universal adjustment platform history and overview of uap ... · uap r&d tests summary...
TRANSCRIPT
logo
area
Universal Adjustment Platform
History and overview of UAP ProjectM. Sosin
Outline
2
Issues of position adjustment in accelerator environment
Alignment system requirements
CLIC DBQ support – reminder
Universal Alignment Platform (UAP)
Results:
UAP PHASE1 tests status and main conclusions
Platform components upgrade
UAP PHASE2 tests
UAP Project and documentation introduction
UAP development schedule
Conclusions
HL-LHC residual doses estimation
Typical issues with position adjustment
Crowded neighbourhood of aligned components Difficult access to regulation mechanisms/screws – (circus
skills needed for some of components regulation)
Fragile equipment around workspace – slow an careful
manipulation
Ergonomics of adjustment Mechanisms not always intuitive
Simple mechanisms => big backlash => multiple measurement andadjustment iterationsneeded =>
Long adjustment time
Alignment system requirements
Limit the presence of personnel in high radiation areas:
Easy access from transport zone
Intuitive kinematics of adjustment system
Possibility of position measurements from bigger distances
Option of remote (distance) adjustment using portable motorized
adapters
5 (6) DOF position adjustment preferred
Accuracy, resolution, stiffness – application dependent
Simple robust and cheap solution
A bit of history – CLIC DBQ adjustment platform
2012-2014
A bit of history – CLIC DBQ adjustment platform
Modified Stewart platform configuration
DBQ Support enabled to reduce pre-alignment
time from one day to 20 minutes
New solution design – adjustable platform concept
Stewart platform adaptation – 3 vertical and 2 horizontal supports
Simplified structure – reduced number of parts
Ergonomic – easy access
With DBQ support, time was reduced to 20 minutes
Second possible use → option for the tunnel
fast re-adjustment
The idea:
Motors
Gears
Trans-missions
Position
feedback
Controller
Portable motorised adapter needed
Position and orientation feedback coming from the absolute
tracker
Option of permanent installation (remote
adjustment) Pos. feedback sensors as eg. WPS needed
Motorized adapter functional prototype designed
and preliminarily tested
Mechanical design
Light and compact
Mobility – fast auto-lock
mechanism
Build-in sensors
Control algorithms adopted to
automated and semi-manual use
Feedback tunel measurements (eg. Laser
tracker or position sensors)
Adapter was designed to match the project needs
Mechanical design
Light and compact
Mobility – fast instalation
Build-in sensors
Ergonomic – simple installation and operation
The adjustment time is about one minute
11
Gearbox and
auto - lock
interface
integrated in
small space
To adjust the DBQ, precise position measurement
are used as an input for the algorithm
INVERSE
KINEMATIC
MODEL
Model created in
SimMechanics and
implemented in
LabVIEW code
Relative sensors
target positions
Temporarly installed
displacement sensors
for precise feedback -
> platform backlash
independent
LASER
SENSORS
*K
Feedback
(MEASURED
DISTANCES)
+
-
Adapter
+
Platform
https://www.micro-epsilon.com
Motors
speed Absolute Tracker
measurements
ALIGNMENT
ERROR
Alignment error
calculation based on the
external, precise
measurements from
Absolute Tracker (AT)
Motorized adapter functional prototype designed
and preliminarily tested
Measurement of the difference between desired and
achieved position showed very good performance
Z Y
X
DBQ reference frame-15
-10
-5
0
5
10
15
20
25
Test 1 Test 2 Test 3 Test 4 Test 5 Test 6 Test 7
Linear displacement error[µm] [µrad]
X position Y position
AT measurement error ~10µm for translations
and ~40µrad for X and Y rotations
14
-250
-200
-150
-100
-50
0
50
100
150
200
250
Test 1 Test 2 Test 3 Test 4 Test 5 Test 6 Test 7
Angular displacement error[µrad]
X rotation Y rotation Z rotation
Universal Adjustment PlatformDefinition of set of design rules and development of standardized and modular components to:
increase safety of surveyors
unify small (<2T) accelerator components adjustment systems
15
Universal adjustment platform –
manual operation concept
Universal adjustment solution – concept of use plug-in motors:a) Platform measurement from distance using a laser tracker;b) Installation of plug-in motors in less than one minute;c) Remote adjustment from distance.
Universal adjustment solution - permanent motors version concept. Platform equipped with WPS sensors
Allows for various operation use cases
Universal Adjustment Platform
Universal Adjustment Platform
Y
ROLL
YAW
PITCH
spherical joint
spherical joint
Joints link (length dependant on platform dimensions)
- longitudinal adjustment jig, constant length->5DOF (Z blocked), variable length->6DOF (impact on Z),
X,Y, Roll, Pitch, Yaw - permitted
- vertical adjustment jig, variable length, the main impact on: Y, Pith, Roll
- radial adjustment jig, variable length, the main impact on: X, Yaw
Standardized equipment
Vertical adjustment jig
Radial adjustment jig
Joints
UAP R&D tests summary Preliminary radiation tests of prototype jigs – 8.2018 – 6.2010
Small UAP functional prototype preliminary tests 10.2018 – 1.2019
(PHASE1):
Verification of jigs and different joints types parameters
Measurements of platform directional stiffness and backlash
Behaviour of platform under different load
Check of the adjustment torques
Adjustment stability
Ergonomics tests
Impact of vacuum longitudinal force
Small UAP tests after joints upgrade - April 2019 (PHASE2):
Same set of tests as for PHASE1
Manual UAP
Small UAP jigs, joints design Jigs (vertical, radial) first batch assembled in 9.2019
LHCGUPS_0001 (radial), LHCGUPS_0007 (vertical)
Spherical joints – Inox-Bronze rotules from Michaud-
Chailly catalogue
Small UAP jigs radiation tests Preliminary 3MGy radiation tests in Fraunhofer Institute 8-10.2018
Report: EDMS 2138404
No operational issues observed, no grease problems (Molykote
BR2 plus)
UAP tests – PHASE 1
21
Small platform functional prototype preliminary tests
performed 10.2018 – 1.2019:
Verification of actuators and different joints types parameters
Measurements of platform directional stiffness and backlash
Behaviour of platform under different load
Check of the adjustment torques
T. Błaszczyk, K. Widuch
22
Small platform functional prototype preliminary tests performed 10.2018 – 1.2019:
Verification of overall platform operation, adjustment
ergonomics and resolution
UAP tests – PHASE 1
T. Błaszczyk, K. Widuch
23
Small platform functional prototype preliminary tests performed 10.2018 – 1.2019:
Stability test after lateral various force
Vacuum – longitudinal force load
UAP tests – PHASE 1
T. Błaszczyk, R. Pedersen
24
Batch of actuator prototypes irradiated in Fraunhofer institute (3MGy step done,
10MGy test ongoing) – no issues detected
Jigs adjustment resolution at µm level
Jigs works well, however small design tuning needed to decrease backlash – to be
solved in next jigs series. Discussion on commercialization of jigs production started
with POWERJACKS
Platform adjustment accuracy typically below +/- 50 µm for 2 iterations approach
(impact of backlash, pre-loading improves situation)
Adjustment ergonomics OK (15 .. 20 minutes adjustment time for big platform
misalignments), gear ratio of vertical jigs to be smaller to decrease resolution
Issues with top plate stiffness and joints backlash detected
– upgrades necessary
Michaud-Chailly joints backlash 20 .. 40 µm
20 mm thick Top plate deforming to much at big lateral load (vacuum test)
Flexible joints (Nitinol, flex-rope) considered as perspective,
however too big resources needed for validation
UAP tests – PHASE 1 -
conclusions
UAP prototype changes after PHASE 1
25
Upgrade of joints design
Upgrade of TOP plate thickness/stiffness (previous one deformed with - vacuum test - lateral forces)
Upgrade of joints assembly plates
Vertical jigs backlash adjusted using
shimming rings
PHASE 2 test 15 – 30 April 2019
UAP zero-backlash joints
26
Zero backlash, self lubricating (sintered bronze SELFOIL) based joints
UAP tests – PHASE 2
27
Tests of Small platform functional prototype with zero-backlash
joints and updated Top plate structure (15.04.2019 –
30.04.2019):
Verification of actuators and different joints types parameters
Measurements of platform directional stiffness and backlash
Behaviour of platform under different load
Check of the adjustment torques
UAP tests – PHASE 2
28
Verification of platform stiffness, operational aspects (adjustment ergonomics, resolution,
accuracy)
T. Błaszczyk, K. Widuch
UAP tests – PHASE 2
29
Stability test
Vacuum – longitudinal force load
T. Błaszczyk, K. Widuch
30
Platform adjustment accuracy below +/- 20 µm for 2 iteration approach
Stability of platform after random lateral load: +/- 30 µm
Ergonomics OK (~15 minutes adjustment time)
Longitudinal (vacuum) force test showed deflections of 2.5 mm at the
height of the Beam tube, what exceeds the requirement +/-0.5mm, given by
vacuum team – temporary fastening mechanism can be added to solve this
issue
Lateral stiffness of platform increased 3x (4.1 µm /kg to 1.3 µm/kg)
Platform behaviour assessed as satisfactory
UAP tests – PHASE 2 - conclusions
UAP Project
31
Objectives:
Propose standardized methods and technical solutions to unify of small (<2T) accelerator
components adjustment systems integration
To involve all potential UAP users to elaborate „in loop” the final versions of standardized
adjustment components and design procedures
UAP Project technical meetings
Agreement on final form of UAP by all stakeholders
Involve potential users in tests and validation of UAP
EDMS 2112762
CONCEPTUAL SPECIFICATIONUNIVERSAL ADJUSTMENT PLATFORM (UAP)
AND DESIGN METHODOLOGY
EDMS 2112762
TECHNICAL NOTEUNIVERSAL ADJUSTMENT PLATFORM (UAP)
Small UAP DESIGN GUIDELINES FOR
ENGINEERS (Version 1)
Revision 0
EDMS 2113940
ENGINEERING SPECIFICATIONSTANDARDIZED JOINTS AND ACTUATORS
FOR SMALL UAPRevision 0 (FIRST PROTOTYPE)
EDMS 2143881
ENGINEERING REPORTSMALL UAP ACTUATORS AND JOINTS
PRELIMINARY PROTOTYPES(Report summarizing design, design
approach and solutions introduced in preliminary prototypes of standardized
joints and actuators, targeted to be used in SMALL UAP preliminary prototype)
UAP Project - baseline documentation
32
Drafts of UAP specifications, engineering notes created for future
user consultations purposes
UAP Project - baseline documentation
33
i.e. UAP DESIGN GUIDELINES (EDMS 2112762) – manual for the engineers how to design the UAP
adopted for user equipment
Step 1: Adapt platform dimensions to supported component dimensions
Step 2: Arrange jigs pattern within Bottom plate volume (top); Step 3: Adjust thickness of the plate and position of radial jigs (bottom)
Step 4: Prepare the space for the UAP functional sub-components
Step 5: Prepare the Top plate initial model and adjust the joints length Step 6: Prepare the Top plate initial
model and adjust the joints length
Step 7: Integrate all user specific features and vertical jig assembly plates
Small UAP prototype document „folder”
34
EDMS 2112762
CONCEPTUAL SPECIFICATIONUNIVERSAL ADJUSTMENT PLATFORM (UAP)
AND DESIGN METHODOLOGY
EDMS 2112762
TECHNICAL NOTEUNIVERSAL ADJUSTMENT PLATFORM (UAP)
Small UAP DESIGN GUIDELINES FOR
ENGINEERS (Version 1)
Revision 0
EDMS 2113940
ENGINEERING SPECIFICATIONSTANDARDIZED JOINTS AND ACTUATORS
FOR SMALL UAPRevision 0 (FIRST PROTOTYPE)
EDMS 2143976
ENGINEERING REPORTSMALL UAP PRELININARY PROTOTYPE
(Report summarizing design of preliminary prototype of small Universal Adjustment
Platform. The small UAP prototype will be used for initial tests of platform
performance, to estabilish final solutions for SMALL and BIG UAPs designs)
EDMS 2143881
ENGINEERING REPORTSMALL UAP ACTUATORS AND JOINTS
PRELIMINARY PROTOTYPES(Report summarizing design, design
approach and solutions introduced in preliminary prototypes of standardized
joints and actuators, targeted to be used in SMALL UAP preliminary prototype)
EDMS 2112762
TEST NOTESMALL UAP PRELIMINARY PROTOTYPE
(SUPP) - TESTS PHASE 1 OVERVIEW
EDMS 2138404
TEST REPORTSMALL UAP ACTUATORS PRELIMINARY
PROTOTYPES – RADIATION TEST REPORT
EDMS 2138361
TEST REPORTSUPP - ACTUATORS AND JOINTS
BACKLASH (PHASE 1)
EDMS 2144482
TEST REPORTSUPP – DIRECTIONAL STIFFNESS OF
PLATFORM (PHASE 1)
EDMS 2144483
TEST REPORTSUPP – STABILITY TEST AFTER
ADJUSTMENT (PHASE 1)
EDMS 2144484
TEST REPORTSUPP – ALIGNMENT ERGONOMICS
OF PLATFORM (PHASE 1)
EDMS 2112762
ENGINEERING REPORTSMALL UAP PRELININARY PROTOTYPE
UPGRADES AFTER TESTS PHASE 1
EDMS ...
TEST REPORTSUPP – DIRECTIONAL STIFFNESS OF
PLATFORM (PHASE 2)
EDMS ...
TEST REPORTSUPP – STABILITY TEST AFTER
ADJUSTMENT (PHASE 2)
EDMS ...
TEST REPORT ???SUPP – ALIGNMENT ERGONOMICS
OF PLATFORM (PHASE 2)
EDMS ...
TEST REPORTSUPP - ACTUATORS AND JOINTS
BACKLASH (PHASE 2)
EDMS ...
TEST REPORTSMALL UAP PRELIMINARY PROTOTYPE
(SUPP) - TESTS PHASE 2 SUMMARY
EDMS ...
TECHNICAL NOTEDESIGN METHODOLOGY OF UNIVERSAL
ADJUSTMENT PLATFORM (UAP) REVISION 1
EDMS ...
ENGINEERING SPECIFICATIONSTANDARDIZED JOINTS AND ACTUATORS
FOR SMALL UAPREVISION 1
IN PREPARATION/VALIDATION AVAILABLENOT READY
UAP PROJECT BASELINE DOCUMENT
ENGINEERING/TEST REPORT
UAP Collaboration workspace
35
https://espace.cern.ch/universal-alignment-platform/
Collaboration workspace created to group important information about the project:
Current status of R&D and tests
Links to important documents and tests
UAP Meetings schedule