waste water- coke plant
TRANSCRIPT
-
8/2/2019 Waste Water- Coke Plant
1/13
COMBINED BIOLOGICAL TREATMENT OF SINTER PLANT WASTE WATER,
BLAST FURNACE GAS SCRUBBER WATER POLLUTED GROUNDWATER AND
COKE PLANT EFFLUENT
By Antoine van HoornEnvironmental Management Corus Staal
This paper was presented at a COMA Meeting in March 2005 held at the Corus Conference
Centre, Scunthorpe
1. The History of Treating Coke Plant Waste Water
The second coke plant at the Corus location IJmuiden was taken into operation in 1972. At aproduction rate of approximately 2 million tons of coke a year for both plants, about 65 m
3/h
of wastewater had to be treated.
From start up on the wastewater was handled according to the traditional and well knownactivated sludge process. So air was put in by very inefficient surface aerators and the sludgewas recycled over a settling basin for reuse. The biomass concentration in the aeration basinwas controlled at a constant level of 3 5 grams/litre.
The activated sludge plant was designed on the basis of experiences with treating domesticwastewater. Already some months after commissioning the plant it became clear that cokeplant effluent is very different from domestic sewage. Overall the removal efficiency wasvery poor. Most of the times only phenols, one of the major components of coke plantwastewater, were removed and not the rest of the COD and thiocyanate. Nitrification,converting ammonia or TKN into nitrate via specialised bacteria which are usually part of thebiomass, never occurred during that time.
In the eighties it became clear that phenol removal only was not sufficient anymore. TheDutch water authorities demanded that that the part of the COD that can be degraded bybiomass should be removed almost completely before it is permitted to discharge the treatedwastewater into the sea.
Due to the fact that there was no room available at coke plant #2 another less roomconsuming treatment system had to be developed. After extensive research including longterm pilot plant testing it was decided in 1988 to build a so called Oxitron fluidised bedsystem. By dissolving pure oxygen in a circulating water flow and keeping the water velocityin the reactors at a level that sand grains stayed in a kind of fluidised state it was possible togrow biomass on these sand grains and to remove almost all the COD from the wastewater.Under these conditionsit also seemed to be possible to grow nitrifying bacteria at the same time. Biomassconcentrations in this system went up to as high as 20 25 grams per litre. So the sameamount of biomass or sludge as in the traditional activated sludge plant could be achieved in amuch smaller volume.
-
8/2/2019 Waste Water- Coke Plant
2/13
Figure 1: The fluidised bed installation at Coke Plant
Treating coke plant wastewater means that all the problems known from sewage works haveto be solved. From several coke plants all over the world was reported that bulking orfloating sludge, pin point flocks causing settling problems and high suspended solids in thetreated effluent are frequently observed. Probably due to the fact that coke plant effluentcontains toxic components the sludge is constantly under stress. One of the components thatcause these toxic effects is probably cyanide, but also other so far unknown substances can beresponsible for these phenomena. Anyway, several plants in the world have the sameproblems and need a lot off attention from plant personnel and often the results as forexample in removal efficiency are still not satisfying.
At the end of the nineties the water authorities concluded that some other waste water flowsfrom the Corus plant in IJmuiden did contain more COD and TKN than allowed. The quality
of the canal and the sea where the Corus wastewaters are discharged to is still not satisfyingand not in accordance with European standards. At the same time it was also found out thatthe problems at the fluidised bed plant could only be solved by investing a considerableamount of money. The problems basically concerned the sand biomass separation, a part ofthe process that during design was underestimated. In reality this part of the installationbecame a major problem to control the process and a bottle neck to continue. The fluidisedbed problems and the pressure from the water authorities directly led to the decision toreconsider the way Corus IJmuiden was treating the different waste water flows.
2. Different Waste Water Flows
In 1997 an inventory was made of the different waste water flows and it was concluded thatthe waste water coming from the gas scrubbers from the blast furnaces, the water comingfrom the flue gas scrubbers from the Sinter Plant end the polluted groundwater from CokePlant #1could be very well treated in combination with coke plant effluent.
2.1 Sinter Plant Waste Water
To prevent emissions to the air from SO2, heavy metals and other harmful components, the
flue gases from the Sinter Plant are cleaned with a patented process based on high pressurescrubbing. The process has been developed by Voest Alpine in Austria and is called Airfine.
-
8/2/2019 Waste Water- Coke Plant
3/13
In the first scrubber SO2 is removed by spraying water in a recycle loop. The pH is regulated
by caustic soda addition. In the second step of the scrubber system very fine water droplets
are sprayed causing the fine particles to be wetted. These particles are together with thebottom flow of both scrubbers sent to the separate water treatment plant.
Figure 2: The high-pressure gas scrubber system at the SinterPlantIn this plant through pH-variations and the addition of different chemicals the heavy metalsare batch wise separated in two steps. In the first step the more harmful components like
mercury and cadmium are removed. The destination of the sludge from this step was
originally storage and possibly controlled dumping as chemical waste material. The rest ofthe heavy metals in the water coming from the first step is treated in a second batch process.
The sludge containing the more harmless metals is used again in the Sinter Plant. Up till nowthe separation in harmful and harmless waste material has not been a success. All the
produced sludge is for the time being put back into the Sinter Plant. For dewatering of the
sludge two filter presses are available.
Table 1 shows the average composition of water produced by the Airfine installation. The
COD and TKN concentrations are higher than is permitted by the water authorities. Metals ingeneral and lead in specific, make a direct discharge to surface water impossible.
2.2 Blast Furnace Gas Scrubber Water
The gas coming from the two blast furnaces is used for energy production.
It has to be cleaned before it is transported to the external power station. The gas is washed in
so called venturi or Bischoff scrubbers. Both furnaces have their own water circulation
system (650 and 850 m3/h respectively for BK#6 and BF#7). Solids are removed from the
water in a shared water treatment plant. To prevent built up of salts and scaling that can causeprecipitation on several critical places in the installation some water has to be extracted from
the circulation loops. Before the discharge of this water is permitted a separate treatment has
to take place to remove all the solids and the heavy metals present is this blow down.
NaOH
Demister
Quench
Stack
Flue gas
Settler
Neutralization
Gravelbedfilter
SewerRecycling
Filter press
Settler
Filter press
Heavy metal precipitation
Finescrubber
Recycling/immobilization
-
8/2/2019 Waste Water- Coke Plant
4/13
Figure 3: Gas treatment at the Blast Furnaces
The settled sludge from the basins in the re-circulating flows and from the basin where theextra treatment takes place is separated through a 3 step hydro cyclone system. The fraction
with the smallest particles contains the most Zn. It is dewatered by a filter press and is stored
for future processing. Nowadays the Zn-concentration is still to low to extract it from thesludge.
The Zn-poor fraction of the sludge, this is the fraction with the more coarse particles, is
dewatered in a decanter centrifuge and is transported back to the Sinter Plant for reuse. The
recycle of scrubber water takes place via the basins 11 en 12. From this recycle about 140
m3/h is withdrawn to keep the risk of precipitation in the installation at a minimum. This
blow down is led to basin 13. Here are the particles separated that are left in the wastewater.
To keep the discharge of Zn as low as possible an addition of sodium sulphide takes place inbasin 13.
Any dissolved Zn will in this way precipitate as insoluble Zn-sulphide. The overflow from
basin 13 contains normally not more than 1 mg/l Zn.
untreated water
treated water
Water treatment
production of electricityfor iron production in BF
Energy production
Sinter plant temporarystorage
temporarystorage
BF-dust
gas
gas
G
G
BF gasexpansion
turbine
courseBF-dust
gas
Bisschofgas
scrubbers
Dust bag
explosionvalves
BIO 2000
Zn-poor
BF-dust
Zn-rich
-
8/2/2019 Waste Water- Coke Plant
5/13
Figure 4: Waste water treatment at the blast furnace department
Table 1 (see below) shows the average composition of blow down water of the blast furnaces
gas scrubbers. Again COD and TKN concentrations are higher than permitted by the waterauthorities. Metals in general and zinc in specific, make a direct discharge to surface waterimpossible.
Despite the fact that a by-pass cooling tower is used in the circulation flow the temperature of
the blow down is fairly high. A separate small cooling tower is used to get the temperature at
levels acceptable for a biological treatment process.
2.3 Polluted Groundwater
At the end of World War 2 a RAF-pilot dropped a bomb by accident on the BTX-recovery of
Coke Plant #1. As a result of this action the ground water at this plant is highly polluted.
BTX concentrations of 5 10 mg/l were found. Local authorities demanded treatment of thiswater. After pilot plant testing it was concluded that biological treatment could clean this
water. For the next 25 years we have to pump up about 40 m3/h to neutralise the pollution.
The average composition is shown in the table below.
2.4 Coke Plant Wastewater
Coke oven gas is cleaned at coke plant #2 in a very traditional way. After cooling and tarseparation ammonia, H2S and BTX are removed from the gas. BTX is prepared for reuse inan installation at coke plant #1. Ammonia liquor coming from the scrubbers is treated in 2stripper columns, a combination of a so called de-acidifier and an ammonia stripper wherefree and fixed ammonia are removed at elevated pH-levels. For pH control caustic soda isdosed. The H2S-gas is converted to hydrogen sulphuric acid. The ammonia gas is oxidised in
this acid plant at the same time.
The gas treatment at coke plant #1 is a little different. Here ammonia sulphate is produced.The ammonia liquor from coke plant #1 is transported by pipeline to coke plant #2 for furthertreatment.
The steam consumption of the combined stripper and acidifier is 11 t/h; the amount ofammonia liquor is app. 60 m3/h and the amount of water coming from the H2S-scrubber app20 m
3/h. NaOH addition is 9 11 l/m
3waste water.
from BF#7 cooling tower
make-up water (WRK)
and gascondensate
from BF#6 MASH-water
and/or Na2S
basin 11 basin 12 basin 13
sludge to sludge to sludge to effluenthydrocyclones hydrocyclones hydrocyclones to Bio2000
clean water basin 11 clean water basin 12 clean water basin 13
to BF#7
to BF#6
-
8/2/2019 Waste Water- Coke Plant
6/13
After stripping the average composition of the wastewater is as shown in the table below.
The main constituents are the high COD, TKN and cyanide concentrations where TKN stands
for Total Kjeldahl Nitrogen (see table 1). This is the total of ammonia nitrogen and possiblypresent organic nitrogen compounds. TSS stands for total suspended solids and is in majority
responsible for the PAH that normally will be found in coke plant effluent.
3. Developing a Combined Treatment Plant
Because all the above mentioned waste water flows contain COD and TKN that can be
removed biologically after extensive pilot plant testing it was decided to develop a combined
biological treatment system.
An extra advantage of the bio treatment is that a main part of the remaining heavy metals will
be absorbed by the bio sludge and the discharge will be even smaller then it is already.
After the pre-treatment at the blast furnaces and at the Sinter Plant the waste water is
transported to a new biological treatment plant at Coke Plant 2. Together with the wastewaterfrom both coke plants and the groundwater from coke plant #1 a total amount of
approximately 320 m3/h has to be handled in the new installation. The resulting cyanide
concentration in the mixture of wastewater is about 15 mg/l. For a biologically treatment thislevel can be harmful under certain process conditions.
Table 1: Composition of the different waste water flows
Flow Temp COD TKNCN-
totalTSS Zn metals Phenols CNS
m3/h C mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
BF140-
15040-44 65-120
130-
1505-20 25-35 2-4 1-3 - -
SP 50-55 35-40 250-450200-
300- 10-25 - 0,3-0,5 - -
CP 80-90 30-35
3.000-
3.500
200-
300 20-60 20-50 - - 500-750
200-
250
GW 35-40 10-12 150-350100-
20010-20
-
8/2/2019 Waste Water- Coke Plant
7/13
Nitrification and COD removal can take place simultaneously in the aerobic part of the
installation. The end products from this conversion are CO2, water and nitrate, NO3-.
Denitrification is the biological process where nitrate is converted by bacteria into nitrogen
gas. This process has to take place under anaerobic or anoxic conditions. So there should bea special part of the installation where dissolved oxygen concentrations are more or less equal
to zero. Denitrifying bacteria however need some COD as feed also. By putting in (part of)
the influent in the anoxic part of the installation and recycling nitrified wastewater, COD and
nitrate come together in this part. Because the denitrification takes place in the first part ofthe installation this is called predenitrification.
The denitrifying part of the biomass is the most sensitive to changes in process parameterslike temperature and pH. Also a lot of components that are biodegradable under aerobic
conditions are toxic for denitrifying bacteria.
4. The New Biological Treatment Plant
The heart of the new water treatment configuration is the biological treatment plant the socalled Bio 2000. This Carrousel type of installation was built in 1999 2000 and is quite
famous in Western Europe where it is applied quite often for the treatment of domesticwastewater.
The large basins with surface aerators and the relatively high velocities make the installationmore a complete mix reactor than a plug flow. The aerators are controlled by measuring
dissolved oxygen continuously and comparing it with a set point of 1,5 to 2 mg/l. Also pH is
controlled by adding caustic soda when the pH is lower than 6,8 or by adding sulphuric acidwhen the pH in the basin is higher than 7.4.
One of the major problems during the first years of operation was keeping the temperature in
the aeration basin low enough, that means lower than 33 C. Through extra cooling of the
water coming from the blast furnaces via a cooling tower and sometimes putting in some coldriver water this maximum temperature level was not exceeded since the summer of 2003.
Behind the BET-plant continuous backwashing sand filters were installed. Despite the fact
that the combination of wastewaters can easily be treated sometimes very fine biological
flocks are present in
-
8/2/2019 Waste Water- Coke Plant
8/13
Figure 5: Floor-plan of the new Biological Treatment Plant
At the picture below you see the carrousel with the surface aerators installed in the blue
boxes. These boxes are isolated to prevent troubles with noise in the direct neighbourhood of
the installation.
The light blue columns in front are the six sand filters; in the back you will see the blast
furnaces nr 6 and 7.
Excess sludge is pumped to a thickener first. After that the sludge is dewatered and mixed
with the coal that goes into the ovens.
Figure 6: The new Biological Treatment Plant
Some dimensions: the aeration volume is 15.000 m3, this means a hydraulic retention time of
33 hours. The settling volume is 1500 m3. The diameter of the settling basin is 29 m. The
surface load is 5 m3/m
2/h.
-
8/2/2019 Waste Water- Coke Plant
9/13
The sludge thickener is a basin with a diameter of 9,5 m and a volume of 250 m3. Average
sludge waste is 45 m3/day with 3 % dry solids. The sludge recirculation flow is max 640 m
3/h
(twice the amount of influent). Dosage of phosphoric acid is based on 2 mg/l phosphate in
effluent. That means app. 5 l/h 75% phosphoric acid has to be added.
5. Performance of the New Biological Treatment Plant
Commissioning the new treatment plant took about 10 weeks. In that period the influent flowswere gradually increased. To start up the biological processes sludge was transported by
truck from a sewage treatment works to introduce nitrifying bacteria and from the industrial
wastewater treatment plant from the company that is distilling the tar coming from the cokeplants. The latter sludge should be adapted more or less to the composition of our wastewater.
COD concentrations from the different waste water flows seemed to be very constant as can
be concluded from figure 7. When this concentration is changing this will only happen
gradually and over a longer period. Especially changes in coal mixture can influence COD
concentrations in coke plant effluent. But also changes in process can have this effect. Forexample changes in coking time. At present for coke plant #1 it is minimal 17 h and for coke
plant #2 19 hours.
TKN-concentrations on the other hand are fluctuating considerably (see figure 8). The
highest variations are observed in coke plant effluent. Roughly TKN concentrations are in therange of 100 300 mg/l. It seems like the ammonia strippers are not working as constant as
always was thought.
Figure 7: COD-concentrations incoming waste water
0
500
1.000
1.500
2.000
2.500
3.000
3.500
4.000
4.500
20
-ju
l-00
31
-aug-0
0
12
-okt
-00
23
-nov-0
0
4-j
an-0
1
15
-fe
b-0
1
29
-mrt-0
1
10
-me
i-01
21
-jun-0
1
2-a
ug-0
1
13
-sep-0
1
25
-okt
-01
6-d
ec-0
1
mg
/l
COD from BF
COD from BF
COD from CP1+2
COD influent Bio 2000
0
100
200
300
400
500
20
-ju
l-00
31-a
ug-0
0
12-o
kt-
00
23-n
ov-0
0
4
-jan-0
1
15-f
eb
-01
29-m
rt-0
1
10-
me
i-01
21
-jun-0
1
2-a
ug-0
1
13-
sep-0
1
25-o
kt-
01
6-d
ec-0
1
mg
/l
from Blast Furnacefrom Sinter Plantfrom Coke Plant 1+2
-
8/2/2019 Waste Water- Coke Plant
10/13
Figure 8: TKN-concentrations incoming waste water
Dutch laws and regulations are in majority based on the European legislation. However,
every country in the European Community has the right to make their local laws andregulations stricter than necessary according to these European directives. For a long time
this was the policy of our government. Since last year our government is taking into account
the big changes that will be caused by the new Water Framework Directive. This new
directive can have a considerable impact on industry the coming years.
As a direct consequence the discharge permit for the bio treatment at coke plant 2 probably isnot more than temporarily. On the longer term, probably within a few years, the limits on
discharging wastewater will change. Especially the limited concentrations for COD, TKN,
suspended solids and the heavy metals that are linked with the suspended solids, will mostlikely become stricter. It is possible that under these circumstances a third treatment step like
activated carbon adsorption or a completely new treatment process will be necessary.
Nowadays the limits for the bio plant are as in table 2.
Table 2: waste water discharge limits
Maximum Average
Flow m3/h 400 340
TSS mg/l 60 30
COD mg/l 100 150
TKN mg/l 30 15
Phosphate mg/l 10 5
Cyanide mg/l 10 6
Thiocyanate mg/l 4 2
Cd mg/l 0.01
Hg mg/l 0.005
As mg/l 0.025
Cr+Cu+Pb+Ni+Zn mg/l 0.8
PAH mg/l 0.005
The performance of the installation is excellent. COD removal efficiency is almost alwaysover 85 % and TKN removal or nitrification is nearly 100 %. Concentrations are most of the
time within the limits set by the authorities (see figure 9).
Thiocyanate is together with phenols responsible for the high COD concentrations in coke
plant effluent. However phenols are very easily to degrade. Nowadays no samples are taken
anymore for analysing the phenol concentration because it is always lower than the detection
limit. From thiocyanate always a small fraction will not be removed. In the treated effluent
most of the times 1 3 mg/l of thiocyanate will be present. Cyanide itself is probably only fora small part degradable. It is also possible that removal of cyanide takes place by adsorption
on the bio sludge. However a small portion of the cyanide can not be biodegradable also.
-
8/2/2019 Waste Water- Coke Plant
11/13
Figure 9: Flow, COD- and TSS-concentrations in treated waste water
Long term BOD tests proved that about 70 100 mg/l cannot be degraded biologically. Forcoke plant effluents only these values are as high as 370 mg/l. This part of the COD consists
of very persistent components. So far these components are not identified. The COD
concentrations in the treated effluent are about 100 mg/l. This means that almost all the
biodegradable COD is removed.
The average suspended solids concentration is 30 mg/l. Some water waste water coming
from the sulphuric acid plant is after neutralisation also transported to the discharge point ofthe bio treatment plant. It is possible that variations in suspended solids concentrations are a
direct consequence of this extra water because Ca-sulphate can be formed. So possible
gypsum particles are part of the suspended solids.
Up till now we did not succeed in keeping denitrifying bacteria in such a state that stabledenitrification over longer period occurred. The possible reason for that is the presence of
toxic components in the incoming coke plant wastewater.
From time to time the nitrification process becomes unstable. This happened frequently
especially in the first two years of operating the bio treatment plant. These instabilities results
firstly in higher nitrite levels and in a later stage in higher ammonia concentrations. When theconditions are not changed finally nitrification will come to a complete stop.
In the years 2001 and 2002 three major failures in nitrification efficiency occurred. No
explicit explanation could be found for these failures. There only are made a few suggestions
and possible causes afterwards. Toxification of the biomass resulting in inhibiting the
nitrification process could have been caused by one or more toxic compounds in one of theinfluent flows. Most likely this has been a cyanide complex that can be present in coke plant
effluent or blast furnace scrubber blow down.
Other reasons are more common like a biomass that was under stress and in that situation
overloaded. Too high food over micro organism levels can have a killing effect on bacteria.
A too high sludge load is often the reason for unhealthy sludge.
Sludge in a stressed condition also can be the result of amongst others higher temperatures
and large variations in wastewater composition.
0
50
100
150
200
250
300
350
1-jan
15-jan
29-jan
12-feb
26-feb
11-mrt
25-mrt
8-apr
22-apr
6-mei
20-mei
3-jun
17-jun
1-jul
15-jul
29-jul
12-aug
26-aug
9-sep
23-sep
7-okt
21-okt
4-nov
18-nov
2-dec
16-dec
30-dec
m3/h
flow
mg/l COD
TSS
-
8/2/2019 Waste Water- Coke Plant
12/13
It can take several weeks before the installation is working well again. In the IJmuiden
situation it is possible to discharge part of the waste water directly without treatment during
the time the biomass is recovering. This situation occurred once so far and was followed byextensive discussions with the water board resulting in a much higher pollution tax that had to
be paid.
TKN concentrations in the treated effluent are around 8,5 mg/l. The variation is about 6 mg/l.
This means that nitrification is complete (over 95 %). This is confirmed by the NH3
concentrations that normally are not exceeding the level of 2,4 mg/l (see figure 10). Thedifference between ammonia and TKN probably are non biodegradable organic nitrogen
compounds.
Figure 10: TKN- and NH3-concentrations in treated waste water
The nitrogen removal rate is high. The nitrate concentrations are around 480 mg/l.Sometimes a little nitrite is found in the effluent but under normal circumstances not more
than 0,2 0,4 mg/l.
Comparing the actual effluent data of 2004 with the limits from the discharge permit learnsthat COD and TKN are well below these limits. Also heavy metals are lower than allowed in
our permit.
CN and suspended solids are the only components that are not always in compliance.
Suspended solids concentrations can be influenced by the small wastewater flow from the
sulphuric acid plant as mentioned before. An investigation is on its way how to handle this
problem.
CN is frequently too high. Suggestion is to find a way to remove CN from coke oven effluent
separately and before biological treatment. All the alternatives found so far are too complex
or produce high amounts hard to settle sludge. Alternative methods consist of oxidation in
combination with Fe-addition.
6. Controlling the Process
One of the most important things in treating wastewater biologically is controlling the
process. There are several ways to do so.
0
5
10
15
20
25
30
35
40
jan-04
jan-04
feb-04
mrt-04
apr-04
mei-04
jun-04
jul-04
aug-04
sep-04
okt-04
nov-04
dec-04
dec-04
mg/l
AmmoniaNH3
0
10
20
30
40
50
60
mg/lTotalKjeldahlNitrogenTKN
TKN
NH3
-
8/2/2019 Waste Water- Coke Plant
13/13
1. By regular analyses of influent and influent. Shift personnel are taking samples of the
influent every day. With so called test kits COD en NH3 are analysed immediately.
These test kits are not accurate, but the results are satisfying enough to see anyessential changes. From the effluent samples are taken on a continuous base using
special sampling devices. These devices are connected to the flow meter so that is itis possible to take volume proportional samples. Every three days a sample collected
during from 24 hours, is analysed by the chemical department. Besides COD and
TKN also the other components are analysed.
2. pH, temperature, Dissolved Oxygen and NH3 are analysed continuously. pH is
controlled between 6,8 and 7.2, DO set-point is 1,5 2,0 mg/l, temperature in theaeration basin should be not higher than 32 C. The ammonia monitor is the most
important one. If ammonia is increasing actions have to be taken. Departments that
are delivering wastewater are contacted to see if nothing has changed in thereprocesses and for example the oxygen input has to be increased. All monitoring is
done by the central control room.
3. The sludge concentration is kept on a level of 4,5 to 5 grams/l. Every other day the
sludge concentration is analysed and excess sludge is wasted based on the results of
these analyses.
4. Every couple of months, app. 4 times a year the sludge is examined by anexperienced microbiologist from an external company. From the microscopic view
and the changes that are observed information gets available about the health of the
sludge.
5. By measuring the respiration rate of the sludge.
Tests are done with an instrument from Strathkelvin in Glasgow. The primary goal is
controlling sludge health by measuring respiration every day.
A secondary goal is recognizing toxic components in influent and inhibition of the biological
processes. The tests done in the second half of 2004 did result in purchasing the Strathtox-model in Feb 2005.
At the moment implementation in day-to-day-operation is taken place. Regular tests are done
by shift personnel.