update to city council: facilities planning and 30% iipl d ... · 12/13/2010  · final report(1)...

27
December 13, 2010 Update to City Council: December 13, 2010 Facilities Planning and 30% P li i D i U d t f Preliminary Design Update for Post Point WWTP Improvements Freeman Anthony, City of Bellingham Public Works Brian Matson Carollo Engineers Brian Matson, Carollo Engineers Please contact Freeman Anthony ([email protected]) or Brian Matson ([email protected]) for more information.

Upload: others

Post on 03-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

December 13, 2010

Update to City Council:December 13, 2010

Facilities Planning and 30% P li i D i U d t fPreliminary Design Update for

Post Point WWTP Improvements

Freeman Anthony, City of Bellingham Public WorksBrian Matson Carollo EngineersBrian Matson, Carollo Engineers

Please contact Freeman Anthony ([email protected]) or Brian Matson ([email protected]) for more information.

Page 2: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Briefing Document TopicsBriefing Document TopicsDiscussed During August 16 Update

1. Basis of Design Flows and Loads

2. Technical Elements2. Technical Elements

3. Site Layout for Recommended Alternative

P bli P F db k4. Public Process Feedback

5. Environmental Requirements

6. Project Cost and Phasing Options

7 Project Schedule and Next Steps7. Project Schedule and Next Steps

Page 3: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Post Point WWTP LayoutAs of August 2010As of August 2010

AA

B&CD

B&C

EE

C

Page 4: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Overall Project SummaryOverall Project SummaryAs of August 2010

Phasing Option

Max MonthBOD Capacity

(lb/d)

Estimated Project Cost

EstimatedCapacity Period

(years)

Current 25,530 (1) -- --

Minimum Phase 1 27,500 $34M 0 to 3

Intermediate Phase 1 33,000 $47M 9 to 16

Design 39,800 $55M 20+

(1) Does not provide reliability under maximum month conditions

Page 5: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Facilities Planning Report &30% Design StatusDecember 13 Council Update

1. Update BOD sampling and impact on project phasing

2. Present layout of proposed Post Point WWTP Improvements

3. Update Cost and Phasing Plan

4 Project Schedule and Next Steps4. Project Schedule and Next Steps

Page 6: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Update on BOD Sampling

1. Comp Sewer Plan estimated 15-20% of BOD f i d t i l di h

Update on BOD Sampling

BOD from industrial dischargersa. Significant Industrial Users (SIUs) are largest

fraction of industrial BODfraction of industrial BOD

2. 4 months of sampling conducted in 2010a 2 large SIU complexes sampled in spring and a. 2 large SIU complexes sampled in spring and

summer monthsb. Variable BOD load and solubilityyc. Squalicum complex is largest BOD sourced. Squalicum BOD averages 10-15% of BODe. Sampling results support initial BOD

estimates in Comp Sewer Plan

Page 7: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

BOD Load ReductionBOD Load ReductionConclusions and Next Steps

1. SIU reduction and conservation may decrease 20-year BOD load by up to 17%a. Extends capacity provided by initial phase

by up to seven years

Cit E l d SIU ti 2. City, Ecology, and SIUs are supporting efforts to reduce BOD discharges

dd l l d3. Additional sampling and monitoring in 2011 will document progress

Page 8: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Proposed WWTP LayoutCEPT BuildingFlow

Splitter Box

Selector/ AS Basin No. 1

Secondary Clarifier Blo eClarifier

AS Basin No. 2 & 3Modifications

BlowerBuilding

AS Basin No. 4(future)

PEPSModifications

Page 9: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

30% Design Site Rendering

View looking Northwest

Page 10: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Chemically Enhanced P i T t t Primary Treatment

(CEPT)

Chemical Room

View looking Southeast

Polymer System

Page 11: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Selector / Activated Sludge

Basin 1

View looking Southeast, Blower Building in background

Page 12: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

E i ti t t Existing structures with Activated Sludge

Basin 4 (future)

Activated Sludge Basin 4 looking Southwest

Basin 4 (future)

looking Southwest

Modified Primary Effluent Pump Station (PEPS) & Activated Sludge Basins

Page 13: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Blower

View looking Southwest

Building

High-speed turbo blowers

Page 14: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Secondary Secondary Clarifier

View looking Northeast

Page 15: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Environmentally Sensitive Areas

BellinghamBay Wildlife Habitat

WetlandsWetlands

Public AccessOpen SpaceInterpretive Trail

NeighborhoodNeighborhoodImpacts

Page 16: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Site Requirements to Address Sensiti e A eas

1. To the extent possible, maintain open

Sensitive Areas

1. To the extent possible, maintain open space and landscaping south of existing facilities

2. Continue to control odors in existing and new facilities

3. Maintain site lines and aesthetics of current facilities

4. Maintain trail access to extent possible

5 Minimize impacts to environmentally 5. Minimize impacts to environmentally sensitive areas

Page 17: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Environmental Documentation

1. State Environmental Policy Act (SEPA) document required for Facilities Planning Report

2. Other City permits prepared during planninga. Critical Areas Ordinance (CAO) exemption

b. Shoreline permit

3. Permits prepared prior to construction4. Joint Aquatic Resources Permits Application (JARPA)

• Section 401• Section 404 or Section 10• Hydraulic Project Approval

5. Section 106 – historic preservation6. Section 7 – endangered species act6. Section 7 endangered species act7. City Demolition/Building Permit8. NPDES Construction Stormwater General Permit

Page 18: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Wetlands and Wildlife Mitigation

1. Plan developed based on recommendations from

gPlan Components1. Plan developed based on recommendations from

wildlife biologists/ecologists and WDFW.

2. Opportunity to create enhanced wetlands for mitigation

3. Opportunity to mitigate wildlife impacts throughthrough…a. Wetlands creationb Habitat enhancement with native plantingsb. Habitat enhancement with native plantingsc. Restricting construction during critical periodsd. Minimizing public disturbanced. Minimizing public disturbance

4. Must balance desire for public (trail) access with wildlife mitigation

Page 19: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Updated Cost EstimateF iliti Pl i R t d 30% D iFacilities Planning Report and 30% Design

Phase 1 Component Preliminary Estimate(in millions)( o s)

CEPT $2.7

PEPS Modifications $3.6

Selector/AS Basin 1 $8.0

AS Basins 2 & 3 Modifications $2.4

Blower Building $8.9

Secondary Clarifier $5.7

Sit k $4 7Sitework $4.7

Subtotal Construction $36.0

Engineering/legal/administration $11 5Engineering/legal/administration $11.5

Total Project Cost $47.5

Page 20: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Total Construction Cost

P li i E ti tPhase 1 Component Preliminary Estimate(in millions)

Maximum allowable construction cost (MACC) $28.0( )

Owner’s Contingency (5%) $1.6

Contractor’s OH&P (5%) $1.6

Contractor’s General Conditions (5%) $1.6

Subtotal (without tax) $33.0

Sales Tax (8.5%) $3.0

Total Construction Cost $36.0

Page 21: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Schedule and Next Steps

1. Current Effort:

Schedule and Next Steps

1. Current Effort:a. Facilities Planning Reportb. Environmental Documentationb. Environmental Documentationc. 30% Design Documents

Page 22: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Facilities Planning Report / 30%

20112010

Facilities Planning Report / 30% Design Schedule and Next Steps

2011Task Sep Oct Nov Dec Jan Feb Mar Apr May

Status Meeting with DOEDraft Report to CityCit Re ie /Comment Period

2010

12/9/

12/9

/City Review/Comment PeriodDraft Report to DOEDOE Review/Comment PeriodReview Meeting with DOEAddress DOE Comments

1/28

12/9

2/28

1/13

Address DOE CommentsFinal Report(1)

Preliminary Enviro. Doc. to CityEnvironmental Review Meeting

Th h ld D t i ti (1)

4/29

12/91/13

2/21Threshold Determination (1)

SEPA Comment Period (1)

30% Design Review Workshop30% Design Comment Period30% D i C l t

11/2

2/21

30% Design Complete 12/7

(1) Schedule shown based on mitigated determination of nonsignificance (DNS).

Page 23: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Schedule and Next Steps

1. Current Effort:

Schedule and Next Steps

1. Current Effort:a. Facilities Planning Reportb. Environmental Documentationb. Environmental Documentationc. 30% Design Documents

2 Next Phase:2. Next Phase:a. General Contractor / Construction Manager

(GC/CM) Selection(GC/CM) Selectionb. Pre-construction services/value engineering

and preliminary cost estimatep yc. Design completion

Page 24: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

General Contractor / Construction

GC/CM Delivery Objectives

General Contractor / Construction Manager (GC/CM) Involvement

GC/CM Delivery Objectivesa. Select most qualified contractor while maintaining

competitionb. Confirm preliminary cost estimate and phasing

before proceeding with designc Incorporate Value Engineering for design and c. Incorporate Value Engineering for design and

constructabilityd. Continuous input from the GC/CM contractor on

t iti f t i d lit opportunities for cost savings and quality enhancement

e. Lock-in Maximum Allowable Construction Cost (MACC) before proceeding with construction

Page 25: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

GC/CM Status of Major ActivitiesGC/CM Status of Major Activities

Activity DateActivity Date

Received Proposals from GC/CM Firms (7) October 29

Notified Most Qualified GC/CM Firms (4) November 11Notified Most Qualified GC/CM Firms (4) November 11

Interviewed Short-Listed GC/CM Firms (4) December 1

Notified Finalists (2) December 2

Issued Request for Final Proposal (RFFP) December 8

Open RFFP, Notify Selected GC/CM Firm December 22

Page 26: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

GC/CM Schedule andGC/CM Schedule andNext Steps

Page 27: Update to City Council: Facilities Planning and 30% iiPl D ... · 12/13/2010  · Final Report(1) Preliminary Enviro. Doc. to City Environmental Review Meeting Th h ld D t i ti (1)

Questions?Questions?