Walk Bridge Program
J u n e 1 6 , 2 0 2 0
Manresa Island Online Public Meeting
www.WalkBridgeCT.com
Housekeeping Items This meeting is recorded.
There may be a few glitches, so please bear with us. We will immediately address any technical difficulties.
Please mute your phone during the presentation.
Please enter any questions or comments in the chat box. We will answer questions at the end of the presentation.
CTDOT will accept questions and comments until July 3, 2020.
Meeting materials are available at walkbridgect.com.
1
2
6/12/2020
2
www.WalkBridgeCT.com
Meet Your Speakers• Jim Fallon, CTDOT
• Lauren DiGovanni, HNTB
• Sarah Walker, HNTB
www.WalkBridgeCT.com
Meeting Agenda
175 T RA INS/DAY
125K PA SSENGERS/DAY
1. Introductions & Meeting Purpose2. Walk Bridge Overview3. Proposed Lift-Span Construction4. Proposed Use of Manresa Island5. Natural Resources, Navigation & Aquatic Resources, Community 6. Minimization and Mitigation Measures7. Federal and State Reviews, Approvals and Permits8. Next Steps9. Questions and Comments
3
4
6/12/2020
3
www.WalkBridgeCT.com
www.WalkBridgeCT.comwww.walkbridgect.com
WA L K B R I D G E R E P L AC E ME N T
R E P L AC E ME N T OF TH E OS BOR N E AV E N U E RA I L ROA D B R I D G E
FORT P OI NT S TR E E T BR I D GE R E P L ACE ME N T A N D ROA DWAY R E A L I G N ME N T
E AS T AV E N U E BR I D G E R E P L AC E ME N T AN D ROA DWAY I MP ROV E ME N T P ROJE CT
CP 2 4 3 I N TE R LOC K I N G P ROJE CT
A N N S T R E E T B R I D G E R E P L AC E M E N T
DA N BU RY BRA N CH D OCKYA R D P ROJE CT
The Walk Bridge Program
5
6
6/12/2020
4
www.WalkBridgeCT.com
240’ Vertical Lift Span• Shortest construction schedule• Lowest risk during construction• Shortest period of navigation
restrictions• Fewest foundations in water• Improved alignment with
Stroffolino Bridge
Project Overview
Anticipated Duration: Approximately 5-6 years
www.WalkBridgeCT.comwww.walkbridgect.com
Proposed Lift-Span Construction
Replacement bridge lift spans will be:
• Constructed off-site using accelerated bridge construction (ABC) techniques
• Floated to the bridge site
• Installed in about 96 hours
7
8
6/12/2020
5
www.WalkBridgeCT.com
Construction Parcels Overview
CTDOT will require parcels for the construction of Walk Bridge for:
• River and rail access and staging • Equipment and material storage • ABC - Replacement bridge lift spans construction o On site location - 68 & 90 Water Street - initially
proposed; less than 0.2 nautical mile from Walk Bridgeo Off site location proposed in Value Engineering Study;
about 2 nautical miles from Walk Bridgeo Barges used to construct and transport lift spans to
bridge site
www.WalkBridgeCT.com
Proposed Use of Manresa Island
Walk Bridge
Manresa Island
9
10
6/12/2020
6
www.WalkBridgeCT.comwww.walkbridgect.com
Proposed Use of Manresa Island
Northern Parcel (Parcel 5/86/2; 92 acres)• No construction use; • Site access only for up to 60 months.
Southern Parcel (Parcel 5/86/1; 33 acres)• Construction easement for 5-acre Staging and Storage Yard
in isolated, previously developed and disturbed area with waterfront access;
• Use for up to 60 months. Active lift span construction for up to 48 months.
www.WalkBridgeCT.com
Staging and Storage Yard: Work Area
• Pre-assembly of structural components;
• Full assembly of both lift span trusses before float-in to the bridge site;
• Berthing of safety boat vessels and emergency rescue operations associated with lift span construction;
• Temporary berthing of construction vessels and barges.
11
12
6/12/2020
7
www.WalkBridgeCT.com
Staging and Storage Yard : Laydown Area
• Storage of construction materials (steel and timber);
• Temporary storage of components from demolition of existing bridge and project site (stone masonry and concrete debris, structural steel members, timber cribbing/pilings).
• No dredged material will be transported to or stored on site.
www.WalkBridgeCT.com
Natural Resources• No freshwater or tidal wetlands exist in staging and storage yard; No impact to intertidal area.• No adverse impact to 100-year floodplain due to minor fill required for site preparation. • No impact to groundwater.
13
14
6/12/2020
8
www.WalkBridgeCT.com
Navigation and Aquatic Resources
• Equipment and material barges about 300 feet outside of channel ≈ No impact to federal navigation channel.
• Previous aquatic protected species and habitat review included Manresa Island area ≈ No additional impact.
• Spud piles used to anchor barges • Barge movements ≈ No impact to river
bottom or increased turbidity.
www.WalkBridgeCT.com
Community
• No impact on existing land uses.• Restored to pre- construction conditions after
project completion. • Employee traffic approximately 22 round-trips per
day (6-day week). • Truck traffic approximately 3 round-trips per day
during peak construction (5-day week; daylight hours).
• Located 0.4 mile from nearest receptor ≈ no perceptible increase in noise.
15
16
6/12/2020
9
www.WalkBridgeCT.comwww.walkbridgect.com
Time of year restrictions and protection protocols for State-listed Species included inpermits and contract specifications
Six-inch layer of geotextile and stone as a separation barrier from existingAreas of Concern
Secure storage of fuels and hazardous materials - Flood Contingency Plan Completely fenced with secure entrance gate
Completely fenced with secure entrance
Minimization and Mitigation Measures
www.WalkBridgeCT.com
Federal and State Reviews, Approvals and Permits
NEPA and Section 106 Re-evaluation Consultation with FTA for Verification of Project FONSI
Coordination with National Marine Fisheries Service
Coordination with CTDEEP Divisions of Wildlife & Fisheries
CTDEEP Flood Management Certification
CTDEEP Structures, Dredging & Fill Permit and Section 401 Water Quality Certification
U.S. Army Corps of Engineers Section 404 and Section 408 Permits
U.S. Coast Guard Bridge Permit
CTDEEP General Permit for Discharge of Stormwater and Dewatering Wastewaters from Construction Activity
17
18
6/12/2020
10
www.WalkBridgeCT.com
Next Steps
Public review comments – through July 3, 2020
NEPA Re-evaluation Consultation with FTA for Verification of Project FONSI – August 1, 2020
Permit application filings – Summer 2020
Final design – Fall 2020
Construction start – Fall 2021
www.WalkBridgeCT.comwww.walkbridgect.com
Stay Involved
www.walkbridgect.com
833-GO2-WALK
@walkbridgect