Using Integrated Asset Management System to perform Corridor-Level Analysis Jim Edgerton AgileAssets Inc. September 30, 2014

Upload: phungdien

Post on 21-Aug-2019

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Using Integrated Asset Management System to perform Corridor-Level Analysis

Jim EdgertonAgileAssets Inc.

September 30, 2014

Page 2: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Acknowledgements

Neil Mastin, P.E.Pavement Program Analyst, Pavement Management Unit (PMU), NCDOT

Cary ClemmonsBridge Program Analyst, Bridge Management Unit (BMU), NCDOT

Charles Pilson, P.E., Ph.D.Senior Principal Consultant, AgileAssets

Abhishek Bhargava, Ph.D.Product Technical Manager, AgileAssets

Page 3: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

• If we can predict what is going to happen under a number of scenarios, we can:– Prepare for any specific scenario– Try to influence what scenario actually plays

out

If you can Model it – you can Manage it…

Page 4: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

AgileAssets Product Portfolio

AgileAssetsTrade-Off AnalystTM

Analysis Across ProgramsAnd Asset Types

AgileAssetsCore System Foundation

AgileAssetsAnalyst Products

Bridge Analyst™

Pavement Analyst™

Safety Analyst™

Mobility Analyst™

AgileAssetsManager Products

Maintenance Manager™ Bridge Inspector™

FacilitiesManager™

Fleet &EquipmentManager™

Sign & Signal Manager™

Right of Way Manager™

ITS-Telecom

Manager™

System Foundation(Configuration, GIS, Reporting, etc.)) Network Manager

Mobile Device Applications

(FDC, PDAs, Tablets)

Product Portfolio

Page 5: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Trade-off Individually Optimum Candidate Scenarios

• Where do the candidate projects come from?• Optimized scenarios from different program

areas representing different high level objectives

Trade-offAnalysis

Pavement Management

System

Bridge Management

System

Other Systems…

Page 6: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

• Each program area contributes a set of optimum scenarios

• These are combined to be able to analyze the trade-offs

Trade-off Individually Optimum Candidate Scenarios

Pavement Management

System

Bridge Management

System

Other Systems…

Trade-offAnalysis

Page 7: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Are We Utilizing Funds Optimally ?Compare Points on Efficient Frontier

Page 8: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

• Bridge & Pavement Management Systems– Inputs:

• Centralized Inventory & Condition Database• Decision Trees• Performance / Deterioration Models

– Methodology• Multi-Objective, Multi-Criteria Optimization Analysis

– Output• Project Level Life-Cycle Report• Network Level Investment and Funding Strategy• Forecasted Condition at Network-Level & Project-Level • Comparative Analysis of Investment Strategies

So far, Individual Asset Networks have been Analyzed

Background

Page 9: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Background

Page 10: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

– Network: I-40 Corridor– Objective:

• Identify Optimal Pavement & Bridge Projects (25 Years)– Optimal =

» Maximize Bridge and Pavement Condition» Meet Budget Constraints» Achieve System Optimal Solution

• Prepare Implementation Schedule and Re-evaluate System Optimal (5-Year Plan)

– Do Bridge & Pavement Projects together where possible, when at a given location on the corridor

– Estimate Traffic Control & Mobilization Cost Savings

NC: I-40 Corridor Analysis

Page 11: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

• Step 1: Define Network & Identify Pavements & Bridges in Network

• Step 2: Run Range of Candidate “Scenarios” in BMS, PMS

• Step 3: Develop Efficient Frontier to Analyze Scenario Combinations

• Step 4: Identify Preferred System Optimal Solution

• Step 5: Prepare Implementation Work Plan & Re-Evaluate Optimality

Tradeoff Analysis Methodology

Page 12: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

576 Sections288 Bridges872 Lane-Miles18 Counties8 Divisions

Step 1: Define I-40 CorridorIdentify Pavement Sections & Bridges on I-40 Corridor

Page 13: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

PMS- PAVEMENT MANAGEMENT

SYSTEM

BMS-BRIDGE MANAGEMENT

SYSTEM

TradeoffSystem

Step 2: Run I-40 Corridor BMS & PMS Scenarios

Page 14: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Step 2: Run I-40 Corridor BMS & PMS Scenarios

Multi-Constraint, Multi-Objective, Multi-Criteria Optimization Analysis

Page 15: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Step 3: Develop Efficient Frontier to Analyze I-40 Scenario Combinations

$9 M ~ Do Nothing

Current LOS: 88.6

I-40 PMS Scenario - $30M / YearI-40 BMS Scenario - $30M / YearTotal Expenditure: $255 M (5 Years)Resulting Network LOS: 89.13Current LOS: 88.6

Page 16: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Step 4: Identify and Analyze System Optimal Work Plan

Plan YearBMS

PreservationBMS

RehabilitationBMS

ReplacementPMS Interstate Maintenance

PMS Reconstruction

PMS Rehabilitation

Grand Total

1 745 14 38 17 8142 3 4 28 25 603 99 2 23 1 18 1434 593 180 7735 113 91 1 5 210

Grand Total 1553 14 6 360 2 65 2000

5-Year PlanAnalyze Bridge & Pavement Project Schedules & Locations on

Map

Page 17: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Step 5: Compare Multiple I-40 BMS-PMS Super-Scenario(s)

Evaluate Impact on Bridge, Pavement and Overall System

Page 18: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Step 5: Re-Evaluate System Optimal After Adjusting Implementation Schedule

• Optimal Solution – Based on Efficient Frontier– Implementation Schedules Not Coordinated

• Implementation Alternative 1– Coordinated Bridge Preservation and Pavement Maintenance Activities– Estimated Traffic Control & Mobilization Cost Savings (0.3%)

• Implementation Alternative 2– Coordinated Bridge Rehabilitation / Replacement and Pavement Rehabilitation /

Reconstruction Activities– Estimated Traffic Control & Mobilization Cost Savings (2.7%)

• Implementation Alternative 3– Coordinated All Possible Bridge and Pavement Activities– Estimated Traffic Control & Mobilization Cost Savings (4.3%)

Page 19: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

87.4

87.6

87.8

88

88.2

88.4

88.6

88.8

89

242 244 246 248 250 252 254 256

Net

wor

k He

alth

Sco

re (U

tility

)

Total 5-Year Planned Cost ($ Millions)

Step 5: Re-Evaluate System Optimal After Adjusting Implementation Schedule

Optimal

Implementation Alternative 3

Implementation Alternative 2

Implementation Alternative 1

Page 20: Using Integrated Asset Management System to perform ... · Using Integrated Asset Management System . to perform Corridor -Level Analysis . Jim Edgerton AgileAssets Inc. September

Jim [email protected]

(919) 573-5219

Questions?