virginia p3 update- 2015• includes maintenance, safety improvements for existing midtown and...

22
VIRGINIA P3 UPDATE- 2015 Jackie Cromwell, VAP3

Upload: others

Post on 01-Jan-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

  • VIRGINIA P3 UPDATE- 2015

    Jackie Cromwell, VAP3

  • VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS

    • PPTA enabling legislation 1995

    • Numerous revisions to PPTA Guidelines over time

    • Creation of VAP3 office in 2010

    • 2014 – Substantial update to PPTA Implementation Manual & Guidelines

    • Goal is to build strategic program, extend VAP3 leadership

    • Virginia is a national leader and 2nd globally in P3 project development

  • I-95 & I-495 EXPRESS LANES PROJECTS

    I-495 Express Lanes • Opened to traffic November 2012 • Virginia’s $409 million investment

    leveraged a $1.9 billion project • Transurban increased its equity

    investment in 2014 • Over 10 million users in first two years I-95 Express Lanes • Opens in December 2014 • Virginia contribution of $71 million

    leveraged $925 million project • Adds to managed lanes system that

    include I-495 Express Lanes

  • ELIZABETH RIVER TUNNEL PROJECT

    • Two-lane tunnel connects Norfolk and Portsmouth

    • Parallels existing Midtown Tunnel under Elizabeth River

    • Includes maintenance, safety improvements for existing Midtown and Downtown Tunnels, extension of MLK Freeway

    • VDOT maintains ownership and oversight

    • Private partner ERC will finance and build facilities, operate and maintain for 58-year concession period

    https://www.driveert.com/wp-content/uploads/2012/01/Preferred-ERC-Project-Map-with_GantriesB.pdf

  • PARTNERSHIPS CREATE HUGE PUBLIC BENEFITS

    P3 Project Project Cost State Contribution

    % of Total Cost

    Jobs Supported

    Economic Activity

    495 Express Lanes

    $ 1.9 B $ 409 M 22 % 31,000 $ 3.5 B

    95 Express Lanes

    $ 925 M $ 71 M 7.6 % 8,000 $ 2 B

    Midtown Tunnel

    $ 2.1 B

    $ 420.5 M

    20 %

    1,700

    $ 170-254 M

    Total Benefits $ 4.9 B $ 901 M 18.4 % 40,700 jobs ~ $5.7 B

  • CHANGES IN PPTA PROCESS

    • 2012 PPTA Implementation Manual and Guidelines were used as foundation to solicit 100+ responses

    • Key responses were:

    – Broad cross section of respondents – Overwhelmingly positive – Both broad and specific – Included in new 2014 PPTA Manual & Guidelines

    • Comments were incorporated in 2014 PPTA Implementation

    Manual and Guidelines – Guidelines including VfM, Risk, and Public Engagement are currently

    being updated and released for public comments

  • PPTA PROJECT DELIVERY FRAMEWORK

    *Parties to be notified and briefed upon request after the Oversight Board decision: ‒ Chairs of General Assembly committees ‒ MPO’s ‒ Interested members of General Assembly ‒ Special interest groups ‒ Regulatory Agencies ‒ Public

    Briefing Focus: ‒ RFI results (as appropriate) ‒ Schedule ‒ Refresh on the high points from Project Development ‒ Preliminary Procurement documents ‒ Risk Analysis and Value-for-Money ‒ Estimated project cost ‒ Potential public subsidy ‒ Potential economic benefits ‒ Preliminary Business Points ‒ Initial Finding of Public Interest

    Briefing Focus: ‒ Detail-Level Screening Report ‒ Desirability as P3 ‒ Feasibility as P3 ‒ HB 2 Prioritization ‒ Duration of P3 development and procurement

    Briefing Focus: ‒ Major Business Points ‒ Updated Risk Allocation & Management Plan ‒ Statutory Audit results ‒ Final Value-for-Money Analysis ‒ Updated economic benefits ‒ Project bid results ‒ Public subsidy (if required) ‒ Final Finding of Public Interest

    Draft and Final Contract Documents posted on P3 Website for review & comment

    Final Contract Documents posted on P3 Website

  • KEY CHANGES IN 2014 PPTA MANUAL & GUIDELINES

    Increase Transparency • Brief Oversight Board at their public

    meetings • Findings of Public Interest • Brief General Assembly

    Transportation Committee Chairmen

    Enhance Competition • Coordinate P3 process with HB 2 • Additional review when there is only

    one proposer • Additional review if material change

    in project scope or risk allocation

  • KEY CHANGES IN 2014 PPTA MANUAL & GUIDELINES

    Increase Public Engagement • Develop P3 Public Engagement

    Guidelines • New VAP3 website information • 24/7 website comment opportunities

    Improve Risk Assessment and Management

    • Revise Risk Management Guidelines • Include risk workshop and

    discussions, risk registers and risk management plans

  • PPTA Steering

    Committee

    Project Development

    Returned to Agency or Proposer

    Unsolicited P3 Projects

    Detail-Level Screening with

    Recommendations

    Policy Review with Recommendations

    Solicited P3 Projects

    Oversight Board*

    Agency

    NO

    High-Level Screening with

    Recommendations

    NO

    PROJECT SCREENING PROCESS

  • PROJECT SCREENING PROCESS

    PPTA Steering

    Committee

    Project Development

    Returned to Agency or Proposer

    Unsolicited P3 Projects

    Detail-Level Screening with

    Recommendations

    Policy Review with Recommendations

    Solicited P3 Projects

    Oversight Board*

    Agency

    NO

    High-Level Screening with

    Recommendations

    NO

    High-Level Screening Criteria • Ability to Transfer Risk • Funding Requirement • Ability to Raise Capital • Complexity of Effectively Leveraging

    Private Sector Innovation/Expertise

    • Consistent with Federal Requirements • Accelerated Project Development • Satisfies Public Transportation Need • Addresses Priorities in State, Regional

    and/or Local Transportation Plan

    • Project Efficiencies through PPTA Delivery

  • PROJECT SCREENING PROCESS

    PPTA Steering

    Committee

    Project Development

    Returned to Agency or Proposer

    Unsolicited P3 Projects

    Detail-Level Screening with

    Recommendations

    Policy Review with Recommendations

    Solicited P3 Projects

    Oversight Board*

    Agency

    NO

    High-Level Screening with

    Recommendations

    NO

    Detail-Level Screening Criteria • Public Need and Benefits • Economic Development • Market Demand for PPTA Delivery • Stakeholder Support • Legislative Considerations • Technical Feasibility • Systematic Interface and Compatibility • Financial Feasibility • Legal/Legislative Feasibility • Project Risks • Life Cycle Management

  • CURRENT VAP3 PIPELINE

    Status of VAP3 Pipeline

    Projects in current VAP3 Pipeline 15

    Projects have completed High-Level Screening 12

    Projects have advanced to Detail-Level Screening 7

    Projects Detail-Level Screening underway 4

    Projects with completed Detail-Level Screening 3

    Projects advanced as P3’s into Project Development 1

  • CURRENT PPTA PIPELINE

  • CURRENT PPTA PIPELINE

  • FUTURE OF VIRIGINIA P3 PROGRAM

    • New 2014 PPTA Manual and Guidelines will continue to strengthen transparency, competition, public engagement, risk assessment and management

    • P3 benefits -- equity, risk sharing, life-cycle costs, timely delivery

    • Continue review of P3 process, decision-making, & accountability

    http://www.transurban.com/files/Washington_DC_495_01.pdfhttp://www.transurban.com/files/Washington_DC_495_01.pdf

  • FUTURE OF VIRIGINIA P3 PROGRAM

    VAP3 Pipeline will broaden in scope: • Real Estate transactions • Optimizing existing assets

    Current VAP3 Pipeline contains procurement types:

    • PPTA • PPEA • VPPA

    VAP3 Pipeline is continuously updated and on Website

    http://www.transurban.com/files/Washington_DC_495_01.pdfhttp://www.transurban.com/files/Washington_DC_495_01.pdf

  • P3 PROGRAM NEXT STEPS

    • Finalized 2014 PPTA Implementation Manual and Guidelines

    • Coordinated with transportation agencies adoption of the 2014 PPTA Manual

    • Finalize Guidelines in early 2015: 1. Risk Management 2. Public Engagement 3. Value for Money Analysis

    • Draft PPEA Manual in early 2015

  • P3 PUBLIC ENGAGEMENT

    • VAP3 new website – live in early December and serves as basis for P3 program & project information

    • Twitter - VAP3 live and serves as quick release of information

    • Apps – under consideration to share and interact with consumers

  • P3 LESSONS LEARNED

    • Permanent office acts as champion, catalyst, guide

    • Consistent, detailed guidelines facilitate delivery, realization of public benefits

    • Continuous reviews of assumptions and conclusions improve project decisions

    • Effective communications focus on benefits produced, broad policy goals advanced

    • Steady flows of information to agencies, officials, planners, media build understanding and trust

    • Others have good ideas, too, and competition is growing

  • P3 SHARED CHALLENGES

    • Public funds are shrinking • Traditional delivery methods are not filling the gap • Political focus too often is short-term and small, not strategic • Engagement allows us to see members of the public as customers

    and consumers of services willing to pay for what they value • P3s remain unnecessarily complex, mystery to many • More standard approaches, terms are needed • New P3 approaches can help fill gaps beyond transportation

  • THANK YOU

    Virginia P3 Update - 2015

    www.p3virginia.org

    Jackie Cromwell

    Virginia Office of Public-Private Partnerships [email protected]

    mailto:[email protected]

    Virginia P3 Update- 2015VIRGINIA LEADERSHIP�IN PUBLIC-PRIVATE PARTNERSHIPSI-95 & I-495 EXPRESS LANES PROJECTSELIZABETH RIVER TUNNEL PROJECTPARTNERSHIPS CREATE�HUGE PUBLIC BENEFITSCHANGES IN PPTA PROCESSPPTA PROJECT DELIVERY FRAMEWORKKEY CHANGES IN 2014 PPTA MANUAL & GUIDELINESKEY CHANGES IN 2014 PPTA MANUAL & GUIDELINESPROJECT SCREENING PROCESSPROJECT SCREENING PROCESSPROJECT SCREENING PROCESSCURRENT VAP3 PIPELINECURRENT PPTA PIPELINECURRENT PPTA PIPELINEFUTURE OF VIRIGINIA P3 PROGRAMFUTURE OF VIRIGINIA P3 PROGRAMP3 PROGRAM NEXT STEPSP3 PUBLIC ENGAGEMENTP3 LESSONS LEARNEDP3 SHARED CHALLENGESTHANK YOU