University of Minho
David SilvaAnabela TeresoGabriela FernandesIsabel Loureiro
AmbithusJosé Ângelo Pinto
![Page 2: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/2.jpg)
Maturity
WorldCist’15
Figure 1: Increasing maturity.M
atu
rity
2
![Page 3: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/3.jpg)
OPM3®
Figure 2: OPM3® third edition.
WorldCist’153
![Page 4: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/4.jpg)
OPM3®
Figure 3: OPM3® Domains.
• Domains
WorldCist’154
![Page 5: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/5.jpg)
• OPM3® Best Practices
OPM3®
Standardize Measure Control Improve
Organizational
Enablers
WorldCist’155
![Page 6: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/6.jpg)
Figure 4: Relations between Best Practices, Capabilities and Outcomes.
OPM3®• OPM3® Construct
WorldCist’156
![Page 7: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/7.jpg)
Figure 5: OPM3® Construct (Example).
OPM3®Best Practice:2630 Improve
Develop Project Charter Process
Capability:Conduct Develop Project Charter
Process Root Cause Analysis
Capability:Implement
Improvements to the Develop Project
Charter Process
Capability:Sustain Develop Project Charter
Process Improvement
Outcome: Develop Project Charter Process
Root Causes Identified
Outcome: Develop Project Charter Process Improvements Implemented
Outcome:Sustainable
Develop Project Charter Process Improvement
WorldCist’157
![Page 8: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/8.jpg)
OPM3® Portugal Project
- Started in 2011 and closed in December 2014;
- Financed by European Union research founding;
- Designed and led by Ambithus;
- Partners of the scientific and technological system,
including Portuguese Universities;
- Intended to carry out an analysis of the sectorial
results.
WorldCist’158
![Page 9: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/9.jpg)
1. Prepare for Assessment;
Figure 6: OPM3® Cycle.
OPM3® Portugal Project• How is OPM3® applied in organizations?
2. Perform Assessment;
3. Plan for Improvements;
4. Implement Improvements;
5. Repeat the Process.
WorldCist’159
![Page 10: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/10.jpg)
- Assessment of the current state of project, program
and portfolio management of the organization;
- Construction and validation of organizational
improvement plans that may be adopted by
organizations;
- Sectorial results will be used as a benchmark.
OPM3® Portugal Project• Benefits for Organizations
WorldCist’1510
![Page 11: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/11.jpg)
Results Analysis
- 18 IST organizations results are the focus of the
paper;
- Organizations distributed throughout the
country;
- 45% Medium, 33% Small, 22% Large.
WorldCist’1511
![Page 12: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/12.jpg)
WorldCist’1512
![Page 13: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/13.jpg)
WorldCist’1513
![Page 14: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/14.jpg)
WorldCist’1514
![Page 15: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/15.jpg)
WorldCist’1515
![Page 16: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/16.jpg)
WorldCist’1516
![Page 17: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/17.jpg)
WorldCist’1517
![Page 18: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/18.jpg)
WorldCist’15
Project Management Processes Large Medium Small
Create Work Breakdown Structure
Large +
Medium +
Small - -
Develop Schedule
Large +
Medium +
Small - -
Direct and Manage Project Execution
Large + +
Medium -
Small -
Perform Integrated Change Control
Large + +
Medium -
Small -
Control Schedule
Large +
Medium +
Small - -
Control Costs
Large +
Medium +
Small - -
Report Performance
Large + +
Medium - +
Small - -
Portfolio Management Processes Large Medium Small
Categorize Components
Large + +
Medium -
Small -
Communicate Portfolio Adjustment
Large + +
Medium -
Small -
Organizational Enablers Areas Large Medium Small
Organizational Project Management Policy &
Vision
Large +
Medium
Small -
Strategic Alignment
Large +
Medium
Small -
Organizational Structures
Large +
Medium +
Small - -
Competency Management
Large +
Medium
Small -
Organizational Project Management
Methodology
Large +
Medium
Small -
18
![Page 19: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/19.jpg)
Conclusions
- Large IST organizations stand out from Medium and Small
organizations, since they globally presented the best results.
- Large IST organizations present positive differences for
Small organizations in 7 PM and 2 Portfolio Management
processes, and 5 OE areas;
- Large IST organizations present positive differences for
Medium organizations in 3 PM and 2 Portfolio Management
processes.WorldCist’1519
![Page 20: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/20.jpg)
Future Work
- Use a larger sample, to create a model that would
simplify the selection of priority PM practices to be
implemented by the different types of organization,
serving as a benchmarking tool.
WorldCist’1520
![Page 21: University of Minho David Silva Anabela Tereso Gabriela ...pessoais.dps.uminho.pt/anabelat/objectos/WorldCist... · •OPM3® Best Practices OPM3® Standardize Measure Control Improve](https://reader033.vdocuments.net/reader033/viewer/2022041802/5e522d0d2abb6f75ab56e141/html5/thumbnails/21.jpg)