volume 4: the brief...the new civic centre working party outlined a concept plan that identified...
TRANSCRIPT
VOLUME 4: THE BRIEF
TENDER No. ULSC 2018/47
FOR
DESIGN OF NEW COMMUNITY
AND CIVIC CENTRE
Closing Date: Thursday 8 November 2018 Closing Time: 4.00pm (Australian Eastern Standard Time)
Sl. No. Revision Date Reviewed by Approved By
1 A 05/10/2018 Asif Faisal
2 B 16/10/2018 Asif Faisal & Mursaleen Shah
3 C 17/10/2018 Mursaleen Shah Mursaleen Shah
The Brief – 2018/47
Design of New Community and Civic Centre
Table of Contents 1 BACKGROUND INFORMATION ............................................................................................................. 3 2 UPPER LACHLAN SHIRE COUNCIL – NEW CIVIC CENTRE ............................................................... 3
2.1 EXISTING SITUATION ................................................................................................................... 3 2.2 PROJECT NEEDS .......................................................................................................................... 3 2.3 DESIGN REQUIREMENTS ............................................................................................................ 4 2.4 INTRODUCTION ............................................................................................................................. 4 2.5 DESIGN PRINCIPLES .................................................................................................................... 5 2.6 SCOPE OF WORKS ....................................................................................................................... 5 2.7 GENERAL ....................................................................................................................................... 5 2.8 DESIGN REVIEWS ......................................................................................................................... 7 2.9 SAFETY IN DESIGN ....................................................................................................................... 7 2.10 SUSTAINABLE DESIGN ................................................................................................................. 7 2.11 ACCESS.......................................................................................................................................... 8 2.12 FINISHES AND MATERIAL SELECTION....................................................................................... 8 2.13 BUILDING SERVICES .................................................................................................................... 9
2.13.1 MECHANICAL ............................................................................................................................ 9 2.13.2 ELECTRICAL .............................................................................................................................. 9 2.13.3 LIGHTING ................................................................................................................................... 9 The consultant is to consider a concept for exterior and interior lighting. ................................................. 9 2.13.4 AUDIO VISUAL ........................................................................................................................... 9 2.13.5 SECURITY .................................................................................................................................. 9 The consultant is to consider the provision of security access to the building. ........................................ 9 2.13.6 HYDRAULICS ............................................................................................................................. 9 The consultant is to engage a hydraulic consultant to prepare a hydraulic concept for the project. This is
to include modelling of the on-site stormwater provisions and pressure tests to address the needs of on-site firefighting equipment. ...................................................................................... 9
2.13.7 FIRE PROTECTION ................................................................................................................... 9 2.13.8 BUILDING STRUCTURE ............................................................................................................ 9 2.13.9 CIVIL INFRASTRUCTURE & LANDSCAPING .......................................................................... 9 2.13.10 TRAFFIC AND PARKING ......................................................................................................... 10 2.13.11 UTILITIES AND SERVICE INFRASTRUCTURE ..................................................................... 10
2.14 DESIGN QUALITY CONTROL ..................................................................................................... 10 2.15 DESIGN DEVELOPMENT DRAWINGS ....................................................................................... 11 2.16 PLANNING APPROVALS ............................................................................................................. 11 2.17 COMPLIANCE WITH STANDARDS ............................................................................................. 12 2.18 ESTIMATES THROUGHOUT THE DESIGN PROCESS ............................................................. 13 2.19 SUMMARY OF DELIVERABLES FOR INCLUSION IN THE PROPOSED REDEVELOPMENT
PROGRAM .................................................................................................................................... 13 2.20 PROPOSED NEW CIVIC CENTRE PROGRAM .......................................................................... 13
2.25.1 KEY PROJECT MILESTONES ................................................................................................. 13 2.25.2 STAGING REQUIREMENTS .................................................................................................... 14 2.25.3 FUNDING OPPORTUNITIES AND CONSTRAINTS ............................................................... 14 2.25.4 VALUE MANAGEMENT ........................................................................................................... 14
2.26 DESIGN PLAN FORMAT .............................................................................................................. 15 2.27 ADDITIONAL SERVICES ............................................................................................................. 15 2.28 PROJECT COMMUNICATION PLAN ........................................................................................... 15 2.29 APPENDIX DOCUMENTS ............................................................................................................ 15
Page | 3
The Brief – 2018/47
Design of New Community and Civic Centre
1 BACKGROUND INFORMATION
Council is seeking design, planning and regulatory consultancy services for the proposed upgrade of the New Civic Centre for Upper Lachlan Shire Council.
Upper Lachlan Shire Council has previously carried out a number of reviews of the Council’s Civic Facilities. Previous proposals have been explored in detail at green field site(s). However, in 2017, it was decided by the elected representatives of Council to establish a committee to finalise a site and a concept for the new Civic Centre. This Committee has chosen to redevelop the existing site located at 44 Spring Street Crookwell NSW 2583 combined with the Heritage Bank Building located at 108 Goulburn Street Crookwell NSW 2583.
A scoping study was commissioned for this site. The proposal to be prepared by the successful tenderer is for the design, estimation of costs based on this design and associated approvals e.g. Development Application to allow the Council to seek funding via grants. Any consultancy services after the completion of Development Application stage is to be by a separate agreement.
This background information has been taken from the Saleyards Civic Centre Proposal, for information purposes. The complete study is included as Appendix A. A scoping study on the Spring Street Site is included in Appendix B.
2 UPPER LACHLAN SHIRE COUNCIL – NEW CIVIC CENTRE
2.1 EXISTING SITUATION
Upper Lachlan Shire Council currently operates out of 44 Spring Street, Crookwell and in separate offices located in Gunning and Taralga. The current facilities do not meet the requirements for public access to Council Meetings or the amenity required for Staff.
In 2017 the Bank of NSW Building at 108 Goulburn Street, Crookwell was offered for sale and was purchased by Upper Lachlan Shire Council as a building for the future development of Council Facilities.
A scoping study was commissioned for the combined sites. This study is included in the Appendices attached.
A detailed field survey of the site and initial traffic counts in Robertson Lane has been commissioned by the Council and is not a requirement for inclusion in this tender.
2.2 PROJECT NEEDS
A community Working Party was also established to assist with development of the New Civic Centre concept plan. In formulating the concept plan, the Working Party reviewed previous projects and participated in community consultation exercises to compile a plan that brings the existing facility in line community expectations and achieves modern design standards.
The New Civic Centre Working Party outlined a concept plan that identified core provision for a New
Civic Centre, these provisions were subsequently supported by staff review. These include:
o New Council chambers,
o Facility for each council department ,
o Centralised Public interaction,
o Community Facilities,
o Retention of Heritage Items.
Upper Lachlan Shire Council endorsed recommendations from the New Civic Centre Working Party to proceed with detail design development. At the conclusion of detail design and development
Page | 4
The Brief – 2018/47
Design of New Community and Civic Centre
application approval the Council will seek grant funding for the project. To enable this funding application, Council requires a scope (design), estimated costs (QS) and schedule (project time line).
2.3 DESIGN REQUIREMENTS
Upper Lachlan Shire Council will engage an experienced Design Consultant to provide
the following services for the New Civic Centre:
o Conduct all investigations and specialist studies to support design and development applications (regulatory approvals). ,
o Prepare design plans, cost plans, project schedule and required reports ,
o Prepare and submit a Development Application,
o Prepare drawings Issued For Construction (IFC) suitable for construction,
o Provide ongoing support for the grants application based on scope, estimate, schedule, responses to Request For Information (RFI) and associated risk assessment.
The Design Consultant shall have prior design experience in Administration Building
design, demonstrate relevant subject matter expertise with examples of similar
buildings and to those proposed here.
The Design Consultant shall have extensive knowledge of relevant building codes and
standards including; Building Code of Australia, NSW Environment Planning and
Assessment Act 1979, Work Health & Safety Acts & Regulations, Disability Discrimination
Act (DDA) and related legislation and guidelines.
2.4 INTRODUCTION
In preparation of the final concept plan for the New Civic Centre, Council and the Working Party
recognised the need to prioritise the redevelopment to align with grant funding and respond to changing
community needs over the medium term (5 to 10 years). The following are suggested for consideration
as a guide:
The first task for the Design Consultant is to conduct a scope (needs) confirmation workshop
with relevant stakeholders to confirm the scope of works. The scoping study (Appendix B)
outlines the core physical works although a workshop is required to identify some specific
aspects that needs attention. The Design Consultant will develop a return brief a
requirements statements outlining the findings and what is required to meet the identified
need from the workshop. This Needs and Requirement is to be submitted to Upper Lachlan
Shire Council as confirmation of the design scope of works.
Upper Lachlan Shire Council requires the proposed facilities achieve high standards in terms
of design quality and the finished facility, however project budget limitations are to be
considered throughout the design and documentation process. It is recommended that Value
Engineering work is undertaken during the concept development stage required for the
Development Application to firm up assumptions for the detailed design and constructions
phases of the project.
This project will adopt value management principles to ensure best value for money whilst
maintaining design quality and ensuring longevity of the proposed facilities and
recommendations must be provided regarding each of the Functional Element for approval.
The development is to comply fully with the latest relevant version of the appropriate
Australian Standards, relevant Guidelines and the Building Code of Australia.
The design will, within the budget limitations, achieve a high standard of sustainable design
outcomes, whilst ensuring the building is cost effective and is based on efficient and
economical design in its operation and construction that meets the current and medium term
needs of the Council.
There will be three design development steps; Concept Design, Preliminary Design and Final
Design.
o Concept Design is 40% design development.
o Preliminary Design is 70% design development.
Page | 5
The Brief – 2018/47
Design of New Community and Civic Centre
o Final Design is 100% design development. Value Engineering test, evaluation and recommendation are be provided to Council for approval against each of the Functional Element (or Work Breakdown Structure if applicable).
2.5 DESIGN PRINCIPLES
The following principles have been prepared to guide the building design process:
A capacity to extend – wherever possible, redeveloped/ new built elements should ensure
that additional components can be added to or extended as needs and priorities require,
Space/rooms flexibility – all built spaces will have use flexibility designed into them,
Optimising solar capture capability – positioning of buildings should allow optimal solar
energy capture,
Transparency – the public and users should be able to have views into and the Public areas
of the Civic Centre,
Use height/ slope relationships – this will optimize use while constraining footprint: variable
building heights should be used to provide optimal rooms/ activity spaces while reducing
the size of the footprint; slopes should be used to reduce the visual mass of buildings,
Multiple access – the design will allow different users and program/ service providers and
building component owners/leaseholders to have different forms of access,
Use zoning – the zoning of uses should be followed so as to create departments
Multiple linkage to surrounds – physical links should be developed / designed with
adjacent, nearby and more remote activities/ facilities.
2.6 SCOPE OF WORKS The scope of works is scheduled in detail from the previous schemes proposed for the green field site(s). Previous plans for a proposed green field’s site are indicative only of the scope of works. Refer to Appendix A for the drawings and Appendix C for the schedule of spaces.
2.7 GENERAL
The Design Consultant is to prepare a design development methodology for the works that
is to be approved by Upper Lachlan Shire Council’s Project Manager. As a minimum the
design methodology is to outline the project team, specialist investigations and studies,
specialist technical resources, design development schedule, innovation opportunities,
review workshops, design process quality management, stakeholder consultation, risk
management, supporting design documentation development and payment milestones. The
design development methodology is to be approved prior to commencement of any
investigation or design work.
The design is to be flexible and efficient and make allowance for future proofing and multiple
use of spaces.
Subject to costs and building performance and energy efficiency parameters, the design
should maximise floor to ceiling heights and external visual connections.
Generally and wherever possible equipment and finishes must have a well-established track
record in the Australian market with local service back-up.
Provide an open, welcoming and inviting entry sheltered from prevailing weather and with a
contemporary look and feel which is appropriate to the town centre precinct. Provide a colour
and materials pallet to the streetscape to assist with ambient lighting levels and safe
supervision.
Liaison with the Upper Lachlan Shire Council’s Project Manager, Upper Lachlan
Shire Council’s Civic Centre operational staff and the Working Party.
Co-ordinate and manage the activities, decisions and outputs of specialist sub- consultants.
Throughout the project, monitor and identify problems and risks, undertake assessments
for the Council’s Project Manager and facilitate early and cost effective resolution to
achieve delivery of the project within the defined parameters.
In conjunction with Council’s Project Manager, assist with the overall planning,
Page | 6
The Brief – 2018/47
Design of New Community and Civic Centre
programming, co- ordination, cost management and control of the project throughout the
design and documentation phases.
Convene regular design team meetings and monitor the work of the sub-consultants.
In consultation with the Design Consultant’s quantity surveyor, establish preliminary
budgets and undertake cost plans at the nominated design milestone points.
In consultation with the Council’s Project Manager, assist in the development of
programs for all phases of the project, monitor and maintain project reporting.
Monitor and co-ordinate consultant program and activities to ensure timely completion of
documents, including drawings, specifications and reports.
Co-ordinate and control the external authority approval process, including, building permits,
fire authority approval, electrical supply authority and water/sewerage authority conditions
of service as appropriate for the design works.
In conjunction with the Council’s Project Manager, the Council’s traffic staff and the
traffic consultant are required to coordinate the development of an effective car parking /
traffic management plan based on the design plan provided for the site cognisant of
budgetary constraints and the existing traffic assessment undertaken for the site.
Present design and incorporate comments from relevant stakeholders.
Undertake a presentation at the end of each of the design phases to the Committee to
gain support and approval before proceeding to the next phase.
Throughout the design process keep track of all changes to project scope, including
reasoning and impacts of change, the associated risks to the project and any subsequent
change to the project budget.
Engage a registered Quantity Surveyor (QS) to develop a project cost plan. Confirm the
scope of architectural and services work and the expected grade of materials and
finishes for the project sufficient to enable the registered QS to prepare an accurate cost
plan(s) for the works. These cost plans will be used to measure the performance of the
project through successive stages. A cost plan will also be used to inform Council’s
future budget inclusions for future construction works.
The Design Consultant must ensure that the registered QS provides a cost plan report at
the conclusion of the following design stages;
o At Concept Design Development (40% project definition)
o At Preliminary Design Development (70% project definition)
o At Final Design Development (100% project definition)
The Design Consultant must ensure that the design responds to cost estimates and remains within the allocated budget.
If the construction tenders received come back above the allocated budget, the
Design Consultant in conjunction with Upper Lachlan Shire Council must undertake
an additional value management (Value Engineering) process to identify cost reduction
strategies to bring the project in line with the allocated budget. This may require
changes to documentation prepare by the Design Consultant and specialist sub-
consultants.
Upper Lachlan Shire Council may engage an independent quantity surveyor or
cost engineer to review the cost plans developed by the registered QS.
The Design Consultant is to prepare an agenda for each project meeting necessary to
complete the design and documentation. A record of each meeting is also to be kept
and circulated including an action list and supporting information and documentation.
The Design Consultant is to make reasonable inquiry with all relevant service providers or
sub-consultants to provide a reliable cost estimate for the design and documentation
services. Council may request a scoping or briefing document to verify services provided.
The Design Consultant is to outline any omissions or assumptions in their proposal. Upper
Lachlan Shire Council may request clarification plus an estimated cost impact of any
omission or assumption to obtain a more reliable total project cost estimate.
Page | 7
The Brief – 2018/47
Design of New Community and Civic Centre
2.8 DESIGN REVIEWS
This project will be subject to regular design reviews to ensure an efficient and functional design outcome. The design review process is outlined as follows and is considered the minimum review requirement:
Design Reviews are to be undertaken throughout the project at key stages. There will be a
minimum of three formal design reviews; at the completion of the Concept Design,
Preliminary Design and Final Design phases. The Design Consultant will keep a record of
any issues arising from the formal design reviews, including proposed and completed
management actions for incorporation into subsequent design development stages.
An independent design review may also be undertaken at any stage throughout the design
development. An independent design review would be commissioned by Upper Lachlan
Shire Council. In addition Upper Lachlan Shire Council may engage other external
consultants to complete a peer review of specific design elements at any stage of the project.
When requested, the Design Consultant is to make available all relevant information and documentation for an independent design review.
2.9 SAFETY IN DESIGN
Health and safety sits at the very highest priority on this project and must be considered in
all aspects of design, construction and operations.
The Design Consultant must undertake a Safety in Design review at Concept, Preliminary
and Detailed design stages and provide a Safety in Design Report to Upper Lachlan Shire
Council at each stage for approval as the building owner and occupier. Upper Lachlan Shire
Council staff will be actively involved in the review of the submissions received and actions
agreed.
2.10 SUSTAINABLE DESIGN
Upper Lachlan Shire Council is seeking to achieve best practice in sustainable design
and construction and ensure the long-term sustainability of the centre by reducing
environmental impacts throughout its service life.
Upper Lachlan Shire Council requires the Design Consultant will adhere to the
following approach in developing sustainable design and construction options:
o The consultant shall use their expertise to nominate appropriate specific goals for the project pertaining to energy consumption and water consumption.
o The consultant shall nominate appropriate sustainable design performance targets,
derived from industry leading sustainable design standards including appropriate
aspects of Green Star, LEED or other tools that may be (in part) applicable to this
facility.
o The consultant will propose and agree targets with the Council and the consultant’s design team,
o At all times the Design Consultant will consider the cost implications of proposed
design features and seek to deliver the best outcomes within the available project
budget.
o The Design Consultant will work with the quantity surveyor or cost engineer during
the concept design phase to establish appropriate budgets for sustainable design
initiatives.
o The Design Consultant will present a concept Sustainable Design Report covering
project goals, benchmark projects, proposed sustainable design initiatives, initial
cost plan of sustainable design features, opportunities for innovation.
o The Design Consultant will provide advice in relation to building fabric
performance including compliance with insulation performance including
suggested improvements over minimum standards, glazing performance and
infiltration performance.
o The Design Consultant will consider and present other non-financial benefits of
selected sustainability initiatives to assist council in decision making during the
design process.
o The Design Consultant shall demonstrate the suitability of selected sustainability
Page | 8
The Brief – 2018/47
Design of New Community and Civic Centre
initiatives using whole of life costing analysis where decisions are required
between alternate solutions. The whole of life costs analysis (cost of ownership)
should include upfront capital costs, energy pricing and escalation rates,
maintenance costs, consumables and elemental replacement costs during the
selected life cycle period.
o Following consultation with Council and members of the design team the Design Consultant will update the Sustainable Design Report to concept design stage.
o A final review of the construction documentation is to be undertaken by the Design
Consultant for compliance against Section J (fabric elements) of the National
Construction Code.
o The Design Consultant shall document an analysis of opportunities and
recommendations to implement energy and water efficiencies, reduce operating
costs, waste and carbon emissions across the main components of the new Civic
Centre. The main components may include but not be limited to:
HVAC including air delivery and distribution methodology,
Solar passive orientation and design,
Building envelope, glazing and insulation,
Heat pumps,
Photovoltaic systems,
Water capture and reuse including innovative reuse solutions,
Variable speed pump installation (all pumps) – circulation and heating,
Heating,
Building Management Systems,
Water efficient fixtures
In determining the most appropriate sustainability initiatives for adoption in the project will
include capital cost, operating cost, environmental impact, health, wellbeing, accessibility,
safety, social, inclusiveness, educational, occupant comfort and satisfaction. Each of these
criteria must be appropriately balanced in order to maintain a holistic appreciation of the
issues at hand. The Design Consultant will advise on an appropriate method of selecting
between alternatives such as by nominating an appropriate scoring system.
2.11 ACCESS
The Design Consultant shall design all spaces to ensure that they meet the relevant
industry guidelines in addition to the requirements of the Disability Discrimination Act
1992 (as amended), Disability (Access to Premises – Buildings) Standards 2010
requirements and Universal Design principles as minimum standards and enhance
BCA/NCC 2016 requirements.
2.12 FINISHES AND MATERIAL SELECTION
The Design Consultant must ensure that the most appropriate materials are selected for
inclusion within the project, giving particular regard to internal and external environmental
conditions.
The Design Consultant may engage a materials expert to ensure that metals, concrete
mixes, protective coating systems, polymers and other materials are appropriately specified
and constructed to minimise ongoing maintenance and the risk of failure. Provide life cycle
risk and costing analysis where required to assist with decision making.
Wet Areas:
o High quality and durable floor finishes to all wet areas,
o High quality steel paint coating applications must be used in accordance with
manufacturers recommendations,
o Wall and ceiling finishes to be highly durable and low maintenance,
o External grade timber products including doors, seating and joinery items to wet areas.
Dry Areas:
o High quality, durable and low maintenance floor finishes throughout dry areas, with
Page | 9
The Brief – 2018/47
Design of New Community and Civic Centre
rubber flooring, vinyl, marine grade carpet and non-slip ceramic tiles as determined
by functional requirements.
External:
o Highly durable external façade and roofing systems which consider the impact of the
environment, with access readily available to all surfaces for cleaning and ongoing
maintenance.
Fixtures and Fitments
o Highly durable fixtures and fitments suitable for high-usage public buildings in harsh environments.
2.13 BUILDING SERVICES
2.13.1 MECHANICAL
The consultant is to consider a concept for mechanical services in the design process,
allowing for plant rooms and external equipment locations and ventilation.
2.13.2 ELECTRICAL
The consultant is to consider a concept for electrical upgrades and services in the
design process, allowing for switchboard rooms, distribution boards,
communications cupboards and the major distribution network that will be required.
2.13.3 LIGHTING
The consultant is to consider a concept for exterior and interior lighting.
2.13.4 AUDIO VISUAL
The consultant is to consider the provision of audio visual systems in the design for the chambers and public areas of the proposal.
2.13.5 SECURITY
The consultant is to consider the provision of security access to the building.
2.13.6 HYDRAULICS The consultant is to engage a hydraulic consultant to prepare a hydraulic concept for the project. This is to include modelling of the on-site stormwater provisions and pressure tests to address the needs of on-site firefighting equipment.
2.13.7 FIRE PROTECTION
The BCA / NCC Analysis is to be incorporated into the design for all aspects of fire
protection.
Avoid the use of sprinkler systems unless absolutely required.
Provide fire hydrants and hose reels throughout as required.
Provide smoke detection, occupant warning system and all other smoke and fire safety
measures required to meet relevant standards and comply with the FER.
2.13.8 BUILDING STRUCTURE
Provide an efficient and cost effective structural design solution to withstand building and
environmental live and dead loads.
Design for the site ground and environmental conditions including consideration of the impact
of ground water and site soil characteristics.
Ensure constructability and future expansion requirements are considered in the design of
structural systems.
Ensure internal slabs make allowance for maintenance and access equipment loadings.
2.13.9 CIVIL INFRASTRUCTURE & LANDSCAPING
The civil and external areas design is to consider aspects for security including lighting, clear
sightlines, safe movement with good connections and access, and mixed use and activities
to promote public use and self-policing.
Page | 10
The Brief – 2018/47
Design of New Community and Civic Centre
A range of traffic calming measures (such as raised pavements, shared zones, pedestrian
crossings, etc.) may be required across the site, in particular adjacent to main circulation
routes. In all such situations, the safety and ease of movement of pedestrians should be
given priority.
Provide an entry forecourt and landscaped areas with passive social/recreation opportunities
for patrons, visitors and the general community, for all ages and abilities.
Provide planting of vegetation for summer shade to paved areas, winter sun and mid-season
sun to pedestrian and gathering areas, wind protection, and consistent with the landscape
character of the region, fully considerate of local soils and climatic conditions. Create a
landscape character which is low maintenance, endemic to the region and culturally
appropriate, and that will grow to a scale appropriate to the proposed facilities and uses.
Provide a drainage strategy which considers:
o Water Sensitive Urban Design / Water Quality Management,
o Stormwater Site Management Plan,
o Site detention analysis,
o Site discharge to minimise pollutants,
o Irrigation systems,
o Water NSW requirements,
o Non reliance on pumped systems wherever possible.
Provide a robust external pavement design which meets minimum Council requirements with
additional allowances for adverse ground conditions or a 30-year pavement design life,
whichever is greater. Provide a pavement construction joint layout which minimises the
opportunity for pavement cracking, and which forms an integral part of the site design.
Provide an earthworks design that, where practicable, minimises the volume of material that
is to be imported or exported. The earthworks shall provide site levels and grading that suit
the topography and achieve the following minimum requirements:
o Falls away from buildings,
o Overland flow paths and freeboard to buildings for flood events,
o Operational building floor levels above drainage structure inlets and outlets.
2.13.10 TRAFFIC AND PARKING
The Design Consultant is to develop a traffic, pedestrian access and parking management
strategy to the Civic Centre when operating with increased patronage.
The traffic, access and parking management strategy is to prioritise pedestrian movements
within and between parking areas and the new facility and clear access and egress points
from Spring Street, Goulburn Street and possibly Robertson Street.
The Design Consultant is to also prepare a detailed site traffic impact and parking
assessment to determine car parking requirements and support any planning application
process through the development of functional designs. This assessment should consider and incorporate adjacent site precinct uses including the adjacent park, the main street and
surrounding residential areas.
2.13.11 UTILITIES AND SERVICE INFRASTRUCTURE
The Design Consultant is to evaluate the location and capacity of existing utility supply points
for electricity, gas, telecommunications, potable water, sewer drainage, stormwater drainage
and recycled water. All existing services are to be identified and detailed on existing condition
plans.
The Design Consultant is to liaise with relevant supply authorities to determine additional
site infrastructure requirements and initiate external service upgrades is required. Any
upgrades are to be incorporated into the concept design plans.
2.14 DESIGN QUALITY CONTROL
The Design Consultant must submit to Upper Lachlan Shire Council’s Project Manager
the deliverables identified for each project stage for approval and sign-off prior to
commencement of design works for subsequent stages.
Page | 11
The Brief – 2018/47
Design of New Community and Civic Centre
The Design Consultant is to submit all documents as a draft to Upper Lachlan Shire
Council’s Project Manager and the PCG for review and comment and amend documents
as directed prior to final issue.
Coordinate documentation in order to issue a single package to the Council’s Project
Manager. Prior to the handover of Deliverables to the Council’s Project Manager, the
Consultant must:
o Review all documents for compliance with the functional Brief. o Review/coordinate all documents, including specialist sub-consultant
documentation.
o Review all documents for compliance with the cost plan provided by the Consultant’s quantity surveyor or cost engineer.
o Provide a document list/transmittal, identified by the project name and number, to list all project documents.
Provide all final documentation in PDF and hard copy format.
Workable digital files used to create PDF files shall be supplied in the following formats:
o Specification in editable MS Word format,
o Images in JPEG or TIFF formats,
o Drawings in DWG (CAD) format and pdf. PDF must be placed in a A3 to suitable scale for viewing.
2.15 DESIGN DEVELOPMENT DRAWINGS
Design development drawings (plans, elevations & sections, etc.) shall be presented
to the Upper Lachlan Shire Council as appropriate for review and approval to proceed
to the next phase. At this time a “Hold Point” shall occur for the necessary approval of
design development by Upper Lachlan Shire Council at the Concept, Preliminary and
Detailed Design stages and each value engineering re-consideration. It is further
suggested to consider a Hold Point at the completion of SID.
The Design Consultant must not proceed with the provision of design services beyond the
current design development stage until Upper Lachlan Shire Council has confirmed, in
writing, its acceptance of the various stages of the design development documentation and
sustainability benchmarks. The Design Consultant must make any amendments to the
design development documents directed by Upper Lachlan Shire Council.
2.16 PLANNING APPROVALS
The Design Consultant is to prepare a Development Application for the project. The
application is to include all associated reports, plans and any other documentation required
and submit the complete application to the Upper Lachlan Shire Council’s Planning
Department for assessment. The Design Consultant shall then undertake a review of the
Development Consent and update the design and documentation to address any issues
identified in the final design plans and documentation.
The preparation and assessment of a site specific Development Application may identify
additional matters to be addressed or require further investigation. Referral bodies may
also request additional information in response to any public submissions received from
the public exhibition process.
Following is a list of documentation required to support a Development Application,
however it is recommended the Design Consultant make their own inquiry as to the
composition and extent of documentation required.
o Statement of Environmental Effects (SEE) needs to be comprehensive and address all relevant local and state legislation.
o Site plan of the land including: Location, boundary dimensions, site area and north point.
Existing vegetation and trees on the site.
Location and uses of existing buildings on the land.
Existing levels of the land in relation to buildings and roads.
Location and uses of buildings on sites adjoining the land.
Page | 12
The Brief – 2018/47
Design of New Community and Civic Centre
o Sketch of the development including:
The location of any proposed buildings or works (including extensions or
additions to existing buildings or works) in relation to the land’s boundaries
and adjoining development.
Floor plans of any proposed buildings showing layout, partitioning, room
sizes and intended uses of each part of the building.
Elevations and sections showing proposed external finishes and heights of
any proposed buildings (other than temporary structures).
Elevations and sections showing heights of any proposed temporary
structures and the materials of which any such structures are proposed to
be made.
Proposed finished levels of the land in relation to existing and proposed
buildings and roads.
Proposed parking arrangements, entry and exit points for vehicles, and
provision for movement of vehicles within the site (including dimensions
where appropriate).
Proposed landscaping and treatment of the land (indicating plant types
and their height and maturity).
Proposed methods of draining the land.
Structural Plans.
o A montage depicting the building height and external configuration, as erected, in relation to its site
o If the development involves a change of use of a building (other than a dwelling-
house or a building or structure that is ancillary to a dwelling-house and other than
a temporary structure):
List the Category 1 fire safety provisions that currently apply to the existing
building.
List the Category 1 fire safety provisions that are to apply to the building
following its change of use.
o If the development involves building work to alter, expand or rebuild an existing
building, a scaled plan of the existing building. The site plan to illustrate the
existing site layout and comparative boundaries of the proposed development.
o Section J Report (Energy Efficiency), Class 2 to 9, Building Code of Australia
o BCA Report, NCC Building Code of Australia 2016.
o Fire Engineering Report.
o Heritage Impact Statement.
o Geotechnical Investigation and Report.
o Traffic Impact Assessment and Report.
o Schedules of materials and finishes
o Water Cycle Management Study.
o Stormwater Management Plan.
o Sedimentation and Erosion Control Management Plan.
o Soil Contamination Report.
o Asbestos Audit Report.
o Waste Management Plan.
2.17 COMPLIANCE WITH STANDARDS
The new Civic Centre shall comply with all current requirements of the Building Code of
Australia, Authorities, and Australian Standards or as approved by the relevant authority,
including but not limited to:
o Building Code of Australia,
o Building Regulations,
o All relevant Australian Standards and Codes,
o Occupational Health and Safety Act,
o Worksafe guidelines,
o Utility Supply Authority Regulations,
o Health Department Regulations,
Page | 13
The Brief – 2018/47
Design of New Community and Civic Centre
o Fire Authority requirements,
o Upper Lachlan Shire Council Local Environment Plan,
o Service NSW,
Plant design, layout, access and material selections shall comply with appropriate work
place health and safety requirements, and other relevant codes and regulations.
The Design Consultant is to liaise with relevant authorities to ensure the design meets all
Code and Authority requirements. The facilities are to be fully accessible and compliant with
Building Code requirements.
2.18 ESTIMATES THROUGHOUT THE DESIGN PROCESS
The Design Consultant, specialist sub consultants and the quantity surveyor or cost
engineer shall review the design development documentation to prepare cost plans in
consultation with the Council Manager and Committee. An initial cost plan is to be
developed following concept design phase, then updated following preliminary and final
designs.
Each cost plan is to determine the total project cost and identify above the line costs, below
the line costs with a contingency appropriate to the level of design information available
Costs associated with achieving the agreed ESD benchmarks and obtaining the relevant
certification must be itemised separately in the cost plans.
When requested, the Design Consultant is to make available all relevant information and
documentation for an independent cost review.
2.19 SUMMARY OF DELIVERABLES FOR INCLUSION IN THE PROPOSED REDEVELOPMENT PROGRAM
Following is a list of deliverables required throughout the design and documentation
development phase of the redevelopment works:
o Scope confirmation workshop.
o Design development methodology.
o Design project management plan.
o Concept design plans with a cost plan to 40% design development.
o Safety in design review and report.
o Sustainable design report.
o Value management workshop and report.
o Development Application with all supporting documentation.
o Preliminary design plans with a cost plan to 70% design development.
o Final design plans with a P90 cost plan to 100% design development.
o Meeting agendas, records and action lists.
o Grant funding application and business case. o Drawings Issued For Construction (IFC) suitable for construction.
2.20 PROPOSED NEW CIVIC CENTRE PROGRAM
2.25.1 KEY PROJECT MILESTONES
Milestone Description Target Completion
1 Issue Design RFT 18 October 2018 (Thursday)
2 Council Accept Design RFT 20 December 2018 (Thursday)
3 Appoint Design Consultant 27 December 2018 (Thursday)
4 Complete Concept Design and initial project estimate
21 February 2019 (Thursday)
5 Complete Preliminary Design and revise project estimate
4 April 2019 (Thursday)
6 Complete Final Design and revise project estimate 8 May 2019 (Wednesday)
7 Submit Development Application 22 May 2019 (Wednesday)
Note. Council is happy to receive a shorter timeframe provided committee consultation is included in the project plan. A detailed project plan to be submitted at the time of signing the contract.
Page | 14
The Brief – 2018/47
Design of New Community and Civic Centre
2.25.2 STAGING REQUIREMENTS
All or part of the proposed works may be subject to further funding and strategic planning
which may require parts of the design or construction to be staged. Staging requirements for
the project will be further developed and agreed with Upper Lachlan Shire Council as the
project progresses via the Committee.
2.25.3 FUNDING OPPORTUNITIES AND CONSTRAINTS
It is currently proposed that the redevelopment of the New Civic Centre would be financed
through a combination of loan borrowings, State and Federal Government grants, rates and
general Council revenue and potentially donations and/or contributions (e.g. discount on
provision of goods and services) from other contributing parties.
The exact combination of funding sources required will be dependent on circumstances at
the time (e.g. level, type and eligibility for government grants and the prevailing market
conditions at the time of any potential asset sale). Given the uncertainty and the lengthy time
before commitments must be locked into place it is premature to determine the exact
financing mix of the project at this time.
The Project Team may be required to assist Upper Lachlan Shire Council with any grant
funding applications for the project by providing relevant professional project advice in
support of any funding applications Council may make.
2.25.4 VALUE MANAGEMENT
A Value Management workshop is to be undertaken at the conclusion of the concept design
phase. The Design Consultant will chair this workshop with the focus on an efficient project
outcome, at acceptable cost and effective project delivery.
Value Management will be undertaken adopting a systematic approach to ensure that
maximum value for money is achieved with a focus on maximising value rather than simply
minimising cost. All Project Team members will proactively participate and define what is
needed, aligning design requirements to ensure minimal waste and maximum benefits.
2.25.5.1 ULSC Project Team
The Project Team from Upper Lachlan Shire Council will be comprised of the following members:
General Manager - Champion;
Director of Works and Operations – Project Manager;
Specialist Project Manager;
Additional staff and consultant as technical advisors when needed.
2.25.5.2 Project Management Plan
The Design Consultant is to prepare a Management Plan to cover all tasks to be carried out under this engagement and associated schedule. This plan is to provide a high level understanding of investigation and design tasks and to identify key decision and review points. As a minimum the Project Management Plan should include the following components:
Brief Project Description
Monitoring and Control
o Reporting
o Tolerances
o Risk Register
Design Team Structure
o List roles and responsibilities
Assumptions and Constraints
o Project approvals
Technical Considerations
o Refer relevant Australian Standards, Industry Guidelines, etc.
o Site constraints / characteristics
Stakeholders
o List relevant stakeholders and proposed consultation
o Communication mechanisms
Cost Estimate
Page | 15
The Brief – 2018/47
Design of New Community and Civic Centre
2.25.5.3 Design Consultant Team including Sub-Consultants
Head Consultant - Architect
Sub-Consultants including:
o Hydraulic Engineering
o Geotechnical Engineering
o Land Surveying
o Traffic Engineering
o Quantity Surveyor or Cost Engineering
o Site investigations (contamination, indigenous heritage, etc)
2.26 DESIGN PLAN FORMAT
The Design Consultant is to provide all final documentation in PDF and hard copy format.
Workable digital files used to create PDF files shall be supplied in the following formats:
o Technical specification in editable MS Word format,
o Images in JPEG or TIFF formats,
o Drawings in DWG (CAD) format and pdf.
2.27 ADDITIONAL SERVICES
Further specialist consultancies may be required and will be engaged in accordance with
Upper Lachlan Shire Council’s procurement policy. These may include:
o Peer Review Consultants,
The Design Consultant may be required to create a brief for any additional consultancy
services and assist with procurement for those services.
The Design Consultant will be required to work cooperatively and openly with any external
service providers appointed by Upper Lachlan Shire Council for the project, including peer
review consultants.
2.28 PROJECT COMMUNICATION PLAN
The Design Consultant is to prepare a Project Communication Plan (PCP) that outlines
specific project communication mechanisms. The Project Communication Plan may be a
sub-component of the Project Management Plan.
The Project Communications Plan outlines the type and frequency of communications with
key stakeholders and responsibilities for any lead communicators and current
communication actions. This plan is to be reviewed periodically throughout the project to
ensure its relevance and to adjust to for any unforeseen circumstances.
The Project Communications Plan aims to:
o actively engage stakeholders in the scoping and development of the project, o inform stakeholders of the progress and status of the project on a regular basis
and at nominated critical milestones,
o deliver a successful, fit for purpose facility that meets the operational and functional requirements of key stakeholders.
2.29 APPENDIX DOCUMENTS
Relevant documentation has been included as Appendix Documents under ‘Volume 5: Attachments’ although this is not a comprehensive list and may require the Design Consultant to source additional documents in completing the design and documentation development: