Report as on 10.11.09 ATR STATUS AT GLANCE W.G.IV Meeting Feedback/ Objection Suggestion from AAUI PWD MCD NDMC Delhi Traffic Police Others Total Cases Closed/ Repetition Total on from Ex. Eng., UTTIPEC, DDA Total received from AAUI for ATR (A+B+C) 19 (17) S.No.29,31 Shifted to N.H.A.I. 26 (20) S.No. 10 shifted to D.T.P. 4 (4) 30 (25) S.No. 10 with D.T.P. from M.C.D. 11 (9) (4 with NHAI & one to be discussed with PWD/DTP/ DMRC & one with DIMTS, 1 with Railway) 90 (75) 2 (2) 88 (73) S.no.35 case with PWD/DTP Sno. 54 case with DTP/MCD Photograph attached (2,7a,7b,1 5a, 15b,16,17, 18,20, 22a,25a,26 a,30a) Action completed by Agency (A) 14 (14) S.No. (2,6,7a,9,1 5a,15b,16,1 7a,25a,26a, 9 (8) S.No. (4,7b,18, 20,21, 4 (4) S.No. (3, 5a,23a, 9 (9) S.No. (1,5c,7c, 8a,8b, 0 36 (35) 1 (1) S.No. (,34,Satish Sudan 35 (34) Photograph attached (2, 9, 16, 15a, 30a PWD), S.No. (13,21) also verified SNo. 1/99 DELHI DEVELOPMENT AUTHORITY UTTIPEC, 2 Email: [email protected] The summarized details of the ATR on each of the feedback/objection/suggestion received through AAUI Status of Road Owning Agencies A. Action completed by Agency B. Action under process C. Action not yet initiated by

Upload: ngonga

Post on 13-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

Report as on 10.11.09

ATR STATUS AT GLANCE W.G.IV Meeting

Feedback/Objection

Suggestion from AAUI

PWD MCD NDMC Delhi Traffic Police

Others Total Cases Closed/ Repetition

Final Total Remarks Verification from Ex. Eng., UTTIPEC, DDA

Total received from AAUI for ATR (A+B+C)

19 (17)

S.No.29,31 Shifted to N.H.A.I.

26 (20)

S.No. 10 shifted to

D.T.P.

4 (4)

30 (25)

S.No. 10 with D.T.P. from

M.C.D.

11 (9)

(4 with NHAI & one to be

discussed with PWD/DTP/ DMRC

& one with DIMTS, 1 with

Railway)

90 (75)

2 (2)

88 (73)

S.no.35 case with PWD/DTP

Sno. 54 case with DTP/MCD

Photograph attached

(2,7a,7b,15a, 15b,16,17,18,2

0, 22a,25a,26a,30

a)

Action completed by Agency (A)

14 (14) S.No.

(2,6,7a,9,15a,15b,16,17a,25a,26a,26b,27a,30a,3

4a)

9 (8)

S.No.(4,7b,18,20,21, 22a,22b,25b,

34b)

4 (4)

S.No.(3, 5a,23a,

23b)

9 (9)

S.No. (1,5c,7c, 8a,8b, 11,13,

30b,42)

0 36 (35)

1 (1)

S.No.(,34,Satish Sudan regarding Outer Ring Road)

(PWD)

35 (34)

Photograph attached (2, 9, 16, 15a, 30a PWD), (3,5a NDMC, 4, 18, (MCD).

S.No.(13,21) also verified

SNo.(1,2,3,4,6,7a,7b

, 7c, 15, 18,20,22a,

23b,25a,25b,26a,27a)

Feedback/Objection

Suggestion

PWD MCD NDMC Delhi Traffic Police

Others Total Cases Closed/ Repetition

Final Total Remarks Verification from Ex. Eng., UTTIPEC, DDA

1/99

DELHI DEVELOPMENT AUTHORITY UTTIPEC, 2ND FLOOR, VIKAS MINAR, ITO,NEW DELHI Email: [email protected] summarized details of the ATR on each of the feedback/objection/suggestion received through AAUIStatus of Road Owning Agencies

A. Action completed by AgencyB. Action under processC. Action not yet initiated by the Agency

Figures in bracket as on 29.09.09

Page 2:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

from AAUI Action under process (B)

1 (1)

S.No.( 27b)S.No. 29

shifted to NHAI

4 (5)

S.No.(12,19, , 24, 33) S.No. 10 shifted to

DTP

0 15 (15)

S. No. (10 ,17b, 26c 28a,28b, ,35,

40,41b, 43,44,45,46,47,48,53)10 from M.C.D

5 (5)

S.No.(14, DMRC)

S.No. 17c with DIMTS

S.No. 31b with Railway.

S.No. 29 with NHAI

39 DDA Dwarka

25 (26)

1 (1)

33,TK Malhotra regarding Nallah

of Saket(MCD)

24 (25)

A photograph of work under

progress only is given

S.No.21,24MCD)

Action not yet initiated by the Agency (C)

4 (2)

S.No. (35,36,58,61)31a shifted to

NHAI, 31b shifted to Railway)

13 (7)

37,38,49,50,51,52,54,55,56,59,60,61,

62

0 6 (1)

54,56,57,58,60,62

6 (4)

S.No.(5b, 31a,32,)

NHAI, ,41a DIMTS, 57 DIMTS, 62

Railway.

29 (14)

29 (14)

MONITORING SHEET ATR Status as on 10.11.09

2/99

Figures in bracket as on 29.09.09

Page 3:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

DELHI DEVELOPMENT AUTHORITY UTTIPEC, 2ND FLOOR, VIKAS MINAR, ITO,NEW DELHI

TELE. FAX. 23379043Email: [email protected]

AAUI ROAMING AMBASSADORS COMPLAINTS/OBSERVATION RECIVED AND FORWARDED BY WORKING GROUP- IV (UTTIPEC) TO ROAD OWNING AGENCIES.

S.No Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

1

A

Mr. D K Bindra 10.11.08Press Enclave Road close to Sheikh Sarai Ph-II….Red Light Pole missing

Received in WG-IV meeting held on 18.12.2008.

Delhi Traffic Police on 3.2.09

Action Completed

As per report given by DTP dated 17.3.09 & 22.5.09 one pole of the traffic signal at Press Enclave Road- Bhagat Singh College has been damaged due to road accident. Work order to the signal maintaining agency has already been issued. New pole is likely to be installed very shortly.As per ATR dated 15.06.09, one pole

1.[As communicated by Dir. (M), PWD, vide letter dated 02.03.09, the matter pertains to Delhi Traffic Police]

2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, and matter pertains to Delhi Traffic Police.

As per report received on 19.08.09 Site-Inspected dated 18.08.09 Missing pole has been fixed.

3/99

Action completed by Agency Action under process Action not yet initiated by Agency

Page 4:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

which was damaged in a road accident has been installed.

S.No Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

2

A

Mr. Ramesh Grover

12.12.08 Defence Colony and CGO Complex…. Poor condition of Subways

Received in WG-IV meeting held on 06.01.2009.

PWD on6.1.09

Action completed.

[As communicated by Dir. (M), PWD, vide letter dated 02.03.09, Subway is cleaned]

As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, and subway cleaned.

As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, work completed.Photograph attached

Lights have been provided and no garbage exists in Sub-way of Defense Colony and CGO Complex. However subways are not cleaned regularly. Both subways are being used by public. Site inspection was carried out on 3.3.09. Photograph attachedAs per letter dated 18.05.09, security guard was on duty, lights were functioning, some steps of stair case found broken, subway was not properly cleaned, railing along steps and one door frame also missing.

4/99

Page 5:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No Name Date of complaint

Brief Description of complain Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

3.

A

Mr. Mahendra Raj

12.12.08 Prithviraj Road ….. Bad Pedestrian Walk Ways

Received in WG-IV meeting held on 06.01.2009

NDMC on 6.1.09

Action completed.

(a) The repairs to the damaged footpath of Prithviraj Road have been carried out. However the whole footpath has been taken up for improvement in the Pavement Improvement Plan.

(b) Tenders have been issued and date of receipt of tender is 03 Mar.’09.

(c) The work is expected to complete within 06 months of award of work.

Photographs of Prithivaj Road are enclosed.

1. As communicated by Dir. (M), PWD, vide letter dated 02.03.09, the matter pertains to NDMC]

2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, and the matter is not with PWD.

As per report received 19.08.09 Site- inspected dated 18.08.09 about 70% of improvement work of the payment/walk-ways completed. Balance work is in progress.

5/99

Page 6:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No.

Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

4.

A

Mr. S Chandrasekhar

13.12.08 Bhikaji Cama Place & Nand Vithi Road … Loose/Broken wires

Received in WG-IV meeting held on 06.01.2009

MCD on 06.01.2009

ATR Completed

As per report given by Ex. Engineer (P)-I, MCD dated 29.5.09 Chief Engineer (Elect.) has reported that Bhikaji Cam Complex is maintained by DDA and loose wires on Nandi Vithi G.K. Part-I fall in the jurisdiction of MCD. The loose wire has been removed by BSES. The photographs before and after are attached.

1. For Nand Vithi Rd. PWD has conveyed that location is not clear.2. [As communicated by Dir. (M), PWD, vide letter dated 02.03.09, the matter pertains to MCD]3. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11 , PWD, the matter is not with PWD.00

As per report received on 19.08.09 Site-inspected dated 18.08.09 loose wires at “nand-Vithi Road” have been tightened. Whereas site of Bhikaji Cama Place has not been attended by the concern deptt.

6/99

Page 7:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

5.

A

Mr. Rajiv Sikri 13.12.08 a) Aurobindo Marg …. Badly planned divider is the U' turn on Aurobindo Marg just after the AIIMS flyover (between AIIMS and Yusuf Sarai)

Received in WG-IV meeting held on 06.01.2009

NDMC6.1.09

Action Completed

(a) The divider (split rotary) on Aurobindo Marg just after AIIMS flyover (between AIIMS & Yusuf Sarai) was constructed by PWD during the construction of AIIMS flyover between2003 2005. The split rotary has not been handed over by PWD to NDMC & is being maintained by them.

The photographs of divider are enclosed.

As can be seen from the photographs due to limited space available in Right of Way of Road it is no feasible to widen the divider (‘U’ turn).

1. This issue will be discussed in working Group-2B with DMRC, Delhi Traffic Police and PWD.

2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, and this stretch is with NDMC.

As verified dated 14.07.09 This complaint has been referred to W.G II-B

7/99

Page 8:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

C

A

b) Delhi Gurgaon Road -- No warning signs to Indicate that there is a concrete divider in road.

C) Mathura Road, Ring Road crossing at Ashram chowk & Shanti Path/Ring road crossing at Moti Bagh, the crossing of Tito marg, Aurbindo Marg, Africa Avenue with Outer ring Road….At major crossings where there is a heavy traffic volume turning right, there must be separate traffic signals…..

NHAI / others on16.2.09

D T P06.01.2009

ATR pending

Action Completed

As per report given by DTP on 22.5.09 the signals are already installed. The facing of the signals at these locations have been undertaken as per the volume and junction geometric. Provision for separate right turning movements at these locations is already available at these junctions.

1. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, issues not clear, is this reference about Central Verge or Something else

As per report dated 14.07.09 site inspected by the F.I on 07.07.09 Right turn signal at all the stated locations have already been fixed and functional.

8/99

Page 9:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

6.

A

Mr. Hari Dang Padmashree

5.12.08 East Delhi/Raj Ghad/Delh/NCR/Toll Plazas/BoarderPosts/Check Points/Expressways …. Bad RoadConditions in above quoted areas.

Received in WG-IV meeting held on 06.01.2009

PWD on6.1.09

Action Completed

Yes 1. Mostly roads are in good condition i.e Rajghat road. Bhopura border to Hindon Air force station is not under the jurisdiction of Delhi PWD; matter pertains to govt. of UP, PWD. The condition of the road with PWD jurisdiction is satisfactory.2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, no specific location mentioned.As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, work completed.

As per report dated 25.5.09 inspection not required because as per ATR most of the roads are in good condition and no further repair work has been undertaken by PWD after receipt of the complaint.

9/99

Page 10:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No.

Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

7.

A

Mr. Jagjyoti Jain

29.11.08 a) Naraina Under Pass- No light in Subway near Border Roads Organization

Received in WG-IV meeting held on 08.12.2009

PWD on10.12.08

Action Completed

Yes 1. As communicated by Dir. (M), PWD, vide letter dated 02.03.09, light is functional. 2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, subway lights area working.As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, work completed.

As verified on 4.3.09 lights have been provided in the Naraina “underpass”.Photograph Attached

10/99

Page 11:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No.

Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

A

A

b) Rajouri Garden Ring Road facing Madhav Park….Verge is wrong place.

c) Rajouri Garden Ring Road Near PedestrianBridge … Verge closed by stop light still operates.

MCD on10.12.08

Delhi Traffic Police on 10.12.08

Action Completed

Action Completed

As per report given by DTC on 22.5.09 and 15.06.09, the signal at Ring Road-MS Marg near Raja Garden Flyover is working as a Pelican Signal since large number of pedestrian cross the road at this location. The newly constructed F.O.B. is at 800 mtrs away from this location; therefore, the signal has not been closed. The Pelican Signal is required at the location for safe pedestrian crossing.

As per ATR dated 19.03.09 from Project Manager, CWG/M-11, PWD, it pertains to M-3, PWD.1. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, and matter relates to Delhi Traffic Police.

Although no ATR received so far from MCD but site was inspected on 4.3.09 and it was found that Central Verge was closed.Site was inspected 4.3.09 and it was found that traffic signal is still operating. By ATR from DTP was received on 17.3.09 and as per ATR the signal at Ring Road – Ms Mang hoor Raja Garden flyover is working as a Pelican Signal since large number of pedestrian cross the road at this location. The newly constructed F.O.B. is at 800 mtrs. Away from this location, therefore, the signal has been closed. The pelican signal is required at the location for safe pedestrian crossing.

11/99

Page 12:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No.

Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

8.

A

A

Mr. N.K. Sethi 2.12.08

3.12.08

A) Mathura Road & Jangpura Extn. (Hospital Road) … Traffic Jam

b) Outer Ring Road & Nehru Place(Hemkunt Tower) …..Traffic Jam

Received in WG-IV meeting held on 08.12.2008.

Delhi Traffic Police on 10.12.08

Delhi Traffic Police on 10.12.08

Action Completed

Action Completed

As per report given by DTP dated 17.3.09 and 22.5.09 and 15.06.09 regular action is being taken by the area traffic officers against u/a parking of vehicles. Cranes are deployed which tow away the obstructively/unauthorized parked vehicles.

As per report given by DTP dated 17.3.09 and 22.5.09 regular action is being taken by the area traffic officers against u/a parking of vehicles. Cranes are deployed which tow away the obstructively/unauthorized parked vehicles.

1. As communicated by Dir. (M), PWD, vide letter dated 02.03.09, matter pertains to Delhi Traffic Police.

2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, and matter pertains to Delhi Traffic Police.

1. As communicated by Dir. (M), PWD, vide letter dated 02.03.09, it is a Delhi Traffic Police matter, it does not pertains to Engg. Deptt., MCD

2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, and matter pertains to Delhi Traffic Police.

As per report dated 14.07.09 As per ATR status dated 11.06.09 necessary arrangement to remove the unauthorized parked vehicles have been made by D.T.P Since the problem of recurring nature, therefore site inspection has not been carried- out

As per report dated 14.07.09 As per ATR status dated 11.06.09 necessary arrangement to remove the unauthorized parked vehicles have been made by D.T.P Since the problem of recurring nature, therefore site inspection has not been carried- out

12/99

Page 13:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

9.

A

Mr. A.V. Anand

5.11.08 Portion of Outer Ring Road from opposite site of Savitri Cinema, G.K.-II & Outer Ring Road towards Panchsheel … Open manhole covers & worn Out road surface.

Received in WG-IV meeting held on 06.01.2009

PWD on 6.1.09

Action Completed

Open manholes covered. Road surface shall be improved by 15.03.2009

1. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, open manholes covered. Road surface being improved.2. As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, work completed.Photograph Attached.

Road surface found repaired, manholes were not found in the level of road surface,

13/99

Page 14:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

10.

B

Mr. T.K. Malhotra

3.12.08 Pavement opp. PVR Saket (main road) & QutabInstitutional Area…. Wholly encroached by Dhabas,PCO, Kiosk, Fruit Walla, Barber, Shoe Maker,Paan stalls and even Police Booth.

Received in WG-IV meeting held on 18.12.2008.

Engineer in ChiefPWD & Engg.in Chief MCD on 22.12.08

Delhi Traffic Police

Action Under process

1. Matter pertains to Licensing Deptt. Of South Zone.

As per report given by MCD dated 17.3.09 action to remove encroachments has already been fixed for 20th March, 09.

2. Also as per report given by MCD dated 17.3.09 joint inspection was conducted on 19.02.2009 and certain structures were removed.

3. As per report received from MCD Office of Assistance Commissioner (South Zone) dated 29.09.09 action taken is same as action taken dated 17.07.09 from MCD Office.

1. [As communicated by Dir. (M), PWD, vide letter dated 02.03.09, the matter pertains to Delhi Traffic Police]2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, and matter pertains to MCD.As per ATR dated 12.06.09 and 10.7.09 from Dy. Director (Maintenance), matter pertains to Delhi Traffic Police. As per ATR Dated 17.07.09 from MCD Office assistance commissioner(south zone)Saket PVR Area:A number of regular encroachment removal actions were carried out by the Enforcement Branch of South Zone during recent weeks. Actions were carried out on 14.01.09,

14/99

Page 15:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

05.02.09, 09.02.09 and 19.02.09&28.05.09. On saket road which connects the press Enclave Road to MB road, there are 13 authorized tehbazaris which are carrying out different kind of trades including Paan stalls, Shoe maker ,PCO,MCD under approval from justice RC Chopra Committee constituted order of Hon’ble Supreme Court in the matter of ‘Gainda Ram Vs UOI&Ors’.Out of these 13 tehbazaris, 3 tehbazaris were running the trade of eatable and cooking was also involved. Regular actions to seize their good were carried out which are visible in the photograph. Action shall be repeated as and when required.Request letter to DCP (South) was also issued to issue

15/99

Page 16:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

instructions to the local police officials to ensure that re-encroachment does not take place. It is planned to relocated/shift these tehbazaris sites to some other nearby areas so that no more blockage on PVR Road appears. One potential site for shifting of these tehbazaris has been located in Pushpavihar where some developmental work is under progress. Some other site is also been examined and the tehbazaris shall be shifted as soon as the feasibility of proposed site is established.Photograph AttachedQutub Institutional Area: A joint enforcement action by health and licensing department was carried out on19.02.09, 26.02.09, 27.05.09.

16/99

Page 17:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

During action various temporary structures raised by the taxi stands in the Institutional area were demolished. Many unauthorized eateries, which were being run in temporary tin-structures, were also removed with the help of JCB.During the action a large number of articles were seized. A letter to DCP (south) was also issued to ensuring that re-encroachment does not take place. Photographs of encroachment removed are enclosed in CD.The encroachment removal action shall continue as and when requiredPhotograph Attachment

17/99

Page 18:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status

Details of Action taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

11.

A

Mr. T.K. Malhotra 3.12.08 Junction at PVR Saket Chowk -- Traffic SignalProblems.

Received in WG-IV meeting held on 18.12.2008.

Delhi Traffic Police on 22.12.08

Action Completed

As per report given by DTP dated 17.3.09 signalized junction at PVR Saket has been made functional. The rusted poles shall be removed and new poles shall be installed.As per report given by DTP dtd. 22.5.09 the signalized junction at PVR Saket is made fully functional. As per report given by AAUI dated 25.08.09 the signalized junction at PVR Saket has been made fully functional. However, for re-location of singnal hardware as per the suggestion of Sh.T.K Malhotra the same is being studied for implementation.

1. [As communicated by Dir. (M), PWD, vide letter dated 02.03.09, the matter pertains to Delhi Traffic Police]

As per dated14.07.09 Site- inspected by J.E.(C) dated10.07.09 at10.05AM and again on 13.07.09 at about 11.47AM &obsevered that “No” Signal is functioning Rusted-Poles have also not been remove still.

S.No. Name Date of Brief Description of complaint Date of Forwarded to / ATR Details of Action Remarks Verification

18/99

Page 19:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

complaint discussion WG-IV of UTTIPEC meeting.

Date Status Taken from Ex. Eng., UTTIPEC, DDA

12.

B

Mr. T.K. Malhotra 3.12.08 Opp. PVR Saket -- over the nallah in the vicinityof the OBC Bank

Received in WG-IV meeting held on 18.12.2008.

PWD/Horticulture (Tree Prunning) on22.12.08 MCD

Action Under process

PWD/MCD to co-ordinate with Horticulture.

1. [As communicated by Dir. (M), PWD, vide letter dated 02.03.09, the matter pertains to MCD]2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, and matter does not pertains to PWD. As Per ATR from MCD received dated 22.07.09 By Dy.director (Hort.) South Zone: Green Park In this regard, it is submitted that light pruining has been done. As regard, heavy pruining, a letter has been sent to Forest Deptt.

19/99

Page 20:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

For permission. After receiving permission from Forest Deptt., heavy pruining will be executed.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status

Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

20/99

Page 21:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

13.

A

Mr. T.K. Malhotra 13.12.08 Received in WG-IV meeting held on 18.12.2008 and 13.02.2009

Delhi Traffic Police on 22.12.08 and 13.02.2009.

Action Completed

As per report given by DTP with ADC (R.P. Cell) dated 17.3.09 regular action is being taken by the area traffic offers.As per report given by DTP dated 22.5.09 and 15.06.09 regular action is being taken by the area traffic offers against u/a parking of vehicles. Cranes are deployed which tow away the obstructively/unauthorized parked vehicles. Boards are being displayed for implementation of one way scheme. Site survey was also conducted with representatives of AAUI also. Action regarding display of parking boards and road marking for parking is to be carried out MCD.

1. [As communicated by Dir. (M), PWD, vide letter dated 02.03.09, the matter pertains to ADC(R.P. Cell) and Delhi Traffic Police]

2.Traffic Police to coordinate with ADC(R.P. Cell)

As per report dated 23.09.09 One crane found deployed by the agency.Yellow-line for parking of vehicles noticed during inspection.Parking beyond yellow line also noticed on “Feroz Gandhi –Marg” and “Veer savarker Marg”. Unauthorized parking also notices on link road i.e. in between “Feroz-Gandhi”&”Veer-Savarkar Marg”.M.S.Board Showing one way traffic noticed at some locations.M.S.Board showing “parking Area” not deployed by the agency

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status

Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

21/99

Lajpat Nagar Central Market (Main Road) …. Threeline parking

Page 22:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

14.

B

Mrs. Veni Mathur 19.12.08 Intersection at Hauz Khas on Aurobindo Marg Received in WG-IV meeting held on 06.01.2009

PWD on6.1.09

DMRC on 16.03.09

Action under process

1. Linked with no. 5 above.2. This issue will be discussed in working Group-2B with DMRC, Delhi Traffic Police and PWD3. [As communicated by Dir. (M), PWD, vide letter dated 02.03.09, This road transfer to DMRC & Traffic Police.4. As per the minutes of the meeting dated 16.3.09 between DTP & DMRC with WG 2B issue has to be sought out by DTP and DMRC.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status

Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

22/99

Page 23:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

15.

A

Mrs. Saroja Vaidyanathan

5.12.08 a) Baba Ganganath Marg Road (going towardsMunirka from Aruna Asaf Ali Road) … ManholesOpen

Received in WG-IV meeting held on 08.12.2008.

PWD on10.12.08

Action completed

Work completed 1. Work shall be completed on 28.2.09 (As ATR PWD)

2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, work completed.

3. As per ATR dated 17.04.09 from Ex. Engineer, PWD CRMD M-112(GOD), New Delhi, work completed.As per ATR

Dated 30.4.2009 from Dy. Dir. (Maint), PWD, work completed.

As per ATR dated 11.5.09 from Ex. Eng. PWD Dn. M-111(NCTD) New Manhole covers has been placed on the open/missing manhole

As verified by FI on 19.3.09 two main holes covered but one main hole yet to be covered.Photograph attached AS per verification dtd. 18.5.09, no manhole covers found missing. S.W. drain and RCC slab of S.W. Drain (mentioned platform in the complaint) found broken at nos. of locations.

23/99

Page 24:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

Ab) Same side of Kendriya Vidyalaya & hajansinghSwimming Academy building Opposite to NIH & FW building … Broken Platforms

PWD on10.12.08

Action completed

Work completed

opening.(Photo enclosed). As per ATR dated 17.04.09 from Ex. Engineer, PWD CRMD M-112(GOD), New Delhi, work completed.

As per ATR dated 30.4.2009 from Dy. Dir.(Maint), PWD , work Completed.

As per ATR dated 11.5.09 from Ex. Eng. PWD Dn. M-111(NCTD New Cerement Concrete slab have been kept at broken/missing platform places.

As per verification dated 18.5.2009 no manhole cover found missing. S.W. drain and RCC slab of S.W. Drain (mentioned platform in the complaint) found broken at nos. of locations.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status

Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

16. Mr. T.K. Malhotra 5.1.09 Mehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction leftIncomplete.

Received in WG-IV meeting held on 06.01.2009

PWD on6.1.09

Action completed

Work completed 1. [As communicated by Dir. (M),

Photograph attachedAs per

24/99

Page 25:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

A PWD, vide letter dated 02.03.09, joint inspection held with AAUI member on 12.02.2009. the work shall be completed within one month.2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, shall be opened for traffic by 25.03.2009.3. As per ATR dated 17.04.09 from Ex. Engineer, PWD CRMD M-112(GOD), New Delhi, it has been mentioned that location of the road was jointly inspected by Sh. T.K. Malhotra, President AAUI and EE, PWD M-112 on 12.2.09 and subsequent

verification dtd. 18.5.09, Work of U turn completed but minor repairs still required.

25/99

Page 26:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

to joint inspection, damaged road surface of U-Turn (Rotary) near DC office Said –ul-Aijab/Anupam Apartments repaired with cement concrete pavement for traffic on 25.3.09.Photograph attachedAs per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, work in progress near to completion.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status

Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

17.

A

Mr. Sunil Gujral 05-01-09 (a) Mehrauli Badarpur Road, U Turn opposite to Saidulajab forest. Received in WG-

IV meeting held

PWD on 13.02.2009

Action completed

Work completed 1. [As communicated by Dir. (M),

26/99

Page 27:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

The road has been broken since the rains and is a nuisance as well as hazard for all traffic taking a ‘U’ Turn.

Action required: Repair of Road.

on 13.02.2008. PWD, vide letter dated 02.03.09, joint inspection held with AAUI member on 12.02.2009. The work shall be completed within one month.

2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11 , PWD, shall be opened for traffic by 25.03.2009

3.As per ATR dated 17.04.09 from Ex. Engineer, PWD CRMD M-112(GOD),New Delhi, it has been conveyed that roads shall be opened for traffic by 25.3.09, CC done, curing in process.

Photograph attachedAs per verification dated 18.5.09 work of U turn completed but minor repairs still required.

27/99

Page 28:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

B

B

(b) Traffic Signal on MB Road opp. to Asiana Market.

Since the light was installed over a year back, it’s been non-functional putting to risk traffic from all sides.

Action required: Fix the traffic signal.

(c) Traffic signal on MB Road & BRT cross-section. No ‘U’ Turn option whereby all traffic towards Sainik Farms has with the traffic coming from other end.Action required: Provide a ‘U’ Turn option at the Red Light.

Received in WG-IV meeting held on 13.02.2009.

Received in WG-IV meeting held on 13.02.2009.

Delhi Traffic Police on 13.2.2009

Delhi Traffic Police on 13.02.2009

PWD/DTP on 13.02.2009

As per the DTP report dated 26.5.09 this issue pertains to DIMTS

Action Under process

Action Under process

As per report given by DTP on 22.5.09 and 15.06.09 work order has been issued to the signal maintaining agency and the work is under progress and is likely to be completed.

As per report given by DTP on 22.5.09 and 5.06.09 matter does not pertain to Traffic Police. Action is to be taken by DIMTS since they maintain the BRT Corridor at this stretch.

As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, work completed.

1. [As communicated by Dir. (M), PWD, vide letter dated 02.03.09, location on U-turn required is not suggested / indicated, whether it is required on MB Road or BRT corridor.

2. As per ATR dated 19.03.2009 from Project Manager, CWG/M-11, PWD, location of U-turn required is not suggested / indicated.

28/99

Page 29:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

Whether it is required on MB Road or BRT Corridor?

3. As per ATR dated 17.04.09 from Ex. Engineer, PWD CRMD M-112(GOD), New Delhi, it has been mentioned that location of U Turn required is not suggested/indicated. Whether it is required on MB Road or BRT corridor?

As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, work under process.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status

Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

29/99

Page 30:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

18

A

Mrs. Arundhati Kotwal

29-01-09 Central Delhi, Karol Bagh Area.

Broken road in Central Delhi, Karol Bagh area. It was broken to replace the old sewage lines two months back. The sewage lines have been replaced but the new road has not been laid.

The exact location is the road leading from Khalsa College, Dev Nagar to Satnagar (Radha Swami Satsang). Entire half side of the road is broken.

Action required: Action required by concerned authorities.

Received in WG-IV meeting held on 13.02.2009.

MCD/ DJB on 13.02.2009

Action Completed

As per report given by Eng.(M)II on 25.05.09 Road cut made by DJB has been repaired by providing mantling Pre-mixing

[As communicated by Dir. (M), PWD, vide letter dated 02.03.09, pertains to MCD]Photograph Attached

Although “No” ATR received so far from M.C.D/D.J.B. But site was inspected on 5.3.09. Road work has been repaired.

As per report dtd. 25.5.09 site was inspected on 21.5.09 and observed that entire stretch of the road has not been repaired as per complaint. This road required relaying.Photograph attached

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status

Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

30/99

Page 31:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

19.

B

Mrs. Veni Mathur 6.2.2009 Hauz Khas

I. Encroachment of public land by Shopkeepers in Hauz KhasAbout 75% of the 8 ft. wide, covered passages (Government Land) meant for walking in front of the shops have been encroached upon, by extending the shops to the end of the colonnade. The people have to walk in the heat and rain while shopping at Hauz Khas E-Block Market and G-Block Market. The shopkeepers even display their goods on the road, forcing the public to walk in the middle of the road, hampering the movement of vehicles.On the sides of the entrance to the central park of the main market – unauthorized, temporary constructions have been erected like juice stall, magazine walas, fruit and vegetable vendors, flower shops, etc. – leaving no area to walk or parking the cars.

Action required: The encroachment – marked with YELLOW – once removed will ensure smooth traffic as well as safety of people, especially elderly citizens in the market area.

Received in WG-IV meeting held on 13.02.2009.

MCD on 13.02.2009

Action Under Process

As per report received from MCD Office Assistant Commissioner (South Zone) dated 29.09.09 is same as report received dated 17.07.09 from MCD Office.

[As communicated by Dir. (M), PWD, vide letter dated 02.03.09, pertains to MCD]As per ATR Dated 17.07.09 from MCD Office assistance commissioner(south zone)I. A major encroachment removal action was carried out on 26.05.09 in G&E Block Market; Hauz Khas by the department .During the action a large number of unauthorized articles kept on public passage were removed. A request to DCP (South) has been made vide L/No. to ensure that re-encroachment does not occur at the site.II.A. There was no construction of commercial establishment found. Only a few hawkers carrying out trade of tea

31/99

Page 32:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

II. Construction of Commercial establishment in the Green Belt Area

A. Construction in the Green Belt Area as shown in the Master Plan between Kaushalya Park and Padmini Enclave,

R-Block Hauz Khas, Pan vendors, tea vendors, Dhabas, stock of building material, vegetable vendor, PCOs have

come up in convenience of local authorities.

B. Connecting road between house numbers G-13 and G-12A Hauz Khas have been blocked and converted into a shop.

C. Side road blocking – By the side of MD International Inn on Aurobindo Marg the side road has been blocked and being used as private parking, thus hampering the flow of traffic at the intersection.Action required: Once the constructed wall is broken down, a smooth traffic flow plan can be put in operation reducing traffic jams near the G-Block market intersection.

stall, mechanic were found and removed during the action on 26.05.09.II.B. The blockage of road between house numbers G-13&G-12A shall be removed by Maintenance department being fixed natured encroachments.III.C. The side road blocking by the side of MD International Inn on Aurbindo Marg by construction of wall shall be removed by Maintenance department being fixed Natured encroachment.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC

Forwarded to / Date

ATR Status

Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

32/99

Page 33:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

meeting.20

A

Mr. T K Malhotra 07-02-2009

Sarvodaya Enclave, South Delhi

The roads are badly fractured and are full of potholes. When driving smoothly these potholes cause a sudden jolt leading to mishaps, which the residents have been witnessing for more than a year.

Action required: Repairs of the potholes and re-carpeting of the road is urgently required.

Received in WG-IV meeting held on 13.02.2009.

MCD on 13.02.2009

Action Completed

[As communicated by Dir. (M), PWD, vide letter dated 02.03.09, pertains to MCD]

As per ATR from Ex. Engineer (Project) South, MCD dated 23.4.09 the work of dense carpeting of roads has been completed in Sarvodaya Enclave.

Site inspected on 1.5.09 work of carpeting has been completed.Photograph Attached

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status

Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

33/99

Page 34:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

21.

AResidents Welfare Association, D-Block, Saket New Delhi-110017

03.03.09 (visited by AAUI on 15.02.09)

Residents Welfare Association D-Block, Saket About 100 meter stretch of the road is badly fractured, full of deep potholes, threatening smooth flow of traffic and working accidents to happen. Photo attached. Action required: It is not a big work to repair the surface of the road, it done quickly but any delay may cause avoidable risks, particularly during late hours in the evening and early morning when number of school buses use the road.

03.03.09 MCD and PWD on 04.03.2009

Action completed Dated25.08.09

As per ATR dated 18.3.09 from MCD, there is water leakage from past approx. one month due to which the road surface has been damaged. The Delhi Jal Board staff has repeatedly been reminded/requested to attend the water leakage but the same has not been attended so far. A letter also has been written to EE, Delhi Jal Board for attending of this leakage on priority. As soon as the water leakage is attended the work department will repair the road on priority.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

34/99

Page 35:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

meeting.22

A

Mr. George Pereira

21.2.09 a)Najafgarh Road and Subways

Condition of the Ganesh Nagar Subway at 3.15 PM on 21.2.2009:-

There was no watchman on duty. A stinking open drain flows

through the subway on the B2 A Block Janakpuri side

There are two dark and stinking corner spaces resembling either spaces meant for storerooms, toilets or pump rooms in the subway. Grills or doors should be put in place to prevent anti-social elements from abusing those spaces.

Action required

Watchman should be required on duty. Grills or doors should be put in place to prevent anti-social elements from abusing those spaces.

Received in WG-IV meeting held on 17.3.09

MCD on 17.3.09 Action completed

No work is required at present.

As per ATR from Ex. Engineer, West Zone, MCD dated 22.4.09, the subway was completed/inaugurated ol only in the year 2007 and since then it is being maintained in good condition. The Chowkidar/watchman has been deputed during the day time by the Project Division as well as the Division. Presently there is no foul smell or insanitary condition in this subway. There is no need as such to enclose the spaces marked for pump rooms, toilets etc. The shops constructed in the subway are yet to be

Site inspected on 8.5.09, all gates of subway found locked. Site again inspected by the JE(C) on 15.5.09 subway found open. Three guards found on duty. However, subway was not cleaned properly. Verified dt 21.05.09 sufficient ventilated, guard on duty, sub way cleaned Photograph attached

35/99

Page 36:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

Ab)Ramesh Nagar Metro Station

Basai Darapur Subway After Ramesh Nagar Metro Station:

No watchman was found here too.

The entrance to the subway from Basai Darapur Village side is broken and dirty.

The entrance from Katra Hospital side, opposite Invitation-K-Banquets is occupied by tentwallahs & decorators who litter the place with garbage and use the space for storing their wares and getting their decorations ready.

Action required

Watchman should be required on duty.

Received in WG-IV meeting held on 17.3.09

MCD on 17.3.09 Action Completed

Pending(within 7 days)

allotted by the R.P. Cell of the MCD due to which the space appears to be isolated. As soon as the allotment is made and shops are occupied there will be frequent movement of visitors and the persons using the subway will feel more secure.As per ATR from Ex. Engineer ,West Zone, MCD dated 22.4.09 1. The watchman shall be deputed for watch & ward during the day time/office hrs.2) The necessary repairs as mentioned have been started and shall be completed within 7 days.As per ATR AC/WZ dated 18.07.09 from MCD regarding

36/99

Page 37:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

Encroachments by tentwallahs should be removed immediately.

encroachment by tant walahs near Invitation –K Banqued Hall, kiriti Nagar. In regard it is submitted that an encroachment removal action has been in front of Invitation Banquet Hall near Kalra Hospital, Kirti Nagar on 12.05.09 with the help of S.T.F. Truck and labour. Temporary encroachment found on the site under reference has been removed. List if items seized and deposited in Municipal store are attached. Photo attachedAs per report by superintending Engineer (p)-I dated 07.10.09recieved on 06.11.09 work is completed.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

37/99

Page 38:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

23(a)A

23(b)

A

Mr. Satish Bahadur

13.3.09 a) Traffic Jam every evening at the Bengali Market rotunda. The Cars are parked three deep by the contractor creating a jam.

b) The pavements in front of the shops have flower sellers the fruit selling shops use the pavement for packing fruit baskets making it

Received in WG-IV meeting held on 17.3.09

NDMC on 17.3.09

Action Completed

Action Completed

Action Completed As per email dated April, 09 from Mr. Ramesh Raina, IDSE, CE(C)-I the parking lot measuring 357.75 Sq. M. area has been allotted to the Secretary, Bengali Market Tenders Association at a license fee of Rs.70,277/- per month for a period of one year w.e.f. 01 Nov.’08 to 31 Oct.’09. On a receipt of a complaint from Babar Road, Colony Lease Holder Association, a show cause notice vide No.D-547/SO (Enf.) dated 18 Feb.’09 was served upon the Secretary, Bengali Market Traders Association to

As per report dated 14.07.09Site- inspected by the J.E(C) dated 07.07.09 and observed that area round about the Bengali market was-used for parking of cars /vehicles this problem will be continue till the parking system managed properly.

38/99

Page 39:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

difficult to walk.

Action required

I need to make roads and pavement safe for people of Delhi.

operate parking lot properly in single lane to avoid any inconvenience to the nearby residents and public visiting the market. In response to the show cause notice the Association stated that in general the parking period of vehicles is very short. However, during movement of parking and withdrawing the parking lot (which is a natural process) it looks like parking in double lane. However concerned Area Inspector has been directed to keep a close watch.

As per email dated April, 09

39/99

Page 40:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

from Er. Ramesh Raina, IDSE, CE(C)-I the flowers and goods used for packing by the shopkeepers are removed as and when found on the public land regularly and deposited in the Store of Enforcement Department at Laxmi Bai Nagar. Photographs of the parking lot & pedestrian area along with soft copy are enclosed please.Photographs

As per report dated 25.5.09, this problem is of recurring nature therefore no verification is carried out.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

40/99

Page 41:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

meeting.24

B

Sh. M.K. Aggarwal 10.3.09 Parking at Jwalaheri market is done in a very haphazard way. On road double parking is done on the side of the market, due to that long jam is there every day in the evening which causes lot of inconvenience to the motorists.

Action required

One lane parking be done onthe market side and if the parking is full on the market side then cars be parked in the free parkingjust opposite side of the marketwhere parking is allowed free by MCD

Received in WG-IV meeting held on 17.3.09

MCD on 17.3.09 Action under process

Photograph attached

S.No. Name Date of Brief Description of complaint Date of Forwarded to / ATR Status Details of Action Remarks Verification

41/99

Page 42:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

complaint discussion WG-IV of UTTIPEC meeting.

Date Taken from Ex. Eng., UTTIPEC, DDA

25.

A

A

Sh. Satish Sudan 14.3.09

8.3.09

(a)Outer Ring Road between Peera Garhi toJanakpuri

There is a big pothole before the Vikaspuri (CRPF) Red Light

Action required

Proper repair needs to be carried out

(b)Pusa Road near Pusa Round about

There are Potholes just before the Roundabout.

Action required

Needs repair before someone falls off accidently.

WG-IV meeting held on 17.3.09

WG-IV meeting held on 17.3.09

PWD on 17.3.09

MCD on 17.3.09

Action Completed

Action Completed

As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, completed on 11.4.09.

As per ATR dated April, 29, 09 from Ex. Eng. (M) I, Karol Bagh Zone work completed and Video attached.

Verified dt21.05.09 Pot hole repaired but not furnished properly Photograph attached

Site inspected by the JE(C) on 11.5.09 “No” pothole seen on Pusa Road near Pusa Round about.

42/99

Page 43:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

26.

A

Sh. Shankar Venkaeshwaran

13.3.09 (a)Aurobindo Marg, between Aurobindo Ashram and Adchini village.

Road surface broken, resulting in break in traffic flow and jams.

Action required.

Road surface needs to be repaired

WG-IV meeting held on 17.3.09

PWD on 17.3.09

Action Completed

As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, surface will be improved very soon up to 30.4.09.

As per report dated 25.5.09 work completed.Photograph Attached

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

43/99

Page 44:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

meeting.A 9.3.09 (b)Between JNU main gate and Munirka

village

Road surface broken, resulting in break in traffic flow and jams.

Action required

Road surface needs to be repaired

WG-IV meeting held on 17.3.09

PWD on 17.3.09

Action Completed

As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, complaint attended.

As per report dated 14.07.09 Site –inspected by the F.I dated 07.07.09 and observed that broken surface of said road has been repaired.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

44/99

Page 45:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

meeting.

B 7.3.09(c)Aurobindo Marg near the IIT side gate

Vehicles parked every Saturday at the Shani Mandir near the IIT side gate

Effectively closing a whole lane in what is an extremely busy road.

Action required

Alternative parking place to be identified or the Mandir shifted.

WG-IV meeting

held on 17.3.09

PWD on 17.3.09

DTP on 30.04.09

Action Under Process

As per report dated 26.5.09, action is taken against vehicles which are found obstructively parked on main road affecting the flow of traffic. Long term solution is to develop parking place for which the action is to be taken by PWD. Shifting of Mandir is also a matter to be taken by PWD with the Religious Committee of GNCT of Delhi.

As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, complaint pertained to traffic.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

45/99

Page 46:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

meeting.27

A

Mrs. Chitra Narain Frequently during

07-08

(a)Ring Road between Delhi University and Bhairon Road Intersection.

The Ring Road frequently forks out into two roads, which are sometimes parallel & meet again, but sometimes branch only. In different directions, this is not clearly indicated & causes a lot of confusion. Such as reversing cars after taking the wrong turn, causing accidents.

WG-IV meeting held on 17.3.09

PWD on 17.3.09

Action Completed

As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, there is only one fork before railway line Bhairon Marg which is just on loop form and joins again with Ring Road after railway bridge.

As per report dated 25.5.09 the problem mentioned in the complaint is related to alignment of the road under reference. Therefore, no physical verification is required.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

46/99

Page 47:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

B (b)Flyovers

A major hazard at flyovers is the careless in thoughtless sign ages. These have caused in the past & will continue to in the future be the cause of tragic accidents for no fault of the drivers. Every flyover should have two indicators:

1) About 50 yds (Or whatever is decreased the optimum distance for drivers to adjust their direction) BEFORE the flyover.

2) Immediately at the intersection of the flyover say about 2-5 yds. before.

WG-IV meeting held on 17.3.09

PWD on 17.3.09

Action under process

As per ATR dated 30.4.2009 from Dy. Dir.(Maint), PWD , estimate under preparation for signage’s work in Zone M1,M2, M3 in the all new flyovers overhead signs, boards are being installed at 100 mtr. Before flyover. One shoulder mounted to signboard is installed just at start of flyover. Further 2 more advance sign boards are being installed at 250 mtr & 300 mtr before flyovers.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

47/99

Page 48:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

28.

B

Sh. Kultar Sood,President Pushpa Mkt. Traders

30.1 .09 a) Traffic congestion in Feroze Gandhi Marg and Veer Savarkar Marg.

There is no systematic parking defined.

The Traffic mafia runs the traffic laws as per their own wish.

Parking sites are more or less used by the shopkeepers particularly on the Veer Savarkar Marg.

The present 5 lane parking on Veer Savarkar Marg (MCD Hospital Road) creates a virtual mess resulting in unruly traffic chaos on this road.

Action required:

If the traffic police maintain the imposed traffic laws on the road, the situation emanating thereby would be far more excellent.

WG-IV meeting held on 17.3.09

MCD & DTP on 18.3.2009

Action Under processDTP

As per report given by DTP on 22.5.09 and 15.06.09 regular action against the traffic violation is taken by the Traffic Police on this road. One way scheme is being implemented by the field officers.As Per ATR dated10.07.2009 by Dy.Director (main)PWD matter pertains to MCD

This has to be sought out by DTP&PWD.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

B b) The situation at the Feroz Gandhi Road has WG-IV meeting MCD & DTP on Action As per report

48/99

Page 49:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

improved considerably since the imposition of one way traffic which was recommended by CRRI and Traffic Police since the year 2007.

Lot is still to be done. Traffic mafia runs its own rule of law with the connivance of MCD Authorities. The vendors, hawkers and squatters occupy the Govt. land which is marked as walk way space. U/a cycle rickshaws presence results in obstruction in the flow of traffic. The motor vehicle sale/purchase mafia has virtually grabbed the Govt. land.The decision to implement a single lane parking on both sides of the roads has not been enforce not yet been marked by the M.C.D to the traffic authorities. We may refer your recommendation where in no visible action appears to have been taken by the MCD to satisfy the earmarked point vis-à-vis from A to G.

Action required:The one way traffic recommended by the joint efforts of CRRI and Traffic Police is a complete success provided it is managed and enforced by the traffic police authorities in an honest way.

held on 17.3.09 18.3.2009 Under process

given by DTP on 22.5.09 and 15.06.09 regular action against the traffic violation is taken by the Traffic Police on this road. One way scheme is being implemented by the field officers.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

49/99

Page 50:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

29

B

Mr. S. Chandrasekhar

6.4.09 Rao Tula Ram Marg.

On Rao Tula Ram Marg just opposite the Subroto Park Bus-stop when heading from airport to city, the central steel railing (green colour) barricade one section has been uprooted and is precariously balanced very close to the road.

For identification the military sign mark “ICBPO” is very close to this uprooted railing on the central barrier separating the roads.

No doubt it has been uprooted by some pedestrians who did not wish to use the nearby foot over bridge.

WG-IV meeting held on 9.4.09

PWD on 9.4.09

NHAI

Action Under process

As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, work under process.As per ATR received dated 17.06.09 from Deputy Director Maintenance PWD that PWD maintains only up to Military Hospital Complaints beyond PWD Jurisdiction This complaints relates to NHAI.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

30 Brig. Rakesh Kohli. 14.3.09 (a)Flyover on Ring Road from Opposite WG-IV meeting PWD on 9.4.09 Action As per ATR Photograph

50/99

Page 51:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

A.

A 13.3.2009

Haldiram at Lajpat Nagar to opposite Vimhans Hospital.

The road has potholes and uneven surfacing since over the last one year. Motorists have to zigzag on the road, which is hazardous.

Action required

Road to be resurfaced properly.

(b)Ring Road from Lajpat Nagar to DND Road junction.

Major traffic jams due to breakdown of truck the previous right.

Action required:

Vehicles blocking the road must have towed away immediately. Breakdown vehicles must be positioned at strategic locations round the clock. Information of road blocks must be displayed well ahead for commuters to plan alternative routes.

held on 9.4.09

WG-IV meeting held on 9.4.09 Delhi Traffic

Police on 9.4.09

Completed

Action Completed

As per report given by DTP on 22.5.09 and 15.06.09 due to breakdown of a heavy goods vehicle a jam was reported which was immediately attended to By Traffic police staff. The Delhi Traffic Police deploy heavy duty crane at important locations in the entire NCT of Delhi for removal of breakdown vehicles during odd hours of the day. Such heavy duty cranes are available round the clock. In addition,

dated 30.4.2009 from Dy. Dir. (Maint), PWD, complaint attended on 19.3.09.Photograph attached

attachedRoad surface found repaired, manholes were not in the level of road As per verification date 18.05.09, no pot holes seen on the sitesurface.

As per report dated 14.07.09As per ATR status dated 11.06.09 the complaint was attended by the D.T.P and also they have deployed heavy duty cranes at important location in the entire N.C.T of Delhi for removal of break down vahichals in odd hours. The problem is recurring nature, therefore Site- inspection has not been carried

51/99

Page 52:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

Quick Reaction Teams are also earmarked in Traffic Unit which responds to such traffic bottlenecks immediately as and when reported in the Traffic Management Centre which works round the clock. Regarding display of information of road blocks to the general public, the suggestion is already being taken into consideration as a part of ITS project which is likely to be implemented before Common Wealth Games – 2010.

out

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

31

C

Dr. B.P. Gupta 10.3.09 (a)Traffic crossing on Mathura Road opposite Tribhuwan Building on Okhla mor crossing.

WG-IV meeting held on 9.4.09.

PWD on 9.4.09 Action Pending

Bad since last 3 months.

52/99

Page 53:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

B 12.3.09

Bad pot hole riddens road.

Action required:

Remetaling after repairs.

(b)Pedestrian pavement encroached by brick work to protect an advertisement on Mathura Road Ashram to Bhogal flyover.

Brick wall constructed which blocks the pedestrian walk way.

Action required:

Demolition of the wall.

WG-IV meeting held on 9.4.09

NHAI

PWD on 9.4.09

NORTHERN RAILWAYS

Action Process

As per ATR Dated:10.07.09By Dy. Director(Main) PWD .This Complaint Related to Northern Railways

1 month old.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

32

C

Sh. Hemraj Dang 20.4.2009 Delhi Gurgaon Toll Plaza, Gurgaon.

Specific problem of major nature: The use of smalr tags not helped as much as it could

WG-iV meeting held on 1.5.09

NHAI Action Pending

53/99

Page 54:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

have. Cash paying customers, seeing the shorter tag lines, are jamming these up and paying cash. There is not penalty in the NHAI contract for the franchisee (DS Construction0. They say this is because the contracts cannot be amended. However, the tariff has just been raised from Rs. 17/- to Rs. 18/-, so changes are possible.

Action required:

A penalty is needed for such people who break the tag line and the rule. We can sort with Rs. 50/- and increase if it is not changing driver behavior. This will enhance revenues reduce delays, and be equitable for all tag customers who have made the investments in the card and pre-paid larger sums with a minimum deposit as well (can’t remember if it is Rs. 1500 or not.)

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

33

BMr. T K Malhotra 03.03.09

(visited by AAUI on 15.02.09)

Saket D Block opposite PVR adjoining Temples street.There is an open nallah flowing in the posh area which is used for pulling filth, garbage. The

03.03.09 MCD and PWD on 04.03.2009

MCD

Case closed,

Does not pertains to UTTIPEC

In the subgroup meeting of WG-IV held on 03.03.2009, it

Case is closed.

54/99

Page 55:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

residents have been staying with this filth and complaining but the nallah continue to remain uncovered.

Photo attached.

ACTION REQUIRED:

The Nallah needs to be covered as early as possible. It wills results in widening the road and provides some room for parking also.

was decided that this complaint does not pertain to transportation aspect, hence, to be deleted.As per ATR dated 18.03.2009 from MCD, ‘Site inspected, there is no proposal with EE (M) IV/SZ for covering of this nallah. Since it a major work, the matter may be referred to Project Division South for taking up necessary action in this regard.

As per ATR from Ex. Engineer (Project) South, MCD dated 23.4.09 the work was awarded to the contractor for covering of the nallah but there was a hindrance

55/99

Page 56:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

of trees falling on both the sides of drain. Accordingly, Dy. Conservator of forest was requested for permission to fell 51 nos. trees. Dy. Conservator of forest refused to accord the permission to fell trees citing the High Court orders dated 27.7.07 passed by the Hon’ble High Court in CWP No. – 15725 of 2006. Hence the case of covering of Nallah was closed.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

34A

Sh. Satish Sudan 14.3.09 (a)Outer Ring Road between Peera Garhi toJanakpuri

There is a big pothole before the Vikaspuri

WG-IV meeting held on 17.3.09

PWD on 17.3.09

Action Completed

Case RepeatedSame as Sr. No. 25

As per ATR dated 30.4.2009 from Dy. Dir. (Maint), PWD, repair under

Case RepeatedSame as Sr. No. 25

56/99

Page 57:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

A 8.3.09

(CRPF) Red Light

Action required Proper repair needs to be carried out

(b)Pusa Road near Pusa Round about

There are Potholes just before the Roundabout.

Action requiredNeeds repair before someone falls off accidently.

WG-IV meeting held on 17.3.09

MCD on 17.3.09

Action Completed

progress & completed on 11.4.09.

As per ATR dated April, 29, 09 from Ex. Eng. (M) I, Karol Bagh Zone work completed and Video attached.

S.No. Name Date of

complaintBrief Description of complaint Date of

discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

35

B

Yogesh kumar agarwal

12-07-09 New friends colony T-Junction on C.V Raman road in front Tamoor Nagar gurudwara

1. Traffic jam at the T-Junction due to unauthorized bus-stop at the signals.(Photo attached)

16.07.09 PWD/DTP dated17.07.09/

Action Under Process

As per report given by DTP dated 29.09.09 Instructions have already been issued to field officers to challan

57/99

Page 58:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

2.Noise pollution due to hawking

3.Hawkers add to chaos and traffic jam

4. Sidewalks not free for distance

Action Required:

1.Prevent buses from stopping at the traffic signals there are already planned bus-stops on this road(No bus-stops should be 100m of traffic signals )2.Remove hawkers’ from side-walks

unauthorized stopping of buses at the signal. The field staffs have reported that action is being taken against such buses. In addition, Rehires and hawkers are also removed from the road. At present, rectification/ restoration of deep settled sewer line between Gurudwara and Nallah at Taimur Nagar is being undertaken by Delhi Jal Board.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

36

C

Kusum Pant 15.07.09 Aurobindo marg the left turn near F-31, Hauz khaas Enclave and IIT flyover

1. After the sewage repair works the side walk for pedestrian has been demolished and that area has been excluded in the road.

2. Bus takes turn at great speed and pedestrian

16.07.09 PWD dated 17.07.09

Action pending

58/99

Page 59:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

have no place to stand before crossing the road.Action required:1. Restore the side- walk.

2. Create a FOB or a subway for the convenience of pedestrians.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

37.

CR.K.Singh 30.08.09 Vivek vihar (Phase-I) there is a road 30ft. wide

according to the map, which stretches between houses no.D-124 &house no.D-198 of Vivek Vihar (Phase-I) which is colony developed by DDA and now maintained by MCD. Some residents who own houses. Situated on this road have erected permanent fixtures made of cement and steel and have taken unauthorizesed possession of as much as 30’x 6’ of this road in front of their houses or on their side. Instances are D-117.D-115& D-208

Of 07.09.09 MCD 09.09.09 ATR Pending

59/99

Page 60:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

and at least 10-12 houses on the same road. As A result, the width of the road has reduced considerably. Instead of being 30’wide, the road is now not more than 20’ wide. To aggravate the matter further. The road has become virtually a parking lot for vehicles. Encroachment being on both side of the road, it become very difficult to negotiate vehicles through the entire stretch of the road, particularly at tunnin points. Quite often there are ugly scenes of residents quarrelling with each other. The no. of vehicles has also increased two –fold during the last one year.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

The market value of the portion of public road which has been encroachment upon will run into corers of rupees. It is in public interest to dismantle this encroachment so that on inconvenience is experienced while driving vehicles and there is enough space for road side parking. I Shall be most happy if AAUI can take up this case with the concerned authorities.

60/99

Page 61:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

38.

CKuljit Singh 01.09.09 Okhla Phase-II

the road outside thefactories, A 139/1, 2 & 3, Okhla Phase II, are totally obstructed due tocows and buffaloesthat are tied up outside the premises and the owners have even madetemporary sheds. They bathe the cows there and litter the area and the road

07.09.09 MCD dated 09.09.09

ATR Pending

61/99

Page 62:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

is always wet which is a health hazard.

The filthy and unclean surroundings are environmentally unfriendly and anuisance to traffic and this encroachment on the road is a major cause fortraffic jams on this road.

I request you to please take immediate action.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

62/99

Page 63:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

39.

BDr. S L Jain 03.08.09 Dwarka:

Towards the sorry state of service lane in sector 2, near plot No. 2, Dwarka, New Delhi. It is very difficult to negotiate with the road. I hope your good offices will bring to the notice of concerned authorities to get the above said service lane repaired.

I am looking forward for the positive and favorable response. 

07.09.09 C.E.DWARKA DDA dated 09.09.09

Action Under process

As per letter received from Chief Engineer (DWARKA) dated 22/9/09 In this reference, it is informed that the pot holes in front of joy Apartment, Plot No.2 Sector-2, Dwarka along with road no.201 has been filled with brick aggregate with lime. Carpeting of the service road shall be done after rainy season is over.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

40. Ashok Saini 31.08.09 Illegal Trespassing of Commercial Vehicles In 07.09.09 DTP Dated Action As per report

63/99

Page 64:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

B Residential Colony: the most unfortunate residents of Delhi, wish to urge your esteem self that we have been the victims of Commercial Vehicles for last 4 years and the situation is worsening day by day. We have complained so many times to the authority but every time they made an excuse. Now, it seems that the concerned department is dumb and deaf. The root cause of the problem is the commercial vehicles which make a short cut from Lal Qua, Subzi Mandi towards the our residential area Singh Sabha Road, 10 & 33 Blocks, Shakti Nagar(Behind Amba Cinema). These vehicles include trucks, Tata-407, Tempos etc. Our lives have become a hell due to the pollution and noise created by these commercial vehicles. Many complaints filed by us are still pending in the department. Specially in the evening, our children can not come out our houses due to the rush and congestion. The barricades installed by our RWA have been removed by the police as their earnings came down. This is a matter of great concern that we the residents are being ignored by the department just to satisfy their greed. This short cut is quite dangerous too as many fatal accidents occurred in the past. A electric pole has been hit and thrown down by a truck just few days back.

09.09.09 Under Process

given by DTP dated 29.09.09 Instructions have already been issued to field officers to challan commercial vehicles plying in the area.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

This might cause many deaths but luckily nobody was nearby. The department is waiting

64/99

Page 65:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

for a disaster to occur.

We would like to request the authority to take quick action and stop this short-cut route for the commercial vehicles atleast.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

41.

CShri Chudamani Ratnam

07.07.09 Greater Kailash Part-ITraffic lights problems in the GK1 area.

(a) At the GK1/Sadiq Nagar (BRT) crossing,  going east/west or west/east the traffic lights are

07.09.09 DIMTS dated 09.09.09

ATR Pending

65/99

Page 66:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

not visible at critical moments of crossing. This is because there is a slope on the GK1 side and the height of the lights is not satisfactory. This needs to be corrected and because it is such a broad crossing  extra sets of lights need to be installed in the road dividers on both east and west sides.

The upslope to the traffic lights on the GK1 side is dangerous. Not only can the opposite side traffic lights not be seen but vehicles slide back on green light. Some earth work needs to be done to make  a more gentle approach to the traffic lights.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

B (b) ) The traffic lights on the north side of Archana (GK1)are not correct. There is no green light for traffic going straight east/west or vice versa. and there is no right turn green light for traffic coming from the north wishing to make

07.07.09 DTP dated 09.09.09

Action Under Process

As per report given by DTP dated 29.09.09 Instructions have been issued to field

66/99

Page 67:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

a right turn

Traffic going north past Archana usually go straight through on red light not realising there is a road coming from left. A speed breaker is required to slow down north going traffic at this crossing.

officers and M/s CMS Traffic Systems Ltd. to rectify the signals.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

42.

ANeeraj Gupta 29.08.09 Either making the Ram Nath Viz Road one

way from blind school to H-478 N.R.N. cross section or remove Pamposh road This is to request you to make the road stretch of Ram Nath Viz Marg , as by making the Pamposh road and A block road one way ,

07.09.09 DTP dated 09.09.09

Action Complete

As per report given by DTP dated 29.09.09 The proposed scheme was discussed in detail in the

67/99

Page 68:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

the whole traffic volume has been shifted to Ram Nath Viz Marg. Traffic and noise levels have risen to such an extent that it has become difficult to live on this once peaceful internal road. This road has become nightmare for the elderly and chilren.

I am also attaching the plan of my colony along with this request letter to explain the problem. Also you are requested to make the traffic management plan of the whole colony and not the part of it so that by giving relief to one small segment the whole system should not be disturbed.

meeting of Working Group IIIA of UTTIPEC held on 25.9.2009. The scheme was dropped in view of its non feasibility.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

43.

BPankaj Dey 31.08.09 Obstructions in front of Traffic light:

With this article I would like to bring to your kind notice that in Delhi there are certain areas where you would find hoardings and signages being put in front of traffic lights, thereby obstructing the view and resulting in confusion among the drivers. one such obstruction is in front of the traffic light installed near Multi specialty hospital at Janakpuri. A large

07.09.09 DTP dated 09.09.09

Action Under Process

As per report given by DTP dated 29.09.09 Instructions have already been issued to all field offices and signal

68/99

Page 69:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

hoarding has come in front of the traffic light in such a way that the central pillar of the hoarding obstructs the view of the traffic light for all those who come from Pankha road side. I shall be grateful if something could be done to prevent such erection of temporary structures.

maintaining agency to remove hoardings/signages/branches of trees etc. in front of traffic light signals to increase visibility and to avoid any untoward incident.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

44.

BPuneet Sachar 29.08.09 Complaint for the traffic mess in

Vasant Kunj by DPS and Vasant Valley School:I have read your article in HT today. I really appreciate the hard work you guys doing.

Can you guys forward my complain to LG reading the mess DPS and Vasant

07.09.09 DTP dated 09.09.09

Action Under Process

As per report given by DTP dated 29.09.09 Instructions have been issued to field officers to prosecute all such school

69/99

Page 70:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

Valley are doing. during the morning hours they block all roads leading to schools. The school have been given apple space for parking but still they allow parents to park the cars on road.To make situation worse the traffic police incharge/beat office has been seen taken bribe and playing cards with the drivers of those cars. If you can take our complaint to the authority so that they can regulate the traffic mess in our area, I will be thankful to you.

buses which are improperly and obstructively parked. For better traffic management in the area during school hours, traffic police personnel shall also be deployed.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

45.

BSumeet Man Singh

31.08.09 Gates for Residents Welfare Associations:

Permission for installation of gates by a RWA or co-operative society of a colony is under your jurisdiction.

I wish to bring to your notice that every colony in South Delhi has installed gates, and a large percentage of these are kept closed day and night. In certain places

07.09.09 DTP dat5ed 09.09.09

Action Under process

As per report given by DTP dated 29.09.09 MCD has already approved guidelines for installation of security iron gates etc. by RWAs in their respective

70/99

Page 71:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

pavements have been built permanently closing these gates and in some pillars have been constructed.

There are three areas of concern.

(1) It is frightening to note that should emergency services be needed, the fastest access has been blocked off

residential localities. In case of any problem, a complaint can be made to the SDPO of the area and his decision shall be final and binding upon the RWA.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

2.There is a greater density of cars on the main feeder roads. Since gates are closed, vehicles instead of taking the first designated entry into the colony take detours of upto five kilometers to reach there destination, which may be only fifty meters away.

3. If the amount of fuel wasted and the emission of gases is calculated, not just of the cars taking the detour, but the general slowing of traffic because of extra volume

71/99

Page 72:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

of vehicles on the main road, the amount is considerable and not to be taken lightly or scoffed at.

RWA’s and co-operative societies would be better off educating its members on driving etiquette within a residential colony and to treat others how they would like to be treated themselves.

Barriers do not lead to solutions.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

46.

BMr. Vivek Chadha 30.08.09 Awareness and non coordination

amongst traffic policeman leads to traffic jams.I would like to bring into your kind notice that every time in Azad market area there are traffic jam because of processions (religious) but traffic people they don’t give awareness to people that on this date they should not take this road at this time but they simply tell that we have given in newspaper

07.09.09 DTP Dated 09.09.09

Action Under process

As per report given by DTP dated 29.09.09 The religious processions are being dealt as per the approved guidelines. Adequate traffic police arrangements are made during

72/99

Page 73:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

but the people are not aware of the fact instead they should put before the procession week before only they should put banners on all related routes and they should coordinate with other police stations also so that public should not

suffer.

I can tell more about these awareness programmes and I also want to be a

part of your programmes.

such religious processions. Awareness for general public is also carried out through issue of press releases, advertisements and information on T.V. channels/F.M. channels etc.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

47 B

Arjun Kumar 3.09.09 Traffic jamming problem in Janak Puri B-! Block:-

Due to increase in traffic on the road from Bharti College towards Check Post, Najafgarh road in Janak Puri and in the absence of either a Traffic Policeman or Traffic Lights traffic generally gets jammed at B-1 Main Road opposite Gurdwara 'T' Junction as well as opposite JanakPuri main Post Office. The problem get confounded particularly during morning

07.09.09 DTP 11.09.09 Action Under Process

As per report given by DTP dated 29.09.09 Instructions have been issued to field officers to regulate traffic at B-I Block, Janak Puri. Traffic staff is being deployed

73/99

Page 74:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

hours schools off timing around 1330 hrs and in the evening. This leads to heavy traffic jam almost daily. There is urgent need for posting of two Traffic Policemen or proving traffic lights urgently.  I tried to send this suggestion to UTTIPEC from their Website but due to some technical problem in the website I could not. Since you are part of the UTTIPEC and your recommendations are given due importance, you are requested to take this serious issue with UTTPEC.

to regulate traffic during morning and evening peak hours. Regarding installation of traffic signal, the same shall be examined for its feasibility.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

48.

BHarvindra Sing 29.08.09 Problem at madhuban chowk,

piampura,DELHI:- Today I have read a news item in HT wherein your active participation in association with the team of LG has solved the traffic problem reported by Saroja Vaidyanathan regarding an open manhole near her dance school. Gr8 job done. Congrats.I am Harvinder Singh, R/O 35, Dhudial Apartments, Near Madhuban Chowk, Pitampura, Delhi-110034 and my

07.09.09 DTP 11.09.09 ATR Under Process

As per report given by DTP dated 29.09.09 Instructions have been issued to field officers to regulate at Madhuban Chowk Pitam Pura. Regarding provision of slip road, the same

74/99

Page 75:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

contact number is 09873459520.I want to make a request to u regarding the position of the point of left turn towards Rohini while coming from Peeragarhi side. It is such a busy crossing that this type of location which has been changed quite recently by blocking the earlier left turning point has created more problem than solving it.

is being examined.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

Action required:- I would like to suggest you to pl depute someone to come and see the position as there is a better scope of providing this left turn from a bit earlier turn. There is road coming out from Rohini and it touches the outer ring road near the underpass. The left turn in question can be opened from here and should be closed from the one recently opened which will be more safe and suitable from every point of

75/99

Page 76:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

view.

I hope u will take up the matter with the concerned authorities and see to set it right at the earliest possible which will save lives and decongest the already congested madhuban chowkIf required I can be reached on my above mentioned mobile number to help understand the position which I have tried to explain .

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

49.

CHarvinder Singh 29.09.09 Encroached service lane SWARAN

APARTMENTS and DHUDIAL APARTMENTS This is to inform u about the position of encroached service lane meant for two Housing Complexes named SWARAN APARTMENTS and DHUDIAL APARTMENTS, Near Madhuban chowk, Pitampura, Delhi-110034.These residential complexes are just on the corner and at the end of the service lane which is coming from Saraswati Vihar. There are two big markets on this

07.09.09 MCD 11.09.09 ATR Pending

76/99

Page 77:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

lane which has a dead end and this service lane is fully encroached by the cars of the customers and shop owners and other REHRIWALAS etc. in a such a bad way that the residents find it impossible to venture out from these complexes. Especially ladies cant even think of going on foot as there are so many outsiders standing whole the day which makes it quite risky too.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

Action required:- There is a big park alongside these markets and this park can be converted into a proper parking place and all the REHRIWALAS be asked to move in(depending upon the deciding authorities) that park so that these residents can live a rightful life.

Moreover this type of encroachment is so dangerous that if there is any emergency like fire etc nothing will be possible except to witness the disaster out of helplessness.

77/99

Page 78:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

I hope u will take up the matter with the authorities concerned and help us all. If required I can be asked to assist u to understand the situation and c how best v can get it solved but at the earliest possible.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

50.

CK.S.Gahunia 03.09.09 No safe provision for pedestrian crossing at

Link Road, Jhandewalan Extension, New Delhi-110055. The above area is between the roundabout of Panchunian Road and roundabout of Arya Samaj Road where a large statue of Hanuman (Mandir) is located. In between this roundabouts there are bus shelters, two on the road going towards C.P. and one across the road going towards Karol bagh. Facing this Bus shelters in both sides of the roads, midway from the 2 roundabouts is used for crossing. The DRMC (metro) left open

07.09.09 MCD on 11.09.09

ATR Pending

78/99

Page 79:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

an area for the public to cross over. 1. These bus shelters are equi-distance from the round abouts. There is a zebra line crossing at Panchunian/Rani Jansi road roundabout which is very inconvenient. 2. To cross this road as it is now takes a wait of 15-20 minutes, that too with the hope one does not get run over by vehicles. 3. For school going children, elderly, physically challenge and infirm pedestrians its virtually impossible to cross this roads. 4. There had been several unreported accidents at the site. We are just hoping no death occurs.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

A letter dated 09 Aug. 2009 address to Jt. Commissioner of Police Traffic had been sent through e-mail and was confirmed by the department of receipt. The matter was conveyed also to ACP traffic (central) telephonically on 10th & 12th August 2009.

1. Action required:- The location of Jhandewalan Metro Station is mid-way from the roundabouts also. Modifying the entry/exit to the platform of Metro Station by relocating / moving it by the stairs

79/99

Page 80:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

going to the platform will open the area and can be used for crossing safely by the pedestrians. The exit/entry will be installed in 4 areas where the stairs going to the platforms are situated. As it is now there are only 2 exit/entry. For a pedestrian seeking safety has to shell out Rs. 6.00 just to cross the street using the concourse of metro station. This is unfair & unjust.

As for security I could see no problem. In fact DRMC (metro) had done feasibility studies on the suggestion mentioned above that got published in one leading newspaper (Hindustan Times) quite sometime ago.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

2. A traffic signage may be installed at the round about where the Hanuman Statue is located While on the subject of traffic at the site mention above, it is about time to demolish the unauthorized structure of Bajaj showroom by the Hanuman Mandir and construct a lane at the site (link Road - Ridge Road) to decongest the heavy traffic at this round about due to the presence of the Hanuman Mandir. It takes good 15 - 20 minutes from Panchunian roundabout to reach the Hanuman Mandir

80/99

Page 81:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

round about in the evenings on any working day. I may as well mention here Jhandewalan Extension is a commercial district center where Videocon Towers, Cycle Market, Anarkaly Bazaar, residence and Lots of offices are situated here besides, worshipers crossing to go to jhandewalan Mandir, about lakhs of people come & go for various purposes. It is high time priority be given to this issue.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

51.

CM.K.Moudgil 29.08.09 Encroachment on Capt.Satish Marg, Rani

Bagh, Delhi Resident of Jagrit Appartment, Capt. Satish Marg, Rani Bagh, Delhi-34 face problem everyday while going to market or board a train at Sakurbasti Railway Station. Sir most of the shopkeeper encroached the road by placing three row of plastic chairs or put a bed. Sir it is 20feet wide road and the occupy near about 15feet road and in the evening the road is over cruded. It is very difficult to pass through the narrow lane. I request you to pl take up the matter with higher authority. I also complaint the local area councilor but sorry to say he is

07.09.09 MCD on 11.09.09

ATR Pending

81/99

Page 82:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

not serious to solving the problem. Today I read Hindustan Time page No 3 in which You mention that if you have any problem then register your complaint. I hope you will take up the matter with the civil authorities.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

52.

CPrem Sagar Nagpal

29.08.09 Grievance about poor road condition in Amar Colony Lajpat Nagar IV New Delhi:- I have read in the daily Hindustan that I can register a complaint on the poor road condition in the locality with you to LG. Accordingly I have to inform you that the conditions of road in front of the Blind School Amar colony Lajpat Nagar IV, and in front of Mother Dairy and Gurdwara Road Amar Colony Lajpat Nagar IV is so bad that the poor Rickshaw alas and scooterist find it very difficult to use the road. I am a senior citizen and finding it very difficult to pass through these roads. I can

07.09.09 MCD on 1109.09

ATR Pending

82/99

Page 83:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

say that condition of most of the roads in the colony is pitiable and in poor condition. These facts have been brought to the notice of the area MLA and counselor but nothing has been done in this regard.

I shall therefore be grateful if you kindly take up the matter with Hon’ble LG for

compliance.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

53.

BRomesh Chander 03.09.09 Gurgaon –Meharouli boarder at Aya Nagar

I am a resident of south Delhi. Since my work place is at Gurgaon, I commute every day to the town via the Meharouli Gurgaon road. On my journey back I notice with grevel, crushed stones etc.at Aya Nagar, across Arjangarh, standing in a row to cross into Delhi. Most of these trucks bear Haryana registration Nos. in devnagri and the Nos. appear deliberately defaced which cannot be read even by pundits of Hindi literature. If my memory serves me well the truck trailers and HTVs are perhaps not allowed to ply on MG Road. Also, the Supreme Court banned mining and crushing of stones in this part of Aravalis , the carrying of gravel and

07.09.09 DTP on 11.09.09 Action Under Process

As per report given by DTP dated29.09.09 Instructions have been issued to field officers to strictly enforce the provisions and take legal action against such HTVs which violate traffic rules and regulations.

83/99

Page 84:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

stones therefore should be presumed not to be permitted by Haryana and Delhi police. It may please be noted that these trucks cross Aya Nagar border and the police vans of both States are invariably seen there but they appear very considerate to truckers and look the other way. Since you take up such issues with great enthusiasm I request you to please verify it and expose the nexus between Traffic Police Delhi, Haryana Police and the mining mafia.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA

As a seasoned public person and a broadcaster (one used to see you on television) you will please verify facts and ask someone to visit the Gurgaon –Meharouli boarder at Aya Nagar on any weekend in the evening after 8p.m. If you find the above –mentioned practices illegal I would request you to please take up the matter.

84/99

Page 85:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

54.

CRohit Sharma 31.08.09 “GURU RAVIDAS MARG” leading from

Chandiwala Estate to Batra Hospital. It is been highly accidental zone. PWD Footpaths are occupied and illegal motor mechanic activities are running which lead to various accidents on the road. Even these kinds of illegal activities lead to the disturbance to the residence of the colony specially for the women as these are the entries to the colony. More than 75% of the traffic road is occupied by these people.

As per the supreme court guide line GURU RAVIDAS MARG come under the restricted area to run commercial units.

07.09.09 MCD/DTP dated 11.09.09 and dated 05.11.09

ATR Pending

85/99

Page 86:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

55. Amit Sharma 10.10.2009

Model Town –II:- I want to inform another problem related to road opposite to Queen Mary’s School, Model Town. There are three schools namely AGDAV Sreejan and Queen Mary’s School in one line situated on a road which is on the backside of Model Town and has become a bypass for trucks, buses and other vehicles to go to Karnal Bypass. For this a heavy vehicular traffic each day travels the said road in very high speed.

There are no peed breakers in front of any school neither there are any signage to show that school children may cross the road. There are two or three accidents in a week of trucks on this road.

10.11.09 MCD on dated 10.11.09

ATR Pending

86/99

Page 87:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

I have also send a mail 2 months back to DDA, PWD, MCD etc for the same problem but no steps were taken. I think authorities are waiting for some accident to happen and then wake up.

Please look into this matter if possible.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

56. Chandra 26.09.09 Road opposite PVR Saket :- Signals though installed now but are not regularly functioning. Also pavements for use of pedestrians are totally encroached.

Action required :- Traffic lights to be put inorder for regular function.

10.11.09 DTP/MCD dated 10.11.09

ATR Pending

87/99

Page 88:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

57. Darshan Malhotra 23.09.2009

BRT corridor crossing at Chirag-Dilli :- I would like to highlight the chaos & unsafe traffic conditions created by vehicles of so called VIP’s &VIP’s at the above crossing. These vehicles coming from Moolchand side invariably go on to the Lane meant for buses & hop & jump lanes like monkeys. While nearing the Chirag-Delhi crossing, they hop into traffic lane meant for traffic from opposite direction & again switch lane &stop in front of the Buses waiting patiently for the signal to go green. These VIP vehicles donot have the patience to wait for signal (meant for Buses ) to go green & they race into traffic when the signal for Cars goes green, there by endangering the safety of Cars etc.turning right at the Signal .This is the “modus operendi”being followed by all so called VIP’s without any regard for the safety &rules….Unfortunately there is no one to check & book them for rash driving & gross violation of traffic rules. Not only so called VIP’s are guilty of above

10.11.09 DIMTS/DTP dated 10.11.09

ATR Pending

88/99

Page 89:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

violation, even the real VIP’s like ministers etc.are guilty of this practice. Only difference is that they shamelessly do this with the help of traffic police /pilot car with glaring sirens.I would be grateful if your organization does something to tame the wild &unruly behaviour of VIP’s & make them sensible & responsible citizens.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

58. Dr.A.K.Banerji 05-09-2009

Okhla (Kalindikunj)barrage,Jasola, Sarita Vihar ,Madanpur Khadar,Jaitpur and Road No.13A :- I am told about a new initiative started by you for better roads and traffic management. It is in this context that I am writing this letter.

1. Traffic signals on road no.13A, starting from Okhla (Kalindikunj) barrage, and running between Jasola and Sarita Vihar, New Delhi are not working properly for the last one year.

2. There is a constant traffic bottleneck almost daily at the crossing of approach road to Okhla (Kalindikunj) barrage, Madanpur Khader, Jaitpur and Road no.13A.A traffic rage incident is waiting to happen .All that is required is installation of a traffic light at this crossing.

3. The slip road connecting road no .13A,

10.11.09 PWD/DTP dated 10.11.09

ATR Pending

89/99

Page 90:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

going to Indraprastha Apollo Hospital is in state of serious disrepair creating daily traffic bottlenecks. This is compounded by Metro construction activities. The road requires quick attention of P.W.D/MCD.

I trust you will be able to help.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

59 Mansi Verma 09-10-2009

Jhilmil Colony , Vivek Vihar :- I am a student of Shaheed Sukhdev College of Business Studies, DU, Jhilmil Colony, Vivek Vihar. I had a compliant to make about a certain stretch of road which is used by millions of people everyday but is in a very bad condition.This stretch of road connects the Shahdara Metro Station to my college in Jhilmil, Vivek Vihar. The road is broken, with open drains on both sides, there is no traffic management mechanism, no pavements for pedestrians. The road is being eaten by encroachments of shops and houses. There is no proper Garbage disposal system and the dustbins are overflowing. The road gets water logged during rains, and the students of our college had to face accidents many times. Its an everyday routine to have traffic jams for hours. Girls face the problem of eve-teasing, but there is no police deployment in the area.

It doesn’t feel that this area is a part of “Millenium City, Delhi”. I read about the work

10.11.09 MCD dated 10.11.09

ATR Pending

90/99

Page 91:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

you had done in the newspaper and got encouraged to file a compliant. However I got confused on whether my complain will be registered or not, as I am not a member of AAUI.Awaiting an early and positive response.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

60. Mansi Verma 06.11.09 Shahdara South, Kasturba Marg :- Interviewed 8 people in areas of Kasturba Marg & Jwaala Nagar of Shahdara South about various issues they face in their day-to-day life.

1. Roads -The road goes by the name  of  Circular  Road .The roads in the area covering Shahdara, Kasturba Marg & Jwaala Nagar were last repaired 4- 5 years back. But the condition of the road shows the poor quality of materials used. People claim that the roads are usually repaired during election time. But this year that wasn’t done.The roads have potholes & small manholes & garbage remains strewn. Drainage- The drains are open & run into narrow lanes with mosquito breeding. The drain is seldom cleaned. There have been 2 dengue cases reported recently.

10.11.09 MCD/DTP dated 10.11.09

ATR Pending

91/99

Page 92:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

1. Crime Rate - The crime rate has increased to a great extent. The locals claim that many women are involved in chain snatching. A particular group called the 'Shashi Varg" are involved in many illegal & criminal activities like sale of illegal liquor, thefts, etc. Gambling is very common in the areas, groups of  men gather in the common park in the afternoon & gamble till late night & get drunk, this causes a nuisance for the residents living nearby.

2.Security - People cannot depend on Police for their safety. Policemen take bribes & let the culprits scot free. People have to take their own safety measures. At times the rickshaw valas are threatened by policemen & also have to pay them to park their rickshaws near the metro stations.

3.Traffic - There are no traffic policemen, there is 1 home guard at the crossroad but is not able to control the heavy traffic. There are constant jams & hence results in accidents, this is more during the monsoons.

92/99

Page 93:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

4.Shops & Houses - People claim that the Govt. has regularized the colony & hence none of the shops or houses are unauthorized.

5.MLAs - The MLAs visit once in 3 months. However a few people claim that the MLA is selfish & is not effective enough.

6. RWA - There is no RWA in the area.

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

     7. Sanitation - The people of Shahdara have got accustomed to the conditions. There is water logging. People let their pigs loose & these pigs enter the garbage dumps & scatter the garbage all around. The residents dump their garbage on the roads. Some people have kept sweeper’s to collect the garbage, yet other people continue to dump the garbage on the roads. Attached some photographs.

People  In  Power - Mr. Jitender Singh Shunty  and  Mr. Narender Nath

93/99

Page 94:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No.

Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

61. P.S.Bakshi Road Maintenance of Vasant Kunj :- I am sorry to bring to your notice the negligence of M.C.D officer responsible for Road Maintenance of Vasant Kunj.I am residing in Vasant Kunj New Delhi Since 1989.I have notice that the road coming from Nelson Mendola road passing in front of Sector-B-10, B-11, B-8, B-7, and turning towards Central market has never been recarpetted for the last 15 years.Everytime patch work is done. Last year they started recarpetting but half of the job was done and than left.

Road going through sector-D-1, D2 towards hospital, it was dug for laying cable for hospital for almost 2 years back but never recarpetted so far. Road behind D-1-D2, Heritage School is also in very bad shape.

I am sure that on paper it must be showing the recarpetting has been done, but actually never done, this is due to corrupt officials of MCD, the job is never done. We elect

10.11.09 PWD/MCD dated 10.11.09

ATR Pending

94/99

Page 95:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

MLA‘s they don’t look after the colony?

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

Another point that occupants living in flats No.221 –to-400, ground floor occupants have done unauthorized construction of occupying 15/20 ft.space of road, and hardly 10ft.space is left to move the cars Association approached officials of DDA & M.C.D to demolish the un-authorized construction occupying Govt.land.

Every time on election M.L.A‘s & M.P’s promise lot of things they will do but after elected never show their faces. You are the Chief Minister to look after the negligence done by staff of other departments.

95/99

Page 96:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

62. Rajiv Chawla 27-10-2009

Civic amenities in Shahdara North Area: - I am taking liberty to write your good self in the hope that something will come out of the pathetic conditions we, the people of Shahdara North Area, are living in.  The main problems of our area are :-

1. Roads inside the OLD YAMUNA BRIDGE is in a very bad condition.

    Last time that road was made by the order of Hon'ble High Court of Delhi in 2002 by instructing all the civic authorities to pool the expenditure and make that road when all the authorities were passing the buck.  IT REALLY NEEDS IMMEDIATE REPAIR/ RENOVATION.

2.  Encroachment on all roads leading to OLD YAMUNA BRIDGE from EASTERN SIDE of the bridge. All the pavements on the roads leading to OLD YAMUNA BRIDGE from EASTERN SIDE are encroached upon by vendors/ khokhas and rickshaw-walas etc.  Roads and pavements from every side of the OLD YAMUNA BRIDGE need repair/renovation.3.  Slow moving vehicles like Cycle Rickshaws, Horse Cart (TONGA), Bullock Card (Bail garhi)

10.11.09 MCD/DTP/Railway dated 10.11.09

ATR Pending

96/99

Page 97:  · Web viewMehrauli-Badarpur Road in front of Anupam Apartments (Saket) … 'U' turn construction left Incomplete. Received in WG-IV meeting held on 06.01.2009 PWD on 6.1.09 Action

must not be allowed at OLD YAMUNA BRIDGE during peak hours at least

S.No. Name Date of complaint

Brief Description of complaint Date of discussion WG-IV of UTTIPEC meeting.

Forwarded to / Date

ATR Status Details of Action Taken

Remarks Verification from Ex. Eng., UTTIPEC, DDA`

Movement of Cycle Rickshaws, Horse Cart (TONGA), and Bullock Cart etc. on OLD YAMUNA BRIDGE during peak hours i.e. 8.00 AM to 11.00 AM and 5.00 PM to 8.00 PM hinders the movement of fast moving traffic.

4.   Leakage of water from above of the OLD YAMUNA BRIDGE

      The problem of water leakage from above the OLD YAMUNA BRIDGE may be plugged that not only hinders the movement the traffic but also put the dirt on scooter/bike rider and cycle rider.  Everybody want to avoid the leaking of water thus making a bottleneck at that spot itself which also hinders the traffic.

5.   Encroachment on Railway Road Shahdara.

      Railway Road Shahdara leading towards Shahdara Railway Station and Shahdara Metro Station is totally encroached upon by rehariwalas, khokhawalas and all the sundry fruitsellers, cyclerickshaw walas etc. which not only prevent the smooth traffic on the road but it is a disadvantage for train catchers.