VERITAS Facili.es Steve Criswell VERITAS Ops. Rev., December 2009 1

Upload: phungmien

Post on 21-Apr-2018

219 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

VERITAS  Facili.esSteve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  20091

Page 2: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

VERITAS Facilities

• Provided  by  SAO

• Site  in  Na.onal  Forest

• U.li.es  at  basecamp

• Backup  power  at  basecamp

• Offices,  electronics  labs,  and  storage  at  basecamp

• Founda.ons  for  telescopes  and  electronic  sheds

• Mirror  lab  at  basecamp

• Vehicles  for  transport

• Heavy  equipment  (maintenance  and  opera.on)

• Communica.ons

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 2

Page 3: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

Current FacilitiesTasks

• In  2009,  Telescope  1  was  relocated  on  budget  and  ahead  of  schedule  using  NSF  construc.on  funds.  (~$270k)

• Smithsonian  maintenance  funding  -­‐  Off  Budget

• Mirror  lab  ven.la.on  upgrade.  (~  $60k)  -­‐  Completed

• Upgrade  the  UPSs  and  ba[eries.    Reinforce  the  shed  founda.ons.  (~$50k)  -­‐  Requested

• Upgrade  FLWO  wide  communica.ons.  (~$100k)  -­‐  Requested

• Repave  basecamp  pavement  and  Telescope  3  area    (~$30k)  -­‐  Requested

• Control  Building

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 3

Page 4: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

• VERITAS  has  displaced  several  support  employers  from  their  offices.  (JW,  ML,  MMT,  TW)

• FLWO  projects  have  lost  drop  offices.

• VERITAS  is  paying  $357/month  to  rent  a  trailer  that  is  too  small  for  our  technicians.

• The  basecamp  bedroom  was  converted  to  the  VERITAS  control  room.

• During  summer  when  collaborators  are  here,  we  have  to  eat  lunch  in  shics.

• VERITAS  has  no  offices  for  observers  (3)  or  visi.ng  collaborators  during  the  summer.

• FLWO  has  no  offices  for  visi.ng  scien.sts.

Why a Central Control Building is Needed.

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 4

Page 5: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

Central  Control  Building  Status

• Conceptual  design  and  Forest  Service  approval  is  complete.

• Final  design  is  at  68%.

• Design  and  building  will  be  LEED  cer.fied.

• Should  have  bids  in  March  2010.

• To  save  $s,  we  dropped  the  dorm  and  reduced  the  floor  area  from  4,500  to  3,000  sf.  Lack  of  day  sleeping  rooms  forces  observers  to  drive  to  the  mountain  acer  a  nights  work.

• Central  building  is  mostly  funded  by  SI.

• We  may  have  money  problems.

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 5

Page 6: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

VERITAS  Central  Building  1

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 6

Page 7: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

Computer

Control

Storage

Open  Office

Office

Office

Lab

Conference

VERITAS  Central  Building  2

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009

Kitchen

7

Page 8: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

VERITAS  Central  Building  3

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 8

Page 9: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

Central Building Cost Estimate 4

Item Estimate Subtotal

Base Bid w 10% MR. $937k

1. Lower Wall $15k

2. Glass Walls $39k

3. Folding Wall $12k

4. Rain Collection $1k

5. Work Benches $5k*

6. Central UPS $55k*

7. Concrete Floors $11k

All Options Subtotal +$138k

Furnishings +$80k

Construction Administration

+$30k

Less Opt. Deleted * -$60k

Grand Total Cost Est. $1,125k

Architect EstimateDec. 2009

NSF Construction - Unencumbered

$680k

NSF Construction - Encumbered

$194k

SI Construction $910k

Total $1,784k

Funding w NSF encumbered & unencumbered $’s

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009

NSF Construction - Encumbered

$194k

SI Construction $910k

Total $1,104k

Funding w only NSF encumbered $’s

9

$659k Surplus

$21k Shortfall

Page 10: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

End  VERITAS  Facili.es  

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 10

Facili.es  Backup  Slides  Follow

Page 11: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

65% Bid Options

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 11

# Descrip.on $

1 Removes  top  half  of  exis.ng  CMU  wall. $14,789

2 Adds  interior  glass  walls. $38,906

3 Adds  accordion  par..on  to  separate  conference  from  kitchen. $11.930

4 Adds  water  collec.on  system  with  cistern. $1,242

5* Adds  built-­‐in  work  counters  in  lab  and  control  room. 4,795

6* Adds  central  UPS  unit  and  wiring. 54,857

7 Replaces  .le  floor  with  finished  concrete  floor. $11,340

Total $137,859

Page 12: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

• Construc)on  stopped  in  April  of  2005.    (5  founda.ons,  water  tank,  underground-­‐u.li.es,  power  entrance  and  powerline  road)  (~  $1,000k).

• The  Horseshoe  Canyon  recontouring  and  revegeta)on  cost  es.mate  report  is  underway.    Recontouring  and  revegeta.on  tasks  are  undefined  and  costs  are  unknown.

• Ques.ons

• If  we  are  giving  the  report  to  the  Na.on,  how  should  it  be  edited?

• Are  we  burying  or  removing  the  Horseshoe  Canyon  infrastructure?

• Will  any  NSF  construc.on  funds  be  available  for  the  Central  building  construc.on?  (~~  $200k).

Horseshoe  Canyon

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 12

Page 13: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

Discussion of Risks

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 13

Page 14: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

• I  have  listed  the  major  risks  that  threaten  VERITAS  on  a  separate  spreadsheet.    In  the  following  slides  I  comment  on  some  of  these  risks.

• We  have  examined  these  risks  to  identify  any  low  cost  actions  we  could  take  to  significantly  reduce  the  risks.    The  actions  we  have  taken  are  listed.  

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009

Risks 1

14

Page 15: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

• Lightning  strikes  could  take  out  a  lot  of  expressive  electronics.  We  shutdown  for  the  monsoons,  installed  lightning  rods  and  are  located  in  a  valley.  We  have  had  only  one  minor  strike  in  the  first  three  years  of  operations.

• Funding  reductions  or  terminations  are  a  constant  threat  to  government  funded  programs.    We  do  good  science,  make  presentations  and  hope  for  the  best.

• Optics  Support  Structure  (OSS)  collisions  could  damage  the  OSS  or  the  positioner.    We  have  had  4  collisions.  In  all  cases,  the  OSS  bent  what  it  hit  and  sustained  no  damage.    We  have  increased  training  and  are  investigating  additional  interlocks.  

• We  are  42  miles  from  the  nearest  hospital.  

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009

Risks 2

15

Page 16: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

• The  original  VERITAS  designers  are  starting  to  disperse.    For  the  most  part,  they  are  retaining  their  connection  to  VERITAS.    The  collaboration  has  modified  its  rules  to  encourage  this.

• We  have  one  mirror  recoating  technician  to  strip,  clean,  recoat  and  anodize  250  mirrors  a  year.      If  he  were  to  leave,  we  would  loose  this  ability.    Currently  industry  is  not  setup  to  do  this  work.    If  they  were,  we  would  have  to  pay  ~  $1,000/mirror.    If  this  were  to  occur,  we  would  hire  and  train  a  new  technician  using  the  original  design  engineer  as  a  teacher.

• Washington  University  designed  and  built  the  FADC  boards.    These  large  complex  boards  have  a  very  low  failure  rate  and  we  keep  spares.    Nonetheless,  if    WU  was  not  available  to  repair  these  boards,  it  would  be  difficult  to  find  these  skills  elsewhere.

• Mirror  lab  vacuum  pump  ($30k)  is  a  single  point  of  failure.    Upgrade  will  provide  a  new  pump  and  current  pump  will  become  the  spare.

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009

Risks 3

16

Page 17: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

Risks 4• The  scientific  and  engineering  VERITAS  staff  is  limited.  Proposals  have  been  

submitted  for  AGIS  and  the  VERITAS  upgrade.    If  awarded,  these  projects  can  impact  VERITAS  Operations.    Fortunately,  most  of  the  work  for  both  projects  takes  place  at  the  collaborating  institutions  not  the  VERITAS  site.

• Wild  fires  are  always  a  risk  in  unpopulated  areas.    We  work  with  the  Forest  Service  to  reduce  the  fire  risk.    The  location  of    VERITAS  in  a  flat  area  with  roads,  few  trees  and  a  water  supply  reduce  the  danger  somewhat.

• Black  helicopters  with  search  lights  are  the  natural  enemies  of  astronomers.    We  work  with  the  Border  Patrol  and  have  had  few  issues.

• At  night  the  basecamp  area  is  active  with  UDAs  drug  transporters  and  government  agencies  chasing  them.    We  brief  observers  and  have  had  few  problems  since  the  basecamp  was  occupied  in  1990.

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 17

Page 18: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

End of Risk Slides

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 18

Page 19: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 19

Safety  and  Environmental  

Page 20: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

• The  VERITAS  site  is  inspected  yearly  by  a  team  of  specialists  from  DC.    A  copy  of  this  years  report  is  available  at  the  review  site.

• All  visiting  observers  must  complete  a  30  minute  safety  briefing  before  they  work  a  shift  for  the  first  time.

• All  manlifts,  cranes,  forklifts  are  inspected  yearly  by  a  independent  inspector.

• All  crane  and  lift  operators  take  yearly  training.

• Harnesses  are  worn  for  all  operations  above  10  feet.

• Bears,  ringtailed  cats  and  rattle  snakes  have  been  observed  within  the  basecamp.  Observers  are  told  to  use  flashlights  and  not  to  feed  wild  life.

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009

Safety and Environmental

20

Page 21: VERITAS(Faciligibbs/VERITAS_OpsReview...Central Building Cost Estimate 4 Item Estimate Subtotal Base Bid w 10% MR. $937k 1. Lower Wall $15k 2. Glass Walls $39k 3. Folding Wall $12k

• Fire  drills  are  conducted  twice  a  year.

• All    waste  is  disposed  of  using  the  FLWO  HazMat  waste  disposal  systems.

• First  aid  (and  CPR)  training  is  conducted  yearly.

• Respirators  and  special  ventilation  systems  are  used  for  mirror  stripping.

•  Hard  hats  are  used  for  all  lift  operations.

• Observing  crews  are  always  at  least  3  persons.  

• Most  observers  stay  at  the  ridge  dorm.    This  requires  mountain  driving  after  a  nights  work.    Mountain  driving  advice  to  provided  to  new  observers.

• There  were  no  injuries  during  the  relocation  of  telescope  1.

• For  the  entire  VERITAS  project,  there  have  been  no  night  time  injuries  and  two  lacerations  and  a  shoulder  injury  during  the  day.

Steve  Criswell  -­‐  VERITAS  Ops.  Rev.,  December  2009 21