water production wells and asr wells procurements · water production wells and asr wells ... pe,...

26
WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS Pre-submittal Meeting Project Number WS85010054-2 March 16, 2017 10:00 am to 12:00 pm

Upload: buituong

Post on 01-May-2018

225 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS

Pre-submittal Meeting

Project Number WS85010054-2March 16, 201710:00 am to 12:00 pm

Page 2: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Welcome and Introductions

Ellen Pimental, Contracts SpecialistDesign and Construction Procurement

Aaron Laroque, PE, Civil Engineer III, Water Services Department

Darlene Helm, PE, Civil Engineer IIIProgram ManagerWater Services Department

Page 3: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Water Production Wells and ASR Wells Procurement

1. Design and Construction Administration & Inspection Services (3 selected)

2. Program Management Services(1 selected)

3. Construction Manager At Risk (2 selected)

Page 4: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Meeting Information

• Please sign in on the sign in sheet

• Please hold questions until after the presentation

• This is your ONLY opportunity to ask the City Staff questions

Page 5: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Meeting OverviewNotification of change to the Request for

Qualifications are posted on our website:

https://www.phoenix.gov/streets/procurement/current-opportunities

It is your responsibility as an RFQ holder to determine, prior to submittal, if notification letters have been issued

Page 6: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

VENDOR REGISTRATION

All Firms MUST Be Registered in the Vendor Management System PRIOR TO SUBMITTING A PROPOSAL

NEW FIRMS ---After Registering--- the City Will SEND AN EMAIL WITH A VENDOR NUMBER WITHIN TWO DAYS

NEW THE VENDOR NUMBER MUST TO BE INCLUDED ON THE COVER OF THE STATEMENT OF QUALIFICATIONS OR ON THE BID PROPOSAL PACKAGE/ENVELOPE. INFORMATION ON HOW TO REGISTER WITH THE CITY IS AVAILABLE AT:

https://www.phoenix.gov/finance/vendorsreg

Page 7: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Agenda Project Description

Scope of Work

1. Design and Construction Administration & Inspection Services

2. Program Management Services

3. Construction Manager At Risk

Page 8: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Agenda

Submittal Requirements

Selection Schedule

Questions?

Page 9: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

PROJECT DESCRIPTION21 total wells in two procurement phases over a 6 year time period

There will be both standard water production wells and ASR Wells

Phase One:

Ten Wells completed by 2020

Total Construction Costs $47,000,000

Page 10: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

PROJECT DESCRIPTION

Install 4 Production Wells

Install 6 ASR Wells

Production Capacity 1,000 to 1,800 gpm.

Page 11: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

PROJECT DESCRIPTION GOALS

The goal of these wells is to augment Phoenix’s potable water resources during times of long-term water shortages, emergency outages, and meeting potable system demand balancing

Page 12: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Scope of Work

WELL DESIGN & CONSTRUCTION ADMINSTRATION & INSPECTION SERVICES

Each design firm will receive a minimum of 3-4 well projects.

WORK FOR WELL DESIGN AND DRILLING

WELL INFRASTRUCTURE DESIGN

Page 13: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Scope of Work

WATER PRODUCTION WELLS AND ASR WELLS –PROGRAM MANAGEMENT SERVICES

One Firm will be selected Serve as primary contact with WSD.

Receive direction from WSD (Engineering and Remote Facilities Divisions) and determine potential impacts and benefits to the Well Construction Program

Create, implement, and review schedule, budget, and project progress.

Etc.

Page 14: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Scope of Work

WELL DRILLING AND INSTALLATION/ TESTING OF INFRASTRUCTURE CONSTRUCTION MANAGER AT RISK SERVICES

Two Firms will be selected

Design phase services

Construction phase services

Page 15: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Questions ??

Page 16: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Statement of Qualifications Criteria Design and CA&I Services

General information (15 points)

Design Experience of the Prime Firm

(17 points)

Construction Administration and Inspection Experience of

the Prime Firm (8 points)

Experience of Key Personnel and Subconsultants (20

points)

Project Understanding and Approach (30 points)

Overall evaluation of the firm and its perceived ability to

provide the required services (10 points)

Page 17: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Statement of Qualifications Criteria Program Management Services

General information (15 points)

Program Management Experience of the Prime Firm

(20 points)

Experience of Key Personnel and Subconsultants

(20 points)

Project Understanding and Approach (35 points)

Overall evaluation of the firm and its perceived ability to

provide the required services (10 points)

Page 18: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Statement of Qualifications Criteria CMAR

General information (15 points)

Experience and qualification of the Firm

(20 points)

Experience of Key Personnel to be assigned to this

project (25 points)

Understanding of this project and approach to performing the

required services (30 points)

Overall evaluation of the firm and its perceived ability to

provide the required services (10 points)

Page 19: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Statement of Qualifications Criteria

SOQ Cover Letter

Clearly display the firm name, firm vendor number,

project title, and project number on the cover of the

SOQ and submittal package.

Evaluation Criteria (including project organizational

chart)

Additional Content (resumes or other information)

Page 20: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Statement of Qualifications CriteriaMAXIMUM pages permitted is 12 pages:

+ Evaluation Criteria (including organizational

chart)

+ Additional Content (resumes or other

information)

+ Photos, charts/graphs or other evaluation

content

= 12 MAXIMUM pages permitted

Page 21: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Statement of Qualifications Criteria Each page side with criteria information will be

counted.

Pages that have photos, charts, and graphs will be counted toward maximum number of pages.

Cover letter, front and back covers, Table of Contents and tab dividers will NOT be counted toward the maximum page limit, UNLESS they include information that may be considered by the selection panel.

Page 22: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Statement of Qualifications Criteria Submit 7 Copies of the SOQ

SOQ is Due:

12:00pm Noon – Arizona local timeThursday, March 30, 2017

Phoenix City Hall

200 West Washington Street, 6th Floor

Submittal Box

Page 23: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Grounds for Disqualification

Receipt of SOQ after the specified cut-off

date and time

Too few copies of the submittal

Deposit of SOQ in the wrong location

Violating the “Contact with City

Employees” policy

Page 24: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

SOQ Due Date

12:00 P.M. Arizona local time

Thursday, March 30, 2016

City Hall, 200 W. Washington Street

6th Floor, Submittal Box

Page 25: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Street Transportation Procurement Section Webpage Request for Qualifications Notifications Plan Holders List Pre Submittal Power Point Presentation Sign In Award Located at :

http://phoenix.gov/streets/procurement/current-opportunities

Page 26: WATER PRODUCTION WELLS AND ASR WELLS PROCUREMENTS · WATER PRODUCTION WELLS AND ASR WELLS ... PE, Civil Engineer III, Water Services Department ... potable water resources during

Questions After Today

Email Your Questions To:

Ellen Pimental Contracts Specialist

[email protected]