validation of re4 cu cooling systems for mass production
DESCRIPTION
Validation of RE4 Cu cooling systems for mass production. L. M. Pant 1,* , Manish Kumar 2 1 Nuclear Physics Division 2 Mechanical Design & Prototype Development Division Bhabha Atomic Research Centre Mumbai - 400085, INDIA * email : [email protected]. RE4/3. RE4/2. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/1.jpg)
L. M. Pant 1RE Workshop, 19/11/12
Validation of RE4 Cu cooling systems for mass production
L. M. Pant1,*, Manish Kumar2
1Nuclear Physics Division2Mechanical Design & Prototype Development Division
Bhabha Atomic Research Centre Mumbai - 400085, INDIA
* email : [email protected]
![Page 2: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/2.jpg)
L. M. Pant RE Workshop, 19/11/12 2
RE4/3
RE4/2
![Page 3: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/3.jpg)
L. M. Pant RE Workshop, 19/11/12 3
• Vicker’s Hardness (HV5) : 90-100• Cu Plates : 1 mm thick• Cu Pipes : 8 mm OD
: 6 mm ID
• Chemical Compositions :• Plates (OFC) : 99.95% (Min) Cu• Pipe (DHP Cu) : 99.85% (Min) Cu
: 0.013 - 0.050% P• Solder (Sn62) : Sn : Ag : Pb & other
62 : 02 : Remaining
• Leak test : 20 bar of Ar
Specifications : Cu plates and pipes
![Page 4: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/4.jpg)
L. M. Pant RE Workshop, 19/11/12 4
Cutting, bending and drilling of Cu plates
![Page 5: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/5.jpg)
L. M. Pant 5RE Workshop, 19/11/12
Cu cooling assembly being soldered in a jig
![Page 6: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/6.jpg)
L. M. Pant 6RE Workshop, 19/11/12
Cu cooling assembly (RE4/3) finished product
![Page 7: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/7.jpg)
L. M. Pant 7RE Workshop, 19/11/12
RE4/2 and RE4/3 Cu cooling system, in queue for leak tests
![Page 8: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/8.jpg)
SAGANA connectors sent from CERN
Some of the connectors had ferrules missing inside them
L. M. Pant 8RE Workshop, 19/11/12
![Page 9: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/9.jpg)
SAGANA Nuts with double ferrules on Cu cooling assemblies, mounted on Al patch panel
SAGANA Nuts
Double SS ferrules from ROTAREX
“crimped”
Double Brass ferrules, on the other side
“not crimped”
L. M. Pant 9RE Workshop, 19/11/12
![Page 10: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/10.jpg)
L. M. Pant 10RE Workshop, 19/11/12
Cu cooling system placed in the Box for dispatch
![Page 11: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/11.jpg)
Some of the SAGANA couplings connected to Cu cooling systems
L. M. Pant 11RE Workshop, 19/11/12
![Page 12: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/12.jpg)
Some of the SAGANA couplings connected to Cu cooling systems
L. M. Pant 12RE Workshop, 19/11/12
![Page 13: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/13.jpg)
Some of the SAGANA couplings connected to Cu cooling systems
Aluminum patch panel,conforming with old HV Tripolar
Longer side of SAGANA coupling is
towards the inside of the “L” profile
L. M. Pant 13RE Workshop, 19/11/12
![Page 14: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/14.jpg)
Difficulties in taking the Brass nut over the bend in the pipe
L. M. Pant 14RE Workshop, 19/11/12
![Page 15: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/15.jpg)
Cu pipes raised much earlier near the “U” bend
L. M. Pant 15RE Workshop, 19/11/12
![Page 16: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/16.jpg)
L. M. Pant 16RE Workshop, 19/11/12
Cu cooling system placed in the Box for dispatch to CERN and Ghent
![Page 17: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/17.jpg)
L. M. Pant RE Workshop, 19/11/12 17
Heat Treated wooden box for transportation of Cu cooling assemblies to CERN & Ghent
Inside size (L x B x H) : 1900 mm x 700mm x 400 mm
Outtside size (L x B x H) : 2015 mm x 820 mm x 550 mm
Weight of empty box : 96 Kg
![Page 18: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/18.jpg)
• RE4/2 : 05 sets : fabricated, leak tested and dispatched to CERN
• RE4/3 : 05 sets : fabricated, leak tested and dispatched to CERN
• RE4/3 : 10 sets : fabricated, leak tested and dispatched to Ghent
: Both the boxes have been received at CERN and Ghent on 11th Nov. 2012
• RE 4/2 : 10 sets : under fabrication for BARC, at the moment
Pilot run for production of first 30 sets of Cu cooling systems for RE4 dispatched on 07th Nov. 2012
After the delivery of the Cu cooling sets, we would like to profit from your expertise and feedback to launch the mass production of the remaining 170 sets, including discussion on SS ferrules and Brass nuts
L. M. Pant 18RE Workshop, 19/11/12
![Page 19: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/19.jpg)
L. M. Pant 19RE Workshop, 19/11/12
Leak test for Cu cooling systems
Cu tubes :OD = 8 mm ID = 6 mm thickness : 1 mm
![Page 20: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/20.jpg)
Cu tube pinched at one end
Safety release
0 -35 bar pressure
transducer
Outlet Pressure20 bar
Inlet pressure 80 bar
Argon gas
Valve A open
Details of leak test facility
Extra Cu pipe : OD = 6 mm length = 100 cm
L. M. Pant 20RE Workshop, 19/11/12
![Page 21: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/21.jpg)
L. M. Pant 21RE Workshop, 19/11/12
Fall in pressure : dp/dt = - 8.43 x 10 - 4 bar / minLeak Rate measured = - 18.27 x 10 - 4 mbar . litre / s
![Page 22: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/22.jpg)
L. M. Pant 22RE Workshop, 19/11/12
Differences in dp/dt : explanationSame RE4/3-001 Cu cooling assembly
25th Aug. 2012 : dp/dt : - 2 .0 x 10 - 2 mbar /sec : Valve A open (19 joints) (6 more joints exposed)
06th Sept. 2012 : dp/dt : - 4.7 x 10 - 3 mbar /sec : Valve A closed (13 joints)
Valve A
![Page 23: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/23.jpg)
L. M. Pant 23RE Workshop, 19/11/12
fall in pressure, dp/dt, for 20 Cu cooling systems
![Page 24: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/24.jpg)
RE42-1
RE42-2
RE42-3
RE42-4
RE42-5
RE43-1
RE43-5
RE43-7
RE43-8
RE43-10
RE43-9
RE43-11
RE43-12
RE43-13
RE43-15
RE43-3
RE43-4
RE43-16
RE43-14
RE43-170
2
4
6
8
10
12
14
RE4/2RE4/3
Y axis : fall in pressure (- dp/dt) x 10 - 4 bar . min -1
CERN Ghent
(-dp/
dt )
x 10
- 4 b
ar .
min
-1
Brass ferrules
L. M. Pant 24RE Workshop, 19/11/12
Brass ferrules
![Page 25: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/25.jpg)
A
mm
B
mm
C
mm
D
mm
Total length
(A+B+C+D)
mm
Total length
cm
Internal radius
cm
Vol
E
cm3
Volume of fixed Cu
tube ID = 0.4 cm
& l = 100 cm
F
cm3
Total volume
(E+F)
cm3
TotalVolume
litreRE4/2 1504 1504 288 144 3440 344.0 0.3 97.264 12.566 109.83
say 110.00 0.110
RE4/3 1766 1766 288 288 4108 410.8 0.3 116.151 12.566 129.08say
130.00 0.130
Vol RE4/3 Cu tube = 1.194Vol RE4/2 Cu tube
dimensions of Cu tubes for RE4/2 and RE4/3
RE4/2 : x 10 -4 bar/min x 1.833 x 10 -4 mbar . litre . s-1
RE4/3 : x 10 -4 bar/min x 2.167 x 10 -4 mbar . litre . s-1
L. M. Pant 25RE Workshop, 19/11/12
![Page 26: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/26.jpg)
RE42-1
RE42-2
RE42-3
RE42-4
RE42-5
RE43-1
RE43-5
RE43-7
RE43-8
RE43-10
RE43-9
RE43-11
RE43-12
RE43-13
RE43-15
RE43-3
RE43-4
RE43-16
RE43-14
RE43-170
5
10
15
20
25
30
RE4/2RE4/3
Y axis : Leak Rate : x 10 - 4 mbar . litre . s -1
CERN Ghent
x 1
0 - 4
mba
r . li
tre
. s -1
L. M. Pant 26RE Workshop, 19/11/12
![Page 27: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/27.jpg)
L. M. Pant 27RE Workshop, 19/11/12
![Page 28: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/28.jpg)
L. M. Pant 28RE Workshop, 19/11/12
![Page 29: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/29.jpg)
L. M. Pant 29RE Workshop, 19/11/12
![Page 30: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/30.jpg)
L. M. Pant 30RE Workshop, 19/11/12
![Page 31: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/31.jpg)
L. M. Pant 31RE Workshop, 19/11/12
![Page 32: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/32.jpg)
L. M. Pant 32RE Workshop, 19/11/12
![Page 33: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/33.jpg)
L. M. Pant RE Workshop, 19/11/12 33
![Page 34: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/34.jpg)
L. M. Pant RE Workshop, 19/11/12 34
![Page 35: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/35.jpg)
L. M. Pant RE Workshop, 19/11/12 35
![Page 36: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/36.jpg)
L. M. Pant RE Workshop, 19/11/12 36
AC Off
![Page 37: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/37.jpg)
L. M. Pant RE Workshop, 19/11/12 37
![Page 38: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/38.jpg)
L. M. Pant RE Workshop, 19/11/12 38
![Page 39: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/39.jpg)
L. M. Pant RE Workshop, 19/11/12 39
![Page 40: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/40.jpg)
L. M. Pant RE Workshop, 19/11/12 40
- 2.857 x 10 -4 bar/min
![Page 41: Validation of RE4 Cu cooling systems for mass production](https://reader036.vdocuments.net/reader036/viewer/2022081514/568164f3550346895dd75e1c/html5/thumbnails/41.jpg)
• Material in terms of Cu pipes, Cu plates, solder etc. have been procured
• Fabrication has started : cutting and bending of pipes and plates in progress
• We would like to finish the mass production in one go
• Tentative schedule of delivering 130 sets at CERN by July 2013RE4/3 : 85 setsRE4/2 : 45 setsTotal : 130 sets
Remaining : 40 sets of RE4/2 for BARC
• The above mentioned 130 sets include the Cu cooling systems for Ghent too, which shall be delivered at CERN
• Please arrange the delivery of SAGANA couplings and SS ferrules as soon as possible for 170 sets
Mass production of remaining 170 sets of Cu cooling systems for RE4
L. M. Pant 41RE Workshop, 19/11/12