university of toronto mississauga campus capital projects university of toronto mississauga campus:...

13
University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

Upload: ellen-meghan-palmer

Post on 12-Jan-2016

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

Page 2: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

Substantial completion is scheduled for April 15, 2011.

Move in is scheduled for July 1st – July 15th, 2011

Page 3: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

* 30kW bifacial photovoltaic solar panels system functional in the process of commissioning.

Page 4: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

Interior finishes: •Drywall is almost complete and painted. •Resilient flooring and carpeting is almost complete. •Ceramic tiling of the washrooms is complete. •Terrazzo work on the ground floor is ongoing. •Installation of T-bar ceiling tiles and fixtures is ongoing. •The contractor is currently working on the feature stair glazing, balustrades, vestibules, and doors.

Page 5: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

Feature staircase

Page 6: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

Building interior furnishings, Audio Visual and lighting installation is 95% complete

Page 7: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

500, 350, 150, 100, lecture theaters complete with fixed seating and acoustical paneling in place

Page 8: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

•Envelope: Glazing and stainless steel fins are installed.

•Installation of stainless steel V panels is almost complete on the 2nd floor and progressing on the other floors.

•The glazing of the bridge is yet to be installed.

Page 9: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

Page 10: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

Lab benches are installed.

Page 11: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

Termination and tie-in activities are ongoing. Millwork installation is ongoing.

Page 12: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

Lecture theatres are installed.

Page 13: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,

University of Toronto Mississauga CampusCapital Projects

University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011

M&E equipment start-up, verification and balancing are ongoing. Weekly meetings with consultants and contractors to ensure timely and successful commissioning process.