university of toronto mississauga campus capital projects university of toronto mississauga campus:...
TRANSCRIPT
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Substantial completion is scheduled for April 15, 2011.
Move in is scheduled for July 1st – July 15th, 2011
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
* 30kW bifacial photovoltaic solar panels system functional in the process of commissioning.
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Interior finishes: •Drywall is almost complete and painted. •Resilient flooring and carpeting is almost complete. •Ceramic tiling of the washrooms is complete. •Terrazzo work on the ground floor is ongoing. •Installation of T-bar ceiling tiles and fixtures is ongoing. •The contractor is currently working on the feature stair glazing, balustrades, vestibules, and doors.
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Feature staircase
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Building interior furnishings, Audio Visual and lighting installation is 95% complete
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
500, 350, 150, 100, lecture theaters complete with fixed seating and acoustical paneling in place
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
•Envelope: Glazing and stainless steel fins are installed.
•Installation of stainless steel V panels is almost complete on the 2nd floor and progressing on the other floors.
•The glazing of the bridge is yet to be installed.
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Lab benches are installed.
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Termination and tie-in activities are ongoing. Millwork installation is ongoing.
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Lecture theatres are installed.
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
M&E equipment start-up, verification and balancing are ongoing. Weekly meetings with consultants and contractors to ensure timely and successful commissioning process.