Introduction Piller Power Systems
Why we need a Power Conditioning System
Dynamic Diesel UPS UNIBLOCK UBTD
Application Data Centre (Tier II to Tier IV)
What makes the difference?
A Langley Holdings Company
The only company which produces rotary and static technologies in the field of power protection
Founded in 1909
Approx. 750 employees
Represented in more than 30 countries of the world
Quality management as per ISO 9001
Uninterruptible Power Supplies & Power Conditioning Systems
400Hz Aircraft GroundPower Supplies
Power supplies for military applications
Frequency conversionsystems 50 / 60 Hz
Piller at a Glance
A Langley Holdings Company
Piller Power Systems Group
Modern Manufacturing
Purpose-built manufacturing in
Osterode and Bilshausen / Germany
14 hectares total area
approx. 50,000m² accommodation
A Langley Holdings Company
UPS & Power Conditioning
AP Premium: 100 kVA to 400 kVA APOTRANS : 25A to 1600A
UNIBLOCK UBR: 150 kVA to 1300 kVA UNIBLOCK UBTD: 400 kVA to 3000 kVA
AR Series: 3 kVA to 100 kVA
UNIBLOCK UBT: 400 kVA to 2000 kVA
A Langley Holdings Company
Piller Power Systems world wide
Piller Taiwan
24h service with APOCONNECT
A Langley Holdings Company
Piller in Middle East / Turkey
• Installed Dynamic / Diesel UPS units in Middle East and Turkey > 40MW• Installed Static UPS units in Middle East and Turkey > 12MW
Some Diesel UPS installations in Gulf countries:
Bahrain Financial Harbour: 3 x UNIBLOCK UBTD 1500 / 1100 kVA
MBC Bahrain 1 x UBTD 800
New Doha International Airport 4 x UBTD 1600 Containerized
Qapco 1 x UBTD 1100 kVA
JCP Saudi Arabia 2 x UBTD 1670
etc……
A Langley Holdings Company
Why do we need a Power Conditioning System ?
Mains disturbances
Short interruptionsTotal failuresFrequency fluctuationsVoltage fluctuationGlitchesHarmonics
Load disturbances
Load fluctuationsUnbalanced loadsOverloadsHarmonicsPeak currentsShort circuits
Power improvementSystem
Intrinsic safety of the Power improvement System
Your power improvement system must be able to cope with all of these disturbances
A Langley Holdings Company
UNIBLOCK UBTD Characteristics
Totally flexible configurations,Medium and Low Voltage
Different Diesel Engineselectable
Customisedbattery forshort backup
Powerbridgefor up to 39sshort backup
or
Totally flexible configurations,Medium and Low Voltage
Different Diesel Engineselectable
Customisedbattery forshort backup
POWERBRIDGEfor up to 39sShort backup
A Langley Holdings Company
UNIBLOCK UBTD – Dynamic Diesel UPS
HQ Bus
UNIBLOCKMachine
POWERBRIDGE
GG
M
Automatic Bypass
Coupling ChokeMains
LV or MV
Diesel Engine
Thyristor converter
A Langley Holdings Company
Complete System Arrangement
POWERBRIDGE
UTILITY
MOTOR INPUT
GENERATOROUTPUT
TO CRITICALLOAD
M
M
AUTOMATIC BYPASS
ISOLATING/ COUPLING CHOKE
BI-DIRECTIONALCONVERTER
D.C.
LINK
M
A Langley Holdings Company
UNIBLOCK-machine, the evolution
Rotating rectifier
Generator windingMotor winding
Ponymotor
Excitation
Fan
Hybrid machine invented in 1981 by PILLER
GeneratorMotor
Traditional system
Damperwinding
Motor winding Generator winding
Exciter winding
A Langley Holdings Company
UNIBLOCK UBTD Motor / Generator
Motor and Generator Windingsin a Common Stator
Common RotorWith Damper Winding
System FanBrushlessExcitation
Bearing
Bearing
A Langley Holdings Company
POWERBRIDGE Schematic
Magnetic SupportTop BearingTop Guard BearingRotating RectifierExcitation GeneratorMain Machine
Flywheel
Bottom Bearing
Bottom GuardBearing
A Langley Holdings Company
POWERBRIDGE bridging time
0
20
40
60
80
100
120
140
0 200 400 600 800 1000 1200 1400 1600 1800
UPS power /kVA
Brid
ging
time
/s
POWERBRIDGE 16.5 MJ bridging time versus load
Available in: 6 MJ , 16,5 MJ , 19 MJ
A Langley Holdings Company
The Choke
VM
Output:Short-circuit current:- 14 x nominal current 10 ms - 3 x nominal current 5 s
Load
VL
7%
Input:
Input Power factor: 0,99
50% 1%
GM
X
Harmonic attenuation: 99%
Mains
Voltage dip: -10% continuous
-20% for 10 min
-50% up top 30s
Harmonic attenuation: 99%
A Langley Holdings Company
Components
Diesel Control Panel Genset
UNIBLOCK UBTD Control Panel
Diesel starter battery
Control battery
A Langley Holdings Company
Components of the Generating-set
Flexible couplingPiller UNIBLOCKMotor / Generator
Diesel Control Cabinet
Diesel Engine
Base FrameMechanical
Overrun Clutch
Rubber Vibration-absorbing Pads
A Langley Holdings Company
Mains operation
1
THYRISTORCONVERTER
G
POWERBRIDGE
MG
UNIBLOCK Machine
DIESEL
MAINS UPS Bus
A Langley Holdings Company
POWERBRIDGE operation
2
THYRISTORCONVERTER
G
POWERBRIDGE
MG
UNIBLOCK Machine
DIESEL
MAINS UPS Bus
A Langley Holdings Company
Diesel operation
3
THYRISTORCONVERTER
G
POWERBRIDGE
MG
UNIBLOCK Machine
DIESEL
MAINS UPS Bus
A Langley Holdings Company
Function overview of a UNIBLOCK UBTD
UPS Output voltage
Diesel speed
POWERBRIDGE speed
Mains
A Langley Holdings Company
Function overview of a UNIBLOCK UBTDwith emergency bus
MG
UNIBLOCK T
THYRISTORCONVERTER
G
POWERBRIDGESHORT BREAK BUS
DIESEL
MAINS UPS
MG
UNIBLOCK T
THYRISTORCONVERTER
G
POWERBRIDGESHORT BREAK BUS
DIESEL
MAINS UPS
321 1
1
3
2
Diesel speed
UPS Outputvoltage
SpeedPOWERBRIDGE
Mains
5 s
15 s
1 min3 min
2 s
MG
UNIBLOCK T
THYRISTORCONVERTER
G
POWERBRIDGESHORT BREAK BUS
DIESEL
Mains UPS
2Short break bus
A Langley Holdings Company
UNIBLOCK UBTD Single unit ratings
LV 50Hz
400V / 415V 380V
420kVA 420kVA
500kVA 500kVA
625kVA 625kVA
800kVA 800kVA
1100kVA 1100kVA
1670kVA 1670kVA
2000kVA 2000kVA
2500kVA 2350kVA
LV 60Hz
380V 440V 480V
400kVA 460kVA 500kVA
500kVA 550kVA 600kVA
600kVA 690kVA 750kVA
750kVA 920kVA 1000kVA
1100kVA 1200kVA 1300kVA
1600kVA 1670kVA 2000kVA
1800kVA 2400kVA
3000kVA
MV
50Hz 60Hz
1670kVA 1670kVA
2000kVA 2000kVA
2500kVA 3000kVA
A Langley Holdings Company
UNIBLOCK UBTD Containerized Version
Advantages:Operating readiness immediately on connecting to the mains. No structural measures for noise attenuation, ventilation or cabling.No expenditure for on-site testing and commissioning.No outlay on complex installation or plant room construction.Temporary use in different locations.Reduced on site programme.
A Langley Holdings Company
Application: Parallel redundant configuration(Tier II)
Load evenly spread between UPS modules
Maintenance of UPS possible without switching to bypass
Disconnector for separation of UPS bus bar
Optional external automatic bypass and external bypass control
Distribution paths upstream and downstream still single-points-of-failure
Number of parallel connected UPS limited by short circuit current capability of UPS bus bar
DUPS1
Manual-Service-Bypass
Unprotected mains/Short break bus
Unprotected loadDUPS
nDUPSn+1
……
Disconnector
UPS distribution 2
UPS distribution 1
Data centre
UPS busbar
G
n
G
+1
Auto-Bypass
A Langley Holdings Company
Application: Data centre with A-B supply and n+1 isolated redundancy (Tier III)
Total installed UPS power (n+1)*100% of rated loadProtects against the loss of one UPSA shorted load has no effect on the other loadsNo limitation in powerRedundancy down to the loadConcurrently maintainableVery high availability
G G
n +1
DUPS1
Mains 1
Unprotected mains/Short break bus
DUPS2
DUPSn
DUPSn+1
Busbar A
Busbar B
STS STS STS STS STS STS
A Langley Holdings Company
Application Large-scale data centre Tier IV with 2 independent UPS systems (n+1)
System + System redundancyMultiple distribution paths simultaneously serving IT load Complementary systems and distribution paths physically separatedComb-like arrangement of bus barsIT equipment dual powered or supplied by STSRedundant supply of individual loadsIt is debatable if 1 x (n+1) gensetsare sufficient
Disconnector
Busbar
UPS busbar
DUPS1
DUPSn+1
DUPS2
Man
ual-S
ervi
ce-
Byp
ass
DisconnectorUPS busbar
DUPS1
DUPSn+1
DUPS2
Man
ual-S
ervi
ce-
Byp
ass
DP
DP
Mains 2
…..Load1
…..Load1
Loadx
Loady
…..Load1
Loadx
…..Load1
Loady
A
B
A
B
A
B
A
B
G
n
G
+1
G
n
G
+1
Unprotected mains/Short break bus
Mains 1
STSSTS
STS STS
A Langley Holdings Company
What makes the difference?
3-times rated current does not allow a safe & fast clearing of downstream faults. Consequence during mains failure:UPS output voltage = 0 , all loads affected !
Ishort
circuit
?
Ishort circuit from the mains
14-times high short circuitcurrent for a quick switch-offof defective loads during all operation modes, mains, battery and Diesel.
14-times rated Current ensures that faulty load is disconnected in 10ms
High short- circuit capacity
A Langley Holdings Company
3-phase output short circuit
UNIBLOCK T Measurements
What makes the difference?
A Langley Holdings Company
22,3 kA
17,5 kA
= 13,6 x In
= 10,7 x In
3-phase output short circuit
UNIBLOCK T Measurements
What makes the difference?
A Langley Holdings Company
What makes the difference?
Crest Factor ExampleLoad current waveform of an IT load
Distortion (THD) 89%Crest Factor 5.5
A Langley Holdings Company
No crest factor limitation
HQ-power independent of the load conditions.
Load voltage
Consequence
Peak current
R M S current1
UBTDLoad current
Peak current
R M S current1
Load currentStatic UPSLoad current
Current limiting
1
Peak current
R M S current3
3
Load voltage
Consequence
What is the crest-factor ?
peak currentR M S current
Crest factor =
What makes the difference?
A Langley Holdings Company
Bridging time:
Bridging short term power interruptions without starting the Diesel Engine
What makes the difference?
A Langley Holdings Company
What makes the difference?Input Voltage tolerance: Compensation of the voltage dips without starting the Diesel Engine
Input Voltage tolerance -10% continuous -20% for 10 min -50% up to 20s
Optional (800 to 2000 kVA)-20% continuous-30% 10 min-50% up to 20s
VLVM
Mains Load
Motor-Generator G
M
G
Thyristor Converter
POWERBRIDGE
A Langley Holdings Company
Reversible function of POWERBRIDGEDealing with load changes:
What makes the difference?
VLVM
Mains Load
Motor-Generator G
M
G
Thyristor Converter
POWERBRIDGE
A Langley Holdings Company
What makes the difference?
Harmonic attenuation 99% :
Mains Load
VM VL
Motor-Generator
GM
6%
1%50%
A Langley Holdings Company
What makes the difference?Mains short circuit:
Motor-Generator
GM
Mains Load
VLVM
Input Choke:
• Piller: 50%
6%
1%50%
A Langley Holdings Company UNIBLOCK Measurements
Single phase inputshort
circuit
What makes the difference?
A Langley Holdings Company
Permissible input frequency deviation:
What makes the difference?
Mains Load
Mains frequency deviation +/-5%VM VL
Motor-Generator
GM
Piller: +/-1% (Adjustable to +/- 5%)If the load can accept
A Langley Holdings Company
Redundant Diesel start Power source.
Possibility to start the Diesel Engine by POWERBRIDGE
What makes the difference?
POWERBRIDGEDiesel starter battery
A Langley Holdings Company
What makes the difference?Piller Engineering / Quality
100 years of experience in design and manufacturing dynamic devices
A Langley Holdings Company
Other Diesel UPS40% of all mainsdisturbances compensated without engine start
UNIBLOCK UBTDUp to 99% of all mains disturbances compensated without engine start
Other Diesel UPS40% of all mainsdisturbances compensated without engine start
UNIBLOCK UBTDUp to 95% of all mains disturbances compensated without engine start
UNIBLOCK UBTDMains failure statistic for medium voltage
What makes the difference?
A Langley Holdings Company
Summery
Wide input voltage tolerance (+15%/-10%, -20% for 10 min, -50% up to 30s)
Very high MTBF Efficiency up to 96%Unlimited crest factorFault discrimination with 14x rated currentLarge overload capacity ( 10% for 1 h, 25% for 10 min, 50% for 2 min )
Fast energy delivery and absorptionConstant output during load fluctuationThe capacity can be extended
A Langley Holdings Company
Summery
RS 232, RS 485 or SNMP adapterUNIBLOCK can supply the UPS Load and the none sensitive load No need to start the engine for every mains failureFreedom to choose many Diesel engine manufacturerCompact constructionsLow maintenance costExcellent frequency stability