update on iogp 423 revision - iagcweb.iagc.org/external/wcpages/wcmedia/documents/6_update on...
TRANSCRIPT
IOGP 423 revision update
IAGC / IOGP Joint HSE & Security ForumHouston, 19th April, 2016
Status of IOGP 423 Version 3.0
• Currently with IOGP secretariat for final review and edits
• Will go to IOGP Safety Committee around end of April. Three week period for review.
• Published pdf should be available sometime in July
Developing a Communications Plan
• Decision made by IOGP to develop a communications plan for roll out of Version 3.0
• E-Poster at SPE HSE International Conference in Stavanger (slides to follow describing highlights)
• Written paper will be published in one of the Energy Institute’s magazines (will reach outside just oil and gas)
• Press release being developed and will be circulated to industry journals when document finally published
• Other publication opportunities being developed
Driving efficiencies in oil & gas through a risk based and systematic approach to contractor
HSE managementIOGP 423 (Version 3.0)
John Blackhall, BP; Lisette Iversen, Statoil; Ian Threadgold, SPE, Threadgold Safety Management; Piet Van Dam, Shell & Scott Bergeron, Kosmos Energy
Content of talk
Slide 5
Driving efficiencies in ‘Oil & Gas’ through a risk based and systematic approach to contractor HSE management • Ian Threadgold
• Background
• Changes
• Supplemental tools
• Benefits
• Acknowledgements
Background
• HSE management - guidelines for working together in a contract environment (IOGP Report 423, June 2010)
• First issued in September 1999 (Report 6.64/291)
• An eight phase contracting process:
Phase 1 - Planning Phase 2 - Sourcing / Capability assessment Phase 3 - Tender and award Phase 4 - Pre-mobilization Phase 5 - Mobilization Phase 6 - Execution Phase 7 - De-mobilization Phase 8 - Evaluation and close-out
Slide 6
Driving efficiencies in ‘Oil & Gas’ through a risk based and systematic approach to contractor HSE management • Ian Threadgold
Client Contractor
Scope of work / context & risk assessment
Capability assessment
Contracting mode
Create tender list
3 - Tender and awardBid documentation
preparation & development of evaluation criteria
Contractor submits bid, including draft key HSE
documentation
Award contractHSE Plan including remedial
actions as agreed
4 - Pre-mobilisation
Development of monitoring plan (modes 1 & 2)
Preparation & selection of subcontractors
5 - Mobilisation
HSE field review or audit Mobilisation including subcontractors
6 - Execution
Deliver monitoring plan (modes 1 & 2) & performance
reporting
Deliver HSE including verification plan &
performance reporting
Monitoring, audits and reporting on subcontractors
activities
7 - De-mobilisation
Acceptance of work and restored site
De-mobilisation, including subcontractors
8 - Final evaluation & close-out
Final evaluation and close-out report
Final evaluation and close-out report
DATA BASE of Suppliers
Review
Joint responsibility for for continuous improvement
Communication of HSE plan - commence orientation & site-specific training
Establish HSE evaluation criteria and capability assessment protocol
Contractors responds to HSE capability assessment
questionnaire and if requested HSE audits
Ensures subcontractors aligned with HSE
requirements
Phases of the contracting process
Post award planning, including completion of HSE plan including verification plan and bridging documentation if applicable
Joint Client / Contractor activities
Review of de-mobilisation aspects of HSE plan / Reassess de-mobilisation risks
DATA BASE of Suppliers Historical record Prior registration New contractors
Bid documents evaluation and clarification
1 - Planning
2 - Sourcing / capability assessment
Changes to IOGP 423
Slide 7
Driving efficiencies in ‘Oil & Gas’ through a risk based and systematic approach to contractor HSE management • Ian Threadgold
Changes include alignment to IOGP 510 & 511 - Operating Management System Four key Fundamentals Ten Elements Integrating risk management (Health, Safety, Security,
Environment & Social Responsibility, represented by “HSE”)
Other changes – more emphasis on . . .
• Risk based aspects of the contracting process throughout all 8 phases
• Defining assurance mechanisms or risk mitigating actions for each phase
• Contractor verifying that risk controls and barriers are being effectively managed, along with monitoring by the client
Slide 8
Driving efficiencies in ‘Oil & Gas’ through a risk based and systematic approach to contractor HSE management • Ian Threadgold
A B C D E
People Assets Environment Reputation Never heard of in the industry
Heard of in the industry
Incident has occurred in
similar operations
Happens several times a year in similar
operations
Happens several times a month in similar
operations
0No health
effect/injury/illness
No damage No effect No impact
1Slight health effect/injury/
ilnessSlight damage Slight effect Slight impact
2Minor health effect/injury/
ilnessMinor damage Minor effect Limited impact
3Major health effect/injury/
illnessLocal damage Local effect
Considerable impact
4 Single fatality Major damage Major effect National impact
5 Multiple fatalitiesExtensive damage Massive effect
International impact
No action requiredControl at workplace level and manage for continuous improvementRequires constant management attention and incorporation of risk reduction measuresVery substantial risk reduction measures and seriously consider alternatives
MEDIUMHIGH
Consequence Increasing Probability
Risk classification and management responseINSIGNIFICANT
LOW
Sev
erity
More emphasis on . . . continued
• Client and contractor working together in a collaborative way
• Contractor using the same process for managing subcontractors
• HSE responsibilities for key client and contractor roles
• Address management system gaps through interfacing and bridging
Slide 9
Driving efficiencies in ‘Oil & Gas’ through a risk based and systematic approach to contractor HSE management • Ian Threadgold
Supplemental reports/tools
• IOGP 423-01; Contractor HSE capability assessment & scoring system;
• IOGP 423-02; HSE plan guidance and checklist;
• IOGP 423-03; HSE bridging document guidance and template.
Slide 10
Driving efficiencies in ‘Oil & Gas’ through a risk based and systematic approach to contractor HSE management • Ian Threadgold
Benefits to using . . .
• Consistent and standardized approach to HSE management in a contract environment includes:• HSE ‘risk’ focus;• assurance mechanisms or risk mitigating actions all through the contract life
cycle;• systematic verification and monitoring of barrier / control effectiveness;• clients and contractors working in a more aligned manner.
• This aligned, standardised and systematic approach should result in:• the reduction of HSE related incidents;• greater retained value in the oil and gas industry;• less incurred costs for clients and contractors.
Slide 11
Driving efficiencies in ‘Oil & Gas’ through a risk based and systematic approach to contractor HSE management • Ian Threadgold
Acknowledgements
The IOGP Safety Committee is acknowledged for sponsoring development of this important industry guidance document revision.
The IOGP 423 Revision Task Force members are acknowledged for all their time and efforts that resulted in this revision, as well as the
companies who provided them the time to participate.
Slide 12
Thank You / Questions
Slide 13
For more information please contact:
www.iogp.org
Registered OfficeLevel 5209-215 Blackfriars RdLondon SE1 8NLUnited KingdomT +44 (0)20 3763 9700F +44 (0)20 3763 [email protected]
Brussels OfficeBd du Souverain,1654th FloorB-1160 BrusselsBelgiumT +32 (0)2 566 9150F +32 (0)2 566 9159