wastewater management innovative sewage ......2 project benefits relocated ststw existing ststw...
TRANSCRIPT
SESSION 1 – WASTEWATER MANAGEMENT
Innovative Sewage Infrastructure for Reinforcing
Sustainable Urban Development
- Largest Cavern STW in Hong Kong
Ir Echo LEONG
Executive Director, AECOM
2015.11.11
2
Project Benefits
Relocated STSTW
Existing STSTW
Release premium river-front land for other
beneficial uses – As part of HK’s pursuit of
sustainable development
Currently, the project is at Investigation stage
The construction is scheduled in Q3 2017 for
commissioning in 2027
Existing STSTW
Footprint: 28 hectares
Treatment Level: Secondary
Treatment Capacity: 340,000 m3/d
Catchment Population: ~700,000
Nui Po Shan
3
Design Considerations of Cavern STW
Special Attentions:
• System Hydraulics
• Cavern Configuration
• Fire Safety – access,
ventilation, protection
measures etc.
• Operation Safety – H2S,
aerosol, confined space etc.
• Construction Programme –
excavation volume, C&D waste
transport etc.
• Sewage and Sludge Treatment
Processes – reliability, cost
effectiveness, energy efficiency
etc.
Preliminary Layout
4
Impact on Construction Programme
Cost Effectiveness – Life Cycle Cost
Tender Competition
Suitability for Cavern Installation
Technological Innovation
Process Reliability
Sludge Handling Requirements
O&M Requirements
Flexibility to Meet Future Design
Requirements
Energy Consumption and Carbon
Footprint
• Evaluation criteria and respective criterion weighting have
been discussed with relevant departments for a balance
view on the selection of the treatment processes for the
cavern STW
• Evaluation criteria for sewage treatment processes:
Process Evaluation Criteria
5
Pilot Test Finish
Cavern Detailed Design
Cavern Construction Start for Commissioning
in 2027
Pilot Test Start
IDC Consultancy
Start
Project Programme
Q2‘15 Q3‘16 Q4 ‘16 Q2 ‘17 Q3 ‘17
• Updated technology review
• Updated life-cycle cost analysis
Interim Process Review 1
Treatment
Process
Confirmation
STW Layout Confirmation and Cavern
Requirements
Cavern Construction
Oct ‘14
First-hand operating experience in local conditions, including start-up and stabilization.
Pilot Study 3
Better understanding of process performance and O&M requirements
Technical Visit 2
Pilot test result will help optimizing process design
Design & Construction of Pilot Plants
6
Potential Sewage Processes
• During the Feasibility Study stage, Compact Activated Sludge
(CAS) selected as preferred process for establishing the
baseline design
• Large footprint / cavern volume and potential high CAPEX could
be a key constraint to the Project
• Alternative compact treatment technologies identified for further
evaluation based on latest technological development and
requirements of the Project:
• Integrated Fixed-film Activated Sludge (IFAS)
• Moving Bed Biofilm Reactor (MBBR)
• Aerobic Granular Sludge (AGS)
7
IFAS Process
Suspended Biomass
• BOD removal and denitrification
• MLSS: ~2,000 mg/L
• SRT: ~4 days
Attached Biomass
• Biofilm carriers in nitrification zone only
• Carrier fill rate – up to 65%
• Specific surface area of carriers: 500-1,200 m2/m3 (typical)
• Reduce the size of nitrification zone and have more stable
nitrification performance
Similar Operation
Requirements as
Activated Sludge
Process
8
IFAS Process
• Commonly adopted for upgrading existing STWs with
conventional activated sludge
• Over 200 installations worldwide
Example: Marquette-Lez-Lille, France
• ADWF: 246,000 m3/d
• Population: 620,000 PE
• Start-up year: 2013
BioFilmChipTM M (1,200 m2/m3, 51% Fill)
• Compact design + Enhanced nitrification
• Flexibility for future expansion
9
MBBR Process
• Attached growth for both C and N removal - compact reactor
• No sludge return – smaller energy use
• Max. allowed approaching velocity of 30 m/h – limit the reactor configuration
• Post solids removal (~200mg/L in MBBR reactor effluent) by dissolved air
flotation (DAF), high-rate clarification, sand filtration, disk filter etc.
Anoxic Zone
• Carrier fill rate – 50%
Aerobic Zone
• Carrier fill rate – 60%
• DO set point – 2 mg/L in BOD removal zone / 5 mg/L in nitrification zone
MBBR Process
SET AS
SET AS
MBBR Process
Example: Ytre Sandviken WWTP, Norway
• ADWF: 33,600 m3/d
• Population: 44,000 PE
• Start-up year: 2014
• AnoxKaldnes™ K3 Media (500
m2/m3) for BOD removal (42% Fill)
• First full-scale installation in early 1990s in Norway
• Over 400 installations worldwide
12
AGS Process
• Simultaneous BOD, P and N-removal
• Simple one-tank concept - No sludge return, no
internal recycle, no clarifier, no moving
decanter, no mixer – lower energy demand,
smaller footprint
• Cycle time: 1 hr fill & decant / 1.5 hr reaction /
0.5 hr settle
• Hydraulic loading limit: 3.5 m/hr
• Good settling property (> 0.2 mm) & high
MLSS concentration (up to 15,000 mg/L) –
smaller reactor size
13 Courtesy Delft University of Technology
Aerobic Granular Biomass Activated Sludge
AGS Process
14
AGS Overview
• First municipal installation in 2010 (Epe STP)
• 10+ full-scale municipal system in operation, with over 40
in design or under construction globally
Example: Garmerwolde WWTP, the Netherlands
• Population: 375,000 PE
• ADWF: 24,000m3/d; PWWF: 100,000m3/d
(AGS)
• Start-up year: 2013
• Compact footprint and energy efficiency
2 nos. 9,500m3 Nereda reactors
handle ~40% of the influent
A/B system handles
~60% of the influent
15
Pilot Study at Existing STSTW
Study Objective
Assess the performance of two potential processes (MBBR and AGS)
under local conditions e.g. saline sewage and collect operation data for
process selection and full-scale design, if applicable
1. Proven Process - MBBR
• Verify treatment performance and energy consumption
• Optimize reactor configuration
• Identify O&M requirements
2. Emerging Process - AGS
• Verify treatment performance and energy consumption
• Assess granule stability and digestibility
• Identify O&M requirements
16
SANI (Sulfate-reduction, Autotrophic-denitrification, and Nitrification
Integrated) process is a unique process, which makes use of the sulfate
ion available in the saline sewage from seawater toilet flushing in Hong
Kong to purify wastewater.
Source: HKUST
SANI® Process
17
SANI® Process
Potential Benefits
• ~80% less biological sludge production
• ~35% energy saving
• No carbon requirement for Denitrification
Included in the Pilot Study
Objective for SANI
• To understand and collect more data of SANI
• Verify treatment performance and potential savings
• Identify design and O&M requirements for future implementation, if the
pilot study results are promising.
18
Pilot Study at Existing STSTW
• Three pilot plants for MBBR, AGS and SANI processes will be
installed at the existing STSTW
• Approximate capacity of each pilot plant: 800-1,000 m3/day
• Tendering completed; currently at design stage
THANK YOU Relocation of Sha Tin Sewage Treatment Works to Caverns