update on alignment kit and stave 250 frame and thoughts for stave 130 m.gibson (ral) 7/6/13
DESCRIPTION
Update on Alignment kit and Stave 250 frame and thoughts for Stave 130 M.Gibson (RAL) 7/6/13. Status of infrastructure for stave 250 module mounting and testing. Stave 130 ‘stuff’. Stave 250 Module Mounting. - PowerPoint PPT PresentationTRANSCRIPT
Update on Alignment kit and Stave 250 frame
and thoughts for Stave 130
M.Gibson (RAL)7/6/13
1
• Status of infrastructure for stave 250 module mounting and testing.
• Stave 130 ‘stuff’
Stave 250 Module Mounting• Now have 3 modified jigs, with 2 assembled onto the bridges using the pre-loaded bearing principle.
• Ivan has started looking at the problem or array handling given the data from Tim, and using Peters drawing.
• A set of data for manual positioning has been created.
• Stave expected 5th June (wed) with the stave frame expected on the 12th . (Wed).
• I am assuming no Kapton between modules ‘cos I havn’t made any or modified the glue pattern.
• Mike is away until June 10th (Monday) at earliest. Need him to bend the linking pipes stave to frame and Ian, Richard, or John to weld the ends on.
• Plenty to do 5th to 12th as we will have to measure the kapton to see if its like the drawing and form a plan. So 19th (Wed) or 20th June we might be in a position to stick a module.
2
250 series jigs showing pre load springs
3
Stave 250 testing infrastructure
• Installation of the CO2 system is progressing. Bunds are installed, along with N2 (for flushing of the test volume).
• The SS pipe installation is progressing slowly because we have lost Mike so I am doing it!
• A design for all the necessary interlocks now exists. Needs converting to a real circuit and the items ordering.
• Automatic fume extraction fan, trunking, and hole in window all exist, just needs fitting.
• I have the CO2 solenoid on my desk and the connectors arrived 30/5/13.
• CO2 detection system is on order and due anytime now.
• Still not done anything about measuring the liquid level of CO2 in the bottles. But ultrasonics looks like the way forwards.
4
Status of CO2 Installation
5
bunds
Stave 130 jigs(now have a model)
6
Thin top plate
Thick bottom plate that the ceramic ball run in
Spring loaded plungers to preload the balls
Springs to provide vertical force for the two part jigs
Cut-out for the Dc/Dc converters
Bump for the new transfer system