ut final project

Upload: alshargabi-musaab

Post on 04-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Ut Final Project

    1/35

    I. INDRODUCTION

    In this project, the students were asked to design a 3 phase low voltage distribution for two

    double storey houses. Apart from that designing, members of the group also have learnt how to

    balance the needs of consumers and providers of energy in order to ensure safe and reliable

    supply.

    The low voltage distribution system of this project consists of loads, cables, proactive device

    and distribution boxes. The main objective of this project is to draw a single line diagram design

    and this design layout of each floor of the two houses was presented in this project. In this task

    each group was given the permission to choose the electrical loads of their houses; the estimation

    electrical load values in this design were given in the calculation parts of this project, this was to

    make sure that the work of each group must be different than the works of the other groups.

    For the best results in electrical installation design and LV distribution requires a study of a

    proposed electrical installation that requires an adequate understanding of all governing rules and

    regulations. The total power demand can be calculated from the data relative to the location and

    power of each load, together with the knowledge of the operating modes (steady state demand,

    starting conditions, non simultaneous operation, etc.).

    From these data, the power required from the supply source and (where appropriate) the

    number of sources necessary for an adequate supply to the installation is readily obtained. Local

    information regarding tariff structures is also required to allow the best choice of connection

    arrangement to the power-supply network, e.g. at medium voltage or low voltage level.

    The whole installation distribution network is studied as a complete system. The distribution

    equipment (panel boards, switchgears, circuit connections ...) are determined from building plans

    and from the location and grouping of loads. The type of premises and allocation can influence

    their immunity to external disturbances.

  • 7/31/2019 Ut Final Project

    2/35

    This dissertation consists of four main parts. First part is an introduction; which describes the

    electrical structure and loadings for the LV distribution system. Second part is the calculation

    part; this explains all the methods applied in calculating the connected load, maximum demand

    and cable sizes. Third part is the discussion and analyses of the results obtained in this project.

    Last part is the appendices, this part is used to show all the calculations and schematic diagrams

    since the technical report pages are limited.

    II. CALCULATIONSHOUSE TYPE C

    A) TYPE: HOUSE C GROUND FLOOR

    Table1 shows the number of Nos in each load connected to the ground floor

    TABLE 1: Ground floor loads

    Load Nos Estimated power

    (W)

    Total Power (W)

    Down light 13 100 1300

    Ceiling fan 2 60 120

    Wall light 2 100 200Wall fan point 1 60 60

    Water heater point 1 1000 1000

    1X13A S/S/0(300mm.A.F.F.L)

    7 250 1750

    1X13A weather proofS/S/0

    2 250 500

    2 X13A S/S/0(300mm.A.F.F.L)

    2 250*2 1000

    1X13A S/S/0 atkitchen and yard

    (1500mm A.F.F.L)

    4 250 1000

    1X15A S/S/0 at

    kitchen (1500mm

    A.F.F.L)

    3 500 1500

    15A S/S/O AIR

    COND POINT

    2 746 1492

    TOTAL CONNECTED LOAD 9922

  • 7/31/2019 Ut Final Project

    3/35

    PMD=PCL x DF

    Assume DF=65%x

    PMD= 9922W x 0.65 = 6448W

    cos3

    ,3For

    )(

    LLMDVIP

    MD

    AV

    WI

    MD11

    85.04003

    6488)(3

    AV

    WI

    MD84.32

    85.0231

    6448)(1

    (PLEASE REFER TO APPENDIX A, FOR THE FORMULAE AND LINE CURRENT

    CALCULATIONS)

    Line Total load per line Current

    (A)

    Cable size Circuit

    breaker

    Current (A)

    R1 4 NOS DOWNLIGHT+ I NOS CEILING FAN 2.3 2 x 1.5mm ) PVC

    cable6

    B1 4 DOWN LIGHT + I NOS CEILING FAN + WALL

    LIGHT

    2.82 2 x 1.5mm ) PVC

    cable6

    Y1 5 NOS DOWN LIGHT+I NOS WALL FANPOINT+1NOS WALL LIGHT

    3.36 2 x 1.5mm ) PVCcable

    6

    R8 I NOS 15A S/S/0 AIR COND POINT 3.8 2 x 4.0mm ) PVC 20

    B7 I NOS 15A S/S/O AIR COND POINT 3.8 2 x 4.0mm ) PVC 20

    Y8 I NOS WATER HEATER 15A S/S/O 5.1 2 x 4.0mm ) PVC 20

    B2 2 NOS 1X13A S/S/O (300MM.AF.F.L) 2.55 2 x 2.5mm ) PVC 20A

    B3 2 NOS 1X 13A S/S/O AT KITCHEN AND YARD

    (1500mm A.F.F.L)

    2.55 2 x 2.5mm ) PVC 20A

    B4 1 NOS 1X13A weather proof S/S/0 + 1X13A

    S/S/0 (300mm.A.F.F.L)

    2.55 2 x 2.5mm ) PVC 20A

    B5 1NOS 1X13A S/S/O (300MM.AF.F.L) 1.27 2 x 2.5mm ) PVC 20A

    B6 1NOS 1X15A S/S/0 at kitchen (1500mmA.F.F.L)

    2.55 2 x 2.5mm ) PVC 20A

    R3 I NOS 1X13A S/S/0 (300mm.A.F.F.L) + I NOS

    1X13A S/S/0 at kitchen and yard (1500mm

    A.F.F.L)

    2.55 2 x 2.5mm ) PVC 20A

    R4 1 NOS 1X13A S/S/0 (300mm.A.F.F.L) 1.27 2 x 2.5mm ) PVC 20A

    R5 1 NOS 2 X13A S/S/0 (300mm.A.F.F.L) 2.55 2 x 2.5mm ) PVC 20A

    R7 1NOS 1X15A S/S/0 at kitchen (1500mm 2.55 2 x 2.5mm ) PVC 20A

  • 7/31/2019 Ut Final Project

    4/35

    A.F.F.L)

    Y3 I NOS 1X13A S/S/0 at kitchen and yard(1500mm A.F.F.L) + 1NOS 1X15A S/S/0 at

    kitchen (1500mm A.F.F.L)

    3.8 2 x 2.5mm ) PVC 20A

    Y4 1 NOS 1X13A weather proof S/S/0 + 1NOS

    1X13A S/S/O (300MM.AF.F.L)

    2.55 2 x 2.5mm ) PVC 20A

    Y5 1 NOS 2 X13A S/S/0 (300mm.A.F.F.L) 2.55 2 x 2.5mm ) PVC 20A

    Y7 1NOS 1X15A S/S/0 at kitchen (1500mm

    A.F.F.L)

    2.55 2 x 2.5mm ) PVC 20A

    (PLEASE REFER TO APPENDIX E, FOR THE SCHEMATIC DIAGRAM OF THE

    GROUND FLOOR)

    B) TYPE: HOUSE C FIRST FLOORTable2 shows the number of Nos in each load connected to the ground floor

    TABLE 2: LOADS IN FIRST FLOOR

    PMD=PCL x DF

    Assume DF=65%x

    PMD = 9528W x 0.65 = 6193.2W

    No Load Item No. NOS Estimate

    Power (W)Total Power

    (W)

    1 Down Light 12 100 1200

    2 Ceiling Fan 4 60 240

    3 Wall Light 1 100 100

    4 1x13A S/S/0 (300mm A.F.F.L) 5 250 1250

    5 2x13A S/S/O (300mm

    A.F.F.L)

    3 250*2 1500

    6 15A S/S/O Air Cond Point 3 746 2238

    7 15A S/S/O Water Heater point 3 1000 3000

    8 Total Connected load 9528

  • 7/31/2019 Ut Final Project

    5/35

    cos3

    ,3For

    )(

    LLMDVIP

    MD

    A

    V

    WI

    MD52.10

    85.04003

    6193.2)(3

    cos

    ,1For

    )(1 VIP

    MDMD

    AV

    WI

    MD54.31

    85.0231

    6193.2)(1

    The table below shows the calculated current for each line (per phase) and the preferred

    circuit breaker with the cable size of type C fist floor.

    (PLEASE REFER TO APPENDIX B, FOR THE FORMULAE AND LINE CURRENT

    CALCULATIONS)

    LINE TOTAL NOS CONNECTED CURRENT (A) CABLE SIZE Circuit breaker(A)

    R 1 (3 Nos down lighting +1nos wall lighting +1 Nos

    ceiling fan)

    2.342 x 1.5mm ) PVC

    cable

    6

    Y1 4 Nos down lighting +2

    Nos ceiling fan

    2.65 2 x 1.5mm ) PVC

    cable

    6

    B1 5 Nos down lighing +1

    Nos ceiling fan

    2.85 2 x 1.5mm ) PVC

    cable

    6

    R 6 1 Nos air condition with

    double poles switch

    3.80 2 x 4.0mm ) PVC 20

    Y6 1 Nos air condition with

    double poles switch

    3.80 2 x 4.0mm ) PVC 20

    B6 1 Nos air condition with

    double poles switch

    3.80 2 x 4.0mm ) PVC 20

    R7 1 NOS water heater with

    Double

    5.09 2 x 4.0mm ) PVC 20

    Y7 1 Nos water heater with

    double poles switch

    5.09 2 x 4.0mm ) PVC 20

  • 7/31/2019 Ut Final Project

    6/35

    (PLEASE REFER TO APPENDIX F, FOR THE SCHEMATIC DIAGRAM OF THE

    FIRST FLOOR OF HOUSE TYPE C)

    C) TYPE: HOUSE C2 Ground FloorThe table 3below shows the loads and number of Nos connected to the ground floor

    Table 3: loads connected to the ground floor in c2

    PMD=PCL x DF

    B7 1 NOS water heater with

    Double

    5.09 2 x 4.0mm ) PVC 20

    B2 2 NOS 1x13A S/S/O 2.54 2 x 2.5mm ) PVC 20

    Y3 1 NOS 1x13A S/S/O 2.54 2 x 2.5mm ) PVC 16

    B3 1 NOS 2x13A S/S/O 2.54 2 x 2.5mm ) PVC 20

    R3 2 NOS 1x13A S/S/O 2.54 2 x 2.5mm ) PVC 20

    Y4 1 NOS 2x13A S/S/O 2.54 2 x 2.5mm ) PVC 20

    B4 1 NOS 2x13A S/S/O 2.54 2 x 2.5mm ) PVC 20

    No Load Item No. NOS Estimate Power(W)

    Total Power(W)

    1 Down Light 14 100 1400

    2 Ceiling Fan 2 60 120

    3 Wall Light 2 100 200

    4 1x13A S/S/0 (300mm

    A.F.F.L)

    7 250 1750

    5 2x13A S/S/O (300mm

    A.F.F.L)

    2 250*2 1000

    6 15A S/S/O Air Cond Point 2 746 1492

    7 1x13A S/S/O Wether proof 2 250 500

    8 1x13A S/S/O at kitchen 4 250 1000

    9 1x15A S/S/O at kitchen 3 500 1500

    10 15A S/S/O water heater point 1 1000 1000

    11 Total connected Load 9962

  • 7/31/2019 Ut Final Project

    7/35

    Assume DF=60%x

    PMD= 9962W x 0.60 = 5977.2W

    cos3

    ,3For

    )( LLMD VIP MD

    A

    V

    WI

    MD15.10

    85.04003

    5997.2)(3

    cos

    ,1For

    )(1 VIP

    MDMD

    AV

    WIMD

    54.3085.0231

    597.2)(1

    The table below shows the calculated current for each line (per phase) and the preferred circuit

    breaker with the cable size of type C2 ground floor.

    (PLEASE REFER TO APPENDIX C, FOR THE FORMULAE AND LINE CURRENT

    CALCULATIONS)

    (PLEASE REFER TO APPENDIX G, FOR THE SCHEMATIC DIAGRAM OF THE

    GROUND FLOOR OF HOUSE TYPE C2)

    LINE TOTAL NOS

    CONNECTED

    CURRENT (A) CABLE SIZE

    R 1 5 No of down light

    and 1 No of fan

    2.85 2 x 1.5mm ) PVC

    cable

    Y1 1 No of wall light,5No of down light and

    1 No of fan

    3.36 2 x 1.5mm ) PVCcable

    B1 1 No of wall

    light,54No of down

    light

    2.54 2 x 1.5mm ) PVC

    cable

    Y4 water heater point 5.9 2 x 4.0mm ) PVC

    B7 Air condition point 3.4 2 x 4.0mm ) PVC

    13A S/S/O 2.54 2 x 2.5mm ) PVC

    15A S/S/O 7.63 2 x 2.5mm ) PVC

  • 7/31/2019 Ut Final Project

    8/35

    D) TYPE: HOUSE C2 First FloorThe table4below shows the loads and number of Nos connected to the ground floor

    Table 4: loads connected to first floor in c2

    PMD=PCL x DF

    Assume DF=60%x

    PMD= 9678W x 0.60 = 5806.8W

    cos3

    ,3For

    )(

    LLMDVIP

    MD

    AV

    WI

    MD5.9

    85.04003

    5806.8)(3

    No Load Item No. NOS Estimate Power(W)

    Total Power

    (W)

    1 Down Light 11 100 1400

    2 Ceiling Fan 4 60 120

    3 Wall Light 1 100 200

    4 Water heater point 3 1000 3000

    4 113A s/s/o 6 250 1500

    5 213A s/s/o 3 500 1500

    6 15A s/s/o 3 746 2238

    7 Total connected Load 9678w

  • 7/31/2019 Ut Final Project

    9/35

    AV

    WI

    MD57.29

    85.0231

    5806.8)(1

    The table below shows the calculated current for each line (per phase) and the preferred

    circuit breaker with the cable size of type C2 fist floor.

    (PLEASE REFER TO APPENDIX D, FOR THE FORMULAE AND LINE CURRENT

    CALCULATIONS)

    (PLEASE REFER TO APPENDIX H, FOR THE SCHEMATIC DIAGRAM OF THE

    FIRST FLOOR OF HOUSE TYPE C2)

    III. DISCUSION AND ANALYSIS

    A) DISCUSION

    In this project the students were asked to draw the schematic diagrams of two types of

    houses; which are house type C and house type C2. Each house consists of two parts which are

    LINE TOTAL NOS

    CONNECTED

    CURRENT (A) CABLE SIZE Circuit beaker

    R 1 (3 Nos down

    lighting +1 noswall lighting +1

    Nos ceiling fan)

    2.32 x 1.5mm )

    PVC cable

    6A

    Y1 4 Nos down

    lighting +2 Nos

    ceiling fan

    2.65 2 x 1.5mm )

    PVC cable

    6A

    B1 4 Nos down

    lighing +1 Nosceiling fan

    2.34 2 x 1.5mm )

    PVC cable

    6A

    R6 1 Nos water heaterwith double poles

    switch

    5.1 2 x 4.0mm )

    PVC

    20A

    R7 1 Nos air

    condition with

    double polesswitch

    3.8 2 x 4.0mm )

    PVC

    20A

  • 7/31/2019 Ut Final Project

    10/35

    ground floor and first floor. There were seven members in the group; four of them were given to

    design house type c while the other three were given to design house type c2.

    To achieve the objectives of the project; members counted all the numbers of Nos in each

    floor according to the task division of the group. An estimated power was chosen for each load asstated in section II (calculation part). In house C demand factor of 65% was chosen while house

    C2 60% of demand factor was chosen. The total connected load of each floor was calculated and

    then the demand factor was obtained by using relevant formula as shown in the calculation part.

    The number of nos in each line were counted in order to obtain the current in each line of

    the four floors. As result of line current, then the current of each circuit breaker was obtained

    according to the standard and safety regulations. In addition to that, the cable size was

    determined.

    There are two types of cables that available in the market, which are copper wire and

    alloy aluminium cable. In this project, a copper wire was chosen because copper cable is

    recognized as high quality product and it is good conductor compare to aluminium , copper has

    greater tensile strength compare to aluminium, even though aluminium is electricity conductive.

    The group members have discussed the type of miniature circuit breaker to use, they have

    agreed upon to choose a suitable one by considering the load and overload current. MCB is

    divided into two; which are domestic and commercial types. In this project, domestic one was

    chosen because of its general use of residential purposes.

    Heavy load such as air conditional and water heater, was assigned to own a separate

    MCB, due to their high load and high overload current, there for, they require high load power

    supply, which may spoil other equipment if combine with other appliance that has lower load

    current or lower power supply. Similar to socket, the socket which provide to high load appliance

    will also has their own MCB, similar load appliance will has similar load current and power

    supply, when over current or short circuit occur, the MCB able to protect the cable and

    equipment if the MCB use is in suitable current rating.

  • 7/31/2019 Ut Final Project

    11/35

    Two different demand factors were estimated due to make comparison between the

    maximum demands of each floor. House C was given 65% demand while 60% demand factor

    was given house type C2. This estimation has shown that when the demand factor is high themaximum demand becomes also high. Hence ground floor of house type C has higher maximum

    demand than the ground floor of house type C2. However, there is also total connected load

    which is another factor that affects the maximum demand of the floor; higher connected gives

    higher maximum demand and vice versa.

    B) ANALYSIS

    1) House type C

    The total connected load, maximum demand, and line currents were obtained by using

    relevant formulae. The total power consumption in the ground floor is 9922w while the first floor

    is 9528w. it can be seen clearly, that the ground floor consumed huge power compare to first

    floor, this is because the kitchen in the ground floor has additional sockets that require bulk of

    power.

    At the side of voltage drop, line of R7, Y8, and B6 in the ground floor can show the

    highest voltage drop, because these lines has sockets such as 1x15A S/S/O at the Kichen, 15A

    S/S/O water heater point, and generally these loads are called heavy loads since they consume

    huge power.

    In this house, demand factor of 65% was estimated in order to compare with the other

    house of type c which its demand factor was estimated as 60%. Since the demand factor is 65%

    for house, the maximum demand was obtained by using formula as shown in section II. Hence,

    the maximum demand of ground and first floors are 6448W and 6193.2W respectively.

    Maximum demand of the ground floor is higher than the first floor although they have the same

    demand factor, this is due to the total connected load of the ground floor is higher than that of the

    first floor.

  • 7/31/2019 Ut Final Project

    12/35

    2) House type C2

    Same as house type C, the ground floor of house C2 has higher power

    consumption than the first floor. This is due to that the ground floor was equipped with

    more kitchen sockets and appliances which consumed more power. This can be seen from

    the total connected load of the ground floor which is 9962, while the total connected of

    the first floor is 9678.

    Although the floors of this house have higher total connected loads compare to

    their respective floors in house type C, but the maximum demand of the ground floor of

    house C2 is lower than that of the house type C ground floor, and the same goes to the

    first floor. This is due to the demand factor, because the demand factor of house type C is

    higher than that of house type C2 as shown in the calculation part.

    3) As generally

    To chose the correct rating of circuit breaker we have to determine the current requirements for

    each line, which also enables us to chose the correct cable size in order to not to affect the cost

    as well. This current is known as Design current, either specified by the manufacturer or can be

    calculated by the formulae.

    cos

    ,1currentlineFor

    1 VIP

    For current calculation in each line refer appendix A85.0231

    1

    V

    PI

  • 7/31/2019 Ut Final Project

    13/35

    For all floors of both type of houses, the lights, fans and bell are used ( 2 x 1.5mm ) PVC

    cable. For the installations of air conditioners, water heater and spare are used ( 2 x 4.0mm )

    PVC cable while the socket outlet 13A is use ( 2 x 2.5mm ) and ( 2 x 4.0mm ) PVC cable ring

    type. Using ring type is intended to save the use of protective fuse. Each cable is installed using a

    conduit in the wall constructions. All the wiring has installations of fuse to give protections and

    this fuse is accordance to the standards. For the light, fan and bell, the used fuse is 6A and for the

    water heater, air conditioner and spare, the used fuse is 20A except for wiring socket outlet ( 2 x

    2.5mm ) PVC cable. But for the socket outlet ( 2 x 4.0mm ) PVC cable, the used fuse is 32A.

    Starting from TNB supply, cut-off fuse is installed before the meter KWH. A protection begins

    with the installations of main switch 40A/60A and then divided into two parts. The first part is

    earth leakage circuit breaker (ELCB) 40A. This section is used to protect the general power

    circuit such as lights, fans, air conditions, water heater and spare. On the water heater placed

    another ELCB 20A to avoid short circuit incidents. The second part is dividing ELCB 40A to

    power socket outlet circuit.

  • 7/31/2019 Ut Final Project

    14/35

    Appendix A (current calculation)

    Type c ground floor

    Loads of R1 (4 NOS DOWNLIGHT + 1 NOS CEILING FAN)

    Given data:

    Load Power Total power

    4 NOS DOWNLIGHT 100 4100=400

    1 NOS CEILING FAN 60 60Total 460

    The current following in R1 is IL_N

    IL_N=

    IL-N =

    IL_N =2.3 A

    The loads of B1 (4 NOS DOWNLIGHT +1NOS CEILING FAN+ 1NOS WALL LIGHT)

    Given data:

    Load Power (w) Total power

    4 NOS DOWNLIGHT 100 4100=400

    1 NOS CEILING FAN 60 60

    1 NOS WALL LIGHT 100 100

    TOTAL 560

    The current following in B1 is

    IL_N=

    IL-N =

    Thus, IL_N =2.82A

  • 7/31/2019 Ut Final Project

    15/35

    The loads in Y1 (5 NOS DOWNLIGHT +1 NOS WALL FAN POINT + 1 NOS WALL LIGHT)

    Given data:

    Load Power (w) Total power (w)

    5 NOS DOWNLIGHT 100 5100=500

    1 NOS WALL FAN POINT 60 60

    I NOS WALL LIGHT 100 100

    TOTAL 660

    The current following in Y1 is

    IL_N=

    IL-N =

    IL_N =3.36A

    Loads of R8 (1 NOS 15A S/S/O AIR COND POINT)

    Given data:

    Load Power(w) Total power (w)

    1 NOS 15A S/S/O AIR

    COND POINT

    746 746

    Total 746

    The current following in R1 is IL_N

    IL_N=

    IL-N =

    IL_N =3.80 A

    Loads of Y8 (1 NOS 15A S/S/O WATER HEATER POINT)

    Given data:

    Load Power(w) Total power (w)

    1 NOS 15A S/S/O WATERHEATER POINT

    1000 1000

  • 7/31/2019 Ut Final Project

    16/35

    Total 1000

    The current following in R1 is IL_N

    IL_N=

    IL-N =

    IL_N =5.1 A

    Loads of Y8 (1 NOS 15A S/S/O WATER HEATER POINT)

    Given data:

    Load Power(w) Total power (w)1 NOS 15A S/S/O WATER

    HEATER POINT

    1000 1000

    Total 1000

    The current following in R1 is IL_N

    IL_N=

    IL-N =

    IL_N =5.1 A

    Loads of B7 (1 NOS 15A S/S/O AIR COND POINT)

    Given data:

    Load Power(w) Total power (w)

    1 NOS 15A S/S/O AIR

    COND POINT

    746 746

    Total 746

    The current following in R1 is IL_N

    IL_N=

    IL-N =

    IL_N =3.80 A

  • 7/31/2019 Ut Final Project

    17/35

    Appendix B (current calculation)

    Type C first floor

    Determine the current requirements of the circuit. This current is known as Design current, either

    specified by the manufacturer or can be calculated by the formulae.

    1. THE LOADS CONNEDCTED TO R1 (3 NOS DOWNLIGHT +1 NOS WALL LIGHT

    +1 NOS CEILING FAN)

    Given data:

    Formula used:

    cos

    ,1For

    1 VIP

    AV

    WI 34.2

    85.0231

    4601

    Load Power Total power3 NOS DOWNLIGHT 100 w 3100w=300w

    1 NOS WALL LIGHT 100w 100w

    1 NOS CEILING FAN 60w 60w

    Total 460

  • 7/31/2019 Ut Final Project

    18/35

    2. THE LOADS CONNEDCTED TO Y1 (4 NOS DOWNLIGHT +2 NOS CEILING FAN)

    Given data:

    Load Power Total power

    4 NOS DOWNLIGHT 100 w 4100w=400W

    2 NOS CEILING FAN 60w 120W

    Total 520W

    Formula used:

    cos

    ,1For

    1 VIP

    AV

    WI 65.2

    85.0231

    2051

    3.

    THE LOADS CONNEDCTED TO B1 (5 NOS DOWNLIGHT +1 NOS CEILING FAN)

    Given data:

    Load Power Total power

    4 NOS DOWNLIGHT 100 w 5100w=500W

    1 NOS CEILING FAN 60w 60W

    Total 560W

    Formula used:

    cos

    ,1For

    1 VIP

    AV

    WI 85.2

    85.0231

    5601

  • 7/31/2019 Ut Final Project

    19/35

    4. THE LOADS CONNEDCTED TO R6 ( 1 NOS AIR CONDITION WITH DOUBLE

    POLES SWITCH )

    Given data:

    Load Power Total power

    1 NOS water heater with

    Double

    746w 746w

    Formula used

    cos

    ,1For

    1 VIP

    A

    V

    WI 80.3

    85.0231

    7461

    5. THE LOADS CONNEDCTED TO Y6 ( 1 NOS AIR CONDITION WITH DOUBLE

    POLES SWITCH )

    Given data:

    Load Power Total power

    1 NOS water heater with

    Double

    746w 746w

    Formula used

  • 7/31/2019 Ut Final Project

    20/35

    cos

    ,1For

    1 VIP

    AV

    WI 80.385.0231

    7461

    6. THE LOADS CONNEDCTED TO B6 ( 1 NOS AIR CONDITION WITH DOUBLE

    POLES SWITCH )

    Given data:

    Load Power Total power1 NOS water heater withDouble

    746w 746w

    Formula used

    cos

    ,1For

    1 VIP

    AV

    WI 80.3

    85.0231

    7461

    7. THE LOADS CONNEDCTED TO R7(1 NOS WATER HEATER WITH DOUBLE

    POLES SWITCH)

    Formula used:

    Load Power Total power

    1 NOS water heater with

    Double

    1000w 1000w=1000w

  • 7/31/2019 Ut Final Project

    21/35

    cos

    ,1For

    1 VIP

    AV

    WI 09.5

    85.0231

    00011

    8. THE LOADS CONNEDCTED TO Y7(1 NOS WATER HEATER WITH DOUBLE

    POLES SWITCH)

    Formula used:

    cos

    ,1For

    1 VIP

    AV

    WI 09.5

    85.0231

    00011

    9. THE LOADS CONNEDCTED TO B7(1 NOS WATER HEATER WITH DOUBLE

    POLES SWITCH)

    Formula used:

    Load Power Total power

    1 NOS water heater withDouble

    1000w 1000w=1000w

    Load Power Total power

    1 NOS water heater with

    Double

    1000w 1000w=1000w

  • 7/31/2019 Ut Final Project

    22/35

    cos

    ,1For

    1 VIP

    AV

    WI 09.5

    85.0231

    00011

    For the power side we used either 13A S/S/O or 15A S/S/O, so that we can take one in each

    S/S/O which can simply be determined the cable size and assume the others as well.

    1. The line current of(2 No 13A S/S/O )

    AV

    WI 54.2

    85.0231

    5001

  • 7/31/2019 Ut Final Project

    23/35

    Appendix C(current calculation)

    Type c2 Ground floor

    1. The line current of R1 (connected to 5 No of down light and 1 No of fan)

    Pt = (5x100) + (1x60)=560W

    AV

    WI 85.2

    85.0231

    5601

    2. The line current of Y1 (connected to 1 No of wall light,5 No of down light and 1 No of fan)

    Pt =(5x100)+(1x100)+(1x60)=660W

    AV

    WI 36.3

    85.0231

    6601

    3. The line current of B1 (connected to 1 No of wall light,54No of down light )

    Pt = (4x100) + (1x100)=500W

    A

    V

    WI 54.2

    85.0231

    500

    1

    4. The line current of Y4 (water heater point)

    Pt = (1x1000) =1000W

    AV

    WI 9.5

    85.0231

    10001

    5. The line current of B7 (15A S/S/O 1 No of Air condition point)

    Pt = (1x1000) =1000W

    For the power side we used either 13A S/S/O or 15A S/S/O, so that we can take one in each S/S/O which

    can simply be determined the cable size and assume the others as well.

    2. The line current of(2 No 13A S/S/O )

    AV

    WI 4.3

    85.0231

    7461

  • 7/31/2019 Ut Final Project

    24/35

    AV

    WI 54.2

    85.0231

    5001

    3. The current for 15A S/S/O

    AV

    WI 63.7

    85.023115001

    Appendix D (current calculation)

    Type c2 first floor

    CALCULATION FOR FIRST FLOOR DOUBLE STORY BUILDING

    LOAD CALCULATION:

    10.THE LOADS CONNEDCTED TO R1 (3 NOS DOWNLIGHT +1 NOS WALL LIGHT

    +1 NOS CEILING FAN)

    Given data:

    Load Power Total power

    3 NOS DOWNLIGHT 100 w 3100w=300w

    1 NOS WALL LIGHT 100w 100w

    1 NOS CEILING FAN 60w 60w

    Formula used:

    pf)power/(v=IL_N

    0.8560w)/231v+100w+(300w=N-IL

    Thus, IL_N =2.3 A

    11.

    THE LOADS CONNEDCTED TO Y1 (4 NOS DOWNLIGHT +2 NOS CEILING FAN)

    Given data:

    Load Power Total power

    4 NOS DOWNLIGHT 100 w 4100w=400w

    2 NOS CEILING FAN 60w 120w

  • 7/31/2019 Ut Final Project

    25/35

    Formula used:

    IL_N=

    IL-N =

    Thus, IL_N =2.65A

    12.THE LOADS CONNEDCTED TO B1 (4 NOS DOWNLIGHT +1 NOS CEILING FAN)

    Given data:

    Load Power Total power

    4 NOS DOWNLIGHT 100 w 4100w=400w

    1 NOS CEILING FAN 60w 60w

    Formula used:

    IL_N=

    IL-N =

    Thus, IL_N =2.34A

    13.THE LOADS CONNEDCTED TO R6 (1 NOS WATER HEATER WITH DOUBLE

    POLES SWITCH)

    Given data:

    Load Power Total power

    1 NOS water heater with

    Double

    1000w 1000w=1000w

  • 7/31/2019 Ut Final Project

    26/35

    Formula used:

    IL_N=

    IL-N =

    Thus, IL_N =5.1A

    14.THE LOADS CONNEDCTED TO Y6 (1 NOS WATER HEATER WITH DOUBLE

    POLES SWITCH)

    Given data:

    Load Power Total power

    1 NOS water heater withDouble

    1000w 1000w=1000w

    Formula used:

    IL_N=

    IL-N =

    Thus, IL_N =5.1A

    15.THE LOADS CONNEDCTED TO B6 (1 NOS WATER HEATER WITH DOUBLE

    POLES SWITCH)

    Given data:

    Load Power Total power

    1 NOS water heater withDouble

    1000w 1000w=1000w

    Formula used:

    IL_N=

    IL-N =

    Thus, IL_N =5.1A

  • 7/31/2019 Ut Final Project

    27/35

    16.THE LOADS CONNEDCTED TO R7 ( 1 NOS AIR CONDITION WITH DOUBLE

    POLES SWITCH )

    Given data:

    Load Power Total power

    1 NOS water heater withDouble

    746w 746w

    Formula used

    IL_N=

    IL-N =

    Thus, IL_N =3.8A

    17.THE LOADS CONNEDCTED TO Y7 (1 NOS AIR CONDITION WITH DOUBLE

    POLES SWITCH)Given data:

    Load Power Total power

    1 NOS water heater withDouble

    746w 746w

    Formula used

    IL_N=

    IL-N =

    Thus, IL_N =3.8A

    18.THE LOADS CONNEDCTED TO B7 (1 NOS AIR CONDITION WITH DOUBLE

    POLES SWITCH)

    Given data:

    Load Power Total power

    1 NOS water heater withDouble

    746w 746w

    Formula used

    IL_N= IL-N =

    Thus, IL_N =3.8A

  • 7/31/2019 Ut Final Project

    28/35

    SCHEMATIC DIAGRAMS

    Appendix E

    GROUND FLOOR HOUSE TYPE C

  • 7/31/2019 Ut Final Project

    29/35

  • 7/31/2019 Ut Final Project

    30/35

    Appendix F

    FIRST FLOOR HOUSE TYPE C

  • 7/31/2019 Ut Final Project

    31/35

  • 7/31/2019 Ut Final Project

    32/35

    Appendix G

    GROUND FLOOR HOUSE TYPE C2

  • 7/31/2019 Ut Final Project

    33/35

  • 7/31/2019 Ut Final Project

    34/35

    Appendix H

    FIRST FLOOR HOUSE TYPE C2

  • 7/31/2019 Ut Final Project

    35/35