ut final project
TRANSCRIPT
-
7/31/2019 Ut Final Project
1/35
I. INDRODUCTION
In this project, the students were asked to design a 3 phase low voltage distribution for two
double storey houses. Apart from that designing, members of the group also have learnt how to
balance the needs of consumers and providers of energy in order to ensure safe and reliable
supply.
The low voltage distribution system of this project consists of loads, cables, proactive device
and distribution boxes. The main objective of this project is to draw a single line diagram design
and this design layout of each floor of the two houses was presented in this project. In this task
each group was given the permission to choose the electrical loads of their houses; the estimation
electrical load values in this design were given in the calculation parts of this project, this was to
make sure that the work of each group must be different than the works of the other groups.
For the best results in electrical installation design and LV distribution requires a study of a
proposed electrical installation that requires an adequate understanding of all governing rules and
regulations. The total power demand can be calculated from the data relative to the location and
power of each load, together with the knowledge of the operating modes (steady state demand,
starting conditions, non simultaneous operation, etc.).
From these data, the power required from the supply source and (where appropriate) the
number of sources necessary for an adequate supply to the installation is readily obtained. Local
information regarding tariff structures is also required to allow the best choice of connection
arrangement to the power-supply network, e.g. at medium voltage or low voltage level.
The whole installation distribution network is studied as a complete system. The distribution
equipment (panel boards, switchgears, circuit connections ...) are determined from building plans
and from the location and grouping of loads. The type of premises and allocation can influence
their immunity to external disturbances.
-
7/31/2019 Ut Final Project
2/35
This dissertation consists of four main parts. First part is an introduction; which describes the
electrical structure and loadings for the LV distribution system. Second part is the calculation
part; this explains all the methods applied in calculating the connected load, maximum demand
and cable sizes. Third part is the discussion and analyses of the results obtained in this project.
Last part is the appendices, this part is used to show all the calculations and schematic diagrams
since the technical report pages are limited.
II. CALCULATIONSHOUSE TYPE C
A) TYPE: HOUSE C GROUND FLOOR
Table1 shows the number of Nos in each load connected to the ground floor
TABLE 1: Ground floor loads
Load Nos Estimated power
(W)
Total Power (W)
Down light 13 100 1300
Ceiling fan 2 60 120
Wall light 2 100 200Wall fan point 1 60 60
Water heater point 1 1000 1000
1X13A S/S/0(300mm.A.F.F.L)
7 250 1750
1X13A weather proofS/S/0
2 250 500
2 X13A S/S/0(300mm.A.F.F.L)
2 250*2 1000
1X13A S/S/0 atkitchen and yard
(1500mm A.F.F.L)
4 250 1000
1X15A S/S/0 at
kitchen (1500mm
A.F.F.L)
3 500 1500
15A S/S/O AIR
COND POINT
2 746 1492
TOTAL CONNECTED LOAD 9922
-
7/31/2019 Ut Final Project
3/35
PMD=PCL x DF
Assume DF=65%x
PMD= 9922W x 0.65 = 6448W
cos3
,3For
)(
LLMDVIP
MD
AV
WI
MD11
85.04003
6488)(3
AV
WI
MD84.32
85.0231
6448)(1
(PLEASE REFER TO APPENDIX A, FOR THE FORMULAE AND LINE CURRENT
CALCULATIONS)
Line Total load per line Current
(A)
Cable size Circuit
breaker
Current (A)
R1 4 NOS DOWNLIGHT+ I NOS CEILING FAN 2.3 2 x 1.5mm ) PVC
cable6
B1 4 DOWN LIGHT + I NOS CEILING FAN + WALL
LIGHT
2.82 2 x 1.5mm ) PVC
cable6
Y1 5 NOS DOWN LIGHT+I NOS WALL FANPOINT+1NOS WALL LIGHT
3.36 2 x 1.5mm ) PVCcable
6
R8 I NOS 15A S/S/0 AIR COND POINT 3.8 2 x 4.0mm ) PVC 20
B7 I NOS 15A S/S/O AIR COND POINT 3.8 2 x 4.0mm ) PVC 20
Y8 I NOS WATER HEATER 15A S/S/O 5.1 2 x 4.0mm ) PVC 20
B2 2 NOS 1X13A S/S/O (300MM.AF.F.L) 2.55 2 x 2.5mm ) PVC 20A
B3 2 NOS 1X 13A S/S/O AT KITCHEN AND YARD
(1500mm A.F.F.L)
2.55 2 x 2.5mm ) PVC 20A
B4 1 NOS 1X13A weather proof S/S/0 + 1X13A
S/S/0 (300mm.A.F.F.L)
2.55 2 x 2.5mm ) PVC 20A
B5 1NOS 1X13A S/S/O (300MM.AF.F.L) 1.27 2 x 2.5mm ) PVC 20A
B6 1NOS 1X15A S/S/0 at kitchen (1500mmA.F.F.L)
2.55 2 x 2.5mm ) PVC 20A
R3 I NOS 1X13A S/S/0 (300mm.A.F.F.L) + I NOS
1X13A S/S/0 at kitchen and yard (1500mm
A.F.F.L)
2.55 2 x 2.5mm ) PVC 20A
R4 1 NOS 1X13A S/S/0 (300mm.A.F.F.L) 1.27 2 x 2.5mm ) PVC 20A
R5 1 NOS 2 X13A S/S/0 (300mm.A.F.F.L) 2.55 2 x 2.5mm ) PVC 20A
R7 1NOS 1X15A S/S/0 at kitchen (1500mm 2.55 2 x 2.5mm ) PVC 20A
-
7/31/2019 Ut Final Project
4/35
A.F.F.L)
Y3 I NOS 1X13A S/S/0 at kitchen and yard(1500mm A.F.F.L) + 1NOS 1X15A S/S/0 at
kitchen (1500mm A.F.F.L)
3.8 2 x 2.5mm ) PVC 20A
Y4 1 NOS 1X13A weather proof S/S/0 + 1NOS
1X13A S/S/O (300MM.AF.F.L)
2.55 2 x 2.5mm ) PVC 20A
Y5 1 NOS 2 X13A S/S/0 (300mm.A.F.F.L) 2.55 2 x 2.5mm ) PVC 20A
Y7 1NOS 1X15A S/S/0 at kitchen (1500mm
A.F.F.L)
2.55 2 x 2.5mm ) PVC 20A
(PLEASE REFER TO APPENDIX E, FOR THE SCHEMATIC DIAGRAM OF THE
GROUND FLOOR)
B) TYPE: HOUSE C FIRST FLOORTable2 shows the number of Nos in each load connected to the ground floor
TABLE 2: LOADS IN FIRST FLOOR
PMD=PCL x DF
Assume DF=65%x
PMD = 9528W x 0.65 = 6193.2W
No Load Item No. NOS Estimate
Power (W)Total Power
(W)
1 Down Light 12 100 1200
2 Ceiling Fan 4 60 240
3 Wall Light 1 100 100
4 1x13A S/S/0 (300mm A.F.F.L) 5 250 1250
5 2x13A S/S/O (300mm
A.F.F.L)
3 250*2 1500
6 15A S/S/O Air Cond Point 3 746 2238
7 15A S/S/O Water Heater point 3 1000 3000
8 Total Connected load 9528
-
7/31/2019 Ut Final Project
5/35
cos3
,3For
)(
LLMDVIP
MD
A
V
WI
MD52.10
85.04003
6193.2)(3
cos
,1For
)(1 VIP
MDMD
AV
WI
MD54.31
85.0231
6193.2)(1
The table below shows the calculated current for each line (per phase) and the preferred
circuit breaker with the cable size of type C fist floor.
(PLEASE REFER TO APPENDIX B, FOR THE FORMULAE AND LINE CURRENT
CALCULATIONS)
LINE TOTAL NOS CONNECTED CURRENT (A) CABLE SIZE Circuit breaker(A)
R 1 (3 Nos down lighting +1nos wall lighting +1 Nos
ceiling fan)
2.342 x 1.5mm ) PVC
cable
6
Y1 4 Nos down lighting +2
Nos ceiling fan
2.65 2 x 1.5mm ) PVC
cable
6
B1 5 Nos down lighing +1
Nos ceiling fan
2.85 2 x 1.5mm ) PVC
cable
6
R 6 1 Nos air condition with
double poles switch
3.80 2 x 4.0mm ) PVC 20
Y6 1 Nos air condition with
double poles switch
3.80 2 x 4.0mm ) PVC 20
B6 1 Nos air condition with
double poles switch
3.80 2 x 4.0mm ) PVC 20
R7 1 NOS water heater with
Double
5.09 2 x 4.0mm ) PVC 20
Y7 1 Nos water heater with
double poles switch
5.09 2 x 4.0mm ) PVC 20
-
7/31/2019 Ut Final Project
6/35
(PLEASE REFER TO APPENDIX F, FOR THE SCHEMATIC DIAGRAM OF THE
FIRST FLOOR OF HOUSE TYPE C)
C) TYPE: HOUSE C2 Ground FloorThe table 3below shows the loads and number of Nos connected to the ground floor
Table 3: loads connected to the ground floor in c2
PMD=PCL x DF
B7 1 NOS water heater with
Double
5.09 2 x 4.0mm ) PVC 20
B2 2 NOS 1x13A S/S/O 2.54 2 x 2.5mm ) PVC 20
Y3 1 NOS 1x13A S/S/O 2.54 2 x 2.5mm ) PVC 16
B3 1 NOS 2x13A S/S/O 2.54 2 x 2.5mm ) PVC 20
R3 2 NOS 1x13A S/S/O 2.54 2 x 2.5mm ) PVC 20
Y4 1 NOS 2x13A S/S/O 2.54 2 x 2.5mm ) PVC 20
B4 1 NOS 2x13A S/S/O 2.54 2 x 2.5mm ) PVC 20
No Load Item No. NOS Estimate Power(W)
Total Power(W)
1 Down Light 14 100 1400
2 Ceiling Fan 2 60 120
3 Wall Light 2 100 200
4 1x13A S/S/0 (300mm
A.F.F.L)
7 250 1750
5 2x13A S/S/O (300mm
A.F.F.L)
2 250*2 1000
6 15A S/S/O Air Cond Point 2 746 1492
7 1x13A S/S/O Wether proof 2 250 500
8 1x13A S/S/O at kitchen 4 250 1000
9 1x15A S/S/O at kitchen 3 500 1500
10 15A S/S/O water heater point 1 1000 1000
11 Total connected Load 9962
-
7/31/2019 Ut Final Project
7/35
Assume DF=60%x
PMD= 9962W x 0.60 = 5977.2W
cos3
,3For
)( LLMD VIP MD
A
V
WI
MD15.10
85.04003
5997.2)(3
cos
,1For
)(1 VIP
MDMD
AV
WIMD
54.3085.0231
597.2)(1
The table below shows the calculated current for each line (per phase) and the preferred circuit
breaker with the cable size of type C2 ground floor.
(PLEASE REFER TO APPENDIX C, FOR THE FORMULAE AND LINE CURRENT
CALCULATIONS)
(PLEASE REFER TO APPENDIX G, FOR THE SCHEMATIC DIAGRAM OF THE
GROUND FLOOR OF HOUSE TYPE C2)
LINE TOTAL NOS
CONNECTED
CURRENT (A) CABLE SIZE
R 1 5 No of down light
and 1 No of fan
2.85 2 x 1.5mm ) PVC
cable
Y1 1 No of wall light,5No of down light and
1 No of fan
3.36 2 x 1.5mm ) PVCcable
B1 1 No of wall
light,54No of down
light
2.54 2 x 1.5mm ) PVC
cable
Y4 water heater point 5.9 2 x 4.0mm ) PVC
B7 Air condition point 3.4 2 x 4.0mm ) PVC
13A S/S/O 2.54 2 x 2.5mm ) PVC
15A S/S/O 7.63 2 x 2.5mm ) PVC
-
7/31/2019 Ut Final Project
8/35
D) TYPE: HOUSE C2 First FloorThe table4below shows the loads and number of Nos connected to the ground floor
Table 4: loads connected to first floor in c2
PMD=PCL x DF
Assume DF=60%x
PMD= 9678W x 0.60 = 5806.8W
cos3
,3For
)(
LLMDVIP
MD
AV
WI
MD5.9
85.04003
5806.8)(3
No Load Item No. NOS Estimate Power(W)
Total Power
(W)
1 Down Light 11 100 1400
2 Ceiling Fan 4 60 120
3 Wall Light 1 100 200
4 Water heater point 3 1000 3000
4 113A s/s/o 6 250 1500
5 213A s/s/o 3 500 1500
6 15A s/s/o 3 746 2238
7 Total connected Load 9678w
-
7/31/2019 Ut Final Project
9/35
AV
WI
MD57.29
85.0231
5806.8)(1
The table below shows the calculated current for each line (per phase) and the preferred
circuit breaker with the cable size of type C2 fist floor.
(PLEASE REFER TO APPENDIX D, FOR THE FORMULAE AND LINE CURRENT
CALCULATIONS)
(PLEASE REFER TO APPENDIX H, FOR THE SCHEMATIC DIAGRAM OF THE
FIRST FLOOR OF HOUSE TYPE C2)
III. DISCUSION AND ANALYSIS
A) DISCUSION
In this project the students were asked to draw the schematic diagrams of two types of
houses; which are house type C and house type C2. Each house consists of two parts which are
LINE TOTAL NOS
CONNECTED
CURRENT (A) CABLE SIZE Circuit beaker
R 1 (3 Nos down
lighting +1 noswall lighting +1
Nos ceiling fan)
2.32 x 1.5mm )
PVC cable
6A
Y1 4 Nos down
lighting +2 Nos
ceiling fan
2.65 2 x 1.5mm )
PVC cable
6A
B1 4 Nos down
lighing +1 Nosceiling fan
2.34 2 x 1.5mm )
PVC cable
6A
R6 1 Nos water heaterwith double poles
switch
5.1 2 x 4.0mm )
PVC
20A
R7 1 Nos air
condition with
double polesswitch
3.8 2 x 4.0mm )
PVC
20A
-
7/31/2019 Ut Final Project
10/35
ground floor and first floor. There were seven members in the group; four of them were given to
design house type c while the other three were given to design house type c2.
To achieve the objectives of the project; members counted all the numbers of Nos in each
floor according to the task division of the group. An estimated power was chosen for each load asstated in section II (calculation part). In house C demand factor of 65% was chosen while house
C2 60% of demand factor was chosen. The total connected load of each floor was calculated and
then the demand factor was obtained by using relevant formula as shown in the calculation part.
The number of nos in each line were counted in order to obtain the current in each line of
the four floors. As result of line current, then the current of each circuit breaker was obtained
according to the standard and safety regulations. In addition to that, the cable size was
determined.
There are two types of cables that available in the market, which are copper wire and
alloy aluminium cable. In this project, a copper wire was chosen because copper cable is
recognized as high quality product and it is good conductor compare to aluminium , copper has
greater tensile strength compare to aluminium, even though aluminium is electricity conductive.
The group members have discussed the type of miniature circuit breaker to use, they have
agreed upon to choose a suitable one by considering the load and overload current. MCB is
divided into two; which are domestic and commercial types. In this project, domestic one was
chosen because of its general use of residential purposes.
Heavy load such as air conditional and water heater, was assigned to own a separate
MCB, due to their high load and high overload current, there for, they require high load power
supply, which may spoil other equipment if combine with other appliance that has lower load
current or lower power supply. Similar to socket, the socket which provide to high load appliance
will also has their own MCB, similar load appliance will has similar load current and power
supply, when over current or short circuit occur, the MCB able to protect the cable and
equipment if the MCB use is in suitable current rating.
-
7/31/2019 Ut Final Project
11/35
Two different demand factors were estimated due to make comparison between the
maximum demands of each floor. House C was given 65% demand while 60% demand factor
was given house type C2. This estimation has shown that when the demand factor is high themaximum demand becomes also high. Hence ground floor of house type C has higher maximum
demand than the ground floor of house type C2. However, there is also total connected load
which is another factor that affects the maximum demand of the floor; higher connected gives
higher maximum demand and vice versa.
B) ANALYSIS
1) House type C
The total connected load, maximum demand, and line currents were obtained by using
relevant formulae. The total power consumption in the ground floor is 9922w while the first floor
is 9528w. it can be seen clearly, that the ground floor consumed huge power compare to first
floor, this is because the kitchen in the ground floor has additional sockets that require bulk of
power.
At the side of voltage drop, line of R7, Y8, and B6 in the ground floor can show the
highest voltage drop, because these lines has sockets such as 1x15A S/S/O at the Kichen, 15A
S/S/O water heater point, and generally these loads are called heavy loads since they consume
huge power.
In this house, demand factor of 65% was estimated in order to compare with the other
house of type c which its demand factor was estimated as 60%. Since the demand factor is 65%
for house, the maximum demand was obtained by using formula as shown in section II. Hence,
the maximum demand of ground and first floors are 6448W and 6193.2W respectively.
Maximum demand of the ground floor is higher than the first floor although they have the same
demand factor, this is due to the total connected load of the ground floor is higher than that of the
first floor.
-
7/31/2019 Ut Final Project
12/35
2) House type C2
Same as house type C, the ground floor of house C2 has higher power
consumption than the first floor. This is due to that the ground floor was equipped with
more kitchen sockets and appliances which consumed more power. This can be seen from
the total connected load of the ground floor which is 9962, while the total connected of
the first floor is 9678.
Although the floors of this house have higher total connected loads compare to
their respective floors in house type C, but the maximum demand of the ground floor of
house C2 is lower than that of the house type C ground floor, and the same goes to the
first floor. This is due to the demand factor, because the demand factor of house type C is
higher than that of house type C2 as shown in the calculation part.
3) As generally
To chose the correct rating of circuit breaker we have to determine the current requirements for
each line, which also enables us to chose the correct cable size in order to not to affect the cost
as well. This current is known as Design current, either specified by the manufacturer or can be
calculated by the formulae.
cos
,1currentlineFor
1 VIP
For current calculation in each line refer appendix A85.0231
1
V
PI
-
7/31/2019 Ut Final Project
13/35
For all floors of both type of houses, the lights, fans and bell are used ( 2 x 1.5mm ) PVC
cable. For the installations of air conditioners, water heater and spare are used ( 2 x 4.0mm )
PVC cable while the socket outlet 13A is use ( 2 x 2.5mm ) and ( 2 x 4.0mm ) PVC cable ring
type. Using ring type is intended to save the use of protective fuse. Each cable is installed using a
conduit in the wall constructions. All the wiring has installations of fuse to give protections and
this fuse is accordance to the standards. For the light, fan and bell, the used fuse is 6A and for the
water heater, air conditioner and spare, the used fuse is 20A except for wiring socket outlet ( 2 x
2.5mm ) PVC cable. But for the socket outlet ( 2 x 4.0mm ) PVC cable, the used fuse is 32A.
Starting from TNB supply, cut-off fuse is installed before the meter KWH. A protection begins
with the installations of main switch 40A/60A and then divided into two parts. The first part is
earth leakage circuit breaker (ELCB) 40A. This section is used to protect the general power
circuit such as lights, fans, air conditions, water heater and spare. On the water heater placed
another ELCB 20A to avoid short circuit incidents. The second part is dividing ELCB 40A to
power socket outlet circuit.
-
7/31/2019 Ut Final Project
14/35
Appendix A (current calculation)
Type c ground floor
Loads of R1 (4 NOS DOWNLIGHT + 1 NOS CEILING FAN)
Given data:
Load Power Total power
4 NOS DOWNLIGHT 100 4100=400
1 NOS CEILING FAN 60 60Total 460
The current following in R1 is IL_N
IL_N=
IL-N =
IL_N =2.3 A
The loads of B1 (4 NOS DOWNLIGHT +1NOS CEILING FAN+ 1NOS WALL LIGHT)
Given data:
Load Power (w) Total power
4 NOS DOWNLIGHT 100 4100=400
1 NOS CEILING FAN 60 60
1 NOS WALL LIGHT 100 100
TOTAL 560
The current following in B1 is
IL_N=
IL-N =
Thus, IL_N =2.82A
-
7/31/2019 Ut Final Project
15/35
The loads in Y1 (5 NOS DOWNLIGHT +1 NOS WALL FAN POINT + 1 NOS WALL LIGHT)
Given data:
Load Power (w) Total power (w)
5 NOS DOWNLIGHT 100 5100=500
1 NOS WALL FAN POINT 60 60
I NOS WALL LIGHT 100 100
TOTAL 660
The current following in Y1 is
IL_N=
IL-N =
IL_N =3.36A
Loads of R8 (1 NOS 15A S/S/O AIR COND POINT)
Given data:
Load Power(w) Total power (w)
1 NOS 15A S/S/O AIR
COND POINT
746 746
Total 746
The current following in R1 is IL_N
IL_N=
IL-N =
IL_N =3.80 A
Loads of Y8 (1 NOS 15A S/S/O WATER HEATER POINT)
Given data:
Load Power(w) Total power (w)
1 NOS 15A S/S/O WATERHEATER POINT
1000 1000
-
7/31/2019 Ut Final Project
16/35
Total 1000
The current following in R1 is IL_N
IL_N=
IL-N =
IL_N =5.1 A
Loads of Y8 (1 NOS 15A S/S/O WATER HEATER POINT)
Given data:
Load Power(w) Total power (w)1 NOS 15A S/S/O WATER
HEATER POINT
1000 1000
Total 1000
The current following in R1 is IL_N
IL_N=
IL-N =
IL_N =5.1 A
Loads of B7 (1 NOS 15A S/S/O AIR COND POINT)
Given data:
Load Power(w) Total power (w)
1 NOS 15A S/S/O AIR
COND POINT
746 746
Total 746
The current following in R1 is IL_N
IL_N=
IL-N =
IL_N =3.80 A
-
7/31/2019 Ut Final Project
17/35
Appendix B (current calculation)
Type C first floor
Determine the current requirements of the circuit. This current is known as Design current, either
specified by the manufacturer or can be calculated by the formulae.
1. THE LOADS CONNEDCTED TO R1 (3 NOS DOWNLIGHT +1 NOS WALL LIGHT
+1 NOS CEILING FAN)
Given data:
Formula used:
cos
,1For
1 VIP
AV
WI 34.2
85.0231
4601
Load Power Total power3 NOS DOWNLIGHT 100 w 3100w=300w
1 NOS WALL LIGHT 100w 100w
1 NOS CEILING FAN 60w 60w
Total 460
-
7/31/2019 Ut Final Project
18/35
2. THE LOADS CONNEDCTED TO Y1 (4 NOS DOWNLIGHT +2 NOS CEILING FAN)
Given data:
Load Power Total power
4 NOS DOWNLIGHT 100 w 4100w=400W
2 NOS CEILING FAN 60w 120W
Total 520W
Formula used:
cos
,1For
1 VIP
AV
WI 65.2
85.0231
2051
3.
THE LOADS CONNEDCTED TO B1 (5 NOS DOWNLIGHT +1 NOS CEILING FAN)
Given data:
Load Power Total power
4 NOS DOWNLIGHT 100 w 5100w=500W
1 NOS CEILING FAN 60w 60W
Total 560W
Formula used:
cos
,1For
1 VIP
AV
WI 85.2
85.0231
5601
-
7/31/2019 Ut Final Project
19/35
4. THE LOADS CONNEDCTED TO R6 ( 1 NOS AIR CONDITION WITH DOUBLE
POLES SWITCH )
Given data:
Load Power Total power
1 NOS water heater with
Double
746w 746w
Formula used
cos
,1For
1 VIP
A
V
WI 80.3
85.0231
7461
5. THE LOADS CONNEDCTED TO Y6 ( 1 NOS AIR CONDITION WITH DOUBLE
POLES SWITCH )
Given data:
Load Power Total power
1 NOS water heater with
Double
746w 746w
Formula used
-
7/31/2019 Ut Final Project
20/35
cos
,1For
1 VIP
AV
WI 80.385.0231
7461
6. THE LOADS CONNEDCTED TO B6 ( 1 NOS AIR CONDITION WITH DOUBLE
POLES SWITCH )
Given data:
Load Power Total power1 NOS water heater withDouble
746w 746w
Formula used
cos
,1For
1 VIP
AV
WI 80.3
85.0231
7461
7. THE LOADS CONNEDCTED TO R7(1 NOS WATER HEATER WITH DOUBLE
POLES SWITCH)
Formula used:
Load Power Total power
1 NOS water heater with
Double
1000w 1000w=1000w
-
7/31/2019 Ut Final Project
21/35
cos
,1For
1 VIP
AV
WI 09.5
85.0231
00011
8. THE LOADS CONNEDCTED TO Y7(1 NOS WATER HEATER WITH DOUBLE
POLES SWITCH)
Formula used:
cos
,1For
1 VIP
AV
WI 09.5
85.0231
00011
9. THE LOADS CONNEDCTED TO B7(1 NOS WATER HEATER WITH DOUBLE
POLES SWITCH)
Formula used:
Load Power Total power
1 NOS water heater withDouble
1000w 1000w=1000w
Load Power Total power
1 NOS water heater with
Double
1000w 1000w=1000w
-
7/31/2019 Ut Final Project
22/35
cos
,1For
1 VIP
AV
WI 09.5
85.0231
00011
For the power side we used either 13A S/S/O or 15A S/S/O, so that we can take one in each
S/S/O which can simply be determined the cable size and assume the others as well.
1. The line current of(2 No 13A S/S/O )
AV
WI 54.2
85.0231
5001
-
7/31/2019 Ut Final Project
23/35
Appendix C(current calculation)
Type c2 Ground floor
1. The line current of R1 (connected to 5 No of down light and 1 No of fan)
Pt = (5x100) + (1x60)=560W
AV
WI 85.2
85.0231
5601
2. The line current of Y1 (connected to 1 No of wall light,5 No of down light and 1 No of fan)
Pt =(5x100)+(1x100)+(1x60)=660W
AV
WI 36.3
85.0231
6601
3. The line current of B1 (connected to 1 No of wall light,54No of down light )
Pt = (4x100) + (1x100)=500W
A
V
WI 54.2
85.0231
500
1
4. The line current of Y4 (water heater point)
Pt = (1x1000) =1000W
AV
WI 9.5
85.0231
10001
5. The line current of B7 (15A S/S/O 1 No of Air condition point)
Pt = (1x1000) =1000W
For the power side we used either 13A S/S/O or 15A S/S/O, so that we can take one in each S/S/O which
can simply be determined the cable size and assume the others as well.
2. The line current of(2 No 13A S/S/O )
AV
WI 4.3
85.0231
7461
-
7/31/2019 Ut Final Project
24/35
AV
WI 54.2
85.0231
5001
3. The current for 15A S/S/O
AV
WI 63.7
85.023115001
Appendix D (current calculation)
Type c2 first floor
CALCULATION FOR FIRST FLOOR DOUBLE STORY BUILDING
LOAD CALCULATION:
10.THE LOADS CONNEDCTED TO R1 (3 NOS DOWNLIGHT +1 NOS WALL LIGHT
+1 NOS CEILING FAN)
Given data:
Load Power Total power
3 NOS DOWNLIGHT 100 w 3100w=300w
1 NOS WALL LIGHT 100w 100w
1 NOS CEILING FAN 60w 60w
Formula used:
pf)power/(v=IL_N
0.8560w)/231v+100w+(300w=N-IL
Thus, IL_N =2.3 A
11.
THE LOADS CONNEDCTED TO Y1 (4 NOS DOWNLIGHT +2 NOS CEILING FAN)
Given data:
Load Power Total power
4 NOS DOWNLIGHT 100 w 4100w=400w
2 NOS CEILING FAN 60w 120w
-
7/31/2019 Ut Final Project
25/35
Formula used:
IL_N=
IL-N =
Thus, IL_N =2.65A
12.THE LOADS CONNEDCTED TO B1 (4 NOS DOWNLIGHT +1 NOS CEILING FAN)
Given data:
Load Power Total power
4 NOS DOWNLIGHT 100 w 4100w=400w
1 NOS CEILING FAN 60w 60w
Formula used:
IL_N=
IL-N =
Thus, IL_N =2.34A
13.THE LOADS CONNEDCTED TO R6 (1 NOS WATER HEATER WITH DOUBLE
POLES SWITCH)
Given data:
Load Power Total power
1 NOS water heater with
Double
1000w 1000w=1000w
-
7/31/2019 Ut Final Project
26/35
Formula used:
IL_N=
IL-N =
Thus, IL_N =5.1A
14.THE LOADS CONNEDCTED TO Y6 (1 NOS WATER HEATER WITH DOUBLE
POLES SWITCH)
Given data:
Load Power Total power
1 NOS water heater withDouble
1000w 1000w=1000w
Formula used:
IL_N=
IL-N =
Thus, IL_N =5.1A
15.THE LOADS CONNEDCTED TO B6 (1 NOS WATER HEATER WITH DOUBLE
POLES SWITCH)
Given data:
Load Power Total power
1 NOS water heater withDouble
1000w 1000w=1000w
Formula used:
IL_N=
IL-N =
Thus, IL_N =5.1A
-
7/31/2019 Ut Final Project
27/35
16.THE LOADS CONNEDCTED TO R7 ( 1 NOS AIR CONDITION WITH DOUBLE
POLES SWITCH )
Given data:
Load Power Total power
1 NOS water heater withDouble
746w 746w
Formula used
IL_N=
IL-N =
Thus, IL_N =3.8A
17.THE LOADS CONNEDCTED TO Y7 (1 NOS AIR CONDITION WITH DOUBLE
POLES SWITCH)Given data:
Load Power Total power
1 NOS water heater withDouble
746w 746w
Formula used
IL_N=
IL-N =
Thus, IL_N =3.8A
18.THE LOADS CONNEDCTED TO B7 (1 NOS AIR CONDITION WITH DOUBLE
POLES SWITCH)
Given data:
Load Power Total power
1 NOS water heater withDouble
746w 746w
Formula used
IL_N= IL-N =
Thus, IL_N =3.8A
-
7/31/2019 Ut Final Project
28/35
SCHEMATIC DIAGRAMS
Appendix E
GROUND FLOOR HOUSE TYPE C
-
7/31/2019 Ut Final Project
29/35
-
7/31/2019 Ut Final Project
30/35
Appendix F
FIRST FLOOR HOUSE TYPE C
-
7/31/2019 Ut Final Project
31/35
-
7/31/2019 Ut Final Project
32/35
Appendix G
GROUND FLOOR HOUSE TYPE C2
-
7/31/2019 Ut Final Project
33/35
-
7/31/2019 Ut Final Project
34/35
Appendix H
FIRST FLOOR HOUSE TYPE C2
-
7/31/2019 Ut Final Project
35/35