update on fms repair stephen trentalange star management meeting october 31, 2014 1
TRANSCRIPT
![Page 1: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1](https://reader036.vdocuments.net/reader036/viewer/2022062516/56649dba5503460f94aab9ae/html5/thumbnails/1.jpg)
1
Update on FMS Repair
Stephen TrentalangeSTAR Management Meeting
October 31, 2014
![Page 2: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1](https://reader036.vdocuments.net/reader036/viewer/2022062516/56649dba5503460f94aab9ae/html5/thumbnails/2.jpg)
FMS Repair Work Summary• Restacking work nearly completed– Small Cells: 100% complete (476/476)– Large Cells: 95% complete (748/788)– External cabling 100% complete
• Running with DAQ: LED/Jet Patch trigger to diagnose problems with HV and signals
• Cable mapping so far is correct for HV/signals• Large cells: various problems ~24/572 channels• Small cells: HV problem: +6V power supply;
working with the electronics techs to diagnose.
![Page 3: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1](https://reader036.vdocuments.net/reader036/viewer/2022062516/56649dba5503460f94aab9ae/html5/thumbnails/3.jpg)
Previous Problems:Updated• 216 Large Cells Left to complete– 34 old FMS Cells (216-34=182)– 90 from PSU by Nov 2 (182-90=92)– 12 bases available (92-12=80 still at PSU)
• Need 5 magnetic shields• Cabling/Stacking 1 week work• Noticed cracking in single small
cell/north side: seems stable
![Page 4: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1](https://reader036.vdocuments.net/reader036/viewer/2022062516/56649dba5503460f94aab9ae/html5/thumbnails/4.jpg)
4
Cosmic Rays Observed
![Page 5: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1](https://reader036.vdocuments.net/reader036/viewer/2022062516/56649dba5503460f94aab9ae/html5/thumbnails/5.jpg)
5
LED Signal
LED IssuesNo Signal
Yale Bases
Russian Bases
![Page 6: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1](https://reader036.vdocuments.net/reader036/viewer/2022062516/56649dba5503460f94aab9ae/html5/thumbnails/6.jpg)
6
Conclusions• Training of 2 extra on site experts in operation/ hardware for
FMS: Sam Heppelman/Grant Webb• Schedule for repair work on bases at PSU is tight, but a stream
of bases is arriving at BNL. Installation is not difficult.• Repair work on individual channels remains before run.• November-January Tasks:
– Repair work on individual channels– Small cell HV (+6V supply)– Spares for HV/LED control machines in hall– Spares for CW low voltage power supplies
• Work on “runaway trigger” problem with Jack/Chris/Eleanor
![Page 7: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1](https://reader036.vdocuments.net/reader036/viewer/2022062516/56649dba5503460f94aab9ae/html5/thumbnails/7.jpg)
7
![Page 8: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1](https://reader036.vdocuments.net/reader036/viewer/2022062516/56649dba5503460f94aab9ae/html5/thumbnails/8.jpg)
8
Stacking the FMS
The South Side is Fully Stacked
The North Side is 90% Stacked
Need the remaining 150 PMT bases from PSU.
Survey of FMS location completed
![Page 9: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1](https://reader036.vdocuments.net/reader036/viewer/2022062516/56649dba5503460f94aab9ae/html5/thumbnails/9.jpg)
9
The Forward Meson Spectrometer1264 Pb-glass cells
788 large cells 476 small cells