user consideration on smrs regarding nuclear power plants
TRANSCRIPT
BADAN TENAGA NUKLIR NASIONAL / National Nuclear Energy Agency JL. KUNINGAN BARAT, MAMPANG PRAPATAN, JAKARTA 12710, TELPON: 5255213
Presented at INPRO Dialogue Forum on Nuclear Energy Innovative
10 – 14 October 2011, IAEA, Vienna, Austria
User Consideration on SMRs Regarding Nuclear
Power Plants Deployment in Indonesia
Adiwardojo
1. Introduction of Nuclear Power
• Indonesia has for a long period planned for the introduction of nuclear power.
• Act No 10 of 1997 on Nuclear Energy. This is the primary legislation in Indonesia
• Act No. 17 of 2007 on Long-Term National Development Plan of Indonesia for 2005 to 2025. This is the basis act of establishing long term commitment for the use of nuclear energy to meet national energy demand.
• Indonesia performed self-assessment on National Nuclear Infrastructure prior to Integrated Nuclear Infrastructure Review and IAEA-INIR mission was held in November 2009
• Action Plan Phase 2 status IFR have been prepared
Nuclear Infrastructure
Development Program (Nov 2009)
Phase 1
Consideration
before a decision to
launch a nuclear
power programme
is taken
Phase 2
Preparatory work
for the construction
of a NPP after a
policy decision has
been taken
Phase 3
Activities to
implement a first
NPP
Maintenance and
continuous
infrastructure
improvement
Pre Project Project Decision
Making Construction Operation/
decommissioning
Nulear power
option included
within the
national energy
strategy
Milestone 1
Ready to make a
knowledgeable
commitment to a nuclear
programme
Milestone 2
Ready to invite bids
for the first NPP
Milestone 3
Ready to commission and
operate the first NPP
10-15 years
Pres.Reg. 5/2006
Act. 17/2007
Feasibility study Bidding process Commissioning
Infr
astr
uctu
re
De
ve
lop
me
nt
Pro
gra
m
1st N
PP
Pro
ject
Status
NPP Dev
FOUNDATION PHYLOSOPHY
• APPLICATION AND
DEVELOPMENT IN
NUCLEAR SCIENCE &
TECHNOLOGY IS FOR
PEACEFUL USES ONLY
• SAFETY & SECURITY IS
THE PRIME
CONSIDERATION
• DEMAND DRIVEN AND
STAKEHOLDER
SATISFACTION
Energy Diversification
– Diversity primary energy use for power generation and reduce fossil fuel dependency (esp. Oil)
Energy Conservation
– Energy efficiency to reduce total domestic energy and electricity demand and increase added value
Environmental Protection
– Reduce SOx, NOx and Green-House-Gases emission to support sustainable development and minimize externalities
Energy Security and Climate Change Mitigation
THE NECESSITY OF NUCLEAR ENERGY
Electricity Production Cost
– Economically competitive and stabilize electricity tariff.
Acquiring of High-Tech Power Generation
– High Technology utilization will increase national industrial capacity
Note : Optimum Energy Mix with non-discriminative
and non-depletion to realize security of energy supply
and to mitigate climate change in order to support
national sustainable development
2. National Energy Policy
19
NATIONAL ENERGY POLICYNATIONAL ENERGY POLICY
SUPPLY SIDE
POLICY
SUPPLY SIDE
POLICY
DEMAND SIDE
POLICY
DEMAND SIDE
POLICY
SECURITY OF
SUPPLY
SECURITY OF
SUPPLY
SOCIETY
AWARENESS
SOCIETY
AWARENESS
ENERGY PRICEENERGY PRICE
PRODUCTION
EXPLORATION
PRODUCTION
EXPLORATION
CONSERVATION
(PRODUCTION
OPTIMIZING)
CONSERVATION
(PRODUCTION
OPTIMIZING)
DIRECT SUBSIDYDIRECT SUBSIDY
DIVERSIFICATIONDIVERSIFICATION
CONSERVATION
(EFFICIENCY)
CONSERVATION
(EFFICIENCY)
20
Natural Gas, 28.57%
Coal, 15.34%
Oil51.66%
Geothermal Power, 1.32%
Hydro Power, 3.11%
ENERGI MIX GOAL 2025ENERGI MIX GOAL 2025
OPTIMIZING
ENERGY
MANAGEMENT
National (Primary) Energy Mix
National (Primary) Energy Mix of 2025
(BaU Scenario)
PRESIDENTIAL REGULATION NO. 5 YEAR 2006PRESIDENTIAL REGULATION NO. 5 YEAR 2006
NATIONAL ENERGY POLICYNATIONAL ENERGY POLICY
Coal, 34.6%
Oil, 41.7%
Geothermal Power, 1.1%
Mini/micro Hydro Power, 0.1%
Power Plant, 1.9%
National Energy Mix 2025
(Presidential Regulation Scenario)
Coal, 33%
Natural Gas, 20.6%
Natural Gas,
30%
Geothermal Power, 5%
Biomass, Nuclear, Hydro
Solar Power, Wind Power,
5%
Oil, 20%
Biofuel, 5%
Coal Liquefaction, 2%
NRE,17%
22
Wind
New and Renewable
Energy
17%5%
5%
2%
5%
Biofuel
Geothermal
Other New and
Renewable Energy NuclearHydroSolar
CBM
Biomass
NEW AND RENEWABLE ENERGY DEVELOPMENTNEW AND RENEWABLE ENERGY DEVELOPMENT(In accordance with the Presidential Regulation No. 5/2006)
Coal Liquefaction
3. Summary of Tentative UC
Objective :
1. To Improve understanding between technology users
and holder by conveying users’ common needs to
technology holders and subsequently to consider
necessary actions together to fulfill the need.
2. To define common characteristics needed by
Indonesia for large and Medium as well as Small Scale
Nuclear Power Plants.
3. To develop group of User Criteria
Group of User Criteria :
1. High Level requirements According to National
Criteria for NPP.
2. Requirements Related to Fuel Cycle Options.
3. Requirements Related to Safety and Regulatory.
4. Requirements Related to Technology Transfers and
Human Resources Development.
5. Requirements for Small and Medium Scale of NPP.
3. Requirement and Concern
3.1. Requirements According to National Criteria for NPP.
1. Nuclear option is consider important from energy
security, environmental sustainability, diversification point of view and economically competitive.
2. Meet the best safety standards at time of deployment.
3. NPP system must be proven.
4. Electricity generation cost from NPP must be lower than that from other energy sources in the same region.
5. Improve national capability in technology know-how, gradually increase in national participation on step by step basis.
3.2. Requirements Related to Fuel Cycle
Options.
1. Assurance of fuel supply at reasonable cost is very
much concern. In general all fuel cycle options (except
for closed fuel cycles) are open for consideration at
this time.
2. Strong commitment to IAEA’s guideline on safeguard.
3. 1st core fuel provided by vendor and reloads possibly
provided by domestic supplier.
4. Management of spent fuel needs to be handled
carefully based on best international practice.
3.3. Requirements Related to Safety & Regulatory
1. Design of NPP satisfies the design proveness requirement.
2. Meet the best safety standards and should follow the best safety analysis approach / method at time deployment.
3. Must comply with national regulation, country of origin and IAEA safety standards.
4. Passive safety system are believed to provide better safety without increase in cost. Passive safety system are therefore preferred but only proven ones can be incorporated.
3.4. Requirement Related to Technology
Transfer & HRD
1. Technology transfer/training is required to achieve
understanding in design, manufacturing, operation,
maintenance, safety analysis, licensing etc.
2. Participation by domestic company in civil work to start
from the 1st unit. local participation for subsequent
units will increase gradually.
Note :
25 % local participation in 1st two units.
40 % local participation in next 4 units.
• Power ranging from Small to Medium (should not exceed 5-10% of the grid capacity) especially for outside Java Island
• Meet legal requirement (National and International)
• Simple and proven technology.
• Significant participation of the local industry during construction and assured local technology and supply for operation and maintenance.
• Small number of qualified manpower for operation and maintenance.
• SMR for coogeneration.
General User Requirement
3.5. Requirements for Small and Medium
Sized NPP
• Use low enrichment uranium and open fuel cycle
• Defence in Depth and multi barriers approach for safety, security and safeguards.
• Inherent and passive safety feature and passive systems incorporated in the design
• Assurance of reliable fuel supply
• Financial support ( Non conventional Financial Scheme ).
• Etc .
Integrated R&D activities on Advanced Reactor : To
master of the reactor technology in line with the
development of advaced reactor in the world.
UNIVERSITIES :
- ITB : Pb-Bi Cooled Reactor
- UGM : Molten Salt Reactor
BATAN : High Temperature Gas Cooled Reactor.
4. Nuclear Energy Innovations
Development in Indonesia
• IFAR will promote national and international cooperation
for Innovative Nuclear Energy System (INS)
development and deployment ( Universities, BATAN,
IAEA ).
• IFAR will also provide a forum where experts and policy
makers can discuss technical and social aspect of
nuclear energy as well as the development and
deployment of INS in the future
• Indonesia as one of International Project on Innovative
Nuclear Reactor and Fuel Cycles (INPRO) Members,
continue to support the IAEA’s INPRO activities to meet
the global energy demand and promote sustainable
economic and social development.
Small & Medium-Sized NPP in Indonesia
Nuclear option is consider importance from energy security, environment sustainability, diversification point of view and economically competitive.
Meet the legal requirements ( national & international ) and technical requirements ( meet the best safety, security and safeguards standards at time of deployment ).
5. General Conclusion
It will be utilized not only for electricity generation but also for the following application : Sea water desalination, Coal Liquefaction, Hydrogen production and Steam for enhanced oil recovery.
It must be proven and meet local grid size and economic requirement ( electricity generation cost from NPP must be lower than that from other energy sources in the same region ).
Easy to construct, operate, maintenance and improve national capability in technology know how, gradually increase in national participation on step by step basis.
Flexible financing arrangement ( soft loan and vendor participation in the investment ).
Requirements for Small NPP in Smaller Grid.
30
MAJOR POWER PLANTS AND ELECTRICITY GRIDSMAJOR POWER PLANTS AND ELECTRICITY GRIDS
Existing Transmission
Planned Transmission
Power Plant
Grissik Palembang
Semarang
Pacific Ocean
AUSTRALIA
Indian Ocean
Bangkok
Phnom
Penh
Ban Mabtapud
Ho Chi
Minh City
CAMBODIA
VIETNAM
THAILAND LAOS
Khanon
Songkhla
Erawan
Bangkot
LawitJerneh
WEST
MALAYSIA
Penang
Kerteh
Kuala
Lumpur
Manila
Philipines
South
China
Sea
NatunaAlpha
Kota KinibaluBRUNEI
Bandara Seri
Begawan
Bintulu
EASTMALAYSIA
Kuching
Banda Aceh
Lhokseumawe
Medan
Duri
Padang
S U M
A T
R A Jambi
BintanSINGAPORE
Samarinda
Balikpapan
Bontang
Attaka
TunuBekapai
KALIMANTAN
Banjarmasin
Manado
SULAWESI
UjungPandang
BURU SERAM
Ternate HALMAHERA
Sorong
PAPUA
JakartaJ A V A
Surabaya
Bangkalan
BALI SUMBAWA
Pagerungan
LOMBOK
FLORES
SUMBATIMOR
I N D O N E S I A
Duyong
West Natuna
Port Dickson
Port Klang
Mogpu
Dumai
Batam
Guntong
MADURA
TOTALCAPACITY
24,000 MW
Total Java-Bali : 18,500 MW
Total Sumatera : 3,200 MW
Total Kalimantan : 800 MW
Total Sulawesi : 650 MWJayapura
Merauke