us-127 public meeting
TRANSCRIPT
![Page 1: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/1.jpg)
• Please mute your microphone. We will open up the meeting for questions at the end.
• If you have dialed in on a telephone, use *6 to mute and un-mute yourself.
THIS SESSION WILL BEGIN SOON AND IS BEING RECORDED.
US-127 Public Meeting
![Page 2: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/2.jpg)
Title VI of the Civil Rights Act
2
Title VI of the Civil Rights Act of 1964 requires MDOT to provide the opportunity for everyone to comment on transportation programs and activities that may affect their community.
Please take the three-question survey found in the chat box.
You can help MDOT comply with Title VI and related statutes, which require the collection of statistical data to aid in assessing MDOT's outreach efforts among those who are affected or interested in this project.
![Page 3: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/3.jpg)
Rebuilding Michigan Project
3
US-127 from Ingham/Jackson County Line to M-36
(Cedar Street)
• Rebuilding Michigan projects are part of the Rebuilding Michigan bond
program focused on state highways and bridges that are critical to our
economy and carry the most traffic.
• Rebuilding Michigan corridors will be designed and built as a single
project.
For more information, visit www.Michigan.gov/MDOT5YearPlan or contact
MDOT Public Involvement Officer Monica Monsma at [email protected].
![Page 4: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/4.jpg)
US-127 Corridor
4
• Urban two-lane interstate
• 22,000 - 35,000 vehicles per day
• 12 miles long
• 10 bridges
• Estimated cost: $62,000,000
• Rebuilding occurs 2022-2023
N
LANSING
MASON
LESLIE
JACKSON
![Page 5: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/5.jpg)
US-127 MainlineRoadway milling and multiple course asphalt resurfacingConcrete Base repairsDrainage improvements.Sign replacement.
US-127 RampsMilling and resurfacingMinor Curb and Gutter replacement
Project Improvements - Road
5
![Page 6: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/6.jpg)
Project Improvements - Bridges
6
1. Kipp Road over US-1272. Barnes Road over US-1273. Covert Road over US-1274. Bellevue Road over US-1275. M-36 EB (Cedar Street) over
US-1276. M-36 WB (Cedar Street) over
US-1277. Columbia Road over US-127
Capital Preventive Maintenance (CPM) and Rehabilitation
8. South Street over US-1279. US-127 over Huntoon Creek10. US-127 NB Off Ramp over
Huntoon Creek
![Page 7: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/7.jpg)
US-127 Bridge Construction
Bridge Work Constructed Part width
1. M-36 EB (Cedar Street) over US-1272. M-36 WB (Cedar Street) over US-1273. Columbia Road over US-127 (Temp Signal)4. Kipp Road over US-127 (Temp Signal)5. Bellevue Road over US-127 (Temp Signal)
Bridge Work Constructed with Full Closure & Detour
1. South Street over US-1272. Barnes Road over US-1273. Covert Road over US-127
![Page 8: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/8.jpg)
US-127 Construction Traffic Pattern
Stage 1 - 2022
Southbound Northbound
POB to North of Colombia Street
Southbound Northbound
North of Colombia Street to POE
![Page 9: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/9.jpg)
US-127 Construction Traffic Pattern
Stage 2 - 2022
Southbound Northbound
POB to North of Colombia Street
Southbound Northbound
North of Colombia Street to POE
![Page 10: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/10.jpg)
US-127 Construction Traffic Pattern
Stage 3 - 2022
Southbound Northbound
POB to North of Colombia Street
Southbound Northbound
North of Colombia Street to POE
![Page 11: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/11.jpg)
US-127 Construction Traffic Pattern
Stage 4 - 2022
Southbound Northbound
POB to North of Colombia Street
Southbound Northbound
North of Colombia Street to POE
![Page 12: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/12.jpg)
US-127 Construction Traffic Pattern
Stage 5 - 2022
Southbound Northbound
POB to North of Colombia Street
Southbound Northbound
North of Colombia Street to POE
![Page 13: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/13.jpg)
US-127 Construction Traffic Pattern
Stage 6 - 2022
Southbound Northbound
POB to North of Colombia Street
Southbound Northbound
North of Colombia Street to POE
![Page 14: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/14.jpg)
US-127 Bridge Construction
South Street Bridge Detour
Bridge Construction
Bridge Road Detour
South Street
Co
llege
Ro
ad
Colombia Road
Ce
dar
Str
eet
/M-3
6
![Page 15: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/15.jpg)
US-127 Bridge Construction
Barnes Road Bridge Detour
Bridge Construction
Bridge Road Detour
Barnes Road
Tutt
le R
oad
Hu
ll R
oad
![Page 16: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/16.jpg)
US-127 Bridge Construction
Covert Road Bridge Detour
Bridge Construction
Bridge Road Detour
Bellevue RoadC
hu
rch
illR
oad
Hu
ll R
oad
![Page 17: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/17.jpg)
Future Outreach
17
Future Scheduled Public Meetings:• Tentative In-Person Meetings in October/November• Additional meetings as-needed/requested throughout the project
US-127 Corridor Website (coming soon)• Check website for updates, presentation slides, future meeting links,
dates and times, and other additional information
![Page 18: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/18.jpg)
Questions and Answers
18
Options• Type your question in the chat box, or • Use “raise hand” icon to speak
Call-in attendees will have an opportunity to unmute and speak.
Written comments: Link in meeting chat box
Contact: MDOT Lansing [email protected](517) 335-3754
![Page 19: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/19.jpg)
What is a State Long-Range Transportation Plan (SLRTP)?
• Multi-modal policy-based planning document that establishes the following for Michigan’s transportation system:
• Vision (Adopted July 2019)
• Goals (Adopted November 2019)
• Objectives (Adopted June 2020)
• Key Strategies (Adopted April 2021)
• Federally required
• 20+ Year Planning Horizon
![Page 20: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/20.jpg)
Michigan Mobility 2045 (MM2045) – Family of Plans
First of its kind integrated long-range transportation plan for all of Michigan
![Page 21: US-127 Public Meeting](https://reader031.vdocuments.net/reader031/viewer/2022012301/61e1dc7989e2e654702dec4d/html5/thumbnails/21.jpg)
Public Comment Period – July 23 – August 31, 2021
• Website: www.michiganmobility.org
• Comment Box available
• Draft Plan Document
• Plan Appendices
• Rail Supplement
• Public/Stakeholder Outreach Report
• System Performance Report
• Strategic Multimodal Corridors Report
• Active Transportation Plan –Executive Summary
• Videos