USIT Bow Hill Road, WA PROJECT HIGHLIGHTS Commissioned May, 2011 Commercial WW, Greenfield Permit(s); Not Required 8/NA/0.3 (TN/TP/Turbidity) Casino, Resort, Truck Stop Injection Well to Aquifer MMF Capacity: 0.2 MGD $22.5/gal 0.5 FTE (Full-Time Employees) PROJECT OVERVIEW System Type(s): Previous Facility Type: Owner: Engineer: Contractor: Operations: Delivery Method: Time To Build: Total Installed Project Cost: Plant Contact Information: Ovivo ® MBR, MBT None Upper Skagit Indian Tribe Wilson Engineering, LLC. Colacurcio, McClure & Sons, Express Electric Water & Wastewater Services Pre-Selection 7 months $4,500,000 Brian Walker | [email protected] “ Working with Ovivo has been a great experience. We appreciate Ovivo’s team approach to design and construction. ” - Jeff Christener © Copyright 2015 Ovivo Inc. All rights reserved ®

Upload: rahul-thukral-pe

Post on 10-Apr-2017

29 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: USIT_ Ovivo MBR

USIT Bow Hill Road, WA

PROJECTHIGHLIGHTS

•Commissioned May, 2011

•Commercial WW, Green�eld

•Permit(s); Not Required

• 8/NA/0.3 (TN/TP/Turbidity)

•Casino, Resort, Truck Stop Injection Well to Aquifer

•MMF Capacity: 0.2 MGD

•$22.5/gal

•0.5 FTE (Full-Time Employees)

PROJECT OVERVIEWSystem Type(s):

Previous Facility Type:

Owner:

Engineer:

Contractor:

Operations:

Delivery Method:

Time To Build:

Total Installed Project Cost:

Plant Contact Information:

Ovivo ® MBR, MBT

None

Upper Skagit Indian Tribe

Wilson Engineering, LLC.

Colacurcio, McClure & Sons, Express Electric

Water & Wastewater Services

Pre-Selection

7 months

$4,500,000

Brian Walker | [email protected]

“ Working with Ovivo has been a great experience. We appreciate Ovivo’s team approach to design and construction. ”

- Jeff Christener

© Copyright 2015 Ovivo Inc. All rights reserved

™®

Page 2: USIT_ Ovivo MBR

DESCRIPTIONConsidering the high quality wastewater treatment and ease of expandability fundamental to the growth and development of the reservation, the Upper Skagit Indian Tribe commissioned the new MBR plant in May 2011. Constructed in a short span of 7 months, the plant is presently handling flows from the tribe’s Resort and is equipped to service also the future expansions including golf course, shopping complex and an additional hotel. As the discharge is going to a ground water aquifer, it has been successfully determined that the effluent quality from the MBR has been meeting all primary drinking water standards.

PLANT DESIGN INFORMATIONFine Screen Type :

Aperture or Slot Size :

Supplemental Aeration Technology :

MBR Blower Type :

Solids Management Data :

SCADA System :

Disinfection Method :

# Process Stages :

Drum Screen

3 mm

Fine Bubble, Disks

Positive Displacement

Membrane Thickening

Wonderware

UV

3

MBR (MEMBRANE ZONE) DESIGNFiltration Mode:

# of Reactors:

Submerged Membrane Unit (SMU):

# SMU:

Design Flux (MMF):

Minimum Temperature:

Peak Factor: