us 278 cursory bridge inspection

Upload: dmartinislandpacket

Post on 30-May-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 US 278 Cursory Bridge Inspection

    1/76

    Cursory Above Water and UnderwaterInvestigation Of

    US 278 East Bound and West Bound

    Over

    MacKay Creek and Skull Creek

    In

    Hilton Head, South Carolina

    Prepared by:

    1180 Sam Rittenberg Blvd, Suite 105Charleston, South Carolina 29407(843) 763-1576 phone(843) 763-1582 faxwww.collinsengr.com Collins Project No. 6336-40

    Bridges over MacKay Creek

    Bridges over Skull Creek

  • 8/9/2019 US 278 Cursory Bridge Inspection

    2/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 1

    Cursory Above Water and Underwater Investigation of

    US 278 West Bound and US 278 East Bound Bridges

    Over MacKay Creek and Skull Creek

    Prepared by:Collins Engineers, Inc.1180 Sam Rittenberg Blvd, Suite 105Charleston, South Carolina 29407

    SUMMARY OF SIGNIFICANT FINDINGS

    Inspection Date: February 11 and 12, 2010

    Significant Conditions Observed:

    US 278 West Bound over MacKay Creeko Crack up to 3/4 in. wide and 10 ft long located on the bottom of the pile

    cap at Bent 2.o Spall measuring 18 in. by 1 ft with 1.5 in. of penetration was located on the

    bottom of the pile cap at Bent 2.o The southernmost pile at Bent 2 exhibited 1/8 in. wide cracks with rust

    stains around all faces of the pile.

    US 278 East Bound over MacKay Creeko Random cracks ranging in width from 1/8 in. up to 1/2 in. wide with rust

    stains located on the piles and pile jackets.o Minor cracks and spalls in the superstructure beams.o A spall measuring 3 ft long by 1 ft wide with exposed reinforcing steel was

    located on the bottom of Beam 6 at Span 29.

    US 278 West Bound over Skull Creeko Approximately 5 ft of vertical undermining of the pier at the east side of the

    navigation channel.o Footing and seal exposure of the upstream nose of the pier at the west

    side of the navigation channel.

    o Missing section of the timber fender system at the west side of thenavigation channel.

    o Cracks up to 1/4 in. wide with rust stains located on the bottom of amajority of the pile cap footings for the approach piers.

    o Light to moderate corrosion of the cross bracing between the steel plategirders.

    o Spall measuring 2 ft long by 10 in. wide with three in. of penetrationlocated on the top of the concrete barrier rail at east end of the bridge.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    3/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 2

    SUMMARY OF SIGNIFICANT FINDINGS (Cont.)

    US 278 East Bound over Skull Creeko Footing and seal exposure of the pier at the east side of the navigation

    channel.o A void between the footing and seal measuring 12 in. vertical with 18 in.

    penetration and one exposed H-pile on the pier at the east side of thenavigation channel.

    o Cracks up to 1/4 in. wide with rust stains located on the bottom of amajority of the pile cap footings for the approach piers.

    o Light to moderate corrosion of the cross bracing between the steel plategirders.

    SUMMARY OF BRIDGE RATINGS

    Bridge Deck Superstructure Substructure

    MacKay Creek WBL 7 6 6

    MacKay Creek EBL 7 5 5

    Skull Creek WBL 7 6 5

    Skull Creek EBL 7 6 5

  • 8/9/2019 US 278 Cursory Bridge Inspection

    4/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 3

    1.0 INTRODUCTION

    SCDOT Bridge Inspection Program

    According to the Federal Highway Administration a bridge is defined as A structure

    including supports erected over a depression or an obstruction, such as water, highway,

    or railway, and having a track or passageway for carrying traffic or other moving loads,

    and having an opening measured along the center of the roadway of more that 20 feet

    between undercopings of abutments or spring lines of arches, or extreme ends of

    openings for multiple boxes; it may also include multiple pipes where the clear distance

    between openings is less than half of the smaller contiguous openings.

    In accordance with Federal Highway Administration guidelines, the South Carolina

    Department of Transportation inspects their bridges at intervals not to exceed 24

    months for above water inspections and 60 months for underwater inspections. These

    inspections are based on the Recording and Coding Guide for the Structure Inventory

    and Appraisal of the Nations Bridges. This publication is governed by the National

    Bridge Inspection Standards (NBIS).

    The NBIS was created in the early 1970s as a result of the Silver Bridge collapse in

    West Virginia. Before this time, there was very little public interest in the inspection and

    maintenance of our nations bridges. After 46 people died as a result of this collapse,

    the U.S. Congress required the Secretary of Transportation to establish a National

    Bridge Inspection Standard and develop a program to train bridge inspectors. These

    inspections are necessary for having an effective bridge maintenance program. The

    SCDOT performs five main types of inspections.

    - Initial Inspections Inspections performed to document the condition of a bridge

    after construction has been completed and the inventoried.

    - Routine Inspections Inspections used to document the physical and functional

    elements of bridges.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    5/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 4

    - In-depth Inspections Close up (arms length or hands on) inspections used to

    document the condition of the structure. Underwater inspections are typically

    considered in-depth inspections.- Scour The channel is inspected below the waterline to determine the level or

    extent of scour or channel migration.

    - Fracture Critical Inspection of critical tension members on a bridge structure.

    Fracture critical members are considered a member in tension that if failure

    occurs could result in partial or total failure of the structure.

    - Special Inspections These inspections are performed after repair, rehabilitation,

    replacement or after significant natural events like flooding, storms or seismic

    events.

    Typically all of these inspection levels are coordinated through the SCDOT Bridge

    Maintenance Office. The responsibility of this office is to coordinate bridge maintenance

    and rehabilitation activities, as well as, overseeing the SCDOT Bridge Management

    System (BMS). The bridge management system is a means for managing state wide

    bridge data throughout their design life. This includes collecting bridge inventory data,

    performing inspections, maintenance and rehabilitation.

    SCDOT Bridge Inspection Report Forms

    The standard SCDOT Inspection Form used by the Office of Bridge Maintenance is

    used as the primary means for inventorying and assigning condition and appraisal

    ratings to bridges in South Carolina. This form lists several bridge characteristics and

    their corresponding codes as listed in the Recording and Coding Guide. Some aspects

    of the form will be presented in the following sections. For a complete view of theinformation contained in this form, please refer to Appendix C.

    - General Bridge Data: This section lists the Bridge Identification Number, and

    general location with respect to route or waterway crossed. It also lists the year

  • 8/9/2019 US 278 Cursory Bridge Inspection

    6/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 5

    it was built or reconditioned, the overall length, number of spans, and the type of

    structure.

    - Geometric Data: This section lists all pertinent bridge geometry such as:waterway navigation clearance, under clearances, vertical clearances, structure

    width, horizontal clearances, number of lanes, and sidewalk dimensions.

    - Condition Ratings: This section lists the inventory and operating rating, the last

    paint application date (if applicable), and the condition ratings of the deck,

    superstructure, and substructure.

    - Critical Inspection Data: This section lists the last inspection date, the inspection

    frequency, and gives an indication if special, fracture critical, or underwater

    inspections have been or need to be performed.

    - Appraisal Ratings: This section lists the overall appraisal of the structure, the

    deck geometry, under clearance, bridge posting, and waterway adequacy. Many

    of these ratings are not assigned by the actual inspector but are calculated using

    FHWA Edit/Update computer program.

    Bridge Element Grout Textual Dataforms are also used by the inspector during routine

    bridge inspection. This form evaluates the condition of: bridge abutments, bents, piers,bearings, girders and beams, truss members, expansion joints, decks, curbs, bridge

    railings or barriers, paint systems, waterway condition, fender system, alignment of the

    roadway, traffic signs, and encroachments. Under these headings in Textual Data form,

    the inspector can add general or specific comments about the items listed above and

    their corresponding NBIS rating. An example of this form is presented in Appendix C.

    NBI ratings typically cover the deck, superstructure, and substructure in the overall

    bridge rating. The PONTIS system described in the following paragraph is an element

    based inspection that inventories and rates every element on the bridge. This includes

    but is not limited to the deck, beams, piles, bearings, railing, joints, etc. The different

    elements rated are according to the material used. For instance, a bare concrete deck

    and a concrete deck with asphalt overlay are considered different elements.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    7/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 6

    The SCDOT PONTIS BMS Element Data Form is a form that lists the Commonly

    Recognized (CoRe) Structural Elements for bridges. PONTIS is owned by the

    American Association of State Highway and Transportation Officials. The system isused to store bridge inventory and inspection data using the NBIS guidelines and also

    assigns condition states to each bridge element. With this system, each element

    corresponds to an element number in the PONTIS System. The total quantity of each

    element is then calculated. This quantity is then recorded as percentage of distribution

    in each corresponding condition state. Condition states are listed from Condition 1 (little

    or no deterioration) to Condition 5 (advanced deterioration). Each condition state is

    described for each element and any feasible actions are also presented. For example:

    If a bridge has 120 reinforced concrete piles this corresponds to Element 205 according

    to the CoRe Elements, and 20 of these piles have deterioration, 17 percent of these

    piles would be listed under Condition State 4 and the remaining 83 percent would be

    listed under Condition State 1. For the Condition State 4 rating, there are three feasible

    actions that can be performed on the 20 piles showing deterioration: do nothing,

    rehabilitate the piles, or replace the piles. PONTIS BMS give a more quantitative

    assessment of every structural element versus the general assessment given for the

    deck, superstructure, and substructure given in the NBI. The SCDOT PONTIS BMS

    Element Data Form is presented in Appendix C.

    Bridge Inspector Certifications

    The training and qualifications of an NBIS bridge inspector are presented in the Code of

    Federal Regulations 650C. The following excerpt is from the FHWA Bridge Inspectors

    Reference Manual:

    A program manager must, at a minimum:

    - Be a registered professional engineer, or have ten years bridge inspection

    experience; and have successfully completed a Federal Highway Administration

    (FHWA) approved comprehensive bridge inspection training course.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    8/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 7

    A NBIS bridge inspection team leader can qualify in five ways.

    - Have the qualifications for program manager as presented above.

    -Have five years bridge inspection experience and have successfully completedan FHWA approved comprehensive bridge inspection training course.

    - Be certified as a Level III or IV Bridge Safety Inspector under the National

    Society of Professional Engineer's program for National Certification in

    Engineering Technologies (NICET) and have successfully completed an FHWA

    approved comprehensive bridge inspection training course, or:

    - Have all of the following:

    - A bachelor's degree in engineering from a college or university accredited by or

    determined as substantially equivalent by the Accreditation Board for

    Engineering and Technology;

    - Successfully passed the National Council of Examiners for Engineering and

    Surveying Fundamentals of Engineering examination;

    - Two years of bridge inspection experience

    - Successfully completed an FHWA approved comprehensive bridge inspection

    training course.

    -Have all of the following:

    - An associate's degree in engineering or engineering technology from a college or

    university accredited by or determined as substantially equivalent by the

    Accreditation Board for Engineering and Technology;

    - Four years of bridge inspection experience; and

    - Successfully completed an FHWA approved comprehensive bridge inspection

    training course.

    -

    The individual charged with the overall responsibility for load rating bridges mustbe a registered professional engineer.

    - An underwater bridge inspection diver must complete an FHWA approved

    comprehensive bridge inspection training course or other FHWA approved

    underwater diver bridge inspection training course.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    9/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 8

    All of the inspectors for this cursory bridge inspection meet or exceed the requirements

    as presented above.

    Long Term Expectation of Bridge Life and Maintenance

    The current AASHTO LRFD code calls for bridges to be designed for a Design

    Life of 75 years (Section 1.2). What the actual in-service life of a structure may be is

    dependent on the owners desires and expectations coupled with the effects of things

    like the bridges exposure to environmental elements, quality of materials, construction

    type and practices used and the level of maintenance. The US 278 Bridges were built

    in the following years; 1982 for the two structures over Skull Creek, 1983 for the

    Westbound lane over MacKay Creek and 1956 for the one Eastbound lane over

    MacKay Creek. This means that they were most likely designed using a Design Life of

    50 years, which was common at that time. Therefore, the Eastbound lane over MacKay

    Creek has already exceeded its intended Design Life and the others are nearing year

    30 of their Design Life. This does not mean that they are no longer functional or safe as

    the ability of a structure to survive and perform well beyond its Design Life has been

    well documented and is mostly dependent on the environment it resides in and the

    maintenance attention it has received.

    Many modern structures are now being designed with a Design Life of 100 years,

    such as the new Ravenel (Cooper River) Bridge in Charleston, SC. The new Oakland

    Bay Bridge in San Francisco has been designed for a Design Life of 150 years. Even

    though these structures are designed to last longer, whether they do or not will be

    greatly dependent on the factors already mentioned.

    Of the several factors that play a role in the reduction of a bridges service life.

    Two of the harshest and one that is present at the US 278 bridges, are the coastal

    environment and heavy traffic use. In this location, these structures are subjected to

    high wave and wind forces as well as being constantly inundated in the corrosive salt

  • 8/9/2019 US 278 Cursory Bridge Inspection

    10/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 9

    water environment. This applies to the superstructure as well as the substructure

    because of the chloride laden air, and our high humidity, transports that corrosive

    element to the bridges girders and concrete deck.

    The result of this long term exposure to a salt laden air and water environment is

    corrosion. Corrosion affects the life of both steel structures and reinforced concrete

    bridges. For steel structures, there are very visual signs of coating failure and

    accumulation of rust on the structural steel members. With concrete structures, the

    deterioration is usually not evident until it has reached advanced stages. This is

    because corrosion attacks the reinforcing steel buried within the concrete and only

    becomes visible once it has caused cracks and fractures (spalls) in the concrete surface

    and rust staining is then seen.

    The other factor mentioned was traffic volume. As the main bridges in and out of

    Hilton Head, these structures see not only large volumes of traffic, but heavy usage by

    truck traffic, which puts additional strain on the structure over time. Again, the

    maintenance of the structure plays the biggest role in preventing deterioration due to

    increase traffic volumes and loads. According to the Average Daily Traffic (ADT)

    volume obtained from the SCDOT for the 2008 period, US 278 traffic volumes within the

    area of investigation range from 44,300 to 57,800. A comparison of this ADT with other

    locations indicates that this volume is the highest in Beaufort County.

    For your reference, some other bridges that were constructed during the 1950s

    and are located in similar coastal environments are listed below. These bridges are still

    open to traffic although we are not aware of the current condition of the structures.

    Little River Intracoastal Waterway Bridge (Horry County, South Carolina), Built

    1935; rehabilitated 1980, Warren through truss swing bridge over Intracoastal

    Waterway on S-26-20 (formerly US 17) in Little River

  • 8/9/2019 US 278 Cursory Bridge Inspection

    11/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 10

    Ben Sawyer Intracoastal Waterway Bridge (Charleston County, South Carolina),

    Built 1945, rehabilitated 2010, Swing bridge over Intracoastal Waterway on SC

    703 in Charleston

    Intracoastal Waterway Bridge (New Hanover County, North Carolina), Built 1956,

    Bascule bridge over Intracoastal Waterway on US 74/US 76 in Wrightsville

    Beach

    Intracoastal Waterway Bridge (Carteret County, North Carolina), Built 1935,

    Swing bridge over Intracoastal Waterway on NC 101

    Surf City Bridge (Pender County, North Carolina), Built 1955, Swing bridge over

    Intracoastal Waterway on NC50/NC210 in Surf City

    Intracoastal Waterway Bridge (Palm Beach County, Florida), Built 1938

    Bascule bridge over Intracoastal Waterway on FL A1A in Palm Beach

    Southern Boulevard Bridge (Palm Beach County, Florida), Built 1950, Bascule

    bridge over Intracoastal Waterway on Southern Boulevard in West Palm Beach

    Oakland Park Blvd. Bridge (Broward County, Florida), Built 1955, Bascule bridge

    over Intracoastal Waterway on Oakland Park Blvd. in Fort Lauderdale

    General Description of the Structures

    Bridge 0720027840300 carries the west bound lanes of US 278 over MacKay

    Creek in Hilton Head, South Carolina. The bridge consists of 54 prestressed concrete

    girder spans and one steel girder span supported by prestressed square concrete pile

    bents. The deck consists of stay-in-place forms and a reinforced concrete deck.

    Bridge 0720027820300 carries the east bound lanes of US 278 over MacKay

    Creek in Hilton Head, South Carolina. The bridge consists of 54 reinforced concrete

    girder spans and one steel girder span supported by multiple reinforced concrete pile

    bents. The structure originally consisted of pile bents with five octagonal concrete piles

  • 8/9/2019 US 278 Cursory Bridge Inspection

    12/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 11

    supporting the reinforced concrete girders. Several of the original piles had a reinforced

    concrete circular jacket. When the bridge was widened, two prestressed concrete piles

    were driven on each side of the bents and support two additional prestressed concretegirders on either side of the bridge. A retrofit cap connected the widened section to the

    original cap. The deck consists of reinforced concrete with an asphalt overlay.

    Bridge 0720027840400 carries the west bound lanes of US 278 over Skull Creek

    in Hilton Head, South Carolina. The bridge consists of 21 approach spans and five

    main channel spans. The main channel piers are comprised of a reinforced concrete

    hammer head piers supported by a submerged footing/seal combination founded on

    multiple steel H-piles. The approach spans are supported by a reinforced concrete

    hammer head pier configuration founded on a waterline pile cap footing supported by

    multiple prestressed concrete piles or prestressed concrete pile bents. The

    substructure units support steel plate girders with transverse steel cross bracing and a

    reinforced concrete deck.

    Bridge 0720027820400 carries the east bound lanes of US 278 over Skull Creek

    in Hilton Head, South Carolina. The bridge is of a similar configuration to the west

    bound bridge. A 22 ft research vessel was used to gain access to the superstructure

    and substructure elements. Due to heavy traffic the decks were visually inspected from

    the inspection vehicle.

    Methods of Investigation

    An inspection team consisting of engineer-divers led by a South Carolina-

    registered Professional Engineer-diver conducted the above water and underwater

    investigation of the four bridges leading to Hilton Head Island on February 11 and 12,

    2010. Access to the bridge site was obtained from C.C. Haig Boat Landing on Pinckney

    Island.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    13/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 12

    The investigation consisted of a cursory inspection of the accessible portions of

    the substructure and superstructure. The cursory inspection was performed on a

    representative sample of the bridge components to detect obvious and gross bridgeconditions. Particular attention was given to any observed areas of excessive

    deterioration or apparent distress, and the condition of any repairs was noted.

    A cursory assessment of the waterway and channel bottom conditions in the

    vicinity of the bridge was also made. The type of channel bottom material was noted, as

    well as the location and extent of any observed scour, riprap, or debris.

    2.0 OBSERVED CONDITIONS AND ASSESMENT

    The following criteria govern the assessment ratings of the structural components of the

    inspected bridges: These criteria are established from the Recording and Coding Guide

    for the Structure Inventory and Appraisal of the Nations Bridges. Report No. FHWA-

    PD-96-001. These codes also follow the SCDOT Bridge Inspection Form Ratings.

    - Code 9 - Excellent Condition

    - Code 8 - Very Good Condition no problems noted.

    - Code 7 - Good Condition some minor problems but functioning as intended.

    - Code 6 - Satisfactory Condition structural elements show some minor deterioration

    but are still functioning as intended.

    - Code 5 - Fair Condition all primary structural elements are sound but may have

    minor section loss, cracking, or spalling.

    - Code 4 - Poor Condition advanced section loss, deterioration, or spalling.

    - Code 3 - Serious Condition loss of section, deterioration, or spalling has seriously

    affected primary structural components. Local failures are possible.- Code 2 - Critical Condition advanced deterioration of primary structural elements.

    Fatigue cracks in steel or shear cracks in concrete may be present or scour may have

    removed substructure support. Unless closely monitored it may be necessary to close

    the bridge until corrective action is taken.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    14/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 13

    - Code 1 - Imminent Failure Condition major deterioration or section loss is present

    in critical structural components or obvious vertical or horizontal movement affecting

    structural stability. Bridge is closed to traffic but corrective action may be put back inlight service.

    - Code 0 - out of service beyond corrective action.

    The following narrative will briefly describe the existing conditions encountered

    during the cursory inspections of US 278 WBL and EBL over MacKay and Skull Creek.

    The inspections were conducted over the course of two days. The weather wasovercast with light rain and an air temperature of 40 F both days. The water under the

    bridge flowed between 0 and 2 ft/s during the inspection. Underwater visibility was

    approximately 2 ft.

    Item 61 Channel and Channel Protection

    The embankments at all four bridges were found to be in very good condition

    (Code 8). The banks along the waterways in the vicinity of the bridges were observedto be in stable condition. Embankment protection in the form of riprap was observed on

    the east and west banks of MacKay Creek and aquatic vegetation and oyster shells on

    the east and west banks of Skull Creek. There was no sign of active erosion. The

    channel bottom consisted of silty sand and oyster shells. There were no signs of heavy

    accumulation of debris or drift.

    US 278 West Bound over MacKay Creek

    Item 58 - Deck

    The concrete deck was found to be in good condition (Code 7). There were no

    noticeable spalls or significant cracks in the deck or the concrete barrier. In isolated

    areas, the expansion joint material had come loose along the shoulder of the roadway.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    15/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 14

    Item 59 Superstructure

    The superstructure was found to be in satisfactory condition (Code 6). Minor cracking

    was noted in isolated locations on the prestressed concrete girders. Several areas of

    concrete spall repair were noted in isolated locations. The steel girders supporting the

    main span showed signs of light to moderate corrosion with no signs of significant

    section loss.

    Item 60 - Substructure

    Overall, the substructure was also found to be in satisfactory condition (Code 6). Minor

    isolated cracks were noted on the piles above the high-water mark. Areas of minor

    isolated spall repair were noted in random locations. The most significant defects were

    located on Bent 2. On the east face of the reinforced concrete pile cap a crack

    measured up to 3/4 in. wide with rust stains. The crack measured approximately 10 ft

    long. The southernmost pile at Bent 2 had cracks up to 1/8 in. wide with rust stains

    around all faces of the pile and extended from the bottom of the pile cap down

    approximately 3 ft. A spall was located on the bottom of the pile cap at Bent 2. The

    spall measured approximately 1 ft by 18 in. with 1 in. of penetration.

    The piles at Bents 40 through 43 were inspected below water and were found to be in

    good condition. The piles exhibited a heavy layer of marine growth from the high-water

    mark to the channel bottom. No significant conditions were noted on the below water

    portions of these piles. Please refer to Photographs 1 to 12 for typical views of the

    conditions encountered on this bridge.

    US 278 East Bound over MacKay Creek

    Item 58 - Deck

    The deck was found to be in satisfactory condition (Code 6). The asphalt overlay

    showed minor signs of deterioration along the joints. Minor delamination of the asphalt

  • 8/9/2019 US 278 Cursory Bridge Inspection

    16/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 15

    overlay up to 18 in. diameter was observed in isolated locations. There were no

    significant defects located on the concrete barrier.

    Item 59 Superstructure

    Overall, the superstructure was found to be in fair condition (Code 5). This condition

    was based on what the inspectors could visually assess from the boat. The bridge

    bearings were not accessible. The steel girders supporting the main span showed

    signs of light to moderate corrosion.

    Random minor cracks were noted on the bottom and sides of the reinforced concrete

    beams. Evidence of previous spall repairs were noted in several locations throughout

    the superstructure and appeared to be in good condition. One isolated spall measuring

    3 ft horizontal by 1 ft vertical was located on the bottom of Beam 6 at Bent 29. The spall

    exposed one reinforcing which exhibited some corrosion but any loss of section could

    not be verified. Other random superficial spalls due to lack of sufficient cover over the

    reinforcing bars were noted on the reinforced concrete diaphragms.

    Item 60 - Substructure

    Several bents of different pile arrangements were inspected below water and were

    found to be in fair condition (Code 5). The piles exhibited a heavy layer of marine

    growth from the high-water mark to the channel bottom. Minor cracking with rust stains

    was observed within the tidal zone on several of the piles. Many of the octagonal piles

    have been retrofitted with concrete pile jackets. These jackets were typically located

    within the tidal zone. Several jackets exhibited minor cracking between 1/8 in. and 1/2

    in. wide with rust stains; however, no significant deterioration such as: large spalls or

    section loss was noted on the inspected piles. Please refer to Photographs 13 to 26 for

    typical views of the conditions encountered on this bridge.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    17/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 16

    US 278 West Bound over Skull Creek

    Item 58 - Deck

    Overall the concrete deck was found to be in good condition (Code 7). There were no

    noticeable spalls or significant cracks in the deck. In areas, the expansion joint material

    had come loose in isolated locations along the shoulder of the roadway. A spall

    measuring approximately 2 ft long by 10 in. wide with no exposed reinforcing steel was

    found on the top of the concrete barrier rail at the east end of the bridge.

    Item 59 Superstructure

    The superstructure was visually inspected from the ground and the inspection boat and

    was found to be in satisfactory condition (Code 6). The steel plate girders exhibited

    minor loss of protective coating and showed no appreciable corrosion. Most of the

    transverse steel cross bracing had more moderate loss of protective coating with some

    minor corrosion. The corrosion was more pronounced where the steel cross bracing

    was connected to the steel plate girders. Due to the height of the structure any loss of

    section could not be verified.

    Item 60 - Substructure

    The inspections of the selected substructure elements revealed the most significant

    deterioration and were rated as fair condition (Code 5). The inspected substructure

    units exhibited a heavy layer of marine growth from the high-water mark to the channel

    bottom. The east channel pier exhibited complete footing and seal exposure with

    undermining of the seal at the upstream nose of the pier. The area of underminingmeasured up to 5 ft vertical. The footing of the pier located at the west side of the

    navigation channel was completely exposed and had approximately 4 ft of seal

    exposure. No undermining of the seal was detected at this pier. Cracks up to 1/4 in.

    wide with rust stains were located on the bottom of a majority of the pile cap footings for

  • 8/9/2019 US 278 Cursory Bridge Inspection

    18/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 17

    the approach piers. These cracks were typically located 6 to 8 in. above the bottom of

    the pile cap footings and were likely caused by corrosion of the internal reinforcing steel

    due to chloride interaction from the saltwater environment.

    The timber fender system on the west side of the navigation channel beneath the west

    bound lane was partially missing.

    US 278 East Bound over Skull Creek

    Item 58 - Deck

    Overall the concrete deck was found to be in good condition (Code 7). There were no

    noticeable spalls or significant cracks in the deck. In areas, the expansion joint material

    had come loose in isolated locations along the shoulder of the roadway.

    Item 59 Superstructure

    The superstructure was visually inspected from the ground and the inspection boat and

    was found to be in satisfactory condition (Code 6). The steel plate girders exhibited

    minor loss of protective coating and showed no appreciable corrosion. Most of the

    transverse steel cross bracing had more moderate loss of protective coating with some

    minor corrosion. The corrosion was more pronounced where the steel cross bracing

    was connected to the steel plate girders. Due to the height of the structure any loss of

    section could not be verified.

    Item 60 - Substructure

    The inspections of the selected substructure elements revealed the most deterioration

    and were found to be in fair condition (Code 5). The inspected substructure units

    exhibited a heavy layer of marine growth from the high-water mark to the channel

    bottom. The east channel pier was found to have up to 5 ft of vertical seal exposure

    along the upstream nose. In addition, a void was detected at the footing and seal

  • 8/9/2019 US 278 Cursory Bridge Inspection

    19/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 18

    interface. The void measured approximately 12 in. vertical with up to 18 in. of

    penetration. A steel H-pile was located in this void and exhibited moderate corrosion

    with no appreciable loss of section. Cracks up to 1/4 in. wide with rust stains werelocated on the bottom of a majority of the pile cap footings for the approach piers.

    These cracks were typically located 6 to 8 in. above the bottom of the pile cap footings

    and were likely caused by corrosion of the internal reinforcing steel due to chloride

    interaction from the saltwater environment.

    3.0 RECOMMENDATIONS

    US 278 West Bound over MacKay Creek

    Item 58 - Deck

    There are no repair recommendations at this time; however, the expansion joint material

    should be monitored for future deterioration and may require replacement in the near

    future.

    Item 59 Superstructure

    It is recommended that the minor cracking of the concrete girders and the condition of

    any repairs be closely monitored during future inspections. The steel girders supporting

    the main span showed signs of light to moderate corrosion and should be cleaned and

    coated with a protective coating suitable for marine environments.

    Item 60 - Substructure

    The minor cracks located within the tidal zone should be monitored for continued

    deterioration during future inspections. The 3/4 in. wide crack with rust stains located

    on Bent 2 should be repaired by routing the crack and filling it with a flexible mastic

    sealant. In addition, the southernmost pile at Bent 2 showed more extensive cracking

    and should be repaired using a similar method.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    20/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 19

    The spall at the bottom of the pile cap at Bent 2 should also be repaired. This would

    include removing all unsound concrete and reforming the area to its original dimensions

    using a non-shrink grout suitable for marine environments.

    US 278 East Bound over MacKay Creek

    Item 58 Deck

    There are no repair recommendations at this time; however, the expansion joint material

    should be monitored for future deterioration and may require replacement in the near

    future.

    Item 59 Superstructure

    It is recommended that the minor cracking of the concrete girders and the condition of

    any repairs be closely monitored during future inspections. The steel girders supporting

    the main span showed signs of light to moderate corrosion and should be cleaned and

    coated with a protective coating suitable for marine environments.

    The spall located on Beam 6 of Bent 29 should be repaired. This would include

    removing all unsound concrete, cleaning and coating any reinforcing steel and

    reforming the area to its original dimensions using a non-shrink grout suitable for marine

    environments.

    Item 60 - Substructure

    There are no pile repair recommendations at this time; however, the piles and pile

    jackets should be monitored for increased deterioration during subsequent inspections.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    21/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 20

    US 278 West Bound over Skull Creek

    Item 58 Deck

    The expansion joint material should be monitored for future deterioration. The 2 ft long

    by 10 in. wide spall at the top of the barrier parapet is primarily cosmetic. It is also

    protected from impact from the median crash barrier.

    Item 59 Superstructure

    The loss of protective coating is relatively minor and should be monitored for further

    deterioration.

    Item 60 - Substructure

    The footing/seal exposure and undermining at the channel piers should be monitored

    closely during future underwater inspections. In addition, it is recommended to perform

    or review a scour analysis of these piers to determine the anticipated depth of scour and

    design countermeasures as necessary.

    The cracks located at the bottom of the pile cap footings that are larger that 1/4 in. wide

    should be routed and sealed with a flexible mastic sealant.

    The portion of the missing fender system on the west side of the navigation channel

    should be replaced.

    US 278 East Bound over Skull Creek

    Item 58 - Deck

    The expansion joint material should be monitored for future deterioration.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    22/76

    US 278 WBL and EBL

    Over MacKay Creek and Skull Creek

    Collins Project No. 6336-40Page 21

    Item 59 Superstructure

    The loss of protective coating is relatively minor and should be monitored for further

    deterioration.

    Item 60 - Substructure

    The footing/seal exposure, as well as voids in the seal, at the channel piers should be

    monitored closely during future underwater inspections. In addition, it is recommended

    to perform or review a scour analysis of these piers to determine the anticipated depth

    of scour and design countermeasures as necessary.

    The cracks located at the bottom of the pile cap footings that are larger that 1/4 in. wide

    should be routed and sealed with a flexible mastic sealant.

    Overall, the four bridges are in satisfactory to fair condition. The type and amount of

    deterioration observed during the cursory inspection are indicative of structures of this

    age. Because the EBL Bridge over MacKay creek is older, (built in 1956), we saw more

    deterioration in the superstructure and substructure. This deterioration has potentially

    reduced some of the structures capacity but does not pose an immediate risk of failure.

    The structure should however be scheduled for significant rehabilitation and/or

    replacement in the near future.

    Respectfully submitted,

    COLLINS ENGINEERS, INC.

    James K. OConnor, P.E.Project Manager

    Originated by:William Barna, P.E.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    23/76

    Appendix A

    References

  • 8/9/2019 US 278 Cursory Bridge Inspection

    24/76

    References:

    Bridge Inspectors Reference Manual, Publication No. FHWA NHI-03-001, 2006.

    Operation and Maintenance of Waterfront Facilities, Publication No. UFC-4-150-07, 2001.

    Recording and Coding Guide for the Structure Inventory and Appraisal of theNations Bridges. Publication No. FHWA-PD-96-001, 1995.

    SCDOT Bridge Design Manual, 2006.

    Underwater Inspection of Bridges, Publication No. FHWA-DP-80-1, 1989.

    AASHTO Guide for Commonly Recognized (CoRe) Structural Elements, 1997.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    25/76

    Appendix B

    Photographs

  • 8/9/2019 US 278 Cursory Bridge Inspection

    26/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 1. View of Downstream Fascia, US 278 WBL over MacKay Creek.

    Photograph 2. View of Upstream Fascia, US 278 WBL over MacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    27/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 3. View of the Main Steel Girder Span, US 278 WBL over MacKay Creek.

    Photograph 4. Typical Underdeck and Prestressed Concrete Girder Condition, US 278WBL over MacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    28/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 5. View of Crack Located on the East Face of Bent 2, US 278 WBL overMacKay Creek.

    Photograph 6. Close Up View of the Crack Located on the East Face of Bent 2, US 278WBL over MacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    29/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 7. View of Spall Located on the Bottom of Bent 2, US 278 WBL over MacKayCreek.

    Photograph 8. View of Cracks with Rust Stains Located on the Southernmost Pileof Bent 2, US 278 WBL over MacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    30/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 9. View of West Embankment, US 278 WBL over MacKay Creek.

    Photograph 10. Typical Above Water Pile and Prestressed Concrete Girder Condition, US278 WBL over MacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    31/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 11. Typical Prestressed Concrete Girder and Pile Cap Condition,US 278 WBL over MacKay Creek.

    Photograph 12. Typical Below Water Pile Condition Showing Heavy Marine Growth, US278 WBL over Skull Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    32/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 13. View of the Downstream Fascia, US 278 EBL over MacKay Creek.

    Photograph 14. Typical View of Superficial Spalls due to Lack of Sufficient ConcreteCover over the Reinforcing Steel in the Diaphragm, US 278 EBL over MacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    33/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 15. Typical Spall Repair Located on Bottom of Reinforced Concrete Beam, US278 EBL over MacKay Creek.

    Photograph 16. Typical Bent with Longitudinally Battered Piles and Concrete PileJacket, US 278 EBL over MacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    34/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 17. Typical Bent with Transversely Battered Piles and Concrete Pile Jacket,US 278 EBL over MacKay Creek.

    Photograph 18. View of the Upstream Fascia, US 278 EBL over MacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    35/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 19. Typical Above Water Reinforced Concrete Pile Condition, US 278 EBLover MacKay Creek.

    Photograph 20. View of a Typical Retrofit Pile Cap, US 278 EBL over McKay Creek.

    Prestressed

    Concrete

    GirderBeam

    Saddle

    Reinforced

    Concrete

    Beam

  • 8/9/2019 US 278 Cursory Bridge Inspection

    36/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 21. Typical Concrete Encasement Condition, US 278 EBL over MacKay Creek.

    Photograph 22. Typical Underdeck and Reinforced Concrete Girder Condition, US 278EBL over MacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    37/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 23. Typical Main Span Steel Girder Condition, US 278 EBL over MacKayCreek.

    Photograph 24. Typical Cracks with Rust Stains on Reinforced Concrete Pile, US 278 EBLover MacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    38/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 25. 3 ft by 1 ft Spall on the Bottom of the Beam 6, Span 29, US 278 EBL overMacKay Creek.

    Photograph 26. 3 ft by 1 ft Spall on the Bottom of the Beam 6, Span 29, US 278 EBL overMacKay Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    39/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 27. View of the Upstream Fascia, US 278 WBL over Skull Creek.

    Photograph 28. View of Typical Exterior Girder Condition, US 278 WBL over Skull Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    40/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 29. View of Typical Interior Girder and Steel Cross Bracing Condition, US 278WBL and EBL over Skull Creek.

    Photograph 30. View of Typical Main Channel Pier Configuration, US 278 WBL over SkullCreek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    41/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 31. View of 2 ft long by 10 in Wide Spall Located on the East End of theConcrete Barrier, US 278 WBL over Skull Creek.

    Photograph 32. Typical Deck Joint Condition, US 278 WBL over Skull Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    42/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 33. Typical Condition of the Intermediate Piers with Cracks at the Bottom, US278 WBL over Skull Creek.

    Photograph 34. View of the Downstream Fascia, US 278 EBL over Skull Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    43/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 35. Typical Crack With Rust Stains Located on the Bottom of the Pile CapFooting for the Intermediate Piers, US 278 WBL over Skull Creek.

    Photograph 36. Typical Interior Girder and Steel Cross Bracing Condition, US 278 EBLover Skull Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    44/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 37. Typical Deck Condition, US 278 EBL over Skull Creek.

    Photograph 38. Typical Deck Joint Condition, US 278 EBL over Skull Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    45/76

    US 278 WBL and EBL

    Over MacKay and Skull Creek

    Collins Project No.6336-40Appendix B

    Photograph 39. Typical View of Intermediate Bents, US 278 EBL over Skull Creek.

    Photograph 40. Typical Shoreline Condition, US 278 WBL over Skull Creek.

  • 8/9/2019 US 278 Cursory Bridge Inspection

    46/76

    Appendix C

    SCDOT Reference Forms

  • 8/9/2019 US 278 Cursory Bridge Inspection

    47/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    48/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    49/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    50/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    51/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    52/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    53/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    54/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    55/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    56/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    57/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    58/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    59/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    60/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    61/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    62/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    63/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    64/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    65/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    66/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    67/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    68/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    69/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    70/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    71/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    72/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    73/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    74/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    75/76

  • 8/9/2019 US 278 Cursory Bridge Inspection

    76/76