last five years, has any officer or principal of your organization ever been an officer or principal of another organization when it failed to complete a construction contract? (If the answer is yes, please attach detail s.)

AlA Document A30S TM - 1986. Copyright © 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING: This AlA"' Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution ofthis AlA"' Document, or any 2 portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AlA software at 09:00:15 on 10/30/2015 under Order No.9981 03204 7 _1 which expires on 05/17/2016, and is not for resale . User Notes: (1701539959)

95

Page 96: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

§ 3.4 On a separate sheet, list major construction projects your organization has in progress, giving the name of project, owner, architect, contract amount, percent complete and scheduled completion date.

§ 3.4.1 State total worth of work in progress and under contract:

§ 3.5 On a separate sheet, li st the major projects your organization has completed in the past five years, giving the name of project, owner, architect, contract amount, date of completion and percentage of the cost of the work performed with your own forces.

§ 3.5.1 State average annual amount of construction work performed during the past five years:

§ 3.6 On a separate sheet, li st the construction experience and present commitments of the key individuals of your organization .

§ 4 REFERENCES § 4.1 Trade References:

§ 4.2 Bank References:

§ 4.3 Surety: § 4.3.1 Name of bonding company:

§ 4.3.2 Name and address of agent:

§ 5 FINANCING § 5.1 Financial Statement.

§ 5.1.1 Attach a financial statement, preferably audited, including your organ ization's latest balance sheet and income statement showing the following items:

Current Assets (e.g., cash, joint venture accoun ts, accounts receivable, notes receivable, accrued income, deposits, materials inventory and prepaid expenses);

Net Fixed Assets;

Other Assets;

AlA Document A3QS TM - 1986. Copyright© 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING: Th is AlA"' Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AlA"' Document, or any 3 portion of it, may result in severe civil and crim inal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AlA software at 09:00:15 on 10/30/201 5 under Order No. 9981032047 _1 which expires on 05/17/2016, and is not for resale. User Notes: (1701539959)

96

Page 97: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Current Liabilities (e.g., accounts payable, notes payable, accrued expenses, provision for income taxes, advances, accrued salaries and accrued payroll taxes) ;

Other Liabilities (e.g., capital, capital stock, authorized and outstanding shares par va lues, earned surplus and retained earnings).

§ 5.1.2 Name and address of firm preparing attached financial statement, and date thereof:

§ 5.1.3 Is the attached financial statement for the identical organization named on page one?

§ 5.1.4 If not, explain the relationship and financial responsibility of the organization whose financial statement is provided (e.g., parent-subsidiary).

§ 5.2 Will the organization whose financial statement is attached act as guarantor of the contract for construction?

§ 6 SIGNATURE § 6.1 Dated at this day of

Name of Organization:

By:

Title:

§ 6.2

M being duly sworn deposes and says that the information provided herein is true and sufficiently complete so as not to be misleading.

Subscribed and sworn before me this day of

Notary Public:

My Commission Expires:

AlA Document A30S TM -1986. Copyright © 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING: This AlA" Document is protected by U.S. Copyright Law and International Treaties . Unauthorized reproduction or distribution of this AlA" Document, or any 4 portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AlA software at 09:00:15 on 10/30/2015 under Order No. 998103204 7 _1 which expires on 05/17/2016. and is not for resale . User Notes: (1701539959)

97

Page 98: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

1 CONTACT INFORMATION

1.1 Organization (Complete Only If a Branch Office Will Be Providing Services to WCPS)

Company Name:

DBA:

Corporate Federal ID Number: DUNS Number:

Address:

City: State: Zip:

Phone: Fax:

Email Address for sending PO's:

Website Address:

1.2 Main Contact for the Person Administering this Contract:

Name:

Title:

Email Address: Phone:

1.3 Other Company Contacts:

Name:

Title:

Email Address: Phone:

Name:

Title:

Email Address: Phone:

2 COMPANY INFORMATION

2.1 Number of years in the asbestos abatement business:

ALL BIDDERS MUST COMPLETE THE REMAINDER OF THIS FORM

If WCPS is required to use MBE certified subcontractors on a project, do you agree to make a good faith effort to

attempt to achieve the goals that would be defined by that project and to submit the requisite MBE paperwork?

WAHSINGTON COUNTY PUBLIC SCHOOLS PURCHASING DEPARTMENT

10435 DOWNSVILLE PIKE, HAGERSTOWN MD 21740

BID 2018-12 - UNIT PRICE CONTRACT FOR ASBESTOS ABATEMENT

WCPS SUPPLEMENTAL QUESTIONNAIRE TO AIA FORM 305—1986—CONTRACTOR’S

QUALIFICATION STATEMENT

98

Page 99: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

2.2 List all the materials that your company is licensed to abate:

2.3 Include a copy of your license to do business in the State of Maryland

2.4 Include a copy of your State of Maryland license for Asbestos Removal/Encapsulation

3 EXPERIENCE (COMPLETE THIS SECTION IN LIEU OF 3.6 ON THE AIA A 305 FORM)

3.1

3.2 Have you performed any contractual work with WCPS in the last five years? If so, list the project(s) and date(s).

3.3

3.3.1 Company:

Contact:

Title:

Email Address: Phone:

3.3.2 Company:

Contact:

Title:

Email Address: Phone:

3.3.3 Company:

Contact:

Title:

Email Address: Phone:

Has your company ever been debarred from doing business with any federal/state/county/city government or school

district? If yes, explain:

Provide the names, titles and contact information for five contracts that most nearly meet an IDQ format, with

references preferred for a school system or non-profit agency, within the State of Maryland. If no work has been

performed in Maryland, list work that is registered with other states, and name the states. WCPS will contact them

as references.

99

Page 100: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

3.4

3.5 Do you have an AHERA certified project designer on staff? Attach a resume for this individual.

3.6

3.7

3.7.1 Company:

Contact:

Title:

Email Address: Phone:

3.7.2 Company:

Contact:

Title:

Email Address: Phone:

4 FINANCING, BONDING AND INSURANCE

4.1

4.2

4.3 Has the firm ever been denied or been unable to receive bonding? If yes, explain:

4.4 Give the maximum value of contract work for which you could obtain a bond during the fiscal year:

Use the attached form to list all permanent employees on your payroll (i.e., project managers, field supervisor,

AHERA certified technician, and licensed technicians for other abatement media). Include their category of work,

their name, title, year of hire by your company, type of certifications, and license #s (if applicable) or dates of

expiration.

Submit a copy of your company’s certificate of insurance with this application to show evidence of current

coverage. The following questions should also be answered.

If awarded this contract, do you agree to obtain, at your cost, and provide evidence of, abatement coverage on an

occurrence basis or a claims made basis (for a minimum of two years after completion of project), as well as

pollution insurance covering asbestos, in the limits stated in these specifications, during the life of this contract?

Submit the resumes of all key employees the abatement contractor intends to use on Washington County Public

Schools projects.

Provide the names and contact information of at least two air monitoring/industrial firms, which have overseen or

provided air monitoring for school projects performed by your firm in the past two years. WCPS will contact them

as references.

100

Page 101: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

5 CITATIONS

5.1

I hereby certify that

has not received any federal, state, or local regulatory violations or citations within the last three years.

Date

6 SIGNATURE

Signature Title

List any state, federal or local regulatory violations and/or citations and their resolution that have been issued to this

branch or corporate office in the last three (3) years. Provide the value of any judgments or liens outstanding

against your organization (use additional paper if needed):

If the response to question 5.1 is “not applicable” or “none,” the following statement must be submitted and signed

by an officer of the firm:

I, the undersigned, hereby certify that the information contained within this supplemental questionnaire is true and

is a correct statement of facts.

Name of Corporate Officer Name of Firm

DateAuthorized Signature

I further affirm that the employees listed in this application are full time, properly trained, and certified employees

of our firm and not part time, contractual, or temporary employees.

I further certify that the undersigned shall abide by and be subject to all applicable federal, state, and local laws and

relations pertaining to any subsequent contract that may be issued.

Printed Name Title

101

Page 102: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

Name Title Year of Hire

Type of

Certification

Certification

Number Expiration Date

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

BID 2018-12 - UNIT PRICE CONTRACT FOR ASBESTOS ABATEMENT

EMPLOYEE CERTIFICATION LIST

102

Page 103: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12

Unit Price Contract for Asbestos Abatement

PRICE PROPOSAL FORMI. Removal /Abatement of Product Units Unit of Measure Maximum Unit Price

1 Removal of pipe insulation-straight Per linear foot $

2 Removal of pipe insulation-fittings, elbows, Ts, etc. Each $

3 Removal of pipe insulation-straight (glove bag method) Per bag $

4 Removal of pipe insulation-fittings, elbows, Ts, etc. (glove bag method) Per bag $

5 Removal of duct transition cloth (flexible connector) Per square foot $

6 Removal of duct and tank insulation Per square foot $

7 Removal of boiler and breeching insulation Per square foot $

8 Removal of ceiling tile- drop in Per square foot $

9 Removal of ceiling tile- glued Per square foot $

10 Removal of ceiling tile- track system Per square foot $

11 Removal of 9" x 9" floor tile Per square foot $

12 Removal of 12" x 12" floor tile Per square foot $

13 Removal of floor tile mastic Per square foot $

14 Removal of linoleum/sheet goods Per square foot $

15 Removal of plaster/troweled on ACM Per square foot $

16 Removal of spray applied fireproofing Per square foot $

17 Removal of floor tile under carpet Per square foot $

18 Removal of tank linings Per square foot $

19 Removal of transite soffit and siding up to 10' high Per square foot $

20 Removal of transite soffit and siding 10'- 20' high Per square foot $

II. Labor Rates for Set up and Clean Up Unit of Measure Maximum Unit Price

1 Supervisor + 3 person team, routine hours (7am-11pm) Per crew, per hour $

2 Supervisor+ 3 person team, non-routine hours (11pm-7am or holidays) Per crew, per hour $

3 Licensed abatement worker, routine hours (7am-11pm) Per hour $

4 Licensed abatement worker, non-routine hours (11pm-7am or holidays) Per hour $

5 Licensed mold abatement worker, routine hours (7am-11pm) Per hour $

6 Licensed mold abatement worker, non-routine hours (11pm-7am or holidays) Per hour $

7 Licensed lead abatement worker, routine hours (7am-11pm) Per hour $

8 Licensed lead abatement worker, non-routine hours (11pm-7am or holidays) Per hour $

III. Disposal Unit Costs Unit of Measure Maximum Unit Price

1 Disposal per container (bag, drum, etc.) Per each $

2 Disposal per 40 cubic yard dumpster Per each $

3 Disposal per 100 cubic yard dumpster Per each $

4 Use of containment shower, one time charge per project Each $

5 Percentage mark up for approved rental equipment Value %

IV. Industrial Hygiene Services Unit of Measure Maximum Unit Price

1 Licensed industrial hygienist (7am-11pm) Per hour, per person $

2 TEM Sampling and Testing Each (Per Sample) $

3 PCM Sampling and Testing Each (Per Sample $

4 TEM Sampling and Testing- 4 Hour Results Each (Per Sample) $

5 PCM Sampling and Testing-4 Hour Results Each (Per Sample) $

V. SUBCONTRACTORS and TRADES (If none, write “NONE”):

103

Page 104: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS 10435 Downsville Pike, Hagerstown, Maryland 21740

CONTRACT AFFIDAVIT

MANDATORY CONTRACT ADDENDUM

COMAR 21.07.01.25

Bidder shall complete and submit this contract affidavit to the Legal Department of Washington County

Public Schools to attach with the contract form.

A. AUTHORITY

I HEREBY AFFIRM THAT:

I, (print name) possess the legal authority to make

this Affidavit.

B. CERTIFICATION OF REGISTRATION OR QUALIFICATION WITH THE STATE

DEPARTMENT OF ASSESSMENTS AND TAXATION

I FURTHER AFFIRM THAT:

The business named above is a (check applicable items):

Corporation: ____domestic ____or foreign

Limited Liability Company: ____domestic ____or foreign

Partnership: ____domestic ____or foreign

Statutory Trust: ____domestic or foreign

Sole Proprietorship: ____and is registered or qualified as required under Maryland Law.

I further affirm that the above business is in good standing both in Maryland and (IF APPLICABLE) in

the jurisdiction where it is presently organized, and has filed all of its annual reports, together with filing

fees, with the Maryland State Department of Assessments and Taxation. The name and address of its

resident agent (IF APPLICABLE) filed with State Department of Assessments and Taxation is:

Name and Department ID Number

Address:

and that if it does business under a trade name, it has filed a certificate with the State Department of

Assessments and Taxation that correctly identifies that true name and address of the principal or owner

as:

104

Page 105: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS 10435 Downsville Pike, Hagerstown, Maryland 21740

Name and Department ID Number:

Address:

C. FINANCIAL DISCLOSURE AFFIRMATION

I FURTHER AFFIRM THAT:

I am aware of, and the above business will comply with, the provisions of the State Finance and

Procurement Article §13-221, Annotated Code of Maryland, which require that every business that enters

into contracts, leases, or other agreements with the State of Maryland or its agencies during a calendar

year under which the business is to receive in the aggregate $100,000 or more shall, within 30 days of the

time when the aggregate value of the contracts, leases, or other agreements reaches $100,000, file with the

Secretary of State of Maryland certain specified information to include disclosure of beneficial ownership

of the business.

D. POLITICAL CONTRIBUTION DISCLOSURE AFFIRMATION

I FUTHER AFFIRM THAT:

I am aware of, and the above business will comply with, Election Law Article §§14-101-14-108,

Annotated Code of Maryland, which requires that every person that enters into contracts, leases, or other

agreements with the State of Maryland, including its agencies or a political subdivision of the State,

during a calendar year in which the person receives in the aggregate $100,000 or more shall file with the

State Board of Elections a statement disclosing contributions in excess of $500 made during the reporting

period to a candidate for elective office in any primary or general election.

E. DRUG AND ALCOHOL FREE WORKPLACE

(Applicable to all contracts unless the contract is for a law enforcement agency and the agency head or the

agency head’s designee has determined that application of COMAR 21.11.08 and this certification would

be inappropriate in connection with the law enforcement agency’s undercover operations.)

I CERTIFY THAT:

(1) Terms defined in COMAR 21.11.08 shall have the same meanings when used in this certification.

(2) By submission of its bid or offer, the business, if other than an individual, certifies and agrees

that, with respect to its employees to be employed under a contract resulting from this

solicitation, the business shall:

(a) Maintain a workplace free of drug and alcohol abuse during the term of the contract;

(b) Publish a statement notifying its employees that the unlawful manufacture, distribution,

dispensing, possession, or use of drugs, and the abuse of drugs or alcohol is prohibited in the

105

Page 106: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS 10435 Downsville Pike, Hagerstown, Maryland 21740

business’ workplace and specifying the actions that will be taken against employees for violation

of the prohibitions;

(c) Prohibit its employees from working under the influence of drugs or alcohol;

(d) Not hire or assign to work on the contract anyone who the business knows, or in the exercise

of due diligence should know, currently abuses drugs or alcohol and is not actively engaged in a

bona fide drug or alcohol abuse assistance or rehabilitation program;

(e) Promptly inform the appropriate law enforcement agency of every drug-related crime that

occurs in its workplace if the business has observed the violation or otherwise has reliable

information that a violation has occurred;

(f) Establish drug and alcohol abuse awareness programs to inform its employees about:

(i) The dangers of drug abuse and alcohol abuse in the workplace;

(ii) The business’s policy of maintaining a drug and alcohol free workplace;

(iii) Any available drug and alcohol counseling, rehabilitation, and employee assistance

programs; and

(iv) The penalties that may be imposed upon employees who abuse drugs and alcohol in

the workplace;

(g) Provide all employees engaged in the performance of the contract with a copy of the statement

required by §E(2)(b), above;

(h) Notify its employees in the statement required by §E(2)(b), above, that as a condition of

continued employment on the contract, the employee shall:

(i) Abide by the terms of the statement; and

(ii) Notify the employer of any criminal drug or alcohol abuse conviction for an offense

occurring in the workplace not later than 5 days after a conviction;

(i)Notify the procurement officer within 10 days after receiving notice under §E(2)(h)(ii), above,

or otherwise receiving actual notice of a conviction;

(j)Within 30 days after receiving notice under §E(2)(h)(ii), above, or otherwise receiving actual

notice of a conviction, impose either of the following sanctions or remedial measures on any

employee who is convicted of a drug or alcohol abuse offense occurring in the workplace:

(i) Take appropriate personnel action against an employee, up to and including

termination; or

(ii) Require an employee to satisfactorily participate in a bona fide drug or alcohol abuse

assistance or rehabilitation program; and

(k) Make a good faith effort to maintain a drug and alcohol free workplace through

implementation of §E(2)(a)-(j),above.

106

Page 107: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS 10435 Downsville Pike, Hagerstown, Maryland 21740

(3) If the business is an individual, the individual shall certify and agree as set forth in §E(4), below,

that the individual shall not engage in the unlawful manufacture, distribution, dispensing, possession,

or use of drugs or the abuse of drugs or alcohol in the performance on the contract.

(4) I acknowledge and agree that:

(a) The award of the contract is conditional upon compliance with COMAR 21.11.08 and this

certification;

(b) The violation of the provisions of COMAR 21.11.08 or this certification shall be cause to

suspend payments under, or terminate the contract for default under COMAR 21.07.01.11 or

21.07.03.15, as applicable; and

(c) The violation of the provisions of COMAR 21.11.08 or this certification in connection with

the contract may, in the exercise of the discretion of the Board of Public Works, result in

suspension and debarment of the business under COMAR 21.08.03.

F. CERTAIN AFFIRMATIONS VALID

I FURTHER AFFIRM THAT:

To the best of my knowledge, information, and belief, each of the affirmations, certifications, or

acknowledgments contained in that certain Bid/Proposal Affidavit dated ,

20 , and executed by me for the purpose of obtaining the contract to which this Exhibit is attached

remains true and correct in all respects as if made as of the date of this Contract Affidavit and as if fully

set forth herein.

I DO SOLEMNLY DECLARE AND AFFIRM UNDER THE PENALTIES OF PERJURY THAT THE

CONTENTS OF THIS AFFIDAVIT ARE TRUE AND CORRECT TO THE BEST OF MY

KNOWLEDGE, INFORMATION, AND BELIEF.

Date:

By:

(Print name of Authorized Representative and Affiant)

(Signature of Authorized Representative and Affiant)

_____________________________________________

(Company name)

107

Page 108: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS 10435 Downsville Pike, Hagerstown, Maryland 21740

MANDATORY BID/PROPOSAL AFFIDAVIT

COMAR 21.05.08.07

Bidder shall complete and submit this bid/proposal affidavit to the Supervisor of Purchasing, Washington

County Public Schools with the bid or offer.

A. AUTHORITY

I HEREBY AFFIRM THAT:

I (print name) possess the legal authority to make this Affidavit.

B. CERTIFICATION REGARDING COMMERCIAL NONDISCRIMINATION

The undersigned bidder hereby certifies and agrees that the following information is correct: In preparing

its bid on this project, the bidder has considered all proposals submitted from qualified, potential

subcontractors and suppliers, and has not engaged in “discrimination” as defined in §19-103 of the State

Finance and Procurement Article of the Annotated Code of Maryland. “Discrimination” means any

disadvantage, difference, distinction, or preference in the solicitation, selection, hiring, or commercial

treatment of a vendor, subcontractor, or commercial customer on the basis of race, color, religion,

ancestry, or national origin, sex, age, marital status, sexual orientation, or on the basis of disability or any

otherwise unlawful use of characteristics regarding the vendor’s, supplier’s or commercial customer’s

employees or owners. “Discrimination” also includes retaliating against any person or other entity for

reporting any incident of “discrimination”. Without limiting any other provision of the solicitation on this

project, it is understood that, if the certification is false, such false certification constitutes grounds for the

State to reject the bid submitted by the bidder on this project, and terminate any contract awarded based

on the bid. As part of its bid or proposal, the bidder herewith submits a list of all instances within the past

4 years where there has been a final adjudicated determination in a legal or administrative proceeding in

the State of Maryland that the bidder discriminated against subcontractors, vendors, suppliers, or

commercial customers, and a description of the status or resolution of that determination, including any

remedial action taken. Bidder agrees to comply in all respects with the State’s Commercial

Nondiscrimination Policy as described under Title19 of the State Finance and Procurement Article of the

Annotated Code of Maryland.

B-1 Certification Regarding Minority Business Enterprises.

The undersigned bidder hereby certifies and agrees that it has fully complied with the State Minority

Business Enterprise Law, State Finance and Procurement Article, §14-308 (a)(2), Annotated Code of

Maryland, which provides that, except as otherwise provided by law, a contractor may not identify a

certified minority business enterprise in a bid or proposal and:

108

Page 109: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS 10435 Downsville Pike, Hagerstown, Maryland 21740

(1) Fail to request, receive, or otherwise obtain authorization from the certified minority business

enterprise to identify the certified minority proposal;

(2) Fail to notify the certified minority business enterprise before execution of the contract of its

inclusion in the bid or proposal;

(3) Fail to use the certified minority business enterprise in the performance of the contract; or

(4) Pay the certified minority business enterprise solely for the use of its name in the bid or

proposal.

Without limiting any other provision of the solicitation on this project, it is understood that if the

certification is false, such false certification constitutes grounds for the State to reject the bid submitted by

the bidder on this project, and terminate any contract awarded based on the bid.

C. AFFIRMATION REGARDING BRIBERY CONVICTIONS

I FURTHER AFFIRM THAT:

Neither I, nor to the best of my knowledge, information, and belief, the above business (as is defined in

Section 16-101(b) of the State Finance and Procurement Article of the Annotated Code of Maryland), or

any of its officers, directors, partners, controlling stockholders, or any of its employees directly involved

in the business's contracting activities including obtaining or performing contracts with public bodies has

been convicted of, or has had probation before judgment imposed pursuant to Criminal Procedure Article,

§6-220, Annotated Code of Maryland, or has pleaded nolo contendere to a charge of bribery, attempted

bribery, or conspiracy to bribe in violation of Maryland law, or of the law of any other state or federal

law, except as follows (indicate the reasons why the affirmation cannot be given and list any conviction,

plea, or imposition of probation before judgment with the date, court, official or administrative body, the

sentence or disposition, the name(s) of person(s) involved, and their current positions and responsibilities

with the business):

D. AFFIRMATION REGARDING OTHER CONVICTIONS

I FURTHER AFFIRM THAT:

Neither I, nor to the best of my knowledge, information, and belief, the above business, or any of its

officers, directors, partners, controlling stockholders, or any of its employees directly involved in the

business's contracting activities including obtaining or performing contracts with public bodies, has:

109

Page 110: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS 10435 Downsville Pike, Hagerstown, Maryland 21740

(1) Been convicted under state or federal statute of:

(a) A criminal offense incident to obtaining, attempting to obtain, or performing a public

or private contract; or

(b) Fraud, embezzlement, theft, forgery, falsification or destruction of records or

receiving stolen property;

(2) Been convicted of any criminal violation of a state or federal antitrust statute;

(3) Been convicted under the provisions of Title 18 of the United States Code for violation of the

Racketeer Influenced and Corrupt Organization Act, 18 U.S.C. §1961 et seq., or the Mail Fraud

Act, 18 U.S.C. §1341 et seq., for acts in connection with the submission of bids or proposals for a

public or private contract;

(4) Been convicted of a violation of the State Minority Business Enterprise Law, §14-308 of the

State Finance and Procurement Article of the Annotated Code of Maryland;

(5) Been convicted of a violation of §11-205.1 of the State Finance and Procurement Article of

the Annotated Code of Maryland;

(6) Been convicted of conspiracy to commit any act or omission that would constitute grounds for

conviction or liability under any law or statute described in subsections (1)—(5) above;

(7) Been found civilly liable under a state or federal antitrust statute for acts or omissions in

connection with the submission of bids or proposals for a public or private contract; or

(8) Been found in a final adjudicated decision to have violated the Commercial

Nondiscrimination Policy under Title 19 of the State Finance and Procurement Article of the

Annotated Code of Maryland with regard to a public or private contract; or

(9) Admitted in writing or under oath, during the course of an official investigation or other

proceedings, acts or omissions that would constitute grounds for conviction or liability under any

law or statute described in §§B and C and subsections D (1)- (8) above, except as follows

(indicate reasons why the affirmations cannot be given, and list any conviction, plea, or

imposition of probation before judgment with the date, court, official or administrative body, the

sentence or disposition, the name(s) of the person(s) involved and their current positions and

responsibilities with the business, and the status of any debarment):

E. AFFIRMATION REGARDING DEBARMENT

110

Page 111: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS 10435 Downsville Pike, Hagerstown, Maryland 21740

I FURTHER AFFIRM THAT:

Neither I, nor to the best of my knowledge, information, and belief, the above business, or any of its

officers, directors, partners, controlling stockholders, or any of its employees directly involved in the

business's contracting activities, including obtaining or performing contracts with public bodies, has ever

been suspended or debarred (including being issued a limited denial of participation) by any public entity,

except as follows (list each debarment or suspension providing the dates of the suspension or debarment,

the name of the public entity and the status of the proceedings, the name(s) of the person(s) involved and

their current positions and responsibilities with the business, the grounds of the debarment or suspension,

and the details of each person's involvement in any activity that formed the grounds of the debarment or

suspension).

F. AFFIRMATION REGARDING DEBARMENT OF RELATED ENTITIES

I FURTHER AFFIRM THAT:

(1) The business was not established and it does not operate in a manner designed to evade the

application of or defeat the purpose of debarment pursuant to Sections 16-101, et seq., of the

State Finance and Procurement Article of the Annotated Code of Maryland; and

(2) The business is not a successor, assignee, subsidiary, or affiliate of a suspended or debarred

business, except as follows (you must indicate the reasons why the affirmations cannot be given

without qualification):

G. SUB-CONTRACT AFFIRMATION

I FURTHER AFFIRM THAT:

Neither I, nor to the best of my knowledge, information, and belief, the above business, has knowingly

entered into a contract with a public body under which a person debarred or suspended under Title 16 of

the State Finance and Procurement Article of the Annotated Code of Maryland will provide, directly or

indirectly, supplies, services, architectural services, construction related services, leases of real property,

or construction.

111

Page 112: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS 10435 Downsville Pike, Hagerstown, Maryland 21740

H. AFFIRMATION REGARDING COLLUSION

I FURTHER AFFIRM THAT:

Neither I, nor to the best of my knowledge, information, and belief, the above business has:

(1) Agreed, conspired, connived, or colluded to produce a deceptive show of competition in the

compilation of the accompanying bid or offer that is being submitted;

(2) In any manner, directly or indirectly, entered into any agreement of any kind to fix the bid

price or price proposal of the bidder or offeror or of any competitor, or otherwise taken any action

in restraint of free competitive bidding in connection with the contract for which the

accompanying bid or offer is submitted.

I. CERTIFICATION OF TAX PAYMENT

I FURTHER AFFIRM THAT:

Except as validly contested, the business has paid, or has arranged payment of, all taxes due the State of

Maryland and has filed all required returns and reports with the Comptroller of the Treasury, the State

Department of Assessments and Taxation, and the Department of Labor, Licensing, and Regulation, as

applicable, and will have paid all withholding taxes due the State of Maryland prior to final settlement.

J. CONTINGENT FEES

I FURTHER AFFIRM THAT:

The business has not employed or retained any person, partnership, corporation, or other entity, other than

a bona fide employee, bona fide agent, bona fide salesperson, or commercial selling agency working for

the business, to solicit or secure the Contract, and that the business has not paid or agreed to pay any

person, partnership, corporation, or other entity, other than a bona fide employee, bona fide agent, bona

fide salesperson, or commercial selling agency, any fee or any other consideration contingent on the

making of the Contract.

K. ACKNOWLEDGEMENT

I ACKNOWLEDGE THAT this Affidavit is to be furnished to the Procurement Officer and may be

distributed to units of: (1) the State of Maryland; (2) counties or other subdivisions of the State of

Maryland; (3) other states; and (4) the federal government. I further acknowledge that this Affidavit is

subject to applicable laws of the United States and the State of Maryland, both criminal and civil, and that

nothing in this Affidavit or any contract resulting from the submission of this bid or proposal shall be

construed to supersede, amend, modify or waive, on behalf of the State of Maryland, or any unit of the

State of Maryland having jurisdiction, the exercise of any statutory right or remedy conferred by the

constitution and the laws of Maryland with respect to any misrepresentation made or any violation of the

112

Page 113: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS 10435 Downsville Pike, Hagerstown, Maryland 21740

obligations, terms, and covenants undertaken by the above business with respect to (1) this Affidavit, (2)

the contract, and (3) other Affidavits comprising part of the contract.

I DO SOLEMNLY DECLARE AND AFFIRM UNDER THE PENALTIES OF PERJURY THAT THE

CONTENTS OF THIS AFFIDAVIT ARE TRUE AND CORRECT TO THE BEST OF MY

KNOWLEDGE, INFORMATION, AND BELIEF.

Date:

By:

(Print name of Authorized Representative and Affiant)

(Signature of Authorized Representative and Affiant)

_____________________________________________

(Company name)

113

Page 114: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WCPS RFP 2018-12

Unit Price Contract for Asbestos Abatement

Specification, Price, and Addenda Signature Acknowledgment

I/We certify that this bid/proposal is made without previous understanding, agreement, or connection with any person,

firm, or corporation submitting a bid/proposal for the same goods/services and is, in all respects fair and without

collusion or fraud; that none of this company's officers, directors, partners or its employees have been convicted of

bribery, attempted bribery, or conspiracy to bribe under the laws of any state or federal government; and that no

member of the Board of Education of Washington County, Administrative or Supervisory Personnel or other

employees of the Washington County Public Schools, has any interest in the bidding company:

Company:

dba: ______________________________________________________________________________

Federal Identification: _______________________

Acknowledgment of Addenda (if applicable) The above company/firm acknowledges the receipt of the following addenda for the above-referenced solicitation.

Bidder acknowledges each addendum by initialing and dating below:

Addendum #1: _____________________ Date: _____________________

Addendum #2: _____________________ Date: _____________________

Addendum #3: _____________________ Date: _____________________

Addendum #4: _____________________ Date: _____________________

Addendum #5: _____________________ Date: _____________________

Proprietary and Confidential Information (please check the appropriate statement)

See Proprietary and Confidential Information in Section I General Terms and Conditions

The offeror acknowledges that there is no proprietary and confidential information included in their

submission. The submission may be used as submitted when a Freedom of Information Act request is

submitted.

The offeror acknowledges that there is proprietary and confidential information included in their

submission. The offeror has included an electronic copy of the proposal (on a flash-drive or CD) in a

separate envelope labeled “REDACTED PROPOSAL” that will be used when a Freedom of

Information Act request is submitted.

The undersigned has familiarized themselves with the conditions affecting the work, the specifications, the

prices provided on the cost proposal, and is legally authorized to make this proposal on behalf of the

company/firm listed above.

Name (Print) _____________________________ Date ______________________

Signature _____________________________ Phone ______________________

Title _____________________________ Fax ______________________

E-Mail Address (for correspondence): __________________________________________________

E-Mail Address (for receiving Purchase Orders): _________________________________________

(Do not place an email address in this space if your company is unable to receive purchase orders

electronically) 114

Page 115: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

AIA®

Document A101TM – 2007

Standard Form of Agreement Between Owner and Contractor

where the basis of payment is a Stipulated Sum

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal

penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:40:50 on

10/15/2009 under Order No.1000391833_1 which expires on 04/12/2010, and is not for resale.

User Notes: (930362960)

1

ADDITIONS AND DELETIONS:

The author of this document

has added information

needed for its completion.

The author may also have

revised the text of the

original AIA standard form.

An Additions and Deletions

Report that notes added

information as well as

revisions to the standard

form text is available from

the author and should be

reviewed.

This document has important

legal consequences.

Consultation with an

attorney is encouraged with

respect to its completion

or modification.

AIA Document A201™–2007,

General Conditions of the

Contract for Construction,

is adopted in this document

by reference. Do not use

with other general

conditions unless this

document is modified.

ELECTRONIC COPYING of any

portion of this AIA® Document

to another electronic file is

prohibited and constitutes a

violation of copyright laws

as set forth in the footer of

this document.

AGREEMENT made as of the « » day of « » in the year « » BETWEEN the Owner: «Washington County Board of Education» «10435 Downsville Pike” Hagerstown, MD 21740 and the Contractor: «» «» «» for the following Project: RFP 2018-12 Unit Price Contract for Asbestos Abatement The Architect/Engineer: «N/A « » « » « » The Owner and Contractor agree as follows. This is a Unit Price contract. Washington County Public Schools’ staff will request contractor(s) as needed to provide a written price quote on a per project basis. The contractor’s price quote shall be based on the unit prices set-forth in this contract. If Washington County Public Schools’ staff accepts the contractor’s price quote for a project, each project shall be summarized and sequentially numbered on the attached template, Exhibit A, entitled Addendum to Contract, and shall be appended to this contract and shall constitute an addendum to this contract.

115

Page 116: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal

penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:40:50 on

10/15/2009 under Order No.1000391833_1 which expires on 04/12/2010, and is not for resale.

User Notes: (930362960)

2

TABLE OF ARTICLES 1 THE CONTRACT DOCUMENTS 2 THE WORK OF THIS CONTRACT 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION 4 CONTRACT SUM 5 PAYMENTS 6 DISPUTE RESOLUTION 7 TERMINATION OR SUSPENSION 8 MISCELLANEOUS PROVISIONS 9 ENUMERATION OF CONTRACT DOCUMENTS 10 INSURANCE AND BONDS ARTICLE 1 THE CONTRACT DOCUMENTS The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9. ARTICLE 2 THE WORK OF THIS CONTRACT The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others. ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be the date of this Agreement unless a different date is stated below or provision is made for the date to be fixed in a notice to proceed issued by the Owner. The initial contract shall be for a period of three (3) years, beginning November 1, 2017 and ending October 31, 2020. WCPS reserves the option to renew this contract for one (1) additional two (2) year period, subject to acceptable performance. Prior to a contract renewal, WCPS and the award firm will communicate regarding performance, pricing, revisions and modifications to this contract. All terms and conditions of the bid will apply to any renewal of this contract. § 3.2 The Contract Time shall be measured from the date of commencement. All work to be performed when School is not in session, or a time frame dictated by the Owner’s Representative when the area will be available for work, i.e. summer/holiday breaks, after school hours, weekends, evenings, and vacation days. § 3.3 The Contractor shall achieve Substantial Completion of the entire Work not later than: The Contractor shall achieve Substantial Completion of the entire Work, as established by mutual consent on a per project/site basis upon acceptance of quote/proposal and execution of a contract addendum. All work to be performed when school is not in session; i.e., summer/holiday breaks, after school hours, weekends and school vacation days.

116

Page 117: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal

penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:40:50 on

10/15/2009 under Order No.1000391833_1 which expires on 04/12/2010, and is not for resale.

User Notes: (930362960)

3

subject to adjustments of this Contract Time as provided in the Contract Documents. «If the work is not completed within the time period specified, and agreed by the parties on a per project/site basis, the contractor will be liable for liquidated damages of $500.00 per calendar day. ARTICLE 4 CONTRACT SUM § 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. The Contract Sum shall be based on the fixed Unit Prices as per the Proposal Sheet for RFP No. 2018-12, subject to additions and deductions as provided in the Contract Documents. As per RFP No. 2018-12, the prices your company has provided are maximum prices allowed during the Contract period. Renewal escalation of the contract prices will be considered if a written request is made within ninety (90) days of the approaching renewal period. Requests must include appropriate documentation to support the rate of increase. Failure to comply may result in denial of the request. Pricing adjustments are NOT automatic; WCPS reserves the right to accept or reject the requested price adjustments. In making this determination, the WCPS Purchasing Supervisor will consider the current market and will not approve increases that exceed market rate indices for labor/overhead/supplies. The Purchasing Supervisor may, at their discretion, elect the rebid the contract rather that incur increases. If a price adjustment is approved, the Award Bidder will be notified in writing by WCPS. The increase will be effective for the renewal period and pricing is then to remain firm for the entire renewal period. § 4.2 The Contract Sum is based upon the following alternates, if any, which are described in the Contract Documents and are hereby accepted by the Owner: «None » § 4.3 Unit prices, if any: (Identify and state the unit price; state quantity limitations, if any, to which the unit price will be applicable.)

Item Price Per Unit ($ 0.00)

§ 4.4 Allowances included in the Contract Sum, if any: (Identify allowance and state exclusions, if any, from the allowance price.)

Item Price None

ARTICLE 5 PAYMENTS § 5.1 PROGRESS PAYMENTS § 5.1.1 Based upon Applications for Payment submitted to the Architect or Owner by the Contractor and Certificates for Payment issued by the Architect or Owner, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents. § 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows: « » § 5.1.3 Provided that an Application for Payment is received by the Architect or Owner not later than the «1st » day of a month, the Owner shall make payment of the certified amount to the Contractor not later than the «15th» day of the «following» month. If an Application for Payment is received by the Architect or Owner after the application date fixed above, payment shall be made by the Owner not later than «Forty-five» («45») days after the Architect or Owner receives and approves the Application for Payment. § 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form and supported

117

Page 118: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal

penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:40:50 on

10/15/2009 under Order No.1000391833_1 which expires on 04/12/2010, and is not for resale.

User Notes: (930362960)

4

by such data to substantiate its accuracy as the Architect or Owner may require. This schedule, unless objected to by the Architect or Owner, shall be used as a basis for reviewing the Contractor’s Applications for Payment. § 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment. § 5.1.6 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:

.1 Take that portion of the Contract Sum properly allocable to completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Contract Sum allocated to that portion of the Work in the schedule of values, less retainage of Five percent» («5.00%»). Amounts for changes in the work shall not be included on an Application for Payment until the Change Order is executed.

.2 Add that portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction (or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing), less retainage of Five percent» «5.00%»). Reference the Washington County Public School’s Supplement Conditions to the AIA Document A201-1997, page 14 of 23, paragraph 9.3.2 for the policy concerning payments for stored materials.

.3 Subtract the aggregate of previous payments made by the Owner; and

.4 Subtract amounts, if any, for which the Architect or Owner has withheld or nullified a Certificate for Payment as provided in Section 9.5 of AIA Document A201–1997.

§ 5.1.7 The progress payment amount determined in accordance with Section 5.1.6 shall be further modified under the following circumstances:

.1 Upon Substantial Completion of the Work, a sum sufficient to increase the total payments to the full amount of the Contract Sum, less such amounts as the Architect or Owner shall determine for incomplete Work, retainage applicable to such work and unsettled claims; and (Section 9.8.5 of AIA Document A201–1997 requires release of applicable retainage upon Substantial Completion of Work with consent of surety, if any.

.2 If final completion of the Work is thereafter materially delayed through no fault of the Contractor, any additional amounts payable shall be in accordance with Section 9.10.3 of AIA Document A201–1997.

§ 5.1.8 Reduction or limitation of retainage, if any, shall be at the sole discretion of the owner. « » § 5.1.9 Except with the Owner’s prior approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site. § 5.2 FINAL PAYMENT § 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Contractor per the Washington County Public School’s Supplement Conditions to the AIA Document A201-1997, paragraph 9.10.

.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work as provided in Section 12.2.2 of AIA Document A201-1997, and to satisfy other requirements, if any, which extend beyond final payment; and

.2 a final Certificate for Payment has been issued by the Architect, or approved by the Owner. § 5.2.2 The Owner’s final payment to the Contractor shall be made no later than 45 days after the issuance of the Architect’s or Owner’s final Certificate for Payment, or as follows: « » ARTICLE 7 TERMINATION OR SUSPENSION § 7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201–1997. § 7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201–1997.

118

Page 119: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal

penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:40:50 on

10/15/2009 under Order No.1000391833_1 which expires on 04/12/2010, and is not for resale.

User Notes: (930362960)

5

ARTICLE 8 MISCELLANEOUS PROVISIONS § 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–1997 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents. « » « » § 8.2 Deleted § 8.3 The Owner’s representative: Mark Mills Director of Maintenance and Operations 301-766-2978 [email protected] § 8.4 The Contractor’s representative: (Name, address and other information)

§ 8.5 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days written notice to the other party. § 8.6 Other provisions: The following provisions may be fully described in the General Conditions of the Contract for Construction and the associated Supplemental Conditions by Washington County Public Schools. ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS § 9.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated in the sections below. § 9.1.1 The Agreement is this executed AIA Document A101–2007, Standard Form of Agreement Between Owner and Contractor. § 9.1.2 The General Conditions are AIA Document A201–1997, General Conditions of the Contract for Construction as presented in the Compact Disc/Project Manual, with modifications. § 9.1.3 The Supplementary and other Conditions of the Contract are those contained in the RFP No. 2018-12. § 9.1.4 The Specifications are those contained in the RFP No. 2018-12 unless modified by the Addenda listed in Section 9.1.5 below: § 9.1.5 The Addenda, if any:

Number Date Pages

ARTICLE 10 INSURANCE AND BONDS The Contractor shall provide bonds as set forth in AIA Document A701-1997 Instructions to Bidders, as amended by Washington County Board of Education and the Washington County Board of Education Supplemental Conditions to the A201-1997 General Conditions of the Contract for Construction Ǥ 10.1 The Contractor shall provide insurance with limits as described within Article 11 of the Washington County Public School Supplement Conditions to the General Conditions of the Contract for Construction AIA Contract A201-1997.

119

Page 120: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal

penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:40:50 on

10/15/2009 under Order No.1000391833_1 which expires on 04/12/2010, and is not for resale.

User Notes: (930362960)

6

§ 10.2 Certificate of Insurance: Prior to proceeding with the work, the contractor agrees to provide a Certificate of Insurance with the application coverage as listed in the Specifications: » List the Certificate Holder and Additional Insured as: Board of Education of Washington County 10435 Downsville Pike Hagerstown, MD 21740 List the Project as: Asbestos Abatement On-Call Services Various Locations This Agreement entered into as of the day and year first written above and is executed in at least three original copies, of which one is to be delivered to the Contractor, one to the Architect for use in the administration of the Contract, and the remainder to the Owner.

OWNER (Signature) CONTRACTOR (Signature)

«Dr. Boyd J. Michael, III Superintendent of Schools»

(Printed name and title) (Printed name and title)

120

Page 121: Unit Price Contract for Asbestos Abatement · 8/22/2017  · WCPS RFP 2018-12 Unit Price Contract for Asbestos Abatement. SECTION I - GENERAL TERMS AND CONDITIONS . 1. Introduction

WASHINGTON COUNTY PUBLIC SCHOOLS RFP 2018-12 ASBESTOS ABATEMENT PROJECT FORM

  

PROJECT NAME:  

 DATE:

 

 SCHOOL/BUILDING:

 

 CONTRACTOR:

 

 

 PROJECT SCOPE: The project work will be performed in accordance with the listed regulations:

Describe what level of containment will be utilized (full containment, criticals only, etc.):  

  

  

Provide detailed description of containment measures to be utilized, including a diagram with proposed construction/location, water requirements, negative air units, etc.        

 Project Designer Name/Accredidation#/State:

 

Description of how project is proposed to be performed (include details on any water, electric shutdown/lockout requirements that may be necessary.   

  

Estimated time frame from commencement of work to completion of project including set-up, abatement, clearance sampling, tear down, etc.  

   FINAL COMPLETION DATE:  

 

 