VIRTUAL PUBLIC MEETING July 2, 2020

Upload: others

Post on 03-Feb-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

  • VIRTUAL PUBLIC MEETINGJ u l y 2 , 2 0 2 0

  • PANELISTS

    Rod Nelson, PE, District Administrator

    Fred Bente, Project Manager

    Mike Taylor, PE, Pre-construction Engineer

    Michael Fabricius, Right-of-way Supervisor

    Doug Enderson, PE, PTOE, Design Project Manager

    Lisa Olmsted, Public Involvement Manager

    1

  • VIRTUAL MEETING AGENDA

    Project Team

    Project Overview

    Project Segments

    Johnson Lane Interchange

    Railroad Overpass

    Q&A

    2

  • PROJECT TEAM

    3

  • Five Mile RoadUnder Construction

    Yellowstone River Estimated completion Fall 2022

    Johnson Lane Interchange+/- 2022* (Tentative)

    RR O’Pass+/- 2023* (Tentative)

    Johnson Ln Intch – RR O’Pass+/- 2024* (Tentative)

    Five Mile Rd to US 87+/- 2025* (Tentative)

    1

    2

    3

    4

    5

    6

    *Letting dates subject to change4

  • FIVE MILE ROADSchedule

    Currently under construction

    Anticipated completion: Fall 2020

    Features

    Roundabout at Old HWY 312

    Two-way stop controlled intersection at Dover Road

    1 2 3 4 5 65

  • YELLOWSTONE RIVER Schedule

    Anticipated completion: Fall 2022

    Features

    Bridge across Yellowstone River

    Bike/Ped Lane

    1 2 3 4 5 66

  • JOHNSON LANE INTERCHANGESchedule

    +/- 2022 (Tentative)

    Granite/LHC selected as CM/GC summer 2019

    Features

    Diverging Diamond Interchange (DDI)

    Safety Improvements

    1 2 3 4 5 67

  • RAILROAD OVERPASSSchedule

    +/- 2023 (Tentative)

    Features

    One bridge crossing the BNSF railroad

    1 2 3 4 5 68

  • JOHNSON LN INTCH – RAILROAD OVERPASSSchedule

    +/- 2024 (Tentative)

    Features

    Arterial road connecting Johnson Lane Interchange to railroad bridge

    1 2 3 4 5 69

  • FIVE MILE ROAD TO US 87Schedule

    +/- 2025 (Tentative)

    Features

    New urban arterial north of Mary Street

    Reconfigured Main Street connection

    1 2 3 4 5 610

  • JOHNSON LANE INTERCHANGEProject Segment Updates

    Diverging Diamond Interchange (DDI)

    Adjacent work:

    Old Hardin Road

    • Johnson Lane

    • Becraft Lane

    • Cole Street

    Frontage Road

    • Sannon Boulevard

    11

  • JOHNSON LANE INTERCHANGEProject Segment Updates

    Construction Manager/General Contractor

    Advantages:Reduces Owner risk, increases Owner control

    Uses most qualified contractor

    Allows for collaboration/innovation

    More predictable schedule, speed of delivery

    Provides for cost certainty, required bids from subcontractors

    Open-book policy (ICE – Independent Cost Estimator)

    12

    Source: www.jacksongalloway.com

  • JOHNSON LANE INTERCHANGEProject Segment Updates

    Traffic Analysis and DesignEnvironmental Review and ComplianceRoad and Bridge DesignMulti-modal Accommodations Electrical DesignUtility DesignRight-of-Way Design & Acquisition

    13

  • JOHNSON LANE INTERCHANGEProject Segment Updates

    Traffic Analysis and DesignEnvironmental Review and ComplianceRoad and Bridge DesignMulti-modal Accommodations Electrical DesignUtility DesignRight-of-Way Design & Acquisition

    Videos of DDI available at:https://www.mdt.mt.gov/pubinvolve/billingsbypass/links.shtml

    14

  • JOHNSON LANE INTERCHANGEProject Segment Updates

    Traffic Analysis and DesignEnvironmental Review and ComplianceRoad and Bridge DesignMulti-modal Accommodations Electrical DesignUtility DesignRight-of-Way Design & Acquisition

    15

  • JOHNSON LANE INTERCHANGEProject Segment Updates

    Traffic Analysis and DesignEnvironmental Review and ComplianceRoad and Bridge Design

    • Trucks• Bridge Clearance• Medians

    Multi-modal Accommodations Electrical DesignUtility DesignRight-of-Way Design & Acquisition

    15

  • JOHNSON LANE INTERCHANGEProject Segment Updates

    Traffic Analysis and DesignEnvironmental Review and ComplianceRoad and Bridge DesignMulti-modal Accommodations

    • Pedestrians• Bicycles

    Electrical DesignUtility DesignRight-of-Way Design & Acquisition

    16

  • JOHNSON LANE INTERCHANGEProject Segment Updates

    Traffic Analysis and DesignEnvironmental Review and ComplianceRoad and Bridge DesignMulti-modal AccommodationsElectrical DesignUtility DesignRight-of-Way Design & Acquisition

    17

  • JOHNSON LANE INTERCHANGEProject Segment Updates

    Traffic Analysis and DesignEnvironmental Review and ComplianceRoad and Bridge DesignMulti-modal AccommodationsElectrical DesignUtility DesignRight-of-Way Design & Acquisition

    17

  • JOHNSON LANE INTERCHANGEProject Segment Updates

    Traffic Analysis and DesignEnvironmental Review and ComplianceRoad and Bridge DesignMulti-modal Accommodations Electrical DesignUtility DesignRight-of-Way Design & Acquisition

    Finalize Design

    Summer 2020

    Right-of-Way Acquisition

    Begin Owner Communication: Fall 2020

    Construction2022 (tentative)

    18

  • RAILROAD OVERPASSProject Segment Updates

    Begins at Yellowstone River BridgeBridge to Span RR Tracks and Coulson RoadTemporary Connection to Coulson Road

    18

  • RAILROAD OVERPASSProject Segment Updates

    Road Design• Preliminary Design• Room for Future Expansion

    19

  • RAILROAD OVERPASSProject Segment Updates

    Road Design• Preliminary Design• Room for Future Expansion

    19

  • RAILROAD OVERPASSProject Segment Updates

    Bridge Design• Railroad Expansion• Expandable Single Structure

    20

  • RAILROAD OVERPASSProject Segment Updates

    Coordination with TEDDFuture Infrastructure Needs

    20

  • ADDITIONAL INFORMATION

    Renderings by NC3D

    www.mdt.mt.gov/pubinvolve/billingsbypass

    [email protected]

    406.294.9668

    222 North 32nd #700Billings, MT 59101

    Virtual Public MeetingPanelistsVIRTUAL MEETING AGENDAProject TeamSlide Number 5Five Mile RoadYellowstone River Johnson Lane InterchangeRailroad OverpassJohnson Ln Intch – Railroad overpassFive Mile Road to US 87Johnson Lane InterchangeJohnson Lane InterchangeJohnson Lane InterchangeJohnson Lane InterchangeJohnson Lane InterchangeJohnson Lane InterchangeJohnson Lane InterchangeJohnson Lane InterchangeJohnson Lane InterchangeJohnson Lane InterchangeRailroad OverpassRailroad OverpassRailroad OverpassRailroad OverpassRailroad OverpassAdditional InformationBillings Bypass Myth-bustingProject MilestonesSlide Number 30Johnson Lane InterchangeRailroad Overpass