vaswani reserve progress report
DESCRIPTION
Vaswani Group is a leading real estate developers and builders in Bangalore. Find out the status of work report.TRANSCRIPT
-
R E P O R T I N G
L I V E F R O M T H E
F I E L D
S T A T U S O F W O R K P R O G R E S S
A S O N
1 2 / 0 7 / 2 0 1 4
-
BLOCK BLOCK BLOCK BLOCK AAAA
-
BLOCK BLOCK BLOCK BLOCK BBBB
-
BLOCK BLOCK BLOCK BLOCK CCCC
-
BLOCK BLOCK BLOCK BLOCK DDDD
-
BLOCK BLOCK BLOCK BLOCK EEEE
-
BLOCK BLOCK BLOCK BLOCK FFFF
-
BLOCK BLOCK BLOCK BLOCK GGGG
-
AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK GROUND & FIRST FLOOR BLOCK WORKS & GROUND & FIRST FLOOR BLOCK WORKS & GROUND & FIRST FLOOR BLOCK WORKS & GROUND & FIRST FLOOR BLOCK WORKS &
PLASTERING FINISHES PLASTERING FINISHES PLASTERING FINISHES PLASTERING FINISHES IN PROGRESSIN PROGRESSIN PROGRESSIN PROGRESS
AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK BLOCK WORKS & PLASTERING FINISHES BLOCK WORKS & PLASTERING FINISHES BLOCK WORKS & PLASTERING FINISHES BLOCK WORKS & PLASTERING FINISHES IN IN IN IN
PROGRESSPROGRESSPROGRESSPROGRESS
-
RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS
IN PROGRESSIN PROGRESSIN PROGRESSIN PROGRESS
-
COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE
WORKS WORKS WORKS WORKS IN PROGRESSIN PROGRESSIN PROGRESSIN PROGRESS
-
CENTRE COURT YARD CENTRE COURT YARD CENTRE COURT YARD CENTRE COURT YARD WATER FEATURE BODY WORKS WATER FEATURE BODY WORKS WATER FEATURE BODY WORKS WATER FEATURE BODY WORKS IN PROGRESS IN PROGRESS IN PROGRESS IN PROGRESS
-
STATUS OF FINISHING WORKS
AMIGO BLOCK
INTERNAL 1ST COAT PAINTING COMPLETED
DOOR FRAMES FIXING COMPLETED
DOOR SHUTTERS FIXING IN PROGRESS
MARBLE 3RD AND 4TH COAT POLISH IN PROGRESS
TILING WORKS IN ALL BATH ROOMS COMPLETED
TILING WORKS IN KITCHEN & UTILITY COMPLETED
CORNICE WORKS COMPLETED
WINDOWS FIXING COMPLETED
TOILET FALSE CEILING WORKS GRID CEILING WORKS COMPLETED
KITCHEN GRANITE COUNTER FIXING IN PROGRESS
LIFT LOBBY FINISHING WORKS - IN PROGRESS
LIFT INSTALLATION IN PROGRESS
EXTERNAL TEXTURE PAINTING - IST COAT COMPLETED
BELLAMY BLOCK
TERRACE OVER HEAD TANK FINISHING WORKS - COMPLETED
EXTERNAL PLASTERING WORK - UNDER PROGRESS. 90% COMPLETED
MARBLE LAYING WORKS COMPLETED UPTO 14TH FLOOR, PENTHOUSE IS IN PROGRESS
BATHROOM/KITCHEN TILING WORKS ARE IN PROGRESS
CEILING PAINTING WORKS ARE IN PROGRESS
STAIRS GRANITE FLOOR WORKS COMPLETED
STAIRS M.S RAILING WORKS - COMPLETED
TOILETS MARBLE COUNTER FIXING IN PROGRESS
UNITS ELECTRICAL WIRING STARTED
FIRE SAFETY WORKS COMPLETED UPTO 11TH FLOOR
WINDOWS FIXING IN PROGRESS
BALCONY S.S RAILING FIXING & GRANITE COPING WORKS - IN PROGRESS
-
RAYA BLOCK
INTERNAL 1ST COAT PAINTING COMPLETED
DOOR FRAMES FIXING COMPLETED
DOOR SHUTTERS FIXING IN PROGRESS
TILING WORKS AT ALL THE BATH ROOMS COMPLETED
TILING WORKS AT KITCHEN & UTILITY COMPLETED
CORNICE WORKS COMPLETED
WINDOWS FIXING COMPLETED
TOILET FALSE CEILING WORKS GRID CEILING WORKS COMPLETED
LIFT LOBBY FINISHING WORKS ARE IN PROGRESS
LIFT INSTALLATION IN PROGRESS
BONARO BLOCK
TERRACE OVER HEAD TANK FINISHING WORKS - COMPLETED
EXTERNAL PLASTERING WORK - UNDER PROGRESS. 93% COMPLETED
MARBLE LAYING WORKS COMPLETED UPTO 14TH FLOOR, PENTHOUSE IS IN PROGRESS
BATHROOM/KITCHEN TILING WORKS ARE IN PROGRESS
CEILING PAINTING WORKS ARE IN PROGRESS
STAIRS GRANITE FLOOR WORKS COMPLETED
STAIRS M.S RAILING WORKS - COMPLETED
TOILETS MARBLE COUNTER FIXING IN PROGRESS
UNITS ELECTRICAL WIRING STARTED
FIRE SAFETY WORKS COMPLETED UPTO 14TH FLOOR
WINDOWS FIXING IN PROGRESS
BALCONY S.S RAILING FIXING & GRANITE COPING WORKS - IN PROGRESS
TERRACE WATERPROOFING WORKS ARE IN PROGRESS
-
KADIN BLOCK
INTERNAL 1ST COAT PAINTING COMPLETED
DOOR FRAMES FIXING COMPLETED
DOOR SHUTTERS FIXING IN PROGRESS
MARBLE 3RD AND 4TH COAT POLISH IN PROGRESS
TILING WORKS AT ALL THE BATH ROOMS COMPLETED
TILING WORKS AT KITCHEN & UTILITY COMPLETED
CORNICE WORKS COMPLETED
WINDOWS FIXING COMPLETED
TOILET FALSE CEILING WORKS GRID CEILING WORKS COMPLETED
KITCHEN GRANITE COUNTER FIXING IN PROGRESS
LIFT LOBBY FINISHING WORKS ARE IN PROGRESS
LIFT INSTALLATION IN PROGRESS
EXTERNAL TEXTURE PAINTING 1ST COAT IN PROGRESS
CARA BLOCK
TERRACE OVER HEAD TANK FINISHING WORKS - COMPLETED
EXTERNAL PLASTERING WORK COMPLETED
MARBLE LAYING WORKS COMPLETED UPTO 14TH FLOOR, PENTHOUSE IS IN PROGRESS
BATHROOM/KITCHEN TILING WORKS ARE IN PROGRESS 90% COMPLETED
CEILING PAINTING WORKS ARE IN PROGRESS
STAIRS GRANITE FLOOR WORKS COMPLETED
STAIRS M.S RAILING WORKS - COMPLETED
TOILETS MARBLE COUNTER FIXING IN PROGRESS
UNITS ELECTRICAL WIRING IN PROGRESS
FIRE SAFETY WORKS COMPLETED UPTO 14TH FLOOR
WINDOWS FIXING IN PROGRESS
EXTERNAL PAINTING WORKS IN PROGRESS
BALCONY S.S RAILING BASE PLATES FIXING & GRANITE COPING - IN PROGRESS
-
SUHUBA BLOCK
INTERNAL 1ST COAT PAINTING COMPLETED
DOOR FRAMES FIXING COMPLETED
DOOR SHUTTERS FIXING IN PROGRESS
MARBLE 3RD AND 4TH COAT POLISH IN PROGRESS
TILING WORKS AT ALL THE BATH ROOMS COMPLETED
TILING WORKS AT KITCHEN & UTILITY COMPLETED
CORNICE WORKS COMPLETED
WINDOWS FIXING COMPLETED
TOILET FALSE CEILING WORKS AND GRID CEILING WORKS COPMLETED
KITCHEN GRANITE COUNTER FIXING IN PROGRESS
LIFT LOBBY FINISHING WORKS ARE IN PROGRESS
LIFT INSTALLATION IN PROGRESS
EXTERNAL TEXTURE PAINTING IST COAT COMPLETED.
PODIUM
PODIUM CENTRE COURTYARD FOCAL TREE YARD RETAINING WALL COMPLETED
OTHER EXTERNAL DEVELOPMENT WORKS:
SEWERAGE TREATMENT PLANT STRUCTURE WORKS - COMPLETED
COMPOUND WALL WORK - ON SOUTH & EAST SIDE - COMPLETED
BASEMENT RAINWATER COLLECTION PITS 4 NOS. - COMPLETED
BASEMENT FLOOR ANTI TERMITE TREATMENT WORKS, SOLING WORKS & PCC WORKS
ARE COMPLETED
BASEMENT FLOOR DRAIN WORKS ARE IN PROGRESS
BASEMENT ELECTRICAL CABLE TRAY WORKS IN PROGRESS
BASEMENT FIRE SAFETY RING MAIN WORKS ARE IN PROGRESS
AMENITY BLOCK STRUCTURAL WORKS COMPLETED UPTO TERRACE,
BLOCK WORKS AND PLASTER FINISHES ARE IN PROGRESS
CLUB HOUSE FIRST FLOOR SLAB SHUTTERING WORKS ARE IN PROGRESS
SWIMMING POOL- R.C BASE SLAB AND SIDE WALL CONSTRUCTION IN PROGRESS
PODIUM WATERPROOING WORKS AND LANDSCAPE WORKS IN PROGRESS
-