v.kain, h. burkhardt, b.goddard, w. hofle, v.mertens, s. redaelli, j.uythoven, j.wenninger
DESCRIPTION
V.Kain, H. Burkhardt, B.Goddard, W. Hofle, V.Mertens, S. Redaelli, J.Uythoven, J.Wenninger. Injection and Associated Protection Devices. Scope - Contents. Scope: Stage A: limit 43 x 43, 156 x 156 with 9 x 10 10 p + per bunch Only commissioning steps which require set-up with beam - PowerPoint PPT PresentationTRANSCRIPT
V. Kain – eLTC – 5March08 1
V.Kain, H. Burkhardt, B.Goddard, W. Hofle, V.Mertens, S. Redaelli, J.Uythoven,
J.Wenninger
Injection and Associated Protection Devices
V. Kain – eLTC – 5March08 2
Scope - Contents
Scope:
– Stage A: limit 43 x 43, 156 x 156 with 9 x 1010 p+ per bunch
– Only commissioning steps which require set-up with beam
• Injection/SPS extraction interlocking not covered
– Commissioning steps are described for one beam
• other beam requires repetition of same steps
– Time estimate per step in general: 1 – 2 shifts maximum
– Not very specific yet about exact values of target parameters
Contents:
– Injection commissioning during phase A.1
– Injection commissioning during phase A.2-A.3
– Injection commissioning during phase A.4
– Injection commissioning during phase A.5
*target parameters need to be properly defined
V. Kain – eLTC – 5March08 3
Injection Region
TDIMKI +90˚
TCDD
TCLIBTCLIA
KickerMKI
LEFT OF IP2 (H plane)
RIGHT OF IP2 (H plane)
TCLIM
SeptumMSI
TCDI
V. Kain – eLTC – 5March08 4
First turn
V. Kain – eLTC – 5March08 5
Preparation Phase A.1, pilot intensity, OP/BT
Requirements: – Transfer line re-commissioned with beam
• With TED in, then TED moved out
– Orthogonal steering available for MSI and MKI
– Settings generated for TDI (out, coarse, protect)
– Shot-by-shot logging configured
– Timing tables verified (BI capture events)
– Remove extraction permit at SPS
– All TCDIs/TCLIs out
– TDI masked (completely IN)
– TCDD in point 2 IN
– MKI ON, kick disabled
• Soft-start done
– All screens in, downstream of TED and downstream of MSI
• Cameras on
BTVSS: first screen in the LHC
V. Kain – eLTC – 5March08 6
First Injections – MKI NOT pulsing Phase A.1, pilot intensity, OP/BT
Enable extraction permit
Injection (MKI disabled):
– Beam should arrive at TDI, off-center
– Steer if required
• orthogonal steering at MSI and MKI already implemented in YASP
– Check signals at screens and BPMs (BLMs no losses)
• BTVSS, BTVSI1, BTVSI2, BPTX, BPMW, BTVST (in front of TDI)
– Steer to have correct offset at TDI on screen
• ~ + 30 mm
Verify BLM readings on TDI:
– Triggered acquisition of BLM readings
• Calibrate parasitically (mGy vs. intensity lost)
– Thresholds should not trigger
Screen in front of TDI
V. Kain – eLTC – 5March08 7
First Injections – MKI pulsing Phase A.1, pilot intensity, OP/BT
Remove extraction permit – enable MKI, pulse Enable extraction permit Inject
Adjust delay such that beam is in middle of waveform
Verify vertical position on BTVST in front of TDI
– Steer MKI angle
– Beware of BETS constraints
Move TDI to PROTECT position– +/- 7 mm
– Remove BIC mask on TDI
Start threading around ring… (Move out injection screens)
V. Kain – eLTC – 5March08 8
Circulating beam – 450 GeV initial commissioning (BI, beam dump,…)
V. Kain – eLTC – 5March08 9
Injection re-steeringPhase A.2, pilot intensity, OP; Phase A.3, 3 x 1010, OP
Phase A.2: after establishing closed orbit:
– Inject & circulate
– Initial optimisation of injection oscillations: re-steer injections
Phase A.3: high precision orbit measurements:
– Inject & circulate
– Optimisation of injection oscillations: re-steer injections
• Minimise to… e < 0.5 (results in 12 % emittance growth without damping)
*target parameters need to be properly defined
V. Kain – eLTC – 5March08 10
450 GeV optics measurements
V. Kain – eLTC – 5March08 11
Injection stability - reproducibility Phase A.4, 3 x 1010, OP
Injected beam: check stability of injection point
– Transfer line and MKI effects
– Inject & dump
– 1000 shots
– Use BPMs and BTVs in injection region + BPMs and BTVs before MSI in transfer line
– Shot-by-shot, restarting after a couple of days (temperatures, MKI soft-start, …)
Circulating beam at injection
– Orbit at injection point/TDI
– Beam sizes at injection point/TDI
– Looking at nominal cycle only…
– Parasitically every time we fill
V. Kain – eLTC – 5March08 12
Aperture in injection region (1) Phase A.4, pilot intensity – 3 x 1010, OP/BT
Aperture bottlenecks in the LHC injection regions:
– MSI, Q5, MKI, D2
– → Q5 tilted
• + 1 mm on IP side
• - 2 mm on IP side
Q5 tight under nominal conditions – n1 = 6.2
MKI and D2 tight for
– Non-kicked injected beam
– Kicked circulating beam → beam in the injection kicker rise time gap (~ 0.9 s)
Injected non-kicked beam
IP2 (n1) IP8 (n1)
MSI ~ 5.5 ( 2 mm trajectory tol.)
~ 5.5 ( 2 mm trajectory tol.)
Q5 8.7 6.2
MKI 6.8/5.4 6.3/6.1
D2 4.9/4.2 6.7/5.1 J. Uythoven
J. Uythoven: InjWG 07-05
V. Kain – eLTC – 5March08 13
Aperture in injection region (2) Phase A.4, 3 x 1010, OP/BT
Aperture measurement: MSI and Q5
– Use injected beam → inject & dump, TDI out
• BLMs triggered acquisition mode
• FBCTs in point 4/point 6
– Transfer line knobs in sigma to measure aperture
– Limited by aperture of MSI
– Calibrate BLMs at MSI (on TCDIM and MSIs)
Aperture measurement: MKI and D2
– Use circulating beam → circulate & dump, TDI needs to be in PROTECT
– Kick circulating beam + scan bump at D2 or MKI
• BLMs triggered acquisition mode
– (Take out bumps at the end)
V. Kain – eLTC – 5March08 14
Scan MKI waveform Phase A.4, 3 x 1010, BT/OP
Scan MKI waveform:
– Inject & dump
– Use screen at TDI (90º downstream)
– Scan kicker delay
Example: LHC extraction commissioning – SPS LSS6 – 2006kick delay was changed, position measured with screen.
V. Kain – eLTC – 5March08 15
Injection Matching (1) Phase A.4, 3 x 1010
Mismatch possibilities – leads to emittance growth and tail repopulation
Emittance growth:
– Betatron, dispersion mismatch – measurement of twiss parameters at injection point
– Energy, steering mismatch – verify with BPMs around the ring → see Jorg’s talk
– Geometry
Tail repopulation: verify with scraped beam from SPS and scrapers in the LHC → stage B
Results from simulations: Dominant effect: betatron and dispersion mismatch
Emittance growth predicitio
n about 3 %
Tail repopulatio
n after s
craping in SPS
V. Kain – eLTC – 5March08 16
Injection Matching (2)Phase A.4, 3 x 1010, OP/ABP
Oscillation of image on matching screen indicates mismatch
– Matching screen in point 3 (will not be there for 2008)
LHC optics needs to be measured
To measure twiss parameters at injection point (dispersion, betas and alfas)
– Matching screen turn-by-turn
– Screens in injection region
Eventually (= stage B) need to control better than:
– Betatron mismatch: < 1.15
– Dispersion: maximum mismatch of 10 cm, 0.001 rad
Screen matching application:used for TI 2: • 2 D fit for beam sizes• optics calculated at any point in the line• same application can be used for LHC
*target parameters need to be properly defined
V. Kain – eLTC – 5March08 17
Increasing intensity4 bunches max injected for 43 x 4316 bunches max injected for 156 x 156
V. Kain – eLTC – 5March08 18
Operational States?
In this phase injection protection starts to play a role
The systems will be commissioned for a certain envelope – Optics
– Emittance
– Crossing-/separation angle, experimental magnet polarity
– Maximum injected intensity
– …
What/who makes sure that the systems are not used outside these “operational states” without re-commissioning or adjusting?
V. Kain – eLTC – 5March08 19
Multi-bunch injectionPhase A.5, 4 x 3 x 1010 or 16 x 3 x 1010, OP/BT
Multi-bunch injection: – Adjust delay for MKI kick
For 16 x 3 x 1010: – Only after setting up the TDI
– For 4 x 3 x 1010: TDI roughly set up
• Optics knowledge from phase A.4
• Centered
Example: LSS4/LSS6 extraction
V. Kain – eLTC – 5March08 20
Setting-up of TDIPhase A.5, 3 x 1010 – 4 x 3 x 1010, BT/collimation team/OP
The required setting of the moveable passive protection devices depends on the LHC aperture. Assume 7.5 .
TDI:– ~ 4m long, ~ 10 m upstream of D1, additional mask in front of
D1 (TCDD)
– Protects machine against MKI failures
– Required setting: 6.8 TDI – setting-up
– At this stage independent of cleaning collimators
– Setting-up like cleaning collimators: covered by Ralph’s talk• Centering, alignment, beam size measurement
– Test of synchronized (automated) setting-up with the beam cleaning collimators
– Verify fill-to-fill reproducibility, orbit feedback
Verify aperture for second beam Verify protection against MKI failure (3 x 1010):
– Trim the MKI angle (beware of BETS limits and critical settings)
– Maximum escaping amplitudes must be < 7.5 and primary loss should only occur at the TDI
TCLIs → Stage B– Unless phase advance between TDI and MKI compromised
V. Kain – eLTC – 5March08 21
Setting-up of Transferline Collimators (TCDI)Phase A.5, 3 x 1010, BT/collimation team/OP
Requirement:
– Transferline optics measured
Setting-up: each TCDI individually (the others need to be out)• Inject & dump
• Centering, alignment, beam size cross-check, set to 4.5
• Use BLMs (local, non-local), BCTs TL/point 4/point 6
– Calibrate BLMs on TCDIs and masks parasitically
• Thresholds set to: maximum allowed loss: 1 x 1011
• Verify response on nearby superconducting magnets
Check phase space coverage: maximum amplitudes escaping system: < 6 • Inject & dump, move out TDI
• Use aperture scan knobs from transfer lines
– Oscillations down the line, generated by combinations of corrector magnets
*target parameters needs to be properly defined
4.5 setting with maximumtolerance
V. Kain – eLTC – 5March08 22
Setting-up transverse damperPhase A.5, 3 x 1010 – 4 x 3 x 1010, RF/OP
Details in Wolfgang’s talk
Commission transverse damper to damp injection oscillations:– Inject & circulate
– Could be done in phase A.4: single bunch: mis-steer injection
• Measure emittance in line and in ring after injection (with and without damping)
– Multi-bunch: injection kicker waveform effect
• Verify with emittance measurement
Commission transverse damper to clean MKI rise time gap → stage B / depending on re-population mechanism and aperture in D2
– Might need to clean abort gap at the same time
V. Kain – eLTC – 5March08 23
Injection protection needs to be revisited for…
New LHC optics version
Emittance changes
Injection re-steering
– Aperture verifications in the injection region
– Transfer line collimator centering needs to be verified
– Injection protection needs to be set up again
Poor reproducibility after re-cycling
– Re-set up injection protection system
Rematching of transfer lines
– Transfer line collimators need to be set up again
Crossing-, separation angle changes, polarity changes of experimental magnets
– Injection re-steering
V. Kain – eLTC – 5March08 24
Conclusions
A commissioning plan has been developed to prepare the LHC injections for up to 156 x 156 with 9 x 1010 particles per bunch
Injection quality and injection protection has been taken into consideration
Details of target parameters still need definition
A “procedure/formalism/check list…” must be put in place to guarantee that the systems are not operated outside the parameters they have been commissioned for.