• Please mute your microphone. We will open up the meeting for questions at the end.

• If you have dialed in on a telephone, use *6 to mute and un-mute yourself.

THIS SESSION WILL BEGIN SOON AND IS BEING RECORDED.

US-127 Public Meeting

Page 2: US-127 Public Meeting

Title VI of the Civil Rights Act

2

Title VI of the Civil Rights Act of 1964 requires MDOT to provide the opportunity for everyone to comment on transportation programs and activities that may affect their community.

Please take the three-question survey found in the chat box.

You can help MDOT comply with Title VI and related statutes, which require the collection of statistical data to aid in assessing MDOT's outreach efforts among those who are affected or interested in this project.

Page 3: US-127 Public Meeting

Rebuilding Michigan Project

3

US-127 from Ingham/Jackson County Line to M-36

(Cedar Street)

• Rebuilding Michigan projects are part of the Rebuilding Michigan bond

program focused on state highways and bridges that are critical to our

economy and carry the most traffic.

• Rebuilding Michigan corridors will be designed and built as a single

project.

For more information, visit www.Michigan.gov/MDOT5YearPlan or contact

MDOT Public Involvement Officer Monica Monsma at [email protected].

Page 4: US-127 Public Meeting

US-127 Corridor

4

• Urban two-lane interstate

• 22,000 - 35,000 vehicles per day

• 12 miles long

• 10 bridges

• Estimated cost: $62,000,000

• Rebuilding occurs 2022-2023

N

LANSING

MASON

LESLIE

JACKSON

Page 5: US-127 Public Meeting

US-127 MainlineRoadway milling and multiple course asphalt resurfacingConcrete Base repairsDrainage improvements.Sign replacement.

US-127 RampsMilling and resurfacingMinor Curb and Gutter replacement

Project Improvements - Road

5

Page 6: US-127 Public Meeting

Project Improvements - Bridges

6

1. Kipp Road over US-1272. Barnes Road over US-1273. Covert Road over US-1274. Bellevue Road over US-1275. M-36 EB (Cedar Street) over

US-1276. M-36 WB (Cedar Street) over

US-1277. Columbia Road over US-127

Capital Preventive Maintenance (CPM) and Rehabilitation

8. South Street over US-1279. US-127 over Huntoon Creek10. US-127 NB Off Ramp over

Huntoon Creek

Page 7: US-127 Public Meeting

US-127 Bridge Construction

Bridge Work Constructed Part width

1. M-36 EB (Cedar Street) over US-1272. M-36 WB (Cedar Street) over US-1273. Columbia Road over US-127 (Temp Signal)4. Kipp Road over US-127 (Temp Signal)5. Bellevue Road over US-127 (Temp Signal)

Bridge Work Constructed with Full Closure & Detour

1. South Street over US-1272. Barnes Road over US-1273. Covert Road over US-127

Page 8: US-127 Public Meeting

US-127 Construction Traffic Pattern

Stage 1 - 2022

Southbound Northbound

POB to North of Colombia Street

Southbound Northbound

North of Colombia Street to POE

Page 9: US-127 Public Meeting

US-127 Construction Traffic Pattern

Stage 2 - 2022

Southbound Northbound

POB to North of Colombia Street

Southbound Northbound

North of Colombia Street to POE

Page 10: US-127 Public Meeting

US-127 Construction Traffic Pattern

Stage 3 - 2022

Southbound Northbound

POB to North of Colombia Street

Southbound Northbound

North of Colombia Street to POE

Page 11: US-127 Public Meeting

US-127 Construction Traffic Pattern

Stage 4 - 2022

Southbound Northbound

POB to North of Colombia Street

Southbound Northbound

North of Colombia Street to POE

Page 12: US-127 Public Meeting

US-127 Construction Traffic Pattern

Stage 5 - 2022

Southbound Northbound

POB to North of Colombia Street

Southbound Northbound

North of Colombia Street to POE

Page 13: US-127 Public Meeting

US-127 Construction Traffic Pattern

Stage 6 - 2022

Southbound Northbound

POB to North of Colombia Street

Southbound Northbound

North of Colombia Street to POE

Page 14: US-127 Public Meeting

US-127 Bridge Construction

South Street Bridge Detour

Bridge Construction

Bridge Road Detour

South Street

Co

llege

Ro

ad

Colombia Road

Ce

dar

Str

eet

/M-3

6

Page 15: US-127 Public Meeting

US-127 Bridge Construction

Barnes Road Bridge Detour

Bridge Construction

Bridge Road Detour

Barnes Road

Tutt

le R

oad

Hu

ll R

oad

Page 16: US-127 Public Meeting

US-127 Bridge Construction

Covert Road Bridge Detour

Bridge Construction

Bridge Road Detour

Bellevue RoadC

hu

rch

illR

oad

Hu

ll R

oad

Page 17: US-127 Public Meeting

Future Outreach

17

Future Scheduled Public Meetings:• Tentative In-Person Meetings in October/November• Additional meetings as-needed/requested throughout the project

US-127 Corridor Website (coming soon)• Check website for updates, presentation slides, future meeting links,

dates and times, and other additional information

Page 18: US-127 Public Meeting

Questions and Answers

18

Options• Type your question in the chat box, or • Use “raise hand” icon to speak

Call-in attendees will have an opportunity to unmute and speak.

Written comments: Link in meeting chat box

Contact: MDOT Lansing [email protected](517) 335-3754

Page 19: US-127 Public Meeting

What is a State Long-Range Transportation Plan (SLRTP)?

• Multi-modal policy-based planning document that establishes the following for Michigan’s transportation system:

• Vision (Adopted July 2019)

• Goals (Adopted November 2019)

• Objectives (Adopted June 2020)

• Key Strategies (Adopted April 2021)

• Federally required

• 20+ Year Planning Horizon

Page 20: US-127 Public Meeting

Michigan Mobility 2045 (MM2045) – Family of Plans

First of its kind integrated long-range transportation plan for all of Michigan

Page 21: US-127 Public Meeting

Public Comment Period – July 23 – August 31, 2021

• Website: www.michiganmobility.org

• Comment Box available

• Draft Plan Document

• Plan Appendices

• Rail Supplement

• Public/Stakeholder Outreach Report

• System Performance Report

• Strategic Multimodal Corridors Report

• Active Transportation Plan –Executive Summary

• Videos