USER MANUAL APPLICATION FOR EXTENSION OF TIME 1. Choose Project 2. Click New Application

Upload: others

Post on 10-Feb-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

USER MANUAL

APPLICATION FOR EXTENSION OF TIME

1. Choose Project

2. Click New Application

Page 2: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

Project

Information

Choose Extension

Month. Enter

Start date,

justification and

click Calculate End

Date button. View

Progress Report

button will be

disabled if you

haven’t submit a

Progress Report Click Button

to Submit

Please complete Progress Report

before submitting application for

Extension

Click Application to View Application

Page 3: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

Review by Secretariat

Click reference no to view application

Complete

information

and click

Submit button

to submit to

secretariat

Complete remarks

and click Submit to

end application for

Director’s approval

Page 4: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

Approval by PPPI

Choose approval

status and extension

number

Approval

months and

new end date

Add remarks

and click

submit

Page 5: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

APPLICATION FOR CHANGE OF SCOPE 1. Applicant View

1. Choose project

2. Click New Application

Page 6: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

2. APPROVER VIEW

Complete

current scope,

new scope and

justification

If necessary,

upload files

To save as draft, click

Save. Click Submit to

submit the form to

PPPI

Page 7: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

Choose approval

status and remarks.

Click Submit button

to submit.

Page 8: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

APPLICATION FOR CHANGE OF PROJECT MEMBER

Click New Application

Choose project

1. Choose one of the

option: Add new

project member or

remove current

project member

2. Click Next

Page 9: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

Complete the

researcher’s

information

Choose internal

or external

researchers

Choose Remove Current

Project members and

click Next

Click Select

Select End Date and

Enter remarks

Click Remove

Member

Page 10: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be
Page 11: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

PROGRESS / FINAL REPORT 1.

2.

3.

Page 12: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

4. For outside grant, have to enter milestone

5. Project Information

Page 13: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

6. Human capital

Page 14: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

7. Budget

8. Research Activities

Click Upload to

upload relevant

document

Page 15: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

9. Publication

10. Intellectual property

Page 16: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

11. Asset

12. Progress Summary

13. Upload related documents

14. Declaration

Page 17: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

15. Status updated

2. HOD VIEW

Page 18: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be

3. PPPI DIRECTOR VIEW

Page 19: USER MANUAL - ums.edu.myProject Information Choose Extension Month. Enter Start date, justification and click Calculate End Date button. View Progress Report button will be