Highlights
2.5 acres | 190 apartments | 2 BHK
100% Vastu compliant | No common walls | 24/7 security | Power back up
Aesthetically designed landscaped area
Manjeera water supply | Water treatment plant | Lab tested ground water
HITEC City 12 km
Kukatpally 4.5 km
Banjara Hills 10 km
Balanagar 4 km
HITEC MMTS Station 5 km
Secunderabad
Railway Station 10 km Airport 40 km
Location
Educational Institutions
DAV Public School 5 km
Indu Talent School 1 km
Sri Chaitanya e-Techno School 4 km
Gowtham Model School/Junior College/Degree College 1.5 km
Navya Jyothi High School 2.5 km
Akshara, the Techno School 3 km
New Era High School 3. 5 km
Bhashya Public School 4 km
Bhashyam Brooks 3.5 km
Proximity
Proximity
Healthcare Facilities
Ushamullapudi Cardiac Center 8 km
Sandhya Hospitals 1.5 km
Happy Children’s Super Specialty Hospital 2.5 km
Remedy Hospital 5 km
BBR Multi Speciality Hospital 8 km
Ark Hospital 5 km
Proximity
Shopping Complexes
More Supermarket 1 km
D Mart 3 km
Value Mart Shopping Mall & Multiplex 3 km
Metro Mall 3.5 km
Brand Factory/NSL Mall 6 km
SHA Theater 3 km
Viswanath/Arjun Theater 5 km
Mallikarjuna Theater 7 km
Clean Water at Navya
• Ground water tested and certified as fit for domestic use by Natural Resources Development Cooperative Society .
• Manjeera water supply.
• Water softening plant.
• Rain water harvesting.
• Sewage treatment plant.
Elevations
Bird View Elevation
Grand entry plaza | 5 blocks | 5 floors | Block to block distance 20’ Boulevards |
Master Plan
East Facing West Facing
Sizes 981 to 1235 sq ft | Spacious clutter free design | Efficient use of floor space 25% common area | Fully Vastu compliant | 6’x4’ living room window | No shared wall between apartments for enhanced ventilation
Floor Plan – 981 sq ft
Floor Plan – 1090 sq ft
East Facing West Facing
Sizes 981 to 1235 sq ft | Spacious clutter free design | Efficient use of floor space 25% common area | Fully Vastu compliant | 6’x4’ living room window | No shared wall between apartments for enhanced ventilation
Floor Plan – 1235 sq ft
East Facing West Facing
Sizes 981 to 1235 sq ft | Spacious clutter free design | Efficient use of floor space 25% common area | Fully Vastu compliant | 6’x4’ living room window | No shared wall between apartments for enhanced ventilation
Model Apartment
Living Room Master Bedroom
Construction Photos
&
Handover Schedule
Block-D (100% CC Block Work Completed & up to 3rd Floor
Plastering works were Completed) -Status As On
08/10/15
Block - D
Handover Schedule
Construction Activity Start Finish
Brickwork 16-May-15 14-Aug-15
Plastering 1-Jun-15 29-Sep-15
Flooring 1-Aug-15 30-Oct-15
finishes/paintings 1-Sep-15 30-Dec-15
External Works 11-Oct-15 18-Feb-16
Handing Over 8-Apr-16
Block-C
(5th Floor Block Work , 1st and 3rd Floor
Plastering works are in Progress - Status As
On 08/10/15
Block - C
Handover Schedule
Construction Activity Start Finish
4th Floor slab 1-May-15 31-May-15
5th Floor slab 1-Jun-15 1-Jul-15
Brickwork 16-May-15 13-Sep-15
Plastering 1-Jun-15 29-Sep-15
Flooring 1-Aug-15 30-Oct-15
finishes/paintings 1-Sep-15 30-Dec-15
External Works 11-Oct-15 18-Feb-16
Handing Over 8-Apr-16
Block - B
(2nd Floor Slab Completed & 1st Floor Block
Work In Progress) -Status As On 08/10/15
Block - B
Handover Schedule
Construction Activity Start Finish
2nd Floor slab 6-Jul-15 5-Aug-15
3rd Floor slab 6-Aug-15 5-Sep-15
4th Floor slab 6-Sep-15 6-Oct-15
5th Floor slab 7-Oct-15 16-Nov-15
Brickwork 6-Jul-15 13-Dec-15
Plastering 20-Aug-15 17-Jan-16
Flooring 29-Oct-15 26-Feb-16
finishes/paintings 29-Nov-15 27-Apr-16
External Works 8-Jan-16 6-Jun-16
Handing Over 4-Sep-16
Block – A
(1st Floor Slab Completed )Status As On
08/10/2015
Block - A
Handover Schedule Construction Activity Start Finish
2nd Floor slab 7-Jul-15 6-Aug-15
3rd Floor slab 7-Aug-15 6-Sep-15
4th Floor slab 7-Sep-15 7-Oct-15
5th Floor slab 8-Oct-15 17-Nov-15
Brickwork 7-Jul-15 14-Dec-15
Plastering 21-Aug-15 18-Jan-16
Flooring 30-Oct-15 27-Feb-16
finishes/paintings 30-Nov-15 28-Apr-16
External Works 9-Jan-16 7-Jun-16
Handing Over 5-Sep-16
Block - E
Handover Schedule Construction Activity Start Finish
Sub Stcture works Including Foundations 1-Jan-16 31-Jan-16
Stilt Slab 2-Feb-16 3-Mar-16
First Slab 4-Mar-16 2-Apr-16
Second Slab 5-Apr-16 5-May-16
Third Slab 6-May-16 5-Jun-16
Fourth Slab 6-Jun-16 6-Jul-16
Fifth floor slab 7-Jul-16 6-Aug-16
Brickwork 2-May-16 30-Aug-16
Plastering 23-May-16 20-Sep-16
Flooring 22-Jul-16 20-Oct-16
finishes/Painting 22-Aug-16 20-Dec-16
External Works 1-Oct-16 8-Feb-17
Handing Over 9-Apr-17
Amenities Block
Excavation work in progress Status As On
08/10/15
Amenities Block
Handover Schedule
Construction Activity Start Finish
Sub Stcture works Including Foundations 1-Jun-16 1-Jul-16
Basement Slab 2-Jul-16 1-Aug-16
Stilt Slab 2-Aug-16 1-Sep-16
First Slab 2-Sep-16 2-Oct-16
Second Slab 3-Oct-16 2-Nov-16
Brickwork 22-Oct-16 20-Jan-17
Plastering 21-Nov-16 21-Mar-17
Flooring&finishes 31-Dec-16 30-May-17
Handing Over 29-Jun-17
Technical Specifications
High Quality Attention To Detail
Foundation & Structure Earthquake resistant RCC framed structure in accordance with IS 456:2000, 1893:2002 Super Structure External and internal partition walls with good quality of cement concrete blocks Wall Finishes • External: 2- coats of plastering in cement mortar mix, painted with Asian Exterior
Paint . • Internal: Sponge finished cement mortar plastering with luppum finish and painted
with Asian Emulsion Paint or equivalent brand. Flooring • Living & Dining, Kitchen & Bedrooms: 2´x 2´ vitrified tiles of reputed make • Balconies, Utilities & Common Areas: Ceramic tiles of reputed make • Toilets: Anti-skid ceramic tiles of reputed make
Specifications
Doors & Windows
• Main Door: Engineered wood door frame and veneer finish flush shutter with melamine polish fixed with SS hardware.
• Internal Doors: Engineered wood door frame and molded shutter painted with enamel paint of Asian or equivalent & fixed with SS hardware
• Windows: Powder coated aluminium sliding frames fitted with plain glass and mild steel safety grills
Kitchen
• Stainless steel sink with polished granite platform
• Provision for exhaust fan
• Provision for water purification system
Dadoing:
• Kitchen: Glazed ceramic tile dado up to 2´ height above platform
• Utility: Glazed ceramic tile dado up to 3´ height
• Toilets: Glazed ceramic tile dado up to door height
Specifications
Toilets
• All sanitary fittings of Hindware/CERA/Parryware or equivalent brand
• All CP fittings & accessories of Hindware /CERA/Parryware or equivalent brand
Electrical
• PVC conduction, point wiring and circuit wiring of Polycab or equivalent.
• Three phase meter distribution box of MCB .
• Modular switches of standard make.
• Provision of power points for refrigerator & grinder in kitchen and washing machine in utility area.
• Provision geyser point in bathrooms.
• Telephone and television points in living room.
• Provision of AC point in master bedroom.
Specifications
Specifications
Parking Adequate car parking in the cellar and stilt floors.
Lifts Automatic passenger lifts of standard make.
Generator Backup power for one light and one fans in all apartments; 30% power backup in common areas .
Water Management
• Manjeera water connection
• Water softening plant for ground water treatment to make the water suitable for domestic use
• Waste water treated by STP and reused for gardening & flushing