Technical Guidelines Development Committee Meeting September 11, 2017 VVSG 2.0 Review and Adoption Process www.eac.gov

Upload: others

Post on 18-Aug-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: VVSG 2.0 Review and Adoption Process - eac.gov · VVSG 2.0 Review Timeline The following is the projected timeline for review and adoption: • September 2017= EAC Executive Director

Technical Guidelines Development Committee MeetingSeptember 11, 2017

VVSG 2.0 Review and Adoption Process

www.eac.gov

Page 2: VVSG 2.0 Review and Adoption Process - eac.gov · VVSG 2.0 Review Timeline The following is the projected timeline for review and adoption: • September 2017= EAC Executive Director

HAVA Requirements

HAVASEC.222.PROCESSFORADOPTION.

(a)GENERALREQUIREMENTFORNOTICEANDCOMMENT.—Consistentwiththerequirementsofthissection,thefinaladoptionofthevoluntaryvotingsystemguidelines(ormodificationofsuchaguideline)shallbecarriedoutbytheCommission inamannerthatprovidesforeachofthefollowing:(1)PublicationofnoticeoftheproposedguidelinesintheFederalRegister.(2)Anopportunityforpubliccommentontheproposedguidelines.(3)Anopportunityforapublichearingontherecord.(4)PublicationofthefinalguidelinesintheFederalRegister

Page 3: VVSG 2.0 Review and Adoption Process - eac.gov · VVSG 2.0 Review Timeline The following is the projected timeline for review and adoption: • September 2017= EAC Executive Director

HAVA Requirements(b)CONSIDERATIONOFRECOMMENDATIONSOFDEVELOPMENTCOMMITTEE;SUBMISSIONOFPROPOSEDGUIDELINESTOBOARDOFADVISORSANDSTANDARDSBOARD.

(1)CONSIDERATIONOFRECOMMENDATIONSOFDEVELOPMENTCOMMITTEE.—Indeveloping thevoluntaryvotingsystemguidelines andmodificationsofsuchguidelines underthissection,H.R.3295—19theExecutiveDirectoroftheCommissionshalltakeintoconsiderationtherecommendationsprovidedbytheTechnicalGuidelinesDevelopmentCommitteeundersection221.(2)BOARDOFADVISORS.—TheExecutiveDirectoroftheCommissionshallsubmittheguidelinesproposedtobeadoptedunderthispart(oranymodificationstosuchguidelines)totheBoardofAdvisors.(3)STANDARDSBOARD.—TheExecutiveDirectoroftheCommissionshallsubmittheguidelinesproposedtobeadoptedunderthispart(oranymodificationstosuchguidelines)totheExecutiveBoardoftheStandardsBoard,whichshallreviewtheguidelines (ormodifications)andforwarditsrecommendations totheStandardsBoard.

Page 4: VVSG 2.0 Review and Adoption Process - eac.gov · VVSG 2.0 Review Timeline The following is the projected timeline for review and adoption: • September 2017= EAC Executive Director

HAVA Requirements

(c)REVIEW.—Uponreceiptofvoluntaryvotingsystemguidelinesdescribedinsubsection(b)(oramodificationofsuchguidelines)fromtheExecutiveDirectoroftheCommission,theBoardofAdvisorsandtheStandardsBoardshalleachreviewandsubmitcommentsandrecommendationsregardingtheguideline(ormodification)totheCommission.

Page 5: VVSG 2.0 Review and Adoption Process - eac.gov · VVSG 2.0 Review Timeline The following is the projected timeline for review and adoption: • September 2017= EAC Executive Director

HAVA Requirements

(d)FINALADOPTION.(1)INGENERAL.—Avoluntaryvotingsystemguidelinedescribedinsubsection(b)(ormodificationofsuchaguideline)shallnotbeconsideredtobefinallyadoptedbytheCommissionunlesstheCommissionvotestoapprovethefinaladoptionoftheguideline(ormodification),takingintoconsiderationthecommentsandrecommendationssubmittedbytheBoardofAdvisorsandtheStandardsBoardundersubsection(c).

(2)MINIMUMPERIODFORCONSIDERATIONOFCOMMENTSANDRECOMMENDATIONS.—TheCommissionmaynotvoteonthefinaladoptionofaguidelinedescribedinsubsection(b)(ormodificationofsuchaguideline)untiltheexpirationofthe90-dayperiodwhichbeginsonthedatetheExecutiveDirectoroftheCommissionsubmitstheproposedguideline(ormodification)totheBoardofAdvisorsandtheStandardsBoardundersubsection(b).

Page 6: VVSG 2.0 Review and Adoption Process - eac.gov · VVSG 2.0 Review Timeline The following is the projected timeline for review and adoption: • September 2017= EAC Executive Director

VVSG 1.0 Review and Adoption Process

• PublishedbyEAConJune29,2005intheFederalRegister‒ F.R.Noticeprovidedinstructionsforsubmittingcommentson-line,by

e-mail,regularmail,andfax.• 90-daypubliccommentperiod• 3publichearings(NewYork,Pasadena,Denver)• 2daymeetingofEACStandardsBoardandEACBoardofAdvisorsto

discussVVSGandreceivecomments.• Resultedinover6500comments• EACwiththeassistanceofNISTstaffreviewedandconsideredall

comments• OnDecember13,2005EACvotedtoadoptthe2005VVSG.(Witha24

monthimplementationtimeframe….)

Page 7: VVSG 2.0 Review and Adoption Process - eac.gov · VVSG 2.0 Review Timeline The following is the projected timeline for review and adoption: • September 2017= EAC Executive Director

VVSG 2.0 Review Timeline

Thefollowingistheprojectedtimelineforreviewandadoption:

• September2017= EACExecutiveDirectorreceivesdraftVVSG2.0fromTGDC/NIST.

• October2017=ProvidesdraftVVSG2.0toStandardsBoardandBoardofAdvisors.

• January2018= StandardsBoardandBoardofAdvisorsmeeting.

• February2018=Begin90DayPublicCommentperiod.• April2018-May2018=EAC&NISTstaffresponse&changes

fromBoards&PublicComment +finalformatting.• May2018=EACvoteonVVSG2.0andimplementationdate.

Page 8: VVSG 2.0 Review and Adoption Process - eac.gov · VVSG 2.0 Review Timeline The following is the projected timeline for review and adoption: • September 2017= EAC Executive Director

VVSG 2.0 Timeline

2017

TGDCMeeting

2018

September

DeliveryofproposedVVSG2.0toEACExec.Dir.

January

May

February

StandardsBoard/BoardofAdvisorsMeetings

90-DayPublicCommentPeriod

ResponsetoandChangesfromPublicComments&

FinalFormatting

PublicHearingonVVSG2.0

EACVoteonAdoptionofVVSG2.0

EACProgrammaticchangesasnecessary

CommissionerBriefings(ongoing)

DeliveryofVVSG2.0toBoards

Page 9: VVSG 2.0 Review and Adoption Process - eac.gov · VVSG 2.0 Review Timeline The following is the projected timeline for review and adoption: • September 2017= EAC Executive Director

Discussion

BrianHancock,Director,[email protected]