THE UNITED REPUBLIC OF TANZANIA MINISTRY OF WATER AND IRRIGATION WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 SEPTEMBER 2010

Upload: trantuong

Post on 20-Nov-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

THE UNITED REPUBLIC OF TANZANIA

MINISTRY OF WATER AND IRRIGATION

WATER SECTOR DEVELOPMENT PROGRAMME

ANNUAL PROGRESS REPORT FY 2009/2010

SEPTEMBER 2010

Page 2: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

TABLE OF CONTENTS

ABBREVIATIONS………………………………………………………………………..iii

LIST OF TABLES……………………………………………………………………………v

EXECUTIVE SUMMARY ............................................................................................. vi

1 INTRODUCTION .................................................................................................. 1

1.1 Background ............................................................................................................................... 1

1.2 Content of the report ................................................................................................................ 1

1.3 Structure of the report .............................................................................................................. 1

2 SUMMARY OF PROGRESS - FY 2009/2010 ................................................................ 1

2.1 Summary of Progress - Component 1 ....................................................................................... 1

2.2 Summary of Progress - Component 2 ....................................................................................... 2

2.3 Summary of Progress - Component 3 ....................................................................................... 2

2.4 Summary of Progress - Component 4 ....................................................................................... 3

3 DETAILED PHYSICAL PROGRESS .............................................................................. 3

3.1 COMPONENT 1: WATER RESOURCES MANAGEMENT AND DEVELOPMENT ............................ 3

3.1.1 Strengthening Basin Level Water Resources Management ...................................................... 3

3.1.2 Integrated River/Lake Basin Management & Development Plans ........................................... 9

3.1.3 Priority Water Resources Management Infrastructure Investment ......................................... 9

3.1.4 Water Quality Compliance and Strengthening Water Laboratories ....................................... 11

3.1.5 Planned and Implemented Activities by the DWR – National Level ....................................... 12

3.2 COMPONENT 2: SCALING UP OF RURAL WATER SUPPLY AND SANITATION .......................... 17

3.2.1 Progress on Management Support to LGAs ............................................................................ 17

3.2.2 Progress on Rural Water Supply and Sanitation Investments ................................................ 18

3.3 COMPONENT 3: SCALING UP URBAN WATER SUPPLY AND SANITATION .............................. 22

3.3.1 Progress on Management support to UWSS Utilities ............................................................. 23

3.3.2 Progress on Urban WSS Capital Investments.......................................................................... 26

3.4 COMPONENT 4: INSTITUTIONAL STRENGTHENING AND CAPACITY BUILDING ...................... 31

Page 3: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

ii

3.4.1 Progress on Operationalizing the new role of the Ministry .................................................... 33

3.4.2 Progress on Technical assistance for strengthening of sub-sector planning and operational capacities................................................................................................................................. 34

3.4.3 Progress in supporting sector coordination, performance monitoring and harmonization of sector policies, strategies and plans ....................................................................................... 35

3.4.4 Progress on the Sector Capacity Building ............................................................................... 37

4 PROGRESS ON ENVIRONMENTAL AND SOCIAL SAFEGUARDS ..................................... 40

4.1 Component 1- Water Resources Management ...................................................................... 41

4.2 Component 2 – Local Level: Scaling –Up of Rural WSS Delivery ............................................. 42

4.3 Component 3: Scaling Up of Urban WSS Delivery .................................................................. 42

4.4 Component 4 – National Level: Support to Sector Institutional Strengthening and Capacity

Building 43

5 FINANCIAL PERFORMANCE .................................................................................. 44

5.1 Component 1: Water Resources Management ...................................................................... 44

5.2 Component 2: Scaling Up of Rural Water Supply and Sanitation ........................................... 46

5.3 Component 3: Scaling Up of Urban Water Supply and Sanitation ......................................... 47

5.4 Component 4: Institutional Strengthening and Capacity Building ......................................... 47

6 PROGRESS ON PROCUREMENT ............................................................................ 48

6.1 Component 1: Water Resources Management ...................................................................... 48

6.2 Component 2: Rural Water Supply and Sanitation ................................................................. 48

6.3 Component 3: Urban Water Supply and Sanitation ............................................................... 50

6.4 Component 4: Institutional Strengthening and Capacity Building ......................................... 50

7 PROGRESS IN MONITORING AND EVALUATION ....................................................... 51

8 CHALLENGES .................................................................................................... 53

9 CONCLUSIONS AND RECOMMENDATIONS ............................................................. 55

9.1 CONCLUSIONS ......................................................................................................................... 55

9.2 RECOMMENDATIONS .............................................................................................................. 56

Page 4: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

iii

ABBREVIATIONS

ADB African Development Bank ADF African Development Fund BOQs Bill of Quantity BWO Basin Water Office BWBs Basin Water Boards CARITAS Latin word means Charity-expression of love CBG Capacity Building Grant CDG Capital Development Grant CSOs Civil Society Organizations CWSD Community Water Supply Department DADs District Agricultural Development Support DWE District Water Engineer DWST District Water and Sanitation Team DFTs District Facilitation Teams DPs Development Partners DUWSAs District Urban Water Supply Authorities DWR Department of Water Resources EMA Environment Management Act EoI Expression of Interest EAs Executive Agencies ESIA Environment and Social Impact Assessment EU European Union FY Financial Year GIS Geographical Information System GoT Government of Tanzania IAs Implementing Agencies HTM Handeni Trunk Main HYCOS Hydrological Observation System HQs Headquarters ICB International Competitive Bidding IDA International Development Agency IDB Internal Drainage Basin IWRM Integrated Water Resources Management IWRMDP Integrated Water Resources Management and Development Plans JICA Japan International Cooperation Agency LAN Local Access Network LVEMP Lake Victoria Environment Management Project LVBC Lake Victoria Basin Commission LGA Local Government Authority LGCDG Local Government Capital Development Grant M&E Monitoring and Evaluation MDGs Millennium Development Goals

Page 5: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

iv

MoWI Ministry of Water and Irrigation MTB Ministry Tender Board MoU Memorandum of Understanding MIS Management Information System NAWAPO National Water Policy NCB National Competitive Bidding NEMC National Environment Management Council NPSC National Policy Steering Committee NWSDS National Water Sector Development Strategy O&M Operation and Maintenance OC Other charges PAD Project Appraisal Document PMO-RALG Prime Minister’s Office- Regional Administration and Local Government PMU Procurement Management Unit PPA Public Procurement Act PPR Public Procurement Regulation RFP Request for Proposal RS Regional Secretariat RWA Regional Water Advisor RWHT Rain Water Harvesting Tank RWSS Rural Water Supply and Sanitation RWSSP Rural Water Supply and Sanitation Programme RWST Regional Water and Sanitation Team ToR Terms of Reference UWSAs Urban Water Supply Authorities WB World Bank WDMI Water Development and Management Institute WUA Water User Association WUE Water User Entities WRMP Water Resources Management Programme WRMA Water Resources Management Act WSDP Water Sector Development Programme WSSA Water Supply and Sanitation Authority WUF Water User Fee WUG Water User Group WSS Water Supply and Sanitation WSSP Water Supply and Sanitation Programme WUAs Water User Associations WUGs Water User Groups

Page 6: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

v

LIST OF TABLES Table 1: Status of Priority Investments

Table 2: Summary of studies and designs in the UWSAs, Small Towns and National Projects

Table 3: WSDP Funded projects which are listed for screening and EIA assessments;

Table 4: Revenues Collection

Table 5: Annual Expenditure

Table 6: Development Fund for Water Resources Component Disbursed in F/Y 2009/10 Table 7: Distribution of the received funds in the F/Y 2009/10 Table 8: Received funds for Water Laboratory Services Table 9: Funds released and spent by components for July 2009 - June 2010 Table 10: Disbursement of the funds for Component Table 11: Funds Disbursement under Component 4 for the FY 2009/2010

Page 7: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

vi

EXECUTIVE SUMMARY

This Annual Progress Report is prepared as per WSDP PAD 2006, it describes and analyses performance for the period from July, 2009 to June, 2010. It captures what has been implemented during the financial year 2009/2010 in accordance to the WSDP work-plan, budget and procurement plan of which implementation is done funds from the basket and earmarked projects as sourced from development partners and the government. It is envisaged that the report will be useful in planning and decision making with regard to further implementation of the Programme.

During 2009/2010, Component 1 of WSDP, which is Water Resources Management, the approved budget was Tshs. 24.47 billion of which, Tshs 3.1billion was for water laboratory; and TShs 979.5million was collected as economic water fees in all 9 water basins. The fund released during the year was Tshs. 16.55billion where Tsh 15.45 billion equivalent to 93% was spent. The component experienced progressive improvements in all sub components except priority water resources investments, which experienced slow progress.

With regard to Component 2; which is Scaling up of Rural Water Supply and Sanitation, the approved budget was TShs. 120 billion out of which, TShs 78.6 billion, equivalent to 66%; was released including earmarked projects. A total of TShs. 60.54 billion, equivalent to 80 %; was spent, mostly because expenditure performance in LGAs was 33% due to the fact that most of works were in the initial stages. Performance in LGAs were noted in the areas of capital investment, where out of 5,726 planned water points; 3,000 were built/rehabilitated, which is equivalent to 52.3%. These are enough to serve 585,250 people. Also, a total of 1,027 demonstration latrines were built.

The approved budget for Component 3; which is Urban Water Supply and Sanitation, was Tsh 127.4.bn, out of which, TShs 84 billion (Tshs 49billion from basket including local funds and Tshs 35billion from earmarked partners), equivalent to 66% were released. Total expenditure performance for this component during the year was 83% of the released fund. Tshs 8.3billion was used for management support and Tshs 61.2billion was used for investments, where large part of it was invested in Dar es Salaam. Performance of this component continued to improve in most of urban areas. For instance, Water production for 19 UWSAs in the year 2009/2010 increased to 113.11 million m3 compared to 110.64 million m3 in 2008/2009. Water production in Dar es Salaam increased to 92.7 million m3 in 2009/2010 compared to 91.7 million m3 in 2008/2009; and the overall production of 205.78 million m3 is equivalent to 67.1% of the total water demand in regional urban centers, which is 306 million m3. The percentage of population served stood at 84% at 19 average hours of service in the 19 regional UWSAs by June 2010.

The budget for Component 4, which is Institutional strengthening and Capacity Building; was TShs. 21.9billion, out of which, TShs 14.6 billion, equivalent to 65.7%, was released. The total expenditure performance for this component was TShs 14.5, which is 99.8% of the released funds. Using this amount, several projects were implemented, including rehabilitation/construction of offices at Ubungo; design of new office building; acquisition and

Page 8: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

vii

distribution of working tools such as vehicles, motorcycles, computers, printers and furniture delivered to the IAs; training of MoWI staff, LGAs and Regional Secretariats; acquisition of Drilling equipments for Drilling and Dam Construction Agency (DDCA); transformation of the Water Resources Institute (WDMI) into an agency; Preparation of the programme management information system and provision of technical support to EWURA.

Other areas of good progress include strengthening the compliance to environmental and social safeguards; where 16 of 34 WRM projects were screened for environmental and social impacts and out of 622 dams evaluated, 18 dams were prioritized for rehabilitation. In RWSS component, only 32 districts have submitted their environment reports; where 208 projects have been screened, out of which, only 10 projects need full EIA. In the UWSS Component, out of 56 sub-projects; 31 projects were screened and 21 qualified for full EIA. The remaining 10 projects fell under category C that required a checklist. For strengthening the capacity in this area, the MoWI has recruited 11 environmental engineers and 8 social experts.

The progress on procurement was also good as three Basins (Pangani, Rufiji and Wami/Ruvu) established Procurement Management Units (PMUs) and their Tender Boards in 2009. The component has 10 consultancies under preparation for Wami/Ruvu, one consultancy procured for Rufiji; and 5 consultancies in execution stage in Wami/Ruvu. For RWSS Component, out of 132 LGAs, 123 have signed the consultancy contracts to support LGAs in provision of technical and facilitation services. Consultants engaged by LGAs are in different stages of implementation. Under UWSS Component, 41.5% of the planned contracts for consultancy services have been initiated as scheduled in the procurement plan for 19 UWSAs, DAWASA/DAWASCO, 118 small towns/DUWSAs and seven National Projects. In the IS&CB Component, the procurement exercise covers MoWI headquarters (including WDMI, DDCA and MCS). A total of 36 contracts have been signed. About 26.4% of planned contracts were initiated.

Main Challenges: The challenges noted during the joint supervision missions conducted in September 2009 and March 2010 was found to agree with those reported in the components. These include inadequate sector monitoring system that affects quality, timeliness and accuracy of program reporting; degradation of water sources and catchment areas; limited sector capacity at all levels; and low community participation in the implementation of water sub-projects in terms of cash and in kind.

Page 9: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

1 INTRODUCTION 1.1 Background

This Annual Progress Report is prepared as per WSDP PAD 2006, it describes and analyses

performance for the period from July, 2009 to June, 2010. It captures what has been

implemented during the financial year 2009/2010 in accordance to the WSDP work-plan,

budget and procurement plan. It is envisaged that the report will be useful in planning and

decision making with regard to further implementation of the Programme.

1.2 Content of the report

The Annual Progress Report shows analysis of physical and financial achievements realized in

the implementation of planned activities in the 4 components of WSDP for the FY 2009/2010. It

discusses how those planned activities were executed; challenges experienced in the course of

implementation and what is the status so far in the execution of activities by the IAs. The report

concludes with recommendations for aspects that need to be prioritized in the coming years.

1.3 Structure of the report

This report is divided in nine chapters: Chapter 1: Introduction; Chapter 2: Progress in the

Quarter 2010; Chapter 3: Physical Implementation; Chapter 4: Safeguards; Chapter 5: Financial

Performance; Chapter 6: Procurement Status; Chapter 7: Monitoring; Chapter 8: Challenges;

Chapter 9: Conclusions and Recommendations. The executive summary is provided before the

1st chapter.

2 SUMMARY OF PROGRESS - FY 2009/2010

2.1 Summary of Progress - Component 1

Implementation of Component 1: Water Resources Management and Development is

progressively improving compared to previous years. Sub components 1A (Strengthening basin

level water resources management) realized achievement in strengthening and establishment

of WUAs, strengthening of water resources monitoring networks and protection of important

water sources as well as monitoring and enforcement. The sub-component achieved its plan by

81.2%. 1B (Integrated river and lake basin management and development plans) Preparation of

two (Rufiji and Internal Drainage basins) out of seven IWRM Plans started. Procurement of

consultants for the other five (Pangani, Ruvuma, Lake Tanganyika, Lake Rukwa and Lake Nyasa

basins) was at a stage of short listing the consultants. Preparation of IWRM plan for Lake

Victoria basin will be funded by Lake Victoria Basin commission under LVEMP II while for

Wami/Ruvu basin it will be funded by JICA.

Page 10: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

2

Preparation of Terms of Reference for the two plans started during the year. and 1D

(Determination of quality of different water sources in the country and strengthening water

laboratories) made significant progress, A total of 3,655 water samples out of 3,500 targeted

were collected from different water sources including wells, rivers, springs and lakes and

analyzed for physical-chemical and bacteriological tests. 3,456 samples (94.6%) were found to

be within the required standards. A total of 60 monitoring water points have been identified in

Dar es Salaam; Sub component 1C (Priority water resources management infrastructure

investment) is still slow.

2.2 Summary of Progress - Component 2

For the period of F/Y 2009/2010, out of 5,726 water points planned to be built/rehabilitated 3,000 water points were built/rehabilitated, which is equivalent to 52.3%. Also, out of 3,000 water points built/rehabilitated 2,341 are functioning, which is equivalent to 78%. The functioning water points are enough to serve 585,250 people. A total of 1,027 latrines were built. Details for the year can be seen in Annex B1(a) and Annex B1(b). Up to June 2010, the provision of consultancy services in ten villages for LGAs was at various stages of implementation including procurement of consultants in 10 villages, prepare inception reports, conducting scoping studies, detailed designs, preparation of bidding documents for drilling of exploratory boreholes and reaming them if found to be productive, advertisement and evaluation of bidding documents for exploratory boreholes and procuring contractors for construction of water sub projects. During the F/Y 2009/2010 capacity development guidelines and strategies were disseminated to all LGAs and RSs. The documents were used to develop capacity development plans in the respective institution.

2.3 Summary of Progress - Component 3

During the year 2009/2010 the overall performance shows a continuous improvement in most of the indicators in almost all UWSAs as compared to the year 2008/2009. General view of the performance is summarized as follows:- (i) The water production of 19 UWSAs in the year 2009/2010 increased to 113.11 million m3 compared to 110.64 million m3 reported in 2008/2009. Dar es Salaam reported water production of 92.7 million m3 in 2009/2010 as compared to 91.7 million m3 of 2008/2009. The overall production reported of 205.78 million m3 is 67.1% proportion of the estimated current water demand of all regional urban centers which stands at 306 million m3; (ii) Unaccounted for Water in the year 2009/2010 including Dar es Salaam improved to 35%

from 37% reported by the end of 2008/2009. This improvement has been due to the efforts made by most of the UWSAs to control non revenue water, rehabilitation of water distribution system and increased domestic metering.

Page 11: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

3

(iii) The percentage population served stands at 84% at average hours of service of 19 regional capitals, while the total number of kiosks increased from 1,649 in the year 2008/2009 to 1,973 during the year of review for 19 UWSAs while 385 kiosks are not operated. In the case of Dar es Salaam, total number of kiosks increased from 195 in the year 2008/2009 to 225 for the year 2009/2010 and percentage population served stands at 68% and the average hours of service is 9 hours; and (iv) As for the case of sewer of 10 UWSAs total of 17,843 connections were reported in 2009/2010 compared to 18,513 sewer customers in 2008/2009. In Dar es Salaam total of 17,682 connections were reported in 2009/2010 compared to 17,132 sewer customers in 2008/2009. Total sewer customers in 2009/2010 of 35,525.

2.4 Summary of Progress - Component 4

During the FY 2009/2010, the WSDP continued to implement several projects including

rehabilitation/construction of office buildings at Maji Ubungo Office Complex were completed;

rehabilitation of two blocks is in progress; design for “Maji House” building was approved;

Working tools such as 215 vehicles, 407 motorcycles, various items of computers, printers,

accessories and furniture have been delivered to IAs; MoWI recruited 129 staff to fill the vacant

posts, 200 staff at MoWI attended short and long term trainings; and Water Resources Institute

(WDMI) was transformed into an agency. Also, the sector MIS framework was put in place,

ready for making it operational during 2010/2011.

3 DETAILED PHYSICAL PROGRESS This chapter summarizes level of progress towards meeting the targets, improving service delivery and the completion of priority activities in the components. 3.1 COMPONENT 1: WATER RESOURCES MANAGEMENT AND DEVELOPMENT

The following are summary of progress achieved in the implementation of the following planned activities in the WRMD:- (i) Strengthening Basin Level Water Resources Management; (ii) Integrated river and lake basin management and development plans; (iii) Priority water resources infrastructure investment; (iv) Water Quality Compliance and Strengthening of Water Laboratories; and (v) Oversee implementation of activities under Water Resources Division.

3.1.1 Strengthening Basin Level Water Resources Management

The planned activities for the F/Y 2009/10 under this sub-component were as follows:-

Page 12: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

4

(i) To strengthen water resources monitoring network, provide support for water resources protection and conservation in all Water Basin;

(ii) To strengthen BWO, MIS and WUA database in all Water Basin; (iii) To undertake water resources assessment, monitoring and enforcement in all Water

Basins; (iv) To facilitate establishment and strengthening of WUAs in all 9 basins and promote

water demand management and conservation; (v) To facilitate training to BWO staff in all 9 Basins and provide short term technical

assistance for financing of Basin Water Boards towards autonomy; (vi) To facilitate Environmental Management Programme and enforcement of legislation

and compliance; (vii) To rehabilitate and furnish water basin offices and laboratory buildings in all 9 water

basins; (viii) To procure computers and other office facilities for basin water offices; and (ix) To carry out river flow measurements from operational river gauging stations, monitor

water levels and water quality at groundwater stations, collect rainfall and Meteorological data from Meteorological stations.

The status of implementation of different activities falling under this category is summarized

below:-

(i) Strengthen the water resources monitoring network, provide support for water resources protection and conservation of 9 basin water offices

Construction, rehabilitation and expansion of hydro-meteorological stations/monitoring network

Surveys of all river flow gauging stations and BOQs and designs for rehabilitation of 292 stations

have been completed. Inventories of climate stations and groundwater monitoring stations and

boreholes drilled have been compiled. BOQ for rehabilitation of 57 river gauging, 7 climatic

stations, replacement of 14 rain gauge and 13 automatic weather stations have been prepared

for Rufiji water basin. In Lake Nyasa Basin BOQs and designs for 29 Hydrometric, 6 Weather

station, 18 rain gauge stations have been prepared. 54 hydrometric stations were designed for

Pangani Water Basin. Tender documents for rehabilitation of 10 stations for Wami/Ruvu Water

Basin have been prepared. Survey and design for construction of 46 monitoring stations was

done for Tanganyika Water Basin. 17 gauging stations have been rehabilitated in Lake Victoria

Basin (15), Ruvuma River and Southern Coast Basin (1) and Rufiji Basin (1). Maintenance of 32

existing manual stations was carried out in Wami/Ruvu Basin. 2 hydrometric and 1 automatic

weather station built by CARE-WWF in Wami/Ruvu water Basin and 2 Water level stations and

discharge measurement have been constructed in Lake Victoria Basin. Three V-Notches

Page 13: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

5

constructed at 3 Springs of Mbwinji in Ruvuma Water Basin. In Rufiji Water Basin, drilling of one

(1) monitoring well and production borehole is on going and 15 Water Quality and Pollution

stations identified and operated, in Lake Nyasa Basin.

To collect and assess meteorological, hydrological and hydrogeological data from all

stations

Hydro meteorological data were collected from 84 out of 88 planned monitoring stations; 8 in

the Internal Drainage Basin, 18 in Pangani Basin, 23 in Lake Nyasa Basin, 8 in Rufiji Basin, 9 Lake

Tanganyika, 8 in Wami/Ruvu Basin and 10 in Lake Victoria Basin. Data from 87 out of 100

planned rainfall stations were collected; 8 in Internal Drainage, 46 in Lake Victoria Basin and 33

in Wami/Ruvu Basin. Data from 9 monitoring wells out of 14 planned and 5 climatic stations

were collected and entered to the Database in Rufiji Basin.

Water Quality Management and Pollution Control

1,328 water samples out of 1,538 planned were collected from various sources and analyzed;

1,022 in Lake Victoria Basin, 144 in Internal Drainage Basin, 70 in Ruvuma Basin, 38 in Nyasa

Basin, 5 in Tanganyika Basin, 46 in Rufiji Basin and 53 in Wami/Ruvu Basin. Monitoring

conducted for effluents from 90 industries out of 95 planed; 45 in Lake Tanganyika Basin, 45 in

Wami/Ruvu Basins and 5 in Pangani Basin. All analyzed samples were in compliance with

available standards.

Protection of Important Water Sources

Efforts were taken by basin water offices to protect important water sources as follows: ToR to

procure a consultant to classify water bodies in the Wami and Ruvu Rivers system prepared,

demarcation of Chamwino wellfield completed, map for protection of Kimbiji aquifer prepared,

demarcation of Nala catchment area on progress, Kizinga, Kimbiji/Mpera and Makutupora

areas identified for demarcation, ToR for valuation of properties along Kizinga river valley

prepared, Consultant procured, Valuation have been done, Situational Analysis report has been

prepared and presented to stakeholders meeting, final report submitted, demarcation work is

on going for Makutupora sub basin (100 sign boards installed), in Wami/Ruvu Water Basin;

In Rufiji Basin, processes to declare Lihogosa swamp as protected water source has been

initiated in collaboration with Njombe District council, Little Ruaha River has been protected

and demarcated, demarcation of Mpolo River is in progress and Environmental Flow

Assessment has been done at Great Ruaha Catchment;

Page 14: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

6

In Internal Drainage Water Basin protection processes for Lake Babati, Maisaka, Mwankoko,

Irao well fields and Mount Kwaraa have been initiated. 1,000 trees were planted at Makomero

Village and training on land use and acquisition for water projects and ESIA conducted at

Babati, 36 WUGs were visited and encouraged on conservation of Water Resources in

Strengthen BWO Management Information System, WUA database and cross-cutting issues

Also a Software for water user data and billing system developed for the development of MIS in

Internal Drainage Basin is now in use.

(ii) Undertake water resources assessment, monitoring and enforcement in all 9 water basins

To resolve conflicts and prosecute defaulters.

Six conflicts were resolved; 1 in Internal Drainage Basin, 3 in Rufiji Basin and 2 in Wami/Ruvu

Basin. Eleven water use conflicts were attended in Pangani Basin. Two defaulters were

sentenced 6 month in jail, two warned not to destroy water sources and four cases are in

process in Wami/Ruvu Basin. One case on vandalism of gauging station is on progress, eight

People jailed for six months and six fined for destruction of water sources and ten cases for

illegal abstractions are on going in Rufiji Basin.

To process water use permit

222 applications for water use permits have been received and processed out of 390 planned;

42 in Internal Drainage Basin, 28 in Lake Victoria Basin, 16 Lake Nyasa Basin, 29 in Pangani

Basin, 16 in Lake Rukwa Basin, 78 in Wami/Ruvu Basin and 13 in Rufiji Basin. 179 water users

were verified and requested to reapply for water use permits. Issuing of water use permits

using the new WRM act awaits regulations to be in place.

(iii) Facilitate establishment and strengthening of WUAs in all Basins and promote water demand management and conservation

To establish and strengthen WUGs, WUAs, and DFTs

Six Provision Management Committees for 6 WUAs are in place in Pangani Basin. The collection

of baseline information for 3 sub-catchments of Luwaita, Lumecha and Songwe in Lake Nyasa

Basin. A total of 178 WUGs have been formed; 89 in Lake Rukwa Basin, 62 in Ruvuma and

Southern coast Basin, 1 in Lake Nyasa Basin and 26 in Rufiji Basin. 10 DFTs out of 17 planned

were formed; 7 in Ruvuma Basin and 3 in Wami/Ruvu Basin. 16 WUAs have been formed; 3 in

Lake Victoria Basin, 7 in Wami/Ruvu Basin and 6 in Lake Tanganyika Basin. One WUA has been

Page 15: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

7

provided with 21 bicycles in Ruvuma Basin. Establishment of catchment council await WRMA

regulations. 3 new WUAs were provided with 3 motorcycles in Rufiji Water Basin. 26 WUAs

were provided with 11 motorcycles and13 Bicycles.

To create awareness to stakeholders

Sensitization to stakeholders on water sources conservation, water policy, Act No 11 of 2009

and importance of registration for water use permits done through TVs and radio talkshows

and programs, participation in Maji Week commemoration, Nanenane exhibition, stakeholders’

meetings and printing and distribution of awareness materials (t-shirts, posters, diaries,

brochures, calendars) in all basins.

To carry out hydrogeological investigations and supervision of drilling sites

183 sites were surveyed; 23 in Lake Victoria Basin, 10 in Lake Nyasa Basin, 59 in Pangani Basin,

76 in Ruvuma Basin and 15 in Rufiji Basin.

To inspect abstractions and install flow meters

177 abstractions were inspected out of 126 planned; 166 in Lake Victoria and 11 in Internal

Drainage Basin. 4 Irrigation schemes were visited and encouraged in good water use and

formation of WUGs. 3 dam sites (Mwalala, Igurubi and Dongobesh) have been identified. The

survey has been conducted at Igurubi dam site in Internal Drainage Basin.

A total of 568 surface water abstractions out of 642 planned were inspected; 131 in Pangani

Basin, 352 in Rufiji Basin and 85 in Lake Tanganyika Basin. 595 wells and boreholes were also

registered in Rufiji Water Basin. 14 irrigation canals were found using water illegally and closed,

3 industries and 1 municipal were monitored in Rufiji Basin. 294 surface water and 167

groundwater users were registered in Lake Tanganyika Basin.

(iv) Facilitate training meetings and provide short term technical assistance to BWO staff in 9 Basins

490 Water Basin Staff out of 500 planned attended various trainings, workshops and seminars

as described below this paragraph; 45 in Lake Victoria Basin, 24 in Lake Rukwa Basin,49 in Lake

Nyasa Basin, 89 in Pangani Basin, 140 in Ruvuma Basin, 31 in Rufiji Basin, 40 in Wami/Ruvu

Basin, 41 in Lake Tanganyika Basin and 31 in Internal Drainage Basins:-

Training for basin water offices were in the following fields: MBA Cooperate Management, Preparation of ESIA, Environmental Engineering, Environmental Flows Assessment,

Page 16: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

8

AUTOCAD, training on HYDATA software, Water quality assurance and quality control, Capacity Development Plans, Water Resources Management Act and environment conservation; training in Office and personnel management, short course in Geographic Information System (GIS) and Database Management;

Meetings and seminars were conducted as follows; Groundwater drilling stakeholders meeting aiming at sensitizing drilling ethics; Water Resources Department and BWOs Working meeting; meeting for 10th Anniversary of the Nile Basin held in DSM; and Annual General Basin Water Board meeting 25 out of 36 planned Board meetings were held; 2 in Internal Drainage Basin, 4 in Lake Victoria Basin, 1 in Lake Tanganyika Basin, 4 in Pangani Basin, 4 in Rukwa Basin, 4 in Rufiji Basin, 3 in Lake Nyasa Basin and 3 in Wami/Ruvu Basin; and

Technical advisors in Integrated Water Resources Management, Transboundary Water Resources, Dam Safety Monitoring, and Water Resources Information Management System have been procured.

(v) Rehabilitate and furnish water basin and laboratory offices in 9 Basins

Rehabilitation and construction of Basin Water Offices and Water Laboratories for Zone-One (Rufiji, Ruvuma, Lake Nyasa and Lake Rukwa)

Outline design completed for Zone I. Detailed design for Tukuyu (Zone I) is completed, the

contract was signed in 30th June 2010. One Store and Office wall fence were rehabilitated in

Ruvuma Basin, minor maintenance was done for toilets in Iringa. Office rehabilitation has been

done in order to contain the IWRMDP Consultants staff in Rufiji Basin.

Rehabilitation and construction of Basin Water Offices and Water Laboratories for Zone-

Two (Pangani, Wami/Ruvu)

Outline design was completed except for Dodoma office and extension of Pangani

Basin Water Office in Moshi and rehabilitation of Nyumba ya Mungu sub-

office.

Rehabilitation and construction of Basin Water Offices and Water Laboratories for Zone-

Three (IDB, Tanganyika and L. Victoria)

Outline design has been completed except for Mwanza Laboratory and Lake Victoria Basin

Water Office. All the procedures are completed for Tukuyu HQ offices’ plot in Nyasa Basin.

Preliminary plans and designs are completed. Plans and designs for HQ Offices were approved

and tendered. Njombe office awaits compensation.

Page 17: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

9

3.1.2 Integrated River/Lake Basin Management & Development Plans

The planned activities for the F/Y 2009/10 under this sub-component were as follows:-

(i) To negotiate and sign contract with consultant for preparation of Integrated Water Resources Management and Development Plans for Rufiji Basin;

(ii) To negotiate and sign contract with consultant for preparation of Integrated Water Resources Management and Development Plans Internal Drainage Basin;

(iii) To prepare Term of Reference (ToR) and Expression of Interest (EoI) for preparation of IWRMD plan for Pangani Basin;

(iv) To prepare ToR and EoI for preparation of IWRMD plan for Lake Rukwa Basin, Ruvuma Basin, Nyasa Basin and Tanganyika Basin;

(v) To prepare EoI and RFP for IWRM&D plans in Wami/Ruvu Basin. The status of implementation of different activities falling under this category is summarized

below:-

(i) The contract to engage a consultant in preparation of IWRM plans for Rufiji Basin has

been signed on 17th May, 2010; (ii) The contract to engage a consultant in preparation of IWRM plans for Internal Drainage

Basin was signed on 20th May, 2010; (iii) Evaluation for short listing report for preparation of IWRMD plans for Pangani, Lake

Rukwa, Ruvuma River and Southern Coast, Lake Nyasa and Lake Tanganyika Water Basins approved by Tender Board on 18/06/2010. RFP and ToR have been submitted to the procurement management unit for review. However, due to financial constraints, engagement of consultants for these plans will not be done in this financial year;

(iv) Agreement was reached between Wami/Ruvu Basin Office and JICA that JICA will prepare EoI and RFP for preparation of Basin IWRM&D Plans. JICA proceed with the process of procuring a consultant;

(v) Reviewed ToRs preparation of IWRMD plan for Lake Victoria Basin has been sent to the World Bank for No Objection.

3.1.3 Priority Water Resources Management Infrastructure Investment

The planned activities for the F/Y 2009/10 under this sub-component were as follows:-

(i) To conduct groundwater survey for 15 sites at Magugu in Internal Drainage Basin; (ii) To process and facilitate establishment of Manda Irrigation Scheme by constructing

multipurpose dam structure along Ruhuhu River in Lake Nyasa Basin; (iii) To drill 3 boreholes and install pumps for augmentation of dry season in Pangani Basin; (iv) To procure consultant to carry out studies and designs of Kikuletwa River floods

management in Pangani Basin; (v) To procure consultant to carry out studies on water resources potential in Mount

Kilimanjaro-Lake Chala and Lake Jipe system;

Page 18: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

10

(vi) To procure consultant to carry out studies and design on the improvement of different water uses in Himo River Catchment;

(vii) To procure consultant to carry out studies and design of water resources assessment in Magereza-Ngaramtoni well field, Arusha Town well-field and Lake Duluti;

(viii) To extract and disseminate lesson in Environmental Flow Assessment for increased understanding of environmental, economic and social implications in Pangani Basin;

(ix) To conduct vulnerable assessment of climate change adaptation; (x) To conduct detailed survey and procure consultant services for design of Ndembera

Dam; (xi) To conduct environmental impact assessment for drilling of 3 production wells in

Usangu; (xii) To procure consultant for design and supervise the drilling works in Rufiji Basin; (xiii) To improve diversion works on the Lukosi River in Rufiji Basin; (xiv) To collect data for development of ToR and EoI for Mwamapuli and Kakese Water

Resources Management in Ruvuma Basin; (xv) To conduct study and design for construction of a dam in Kwimba District for the

purpose of water supply in Ngudu Town; and (xvi) To prepare catchment strategy for Kizinga River Management.

Status of Priority investments for each Basin Water offices is shown in Table 1 below:

Table 1: Status of Priority Investments

No. Basin Implementation Status

1. Pangani Basin Tender Documents for drilling of thirty (30) exploratory and

production boreholes in Hai and Rombo Districts were evaluated.

2. Rufiji Basin Detailed Survey for Ndembera dam was completed. The Expression

of Interest has been advertised for the feasibility study and design of

the dam as well as Social and Environmental studies. The EoI has

been opened and evaluated.

Tender documents for procuring a consultant to carry out

Environmental Impact Assessment for Drilling of 3 production wells

in Usangu has been prepared and submitted to the World Bank for

no objection. Groundwater survey has been completed in the Nine

Villages

ToR for procuring a consultant to carry out Environmental Impact

Assessment for Training of Great Ruaha river at Ukwavila has been

prepared and submitted to MoWI for comments.

3. Lake Rukwa

Basin

Pre- feasibility studies have been carried out for Mwamapuli and

Kasese water resources management. This activity will be conducted

in the preparation of IWRM&D plans.

Page 19: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

11

No. Basin Implementation Status

4. Wami/Ruvu

Basin

The Basin Water Office participated in the development of Kimbiji

well field and its demarcation, evaluation of Consultants for detailed

study of Kimbiji/Mpera Aquifers for sustainability, evaluation of

Consultants for supervision of Kimbiji/Mpera aquifer development

and design review and evaluation of borehole drilling in Kimbiji and

Mpera conducted in collaboration with DAWASA. Situation Analysis

report for formulation of Management strategy and implementation

of the Water Resources Management in Kizinga catchments was

completed.

5 Internal

Drainage Basin.

Study and assessment of dams with capacities over 50,000m3 is

completed. 100 dams have been assessed and it was found that 18

dams need rehabilitation and ToR has been prepared

N.B Due to shortage of funds, only drilling of thirty (30) exploratory and production boreholes

in Hai and Rombo Districts will be executed in this financial year and other priority investments

will have to be dropped.

3.1.4 Water Quality Compliance and Strengthening Water Laboratories

The planned activities for the F/Y 2009/10 under this sub-component were as follows:-

(i) To collect and analyze 3,500 fresh water samples from different water sources;

(ii) Collect and analyze 300 wastewater samples from municipals and industries;

(iii) To evaluate usage of the existing data;

(iv) Rehabilitation and furnish water laboratory buildings;

(v) Purchase and install laboratory equipment and instruments for 16 water laboratories;

and

(vi) Purchase of laboratory chemicals and reagents for 16 water laboratories.

The status of implementation of different activities falling under this category is summarized as

follows:-

(i) A total of 3,655 water samples out of 3,500 targeted were collected from different

water sources including wells, rivers, springs and lakes and analyzed for physical-chemical and bacteriological tests. 3,456 samples (94.6%) were found to be within the required standards. A total of 60 monitoring water points have been identified in Dar es Salaam.

Page 20: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

12

(ii) In order to ensure the effluents discharged to the receiving water bodies are within the allowable limit, 302 of 300 targeted wastewater samples were collected from urban centres stabilization ponds and analyzed 280 (92.7%) were found to be within the required standard.

(iii) In order to ensure that the chemicals used for water treatment were within the required standards a total of 34 samples of chemicals were analyzed and the results showed that, the chemicals had the required quality. The chemicals analyzed were Aluminum Sulphate (15) and Calcium Hypochlorite (19).

3.1.5 Planned and Implemented Activities by the DWR – National Level

This section presents activities carried out at the headquarters of Water Resources Division in achieving the WSDP targets. The next subsections describe the planned activities and their status of implementation:- The following are planned activities:- (i) Strengthening of the Dam Safety Unit; (ii) Water Resources Monitoring, Assessment and Enforcement; (iii) Establishing and strengthening Basin Water Offices; (iv) Environmental and social management; and (v) Lake Victoria Environment Management Project. Status of Implementation for activities under this category is as follows:- (i) Strengthening of the Dam Safety Unit

Visual Evaluation/Inventory of dams Total of 641 dams were evaluated in Lake Victoria, Lake Tanganyika, Wami/Ruvu, Internal Drainage, Pangani, Rufiji and Ruvuma and Southern Coast. Most of them found to have problems in the: embankment settlement comprising leakage, erosion of crest, upstream and downstream slopes, availability of holes and bushes; spillway comprising concrete crest weir, bottom disposition and presence of bushes; On the reservoir comprising retention capacity and floating weeds were evaluated. For the dam inventory; dam location, water use for the dam, dam type, size of the dam (embankment, spillway and reservoir), construction materials used and spillway type were identified. Generally observation for the visual evaluation and dam inventory can be summarized as:- (a) More than 80% of the dams are Homogenous (Earth fill dams) and are poorly

constructed; (b) Most of the dams experience embankment settlements especially in Wami/Ruvu Basin

(70%);

Page 21: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

13

(c) Most of the dams are in bushes so they hinder access e.g. Ruvuma and Southern Coast Rivers Basin 43% of the dams are in bushes, Wami/Ruvu Basin (68%) and Lake Victoria Basin (78%);

(d) Most of the dams have anthills and holes: Ruvuma and Southern Coast Rivers Basin 42%, Wami Ruvu Basin (25%) and Lake Victoria Basin (84%). This could be one reason for failure of some of these dams;

(e) Some of the dams are broken;Ruvuma and Southern Coast Rivers Basin (3 dams) are broken, Wami Ruvu Basin (8 dams) and Lake Victoria Basin (13 dams);

(f) Leakage and inadequate spillway is a general problem to all visited dams.

Implemented activities towards dams rehabilitation and construction The identified dams were classified according to their risk potential based on height and reservoir capacity. Most of the dams found to require extensive rehabilitation. Due to the financial constraints, prioritization of the activities towards rehabilitation was done. In that respect, the following has been done in this financial year:- (a) Location maps for risks dams with ≥50,000 m3 prepared by using GIS program; (b) Design and Preparation of ToR and RFP for Farkwa and Lugoda (Ndembera) dams has

been completed and submitted; (c) Topographical survey, designs and preparation of engineering drawings, review of bills

of Quantities and preparation of tender Documents for rehabilitation of 19 prioritized dams in the Internal Drainage (18) and Lake Victoria (1) Basin has been completed;

(d) Preparation of Quick Economic Evaluation for 20 risks dams (>1,000,000 m3) has been conducted. Quick economic evaluation for 20 risks dams revealed that 10 (Mtera, Mchira, Songwa, Nyumba ya Mungu, Mindu, Kalimawe, Mwamapuli, Kidatu, Nhumbu and Mariadi) fall under category Very High A;

(e) Inventory and Visual Evaluation of Tailing dams was carried out in 9 mines of Williamson Diamond Limited (Shinyanga District), El-Hillal Diamond Limited (Shinyanga), Resolute Gold Mine (Nzega), North Mara Gold Mine (Tarime), Geita Gold Mine (Geita), Tulawaka Gold Mine (Biharamulo), Bulyanhulu Gold Mine (Kahama), Buzwagi Gold Mine (Kahama) and Kiwira Mine and Power Limited (Ileje);

(f) Reconnaissance survey for 11 potential sites for dam constructions was conducted on request of Rombo District (Annex 2). Technical report submitted to the District Executive Director of Rombo District Council. The following recommendations were made: stone masonry or concrete dam structure is proposed for Shia valley in Keni village and Kikelelwa valley in Kikelelwa village; series of Stone masonry or concrete dams/Intakes proposed for Nalemoru valley in Kikelelwa village, Marwe valley in Kisale village, Ungwasi/ Lumi valley in Ushiri village; stone masonry/concrete/earth fill dam proposed for Washi valley in Kirwa and Tarakea valley in Mbomai village.

(g) Maps with dams locations:

A map showing 33 dams under high risk with reservoir capacity greater than one million cubic meters was prepared. (annex 2);

Page 22: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

14

A map showing 14 tailing dams of Williamson Diamond Limited (3), El-Hillal Diamond Limited (1), Resolute Gold Mine (2), North Mara Gold Mine (1), Geita Gold Mine (2) Tulawaka Gold Mine (1), Bulyanhulu Gold Mine (1), Buzwagi Gold Mine (1) and Kiwira Coal and Power Limited (2) was prepared (annex 2).

(ii) Strengthen the water resources monitoring network, provide support for water

resources protection and conservation in all 9 basins WRMA became law in August 2009. Regulations for WUAs were gazetted in January 2010 and other two Regulations (i.e. procedure for nomination of Board Members Regulation, 2010; GN187 and Water Use, Abstraction and Discharge Regulations, 2010; GN 190) were finalized and gazetted on 21st May, 2010. Regulations for nomination of members for NWB were gazetted on May 21, 2010 through GN. 187. Chairperson position for NWB was advertised and the deadline for submission of applications was June 12, 2010. However, there was no response. The process to nominate the chairperson is ongoing. Meeting for stakeholders to nominate members of the Board will be conducted on July 22-23, 2010. In order to monitor groundwater resources development, drilling permits are issued to the drilling companies adhering to the existing drilling regulations and standards. In this financial year, 19 water drilling permits were issued and 944 drilled boreholes were registered. (iii) Facilitate the establishment and strengthening of WUAs in all 9 basins and promote

water demand management and conservation In order to strengthen roles and functions of the BWO, Basin Water and Water User Associations and participatory basin management, Training manuals from 3 basins (Rufiji, Pangani and Wami-Ruvu) were collected and ToR to review and harmonize the manuals was prepared. Training on Water Resources Management Act was conducted to BWOs’ and DWR’s staff in February 2010. Progress reports for the second quarter was prepared and submitted to PCT. (iv) Environmental and social management A total of 12 EIA reports were reviewed and comments provided to NEMC. Site verification was done on the respective projects .Training on environmental reporting was conducted to BWOs, RS offices, UWSAs’ offices and DWR staff during the reporting year. No objection from WB was issued on Draft Contract, and the Contract is in the process to be finalized for signing. Seven out of 9 basins submitted their proposals of establishment of monitoring stations. The proposed stations were reviewed, gaps identified and advice was given accordingly.

Page 23: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

15

(v) Facilitate the Transboundary water resources management and development The Joint Songwe River Basin Development Project meeting was held in September 2009 Mbeya, Tanzania and in November 2009 Mzuzu, Malawi. The first Regional Lake Nyasa Basin Conservation and Development Project Preparation Meeting was held from 11th – 14th April 2010 in Maputo, Mozambique. Songwe River Trans-boundary Catchment Management Project is on-going by WWF, in Nyasa Basin. A consultative meeting on Lake Tanganyika Trans boundary issues was held at Kalemie in DR Congo.

Strengthening Institutional Capacity for Managing Shared Water and Fisheries Resources

In harmonization of policies, legislations and regulatory standards the project staff Participated in Kisumu in reviewing 10 regional ToRs:- Conducting Water Hyacinth Surveillance and Implementing Management Strategy for Lake Victoria Basin; Developing regional standards for industrial and municipal effluent discharges into sewerage and river systems; Developing SLM strategy for Lake Victoria Basin; Review and Harmonize the National Policies, Legal and Institutional Frameworks Governing Utilization of Water Resources in the Lake Victoria Basin; Developing Lake Victoria Basin Decision Support System (LVBDSS) for The Lake Victoria Basin; Developing Water Resources Monitoring and Information system (WRMIS) for surface water, ground water and water quality including a GIS based database for the land use, Hydrology and biodiversity in the Lake Victoria Basin; Atmospheric Deposition Monitoring (ADM) Network in the Lake Victoria basin; To establish the Lake Victoria environmental trust fund (LVETF); Review and harmonize the Regional policies, legal and institutional frameworks governing utilization of fisheries resources in the Lake Victoria Basin; Development of Regional Integrated Water Resources Management Plan (RIWMP) For The Lake Victoria Basin. During the period under review the project conducted expert’s workshop in Mwanza to establish monitoring procedures and action plans for forest cover, water quality, crop production, wetlands, water hyacinth, atmospheric deposition, effluent discharges, fish stock and noxious weed; Training of data collectors at water hyacinth hotspot areas has been conducted at 6 villages in Kagera Region. In each training centre 3 members of BMUs were trained; Action plan and budget to collect data in priority catchments area for Monitoring of forest cover, regeneration, damage, biodiversity and Data Collection has been developed. In order to monitor P and N nutrients, samples from treatment sites in Mwanza Region were collected and analyzed; Hydrological data were collected from Mwanza, Kagera and Mara Regions for monitoring purposes; In order to promote Research, workshop on research topics prioritization was conducted for implementing institutions and research experts held in Kibaha, Coast Region.

Page 24: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

16

Point Sources Pollution Control and Prevention This component aims at reducing environmental stresses within the lake and its littoral zone, through the rehabilitation of priority wastewater treatment facilities, promotion of industrial cleaner production technologies, installation of the lake navigation equipment, and implementation of a contingency plan for the oil spills and hazardous wastes management in the Lake Victoria basin. During the period under review, nine (9) ToRs for engaging consultancy for Rehabilitation of wastewater treatment facilities have been prepared ready for further procurement steps. The project held consultation meetings with LVBC, SUMATRA, TPA on Pollution risks management and safety of navigation.

Watershed Management This component seeks to reduce environmental stresses from the lake basin through implementation of sustainable soil and water management practices and livelihoods improvement interventions, using community-driven development approaches, to improve water use efficiency in the Lake Victoria basin and generate positive externalities to downstream countries. The following has been done; the abandoned Buhemba Gold Mine in Musoma was inspected and found to be insecure. The TSF is freely accessed by animals and people, the open pits have been encroached by artisan miners who use mercury for gold amalgamation. The toxic chemicals used for gold extraction such as lead nitrate are left in unlocked containers. Industries have been visited and given data sheet to fill in.

Preparation of Terms of Reference (ToR) for various consultancies The following has been done:- Preparation of ToRs for engaging consultancy services to Review guidelines, standards and procedures for governance of fisheries was prepared; Draft ToRs for synthesizing and apply research information gathered during LVEMP I was prepared. Also, ToRs for engaging consultancy services were prepared on ‘Synthesize and apply research information gathered during LVEMP I’, 'Procurement of field vehicles’, ‘Procurement of motorcycles’, ‘procurement of office equipment, furniture and supplies’ and ‘Develop water hyacinth management plan’; Consultative meeting with fisheries experts were held to seek clarifications on fish levy, surveillance, framework surveys and harmonization of political and regulatory standards. Detailed engineers estimates carried out for rehabilitation of Bukoba Laboratory and adverts for specific procurement have been prepared; Terms of References for engaging consultants to develop training modules for environmental and social economic impact of LVB and preparation, implementation, monitoring and evaluation of CDD projects were initiated; Terms of reference for engaging consultancy in implementing environmental awareness programs to communities using Local NGOs and CBOs and prepare inventory of all available data and information on LVBD was initiated; ToRs for engaging a consultancy on designing project website was initiated.

Page 25: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

17

Project Coordination and Management The objective of this component is to facilitate the effective coordination, communication, monitoring and evaluation of project activities by the National Project Coordination Team (NPCT) and Establish an integrated project M&E System for planning and management decision making and which will periodically be updated. The following has been done in this quarter. Staff participated in commemoration (World wetlands Day (WWD) 2nd Feb 2010), Workshops, Meetings (with TASAF, DASIP, NTACT, NSPC and LGAs), Familiarization Visits, Collaboration Consultative forum; Conduct media campaigns through newspaper, TV, radio talk shows public dialogue, Production of materials such as posters, flyers fact sheets - A total of 220 Project brochure/flyers were disseminated to participants at Musoma and Shinyanga workshops and general public.

3.2 COMPONENT 2: SCALING UP OF RURAL WATER SUPPLY AND SANITATION

During the period of F/Y 2009/2010, the implementation of sub projects carried out by the LGAs that could not manage to complete the implementation of sub projects as planned for F/Y 2008/2009. Implementation of sub-projects involved sensitization of the communities on sanitation and hygiene, construction of demonstration latrines, construction and rehabilitation of small scale water facilities. 123 LGAs are implementing large scale schemes which involve consultants for provision of technical and facilitation services in their areas. For the remaining 8 LGAs full swing implementation will start after completing procurement of consultants.

The following are summaries of progress achieved in the implementation of planned activities

in the RWSS. The implementation of sub projects is divided into two parts namely:-

(i) Management support to LGAs; and (ii) Rural Water Supply and Sanitation Investments.

3.2.1 Progress on Management Support to LGAs

Planned Activities for FY 2009/2010 under this category:- (i) Coordinating procurement of vehicles for LGAs for supervision of water supply projects; (ii) Procurement of computers and its accessories for LGAs; (iii) Prepare, disseminate guideline and provide specifications for establishing/improving

MIS for community water supply division and coordinating establishment/improvement of MIS for LGAs;

(iv) Training on sanitation and hygiene in communities; (v) Prepare and disseminate guidelines for rain water harvesting; (vi) Developing innovation window for programme application and facilitating

establishment of hand pump supply chain; (vii) Provision of consultancy service for water point mapping in LGAs; and (viii) Procurement of Programme Management Support Consultant (PMSC) for CWSD. Status of implementation for Management support to LGAs:

Page 26: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

18

(i) 67 vehicles were procured and delivered to 67 LGAs; (ii) 132 printers and 132 scanners delivered to all LGAs; (iii) ToR for engaging a consultant to harmonize rural water supply databases was prepared.

The consultant was engaged in March 2010 and task carried out by consultant identified by GTZ support project office. The first database had been developed by GTZ support project office, while the second had been developed in the RWSSP pilot project funded by WB (year 2002 – June 2008);

(iv) 20 artisans were trained on construction of improved latrines, 2 demonstration latrines were constructed at Mwenda pole grounds and at the market area in Kibaha TC during commemoration of Maji Week;

(v) RFP issued to shortlisted consultants and will be submitted to MoWI on 15th May 2010. The consultant to be engaged shall prepare guidelines on rain water harvesting;

(vi) No objection for inviting consultant to submit proposal for innovation window sub projects has been secured. Also No objection for advertising EoI for suppliers to establish centers for hand pumps and spare parts supply chain has been secured;

(vii) Evaluation of EoI for consultants for water point mapping was done whereby consulting firms have been shortlisted. The short list of consultants has been sent to WB for no objection;

(viii) RFP for procurement of PMSC issued to 6 shortlisted consultants and will be submitted to MoWI on 15th May 2010.

3.2.2 Progress on Rural Water Supply and Sanitation Investments

Planned activities for FY 2009/2010: (i) Construction of 729 sub projects and rehabilitation of 463 sub projects which includes

shallow wells/boreholes, piped water supply schemes, charco dams and rain water harvesting systems;

(ii) Construction of 4,279 water points and rehabilitation of 1,447 water points; (iii) Construction of 41 offices for LGA Water Departments and rehabilitation of 5 offices for

LGA Water Departments; (iv) Planned activities for earmarked projects. Implementation status for FY 2009/2010: (i) 456 sub projects were constructed and 381 sub projects were rehabilitated (ii) 1,632 water points were built and 1,368 were rehabilitated. Out of 3,000 water points

built/rehabilitated 2,341 are functioning and enough to serve an equivalent of 585,250 people with clean and safe water

(iii) Awareness of people on sanitation and hygiene education carried out in which 1,219,416 people were sensitized;

(iv) 1,027 demonstration latrines were constructed; (v) 2,652 artisans were trained on construction of sanplats and low cost sanitary toilets (vi) 17,133 school sanitation clubs were formed (vii) 4,908 sanplats were produced (viii) 25 water department offices for LGAs were constructed and 2 offices rehabilitated

Page 27: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

19

(ix) Implementation for earmarked projects:- Masoko water supply project 1. Contractor Procured 2. Route establishment and mobilization of materials in progress. Mwakaleli I Contractor Procured Mwakaleli II Kapondelo water supply scheme 1. Camp established at Kandete Township 2. Intake constructed 3. Tank Foundation cast 4. Pipe laid 3000m 5. Trench excavated by 4700m Malyasi Water Supply Project 1 Camp established at Bumbigi village 2. Intake has been constructed 3. 120m3 storage tank constructed. 4. 5000m of trench excavated Kalinga Water Supply Project 1. Contractor procured 2. Mobilization completed 3. Route establishment completed 4. Tank bottom slab cast constructed 5. Tank wall reinforcements fixed 6. 12,000m of trench excavated. Nyandege Water Supply Project 1. Contractor procured 2. Mobilization completed 3. Route establishment in progress 4. Construction of 12 DPs completed and 22 are in finishing stage 5. 10,000m of trench have been excavated 6. Tank (500m3) foundation excavated 7. Materials gathered at site 40m3 aggregates and 30m3 sand Kakonko water supply project 1. Design report from consultant reviewed 2. Tender for procurement of contractor advertised

Page 28: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

20

Milola water supply project 1. Pipes, fittings and building materials procured 2. 18 metres of gravity main rehabilitated Mputwa water supply project Inventory for rehabilitation for the scheme is done Iwungilo water supply project Transmission main 14.9 km of pipe networks laid, pipes and fittings, water committee and water funds established, construction of 2 storage tanks of 50,000 liters capacity in progress Kidete water supply project Contract signed in January, 2010 and site possession has been done Monduli and Longido water supply project Part debt payment to contractor (November 2009). Same – Mwanga and Korogwe Water Supply projects 1. Feasibility study report submitted. 2. Draft design report submitted. 3. Final design report submitted. 4. RFP for consultant who will review final design report, tender documents and supervise construction of phase I has been prepared Mwanza and Mara Water Supply Projects Construction of 34 boreholes and construction of 34 platforms with hand pumps has been completed Coast and Dar es Salaam Peri-urban Water Supply Projects Project was completed in 15th March 2010 and handed over to the community Tabora Water Supply Project 1. Social and economic impact assessment in all districts of Tabora have been conducted 2. Ground water quality was assessed 3. Rural water supply and sanitation plans was prepared 4. Detailed ground water survey is in progress Hai Water Supply Project (Machame, Mkalama and Levishi Water Supply Projects) Machame water supply project 1. 38 DPs was constructed out of 116 planned to constructed (32.76%) 2. 5.779 km pipe were layed which makes pipe work completion by 99%

Page 29: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

21

Mkalama Water Supply Project 1. Construction of intake and fence was completed 2. Rehabilitation of intake was completed 3. 6.646 km excavation of trench has been completed 4. Pipes laid 2kms Levish water supply project Construction of the project was completed by 100%

West Kilimanjaro water supply scheme 1. 5.619 km excavation of trench has been completed; 2. Pipes laid 0.81 km pipe which makes pipe work completion by 5%. Moshi Rural water supply project Construction of 3 intakes has been completed and the construction of 2 intakes is in

progress (85%); Construction of 5 storage tanks ranging from 20m3 to 150m3 in progress (65%); Construction of 10 BPs have been completed; Pipes laid 20 kms; Construction of 9 HC was completed. Implementation status for Dams Excavation of spillway: Masuguru, Mti Mmoja, Sasajila, Kawa, Salamakati, Ingodin, Nyambori, Mwanjoro and Bulenya (100%), Wegero (40%) and Matwiga (85%) Excavation of core trench: Mti Mmoja, Sasajila, Kawa, Ingodin, Matwiga, Salamakati, Nyambori, Bulenya,Wegero, Habiya and Mwanjoro (100%), Seke Ididi (95%) and Iguluba (50%).

Filling and compaction of core trench with clay soil: Masuguru, Mti Mmoja, Sasajila, Ingodin, Matwiga, Salamakati, Wegero and Nyambori (100%), Habiya(65%) and Seke –Ididi (95%) Filling and compaction of embankment with clay soil: Masuguru, Mti Mmoja, Ingodin, Salamakati, and Bulenya (100%), Sasajila (60%), Matwiga (20%) and Nyambori (35%) Stone pitching upstream of the embankment: Masuguru, Mti Mmoja, Ingondin and Bulenya (100%) Excavation of reservoir: Wegero and Ingodin (100%)

Page 30: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

22

Construction of inlet/out let chamber: Masuguru, Mti Mmoja and Ingondin (100%) and Salamakati (80%) (ii) Completion of the construction of 4 dams: Nyambele (Bunda) and Kinyambwiga (Bunda), Nyashitanda (Misungwi) and New Sola (Maswa) Nyambele: Excavation, filling and compaction of core trench with clay soil have been completed by 100%. Excavation of spill way has been completed by 100%. Filling and compaction of embankment with clay soil was completed by 100%. Construction of intake/out let chamber was completed by 100%. Stone pitching was completed by 50%. Kinyambwiga: Construction of the dam was completed since last FY 2008/2009 but during the period of defect liability period DPs, Cattle trough and valve got defects. The contractor is still working to rectify the defects. New Sola: Construction of the dam has been completed since last FY 2008/2009. The work remained is construction of cut - off wall. Contractor has already reminded to complete the work. Nyashitanda:

Construction of the dam has been completed to 97%. The remaining works are construction of cattle trough, 1 DP and inlet/outlet pipe. Contractor has already reminded to complete.

Table 2 and Annex B2 show numbers of the planned and implemented sub projects with percentage for April - June 2010 and F/Y 2009/2010.

3.3 COMPONENT 3: SCALING UP URBAN WATER SUPPLY AND SANITATION

This component comprises of Dar es Salaam Water and Sewerage Authority (DAWASA), 19 Urban Water Supply and Sewerage Authorities (UWSAs) and 106 District capital and small towns water utilities. The components also include 7 National Water Supply projects (NPs) of Wanging’ombe, HTM, Makonde, Maswa, Chalinze, Mugango-Kiabakari and KASHWASA. All authorities are monitored, regulated and supported by the Ministry of Water and Irrigation (MoWI) under the Commercial Water Supply and Sewerage Division as well as EWURA. The planned activities implemented during the financial year 2009/2010 were in the following sub components:-

1. Management Support to UWSS Utilities; and 2. Urban WSS Capital Investment.

Page 31: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

23

3.3.1 Progress on Management support to UWSS Utilities

The planned activities under management support were grouped in the following key areas:- (i) Rehabilitation and construction of new offices in UWSAs and DUWSAs; (ii) Provision of capacity building supports to UWSAs, DUWSAs, national water supply

projects and small towns by procurement of Goods (Vehicles, Motorcycles, Computers and accessories);

(iii) Carry out studies and designs of Urban Water Supply and Sewerage systems in all UWSAs and their respective DUWSAs;

(iv) Provision of financial support for incremental costs (purchasing of fuel, office management facilities and facilitating site/field supervision to all UWSAs.

The key achievements in the implementation of the planned activities in this sub-component

are outlined below:-

(i) Rehabilitation and construction of office buildings Construction of new office in Sumbawanga UWSAs, Consultant has finalized draft detail designs, tender document and specifications; Construction of new office in Babati UWSAs, Procurement of a contractor for construction of office has been concluded; Contract of works is expected to be signed in July 2010; Musoma UWSAs has rehabilitated the office from the own source; Other UWSAs of Bukoba, Kigoma, Iringa, Lindi, Shinyanga and Singida are processing title deeds. Kilwa Masoko and Tunduma DUWSAs have already submitted the offer for the land on which they can construct the offices. (ii) Provide capacity building supports to UWSAs, DUWSAs, national water supply

schemes and small towns: Procurement of Goods (Vehicles, Motorcycles, Computers and accessories)

10 vehicles (5 Pick - up double cabins and 5 land cruisers) for eight DUWSAs of (Kilwa Masoko, Makete, Urambo, Vwawa, Misungwi, Igunga, Bariadi and Bunda) as well as two National Projects of Makonde and HTM have been purchased and delivered to respective utilities. 42 sets of office facilities have been purchased and delivered to 42 DUWSAs. Each set consist of (1) Desktop computer, (1) printer and (1) UPS. (iii) The summary of status of studies and designs in the UWSAs, small towns and National

Projects is summarized in the table below:- Table 2: Summary of studies and designs in the UWSAs, Small Towns, and National Projects

TOWNS STATUS

Group 1 (Bukoba, Musoma, Mtwara, Lindi, Kigoma, Sumbawanga and Babati)

Studies, design and preparation of Tender documents in towns of Bukoba and Musoma were completed under financing from AFD.

ACP/EU Water Facility Upgrading Program for Seven Towns The procurement of consultant has been concluded and the

Page 32: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

24

consultant has started assignment on 1st June 2010. The consultant will carry out feasibility studies and preparation of tender documents for water supply and sewerage works in towns of Bukoba, Babati, Lindi, Sumbawanga, Mtwara, Musoma and Kigoma.

Supervision of works on going at the towns of Bahati, Lindi, Mtwara and Sumbawanga.

Group 2 (Morogoro and Tabora)

Draft detailed study report for water supply and sewerage system for Morogoro Municipality was submitted.

Final detailed report and tender documents for Tabora Municipality and the Draft tender documents for Sikonge and Urambo town ships was submitted.

Group 3 (Arusha, Dodoma, Moshi and Tanga)

Detailed study report in Arusha municipality was submitted.

Studies and designs for Dodoma municipality are completed.

The consultant submitted Draft Detailed Design for immediate works and for each phase of the project, Contract Bidding documents and Specifications for Tanga city.

The consultant has submitted preliminary detailed design and tender documents for Moshi Municipality

Group 4 (Mbeya, Mwanza, Iringa, Songea, Shinyanga and Singida)

Consultant procured and Inception report was submitted for Mwanza, Iringa and Songea.

The consultant has submitted final design report for Shinyanga.

Contract was signed for Mbeya on 3rd June 2010.

Group 5 (Small towns and NPs)

The towns which design and preparation of tender documents have been completed are towns of Urambo and Sikonge in Tabora region, Karatu, Katesh and Orkesumet in Manyara region, Kilwa Masoko in Lindi region, Same and Mwanga in Kilimanjaro, Kahama, Ushirombo and Maswa townships in Shinyanga.

The towns which are in mid stages of design and preparation of tender documents are towns of Loliondo and Wasso in Arusha region, Pangani and Muheza in Tanga.

The towns which have just started studies, design and preparation of tender documents are towns of Mbinga, Namtumbo and Tunduru in Ruvuma, Sengerema, Geita, Magu, Nansio and Misungwi in Mwanza, Chunya, Rujewa, Vwawa, Kasumulu, Mbalizi, Kyela, Tunduma, Mlowo, Tukuyu and Itumba in Mbeya and Kilolo, Makambako, Njombe, Makete, Mafinga and Wanging’ombe in Iringa.

Procurement of consultant for feasibility study for Makonde and HTM national projects under GTZ has been concluded and consultant has started mobilization.

Page 33: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

25

The small towns under Bukoba, Singida, Sumbawanga and Tanga. Consultants will be procured and start work during the 1st phase of WSDP.

The remaining towns to be covered during the 2nd phase of WSDP.

Page 34: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

26

(iv) Training: Professional training in the field of IFRs were conducted in all UWSAs, 10 DUWSAs and 7 National projects.

All UWSAs were trained and prepared capacity development as well as National projects of Chalinze and KASHWASA and Korogwe DUWSA. Training on preparation of CD plan for remaining National Project and 47 DUWSAs and 10 small towns will be implemented through capacity building for regional and district water supply and sewerage authorities under GTZ before September 2009.

3.3.2 Progress on Urban WSS Capital Investments

The planned activities under capital investment were mainly grouped in the following areas:- (i) Completion of Dar es salaam Water Supply and Sanitation program (DWSSP); (ii) Continue with ongoing construction works in Tabora and Dodoma funded by SECO,

Singida Water Supply Improvement Project funded by BADEA, Mwanza, Iringa and Mbeya towns Water Supply projects funded by EU and KfW, Chalinze Water Supply Project Phase II (Package F and H) funded by BADEA and package J funded by Chinese government;

(iii) Implementation of Dar es salaam and Morogoro water supply projects through MCC funds;

(iv) Construction and expansion of water supply system for Babati, Mtwara, Masasi, Nachingwea, Lindi and Sumbawanga towns;

(v) Support immediate works to improve water supply services of 7 national water supply projects;

(vi) Improve water supply systems in the towns of Misungwi, Igunga, Bariadi, Bunda, Mugumu, Ikwiriri, Kibiti, Utete, Mpwapwa, Turiani, Mvomero, Kilosa, and Gairo;

(vii) Customer connection for Kahama and Shinyanga towns in Lake Victoria - Kahama/Shinyanga Water Supply project.

The Summary on the status of implementation of Urban WSS Capital Investment under WSDP for financial year 2009/2010 is described below and detailed out in Annex I. (i) Dar es Salaam WSS Capital Investments The component continues with improvement of water supply services in the city of Dar es Salaam through improvement of water production at Lower Ruvu waterworks and improvement of water supply services under DWSSP. (a) Consultancy

Construction of Kidunda dam: Consultant for Feasibility Study, detailed design and preparation of tender document has been procured and the contract was signed on 8th February 2010. Starting of the assignment is delayed due to delay in payment of the consultant advance payment.

Page 35: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

27

Development of Kimbiji and Mpera groundwater for Dar es Salaam Water Supply: Consultants submitted their proposals on 3rd May 2010, and evaluation report submitted to WB for No Objection.

(b) On-going projects (Under MCC)

Expansion of Lower Ruvu (WTP) The Consultant submitted the Draft Tender Documents, Final ESIA report and Final Design report. Pre-qualification exercise has been completed and bids issued to prequalified bidders. The preparation of RFP for procurement of the Construction Supervisor is completed and consultant will submit proposal on 16th August 2010.

Contract for detailed design of a new parallel 55 km transmission main pipe from Lower Ruvu Treatment Plant to University Reservoirs was signed on 5th May 2010 and the assignment commenced on 20th May 2010.

Rehabilitation of Morogoro Water Supply System The Consultant submitted the Draft Tender Documents, Final ESIA report and Final Design report. Pre-qualification exercise has been completed and bids issued to prequalified bidders. The preparation of RFP for procurement of the Construction Supervisor is ongoing.

Reduction of Non Revenue Water (NRW) Baseline Study and Preparation of Technical Specification for Performance Based Contract for the NRW. Proposals were submitted on February 2010 and evaluation was completed in March 2010. Contract negotiations between MCA-T and the selected Consultant held on May 18, 2010 and the Contract has been prepared. NRW Construction Works (Construction of Secondary and Tertiary distribution system at Tegeta to Bagamoyo-Part 2) The consultant working on the preparation of designs and tender documents has submitted the Final Design Report and Tender Documents for review. The procurement process of contractors for NRW works commenced. MCC has dropped this project and it will be financed under WSDP Basket Fund.

Programme Coordination and Technical Assistance to DAWASA, DAWASCO and MORUWASA The consultant has submitted the Inception report, Baseline Capability Assessment report, Asset Management report, Billing and Revenue Collection report and Tariff report for MORUWASA. The base period of this contract will end after 18 months. Depending on consultant performance the option 1 & 2 of the assignment will be exercised. The Consultant will also supervise the implementation of NRW works.

(c) On-going projects (Under DWSSP)

Page 36: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

28

Supply and Installation of Infill Mains and customer connections Part2A, Part 2C, Part 2E (Kibaha town, Kwa Matiasi, and Kongowe, Visiga Mlandizi areas) were all completed and the contractors are in defects liability period. Supply and Installation of Infill Mains and customer connections and district metering (Part 3&4) Part 3A (Bulk metering in the whole network within DSM): Part 3B (installation of infill main and customer connection): Part 3C (installation of infill main and customer connection): were all completed. A total of 70 bulk meters were installed, 40 kiosks were constructed, 31 public stand points were installed and 13,328 customers were connected, (d) Community water supply and sanitation systems in peri urban and low income settlements of Dar es salaam project under BTC The project aims at improving the living condition of the communities in peri urban low income settlements of Dar es Salaam city. The expected results and the status of implementation is outlined below:- Result 1 60 water supply systems in the selected peri urban and low income areas are designed and installed: Design reports together with the tender documents is expected to be submitted on the 31st August 2010. Twenty test boreholes have been drilled. Result 2 Hygiene practices and pilot sanitation facilities and services in the selected peri urban and low income areas are improved in a sustainable manner: Three consultancy companies for the three municipals were hired. Three advocacy workshops were held in the three municipalities. The workshops were meant to create awareness on water and sanitation practices and on the relation between water, a sound environment and health and training of communities on fundamental hygiene practices. Result 3 Comunity Owned Water Supply and Sanitation Organization (COWSSO) are trained to manage, operate and maintain the water supply and sanitation facilities and services in an efficient, transparent and sustainable manner and are accountable to the users: the consultant has produced final report on the best available practice on sanitation facilities, water and sanitation services for Dar es salaam and design efficient and effective management structures on local level. Result 4 Innovative models of O&M by COWSSO and innovative technical options for water and sanitation infrastrucuture and services are documented and disseminated on city, national and international levels and information water supply and sanitation policies and Integrated water resources management (IWRM) are dissemninated on local level:

Page 37: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

29

(ii) Group One Towns (Babati, Lindi, Mtwara, Kigoma, Musoma, Bukoba and Sumbawanga)

Sumbawanga: Construction works to improve water supply systems which involves drilling of 10 New Boreholes plus power Supply and Collector mains and rehabilitation works which include:-

The supply and installation of approximately 46.2km of distribution pipe works.

The replacement of short sections of the existing transmission mains.

The replacement/installation of New valves in the distribution system.

The supply and installation of consumer and Bulk flow water meters.

Provision of chlorine dosing equipments to treat ground water. The progress of works is at 50% for drilling and 28% for rehabilitation works. Mtwara: Construction works to improve water supply systems which involves rehabilitation of existing well field, refurbishment of Mtawanya booster pumping station and transmission main, Limited works at Mangamba treatment plant, providing minor extension to the existing network. The progress of works is at 45%. Babati: Immediate construction works to improve water supply systems which involves Drilling of 10 boreholes, Construction of three storage tank, Construction of treatment plant, laying of transmission and distribution pipeline. The general progress of wok is at 90% for drilling and 45.2% for civil works. Lindi: Immediate construction works to improve water supply systems which involves Supply and installation of approximately 47 Km. Pipeworks (50mm to 250mm diameters), Procurement of power supply to Kitunda well fields, Construction of 680m3 storage tank at Kitunda, Construction of 4 no break pressure tanks, Supply and installation of 380 consumer and bulk meters, Supply 2,650 domestic meters to be installed by LUWASA, Replacement of two booster pumps and development of Kitunda wells. The general progress of wok is 50%. (iii) Group Two Towns (Morogoro and Tabora) Tabora: Contract for installation of Bulk water meter at Igombe station, zone water meter and construction of meter chambers is 65% completed. (iv) Group Three Towns (Arusha, Dodoma, Moshi and Tanga) Dodoma: Contract for supply and installation of electromagnetic flow meters, manometer, valves and fittings and construction of Reinforced concrete flow meter chambers and valve spindle surface covers is 65% completed. Procurement of contractor for construction works of water supply and sewerage project for University of Dodoma in underway. Most of the works for Arusha and Tanga will be implemented in 2nd phase of WSDP. (v) Group Four Towns (Mbeya, Mwanza, Iringa, Songea, Shinyanga and Singida)

Page 38: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

30

Mwanza: Construction of sewerage system which involves sewer pipelaying, pump station, three oxidation ponds, two sludge settling tanks, and manholes is at 75%. Iringa: Construction of a water treatment plant and associated structures and rehabilitation of existing network is 75% for transmission work, 50% for distribution work and 50% to completion of civil works. Mbeya: The project for Expansion of water supply and sewerage network in Mbeya is at 98% complete for storage tanks, distribution network is at 75%, transmission main is at 80% and construction of intake is at 98%. Singida: Rehabilitation and expansion of water supply continues and it is approximately 12% completed. (vi) Group Five Towns (106 Small towns and 7 National projects) Chalinze: Construction works for Chalinze water supply project phase II (package F&H) continues and it is 22% done. The scope of works include supply and installation of transmission main, construction of 5 ground and 3 elevated reservoirs, supply and installation distribution pipeline and construction of water kiosks. Igunga: Rehabilitation and expansion of phase I water supply is completed. The scope of works included Rehabilitation of gravity mains and civil works from Bulenya dam to Igunga Town (Lot No. IG 13); Rehabilitation of water distribution system and civil works in Igunga Town (Lot No. IG 14); Rehabilitation of gravity mains, water pipe distribution systems and civil works from Igunga Town to the villages of Mbutu, Ibutamisuzi and Hindish (Lot No. IG 15). Construction of water treatment plant, pumping facilities and storage facilities for Igunga Town water supply and related three villages mentioned above is 65% completed. Bunda: Construction of phase I of water supply works is completed; two storage tanks pump house, pump attendant house and access road were constructed. The consultant for Musoma procured under WSDP is expected to design for treatment plant and transmission line from the source to new tanks. The designs are expected to be ready by December 2010. Misungwi: Rehabilitation and expansion of water supply is completed. The scope of works included Supplying of steel pipes and fittings, Installation of pumps, Laying raising main, and Rehabilitation of pumping station, Supplying and installation of electricity line and Rehabilitation of sump well. The Project is expected to be inaugurated in July 2010. Construction/expansion of the distribution system is underway. Mugumu: Construction of water supply in Mugumu was completed and the construction of intake, laying of transmission line, construction of 2 cattle troughs and 12 kiosks, procurement and installation of generator and submersible pump. The Project is expected to be inaugurated in July 2010.

Page 39: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

31

Mpwapwa and Utete: Construction of water supply and sanitation projects is completed. The project cost is Euros.3.5 million. The Project is expected to be inaugurated in July 2010. Population served is 9,335 (Utete) and 50,941 (Mpwapwa) Ikwiriri and Kibiti: Construction of water supply systems are at 60% and 69% respectively. Mvomero, Gairo, Kilosa and Turiani: procurement of contractors has been concluded and Contracts signed for Gairo and Turiani. Contractors for Kilosa and Mvomero have requested for price adjustment. Masasi and Nachingwea: Procurement of conctractor for the project has been concluded. Contracts for work is expected to be signed in July 2010.

(vii) Immediate works to improve water supply services in DUWSAs were implemented in 30 DUWSAs and 3 National projects in FY 2009/2010.

The amount and names of the DUWSAs are Mugumu (Tshs. 802,300,000), Sengerema (Tshs. 362,000,000), Handeni (Tshs. 43,826,200), Kibondo (Tshs. 50,000,000), Kasulu (Tshs. 100,000,000), Mwanga (Tshs. 162,000,000), Mikumi (Tshs. 10,000,000), Kasumulu (Tshs. 90,000,000), Lamadi (Tshs. 20,000,000), Manyoni (Tshs. 300,000,000), Mahenge (Tshs. 200,000,000), Pangani (Tsh 40,000,000), Itumba – Isongole (Tshs 56,000,000), Chiwambo (Tshs 223,000,000), Monduli (Tshs 30,000,000), Kashwasa (Tshs 129,594,458), Kahama (Tshs 160,294,225), Ngudu (Tshs 9,000,000), Handeni Trunk Main (HTM) (Tshs 217,000,000), Mlowo (Tshs 250,000,000), Urambo (Tshs 68,586,800), Chunya (Tshs 50,000,000), Himo (Tshs 100,000,000), Kilindi (Tshs 50,000,000), Tunduma (Tshs 54,000,000), Misungwi (Tshs 730,000,000), Makonde (Tshs 50,000,000), Chato (Tshs 96,000,000), Muheza (Tshs 54,000,000), Bunda (Tshs 182,518,475), Igunga ( Tshs 1,895,447,687), Mwanhunzi (Tshs 99,373,143) and Bariadi (Tshs 539,000,000).

3.4 COMPONENT 4: INSTITUTIONAL STRENGTHENING AND CAPACITY BUILDING

(a) Operationalizing the new role of the Ministry:-

Rehabilitation and construction of offices at Ubungo;

Construct new office at Ubungo (Maji House);

Procurement of vehicles for MoWI, BWOs and Rs;

Procurement of Motorcycle for MoWI, BWOs and Rs;

Procurement of Computers, accessories and other office equipments

Installation of Management Information Systems (MIS) (b) Technical Assistance for Strengthening of Sub-Sector Planning and Operational

Capacities:-

General Programme Management Support (3 contracts - Rural WSS, Urban utilities and WRM);

Page 40: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

32

Development of regulations and Sub-sector operational procedures and guidelines (including environmental management monitoring);

Environmental Management Act (Implementation support project Coordination and Follow up ESMF and (RPF);

Strengthening of Water Resources monitoring, assessment and enforcement – including protection of important water sources; water demand management strengthening legislations and enforcement; integrated water resources planning, trans-boundary water management, and variety of cross cutting activities such as disaster management, public awareness, inter-agency networking and establishing a water resources management information system;

Cross sectoral assistance to strengthen the harmonization and coordination of water resources policy, Institutional responsibilities and plans between the key partner government sector;

Procure Consultant for assessing relevance of MCS;

To construct new Maji Central Stores at compound Boko area DSM. (c) Support to Sector Coordination and Performance Monitoring

Harmonize sector policies strategies and plans;

Support PCT, TWGs, Sector Working Group and CWB;

Facilitate Joint Water Sector review and stakeholders’ consultative meeting;

Monitor Performance of WSDP implementation;

Preparation of Technical and Financial report.

(d) Sector Capacity Building

Train MOWI and RS’s staff;

Perform sector staff augmentation;

Training on Strategic Framework and Guidelines for Capacity Development;

Support for Local Private Sector (Drilling companies, Maintenance supply chains, consulting firms, contractors as well as transformation of the Drilling and Dam Construction Agency;

Support Water Development and Management Institute and other Sector related training Institutions;

Strengthening the Information, Education and Communication Unit;

Educate the general Public stakeholders on how they will participate in water and Irrigation Sectors;

Support NGOs and CBOs; and

Logistical support and Technical assistance to EWURA in regulation Administration.

Page 41: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

33

The Summary of implementation of sub-components under the Component 1 is described below:-

3.4.1 Progress on Operationalizing the new role of the Ministry

Rehabilitation and construction of offices at Ubungo Building Block B: The rehabilitation was completed and handover was done on January, 2010. Rating tank: Rating tank was completed and handover was done on March, 2010. However additional works on IT and AC for block B and Rating tank are expected to be completed in August, 2010.Block H: Extension was completed, handover was done January, 2010. Block K: Rehabilitation was completed; hand-over was done on July 2009. New Toilet block has been completed and handover was done in July, 2010. The Block E and D the rehabilitation is in progress, working drawings waiting for the approval of addendum by the MTB. The overall work completion for phase I of is 72%.

Construct new office at Ubungo (Maji House) The review of inspection report, conceptual master plan, schedule of accommodation and preliminary cost plan was done in March, 2010, while preliminary designs and submitted in June, 2010. Detailed design and Production information is to be completed and submitted for tender action on February, 2010.

Procurement of vehicles for MoWI, BWOs, LGAs and RSs 215 vehicles out of 250 have been procured and delivered to MoWI, Basins, Regional Secretariats, PMO RALG, Zonal Water Laboratories, and LGAs. These include 57 Nissan Station Wagon from DT Dobie, (132) Toyota Land cruiser Hardtop and (39) Toyota Hilux Double Cabin from Toyota Tanzania Ltd. The remaining vehicles, (5) Toyota Hilux D/Cabin and (17) Toyota Land Cruiser Hardtop will be delivered in September, 2010.

Procurement of Motorcycle for MoWI, BWOs and Rs All 407 motorcycles have been procured and delivered to MoWI, BWOs, Regional Secretariats, and LGAs.

Procurement of Computers, accessories and other office equipments The total of (316) units of desktop computers; 113 units of laptops, and accessories, (214) printers, (170) scanners, 16 Units of Digital Projector, (175) Units of Facsimiles, 43 Units of Digital camera; 11 Units of DVD Recorder and Player; 2 Units of TV – 21 Inches; 10 Units of TV – 36 Inches and 10 Units of Satellite Dishes have been procured and delivered to MoWI, Basin Water Offices, LGAs and Regional Secretariats. The remaining office equipments will be delivered in August 2010. These includes (17) units of heavy duty Photocopiers, (112) units of medium duty photocopiers and 1 Unit of Plotter and 2 Units of Digitizer.

Page 42: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

34

Procurement of Computers and other office equipment for MOWI, RSs, LGAs, BWOs, DUWSS

The total of (316) units of desktop computers 113 units of laptops, and accessories, (214) printers, (170) scanners, 16 Units of Digital Projector, (175) Units of Facsimiles, 43 Units of Digital camera; 11 Units of DVD Recorder and Player; 2 Units of TV – 21 Inches; 10 Units of TV – 36 Inches and 10 Units of Satellite Dishes haven procured and delivered to MoWI, Basin Water Offices, LGAs and Regional Secretariats. The remaining office equipments will be delivered in August 2010. These includes (17) units of heavy duty Photocopiers, (112) units of medium duty photocopiers and 1 Unit of Plotter and 2 Units of Digitizer.

Installation of Management Information Systems (MIS) The sector MIS framework is in place. The implementation of the sector Programme management information system is in progress whereby the installation, test and training of users at MoWI HQ have been progressing since June, 2010. This has been done together with data collection and data entry. Training for the other implementing agencies scheduled to take place before September, 2010. The design of document management information system and file tracking system for the Ministry was completed in April, 2010; key word list was established to support preparation of index system. The system will be operated in FY 2010/2011. The design of transport management system was completed in June, 2010, and the system will be operated in FY 2010/2011. The ICT Strategy for MoWI is in place since late June, 2010 and its operation will commence in FY 2010/2011. Also the Ministry website is operating and it has been updated routinely with two staff dedicated webmasters staff. The LAN for the Ministry was improved through the installation of new switches and software, and the ICT unit staff were equipped with (9) laptops, (2) servers and (2) printers.

Preparation of the Client Service Charter The preparation of client service charter was completed in June, 2010 and inauguration will be in mid August, 2010.

3.4.2 Progress on Technical assistance for strengthening of sub-sector planning and

operational capacities

Technical Assistance Four technical advisers for DWR were recruited to provide assistance to the department since January, 2010, this has improved the quality of work particularly in report writing, planning and budgeting. For the Rural WSS evaluation for the procurement of the consultant was completed

Page 43: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

35

in July, 2010 and report awaits MTB approval, while the opening of RFP to procure consultant for Urban Utilities will be done in 31/08/2010.

Development of regulations and Subsector operational procedures and guidelines (including environmental management monitoring)

In order to strengthen legal framework for the programme implementation the two water Acts; The Water Resources Management Act of 2009 and Water Supply and Sanitation Act of

2009 together with their four respective regulations are operational, while other eight regulations are in preparation stage. Also four regulations which support the two acts were ready for Water and Sanitation Act completed and operational.

Environmental Management Act (Implementation support project Coordination and Follow up ESMF and RPF)

Note: See safeguards report.

Strengthening of Water Resources monitoring, assessment and enforcement – including protection of important water sources; water demand management, strengthening legislations and enforcement; integrated water resources planning, transboundary water management, and variety of cross cutting activities such as disaster management, public awareness, inter-agency networking and establishing a water resources management information system

Note: See Component One Report

Cross sectoral assistance to strengthen the harmonization and coordination of water resources policy, Institutional responsibilities and plans between the key partner government sector

Note: See Component One Report.

Procure Consultant for assessing relevance of MCS. Evaluation has been completed and the report has been sent to the MTB for approval.

Construction of new Maji Central Stores at compound in Boko area DSM The construction of new offices has not yet started until the study on the relevance of Maji Central Stores has been completed.

3.4.3 Progress in supporting sector coordination, performance monitoring and

harmonization of sector policies, strategies and plans

Harmonize sector policies, strategies and plans The water sector policies, strategies, laws and plans have been harmonized with the WSDP after the Mid Term Review of March, 2010 and April, 2010.

Page 44: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

36

Support PCT, TWGs, Sector Working Group and CWB The inputs for the meetings were prepared, circulated to members in advance and were basis for discussions during the meetings. Four Thematic Working Groups meetings were convened for each of the four themes (Institutional Development and Capacity Building, Planning and Financing, Performance Monitoring and Sanitation and Hygiene) in October 2009, January, March and May, 2010 respectively, and one Water Sector Working Group meeting was held in March, 2010. Also, one extraordinary TWG for Planning and Finance was held in June, 2010 together with several informal meetings between MOWI, PCT and Development Partners Secretariat (DPG-Water Secretariat) to discuss and resolve emerging issues during the course of implementation of WSDP activities.

Facilitate Joint Water Sector review and stakeholders’ consultative meeting PCT continued with the follow up on the undertakings as agreed in the last JWSR held in October, 2009 and preparation of the documents for the 2010, JWSR is in progress.

Monitor Performance of WSDP implementation The fifth Joint Supervision and Mid - Term Review Mission involving the Development Partners, other Water Sector Stakeholders was conducted in March and April, 2010 and the Aide Memoire for the mission together with the Financial Report to track and monitor WSDP implementation were produced.

Annual technical and financial audit report RFP to procure consultant for conducting Technical Audit Report for FY 2007/2008 and 2008/2009 was distributed to the short listed consultants in March 2010 and the opening of technical proposal was done in May, 2010, followed by evaluation and negotiations at the end of June, 2010.

Development and Implementation of Communication Strategy - Strengthening the Information, Education and Communication Unit

Identification of the required communication equipments was done and handled over to PMU. Preparation of tender documents is in progress. Action Plan for the implementation of WSDP Communication Strategy was developed and disseminated to LGAs, WSSAs, and Water Basin Offices. The implementation of the strategy is going on at all levels through dissemination of NAWAPO and NWSDS media/communication tools such as fliers, TV programmes (documentaries, situational comedy and drama series), radio and TV advertisements, audio and visual music. To date all members of parliament, Sector Ministries (15), NGOs (20), Development Partners (16), Higher Education Institutions (10), BWOs, District Water Engineers (82), Regional Secretariats (21), Schools (100) have received communication tools.

Page 45: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

37

3.4.4 Progress on the Sector Capacity Building

Strengthening the capacity of Ministry staff – including short term recruitment of skilled manpower to fill the gaps in all essential fields; training of existing Ministry staff, Basin staff, Water Specialist in Regional Administration Secretariat, and key staff of water related Ministries and institutions to better enable them to implement the functions assigned to their sections and units by the new structure.

Recruitment of skilled manpower to fill the gaps in all essential fields For the FY 2009/2010 the Ministry recruited 129 to fill the vacant post, which include (10) Engineers, (19) Hydrologists, (1) Economist, (23) Technicians (Hydro-geologists), (14) Community Development officers, (1) Legal Officer, (10) Supplies Officers, (2) Computer Operators, (3) Information Officers, (9) Hydrologists, (6) Environmental Engineers, and (31) Technicians.

Training of existing water sector staff The total of 200 staffs has attended both short and long term training courses.

Perform Sector staff augmentation The list of staffs to be transferred to the LGAs has been identified, updated and sent to the Public Service Management for approval. The POPSM is reviewing the list and approval is expected before September, 2010. MoWI and PMO- RALG are making follow up.

Training on Strategic Framework and Guidelines for Capacity Development On CD Plans, all divisions and units at MoWI, Executive Agencies, BWOs, 132 LGAs, 21 Regional Secretariats and WSSAs have completed their CD plans. The inputs have been incorporated in the MTEF and implementation has begun in July 2010.

Page 46: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

38

Support for Local Private Sector (Drilling companies, Maintenance supply chains, consulting firms, contractors as well as transformation of the Drilling and Dam Construction Agency)

The contract for lot 1 & 2 for purchase of Drilling Machines for DDCA (Public Drilling Agency) signed July 2010 and delivery is expected in December, 2010. The remaining Lot 2 will be signed before the end of August, 2010. This process is covering 8 out of 20 Heavy Duty Drilling Rigs that are planned to be purchased within phase one. Additional Heavy duty Drilling Rigs amounting to 22 are earmarked to purchase in phase two. Contracts for purchase of Ground Water Exploration equipments and Earthwork machines for DDCA were signed in July, 2009. Earthwork machines were delivered in January 2010. Four out of the six ground water exploration equipments were received by DDCA in January 2010. The remaining equipments are expected to be delivered in October, 2010. Evaluation for the purchase of soil laboratory and design equipments has been completed and the report was sent to the MTB for approval early in August, 2010. Institutional strengthening and capacity Building of DDCA is ongoing and aims is to strengthen its general administration. Office construction, training, office/operational equipments and transport and the establishment of a Management Information System are to be accomplished by July 2011. The DDCA Strategic Plan and its Client Service Charter are in place. The corporate business plan was completed in July 2010. The recruitment of the Chief Executive Officer for DDCA is in the vetting stage before interview; while the recruitment of other two senior posts (Technical Support Manager and Business Support Manager) will follow after the CEO.

Support Water Development and Management Institute and other Sector related training Institutions

Contract for purchase of 3 Pick up Double Cabin vehicles and 1 minibus was signed in February 2010 and delivery is expected to be in October, 2010. Opening of the bid documents for purchase of laboratory equipments and chemicals reagents was done in June, 2010, evaluation was conducted and completed, the report was sent to the WB for approval. Recruitment of the Chief Executive Officer is at the vetting stage; however Chairman of the Board is in place. ToR for procuring consultant for the design and supervision services for the rehabilitation and construction of hostel blocks, lecture theatres, laboratories, Classrooms and conference hall were sent to World Bank for No objection by mid July, 2010. As part of Capacity Building process the contract for purchase of library books was signed and over 50% of first consignment was delivered to WDMI. The rest will be delivered early in September, 2010. Student enrollment has increased from 100 in 2008 up to 120 per intake in 2009/2010 academic year. However rate of increase in student’s enrollment at WDMI is rather low due to limited number of students sponsored by MoWI, and the number of privately sponsored students is not growing and it is likely to decrease due to lack of loan opportunities.

Page 47: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

39

For instance, last year 25 female students were qualified for registration but could not enroll as they were not able to pay. The curricular for two new courses (Diploma in Irrigation Engineering and Bachelor of Science in Water Supply Engineering) had been prepared and submitted to NACTE for approval by the mid of June, 2010. Currently, the WDMI is implementing the capacity Building projects under EU/GTZ project on human resources and organizational development in the Water Sector. A draft report on market needs and demands of WDMI was ready in the mid of March, 2010. The Institute is also developing a plan for becoming a competitive and autonomous training institution with sustainable funding. The project also involves improvement of the capacity of WDMI to offer improved training programmes and courses as part of the continuous education scheme in the water sector. This includes developing appropriate curriculum and start a process of course accreditation, develop new/update staff capacities, market the specific courses through website and other means and conduct initial courses.

Support of the NGOs and CBOs Awareness training on the role of CSOs and CBOs in implementing WSDP, opportunities and challenges in Water Resources Management Act and Water Supply and Sanitation, understanding of NAWAPO, Water Sector Reforms, Water Sector Development Strategic Plans and Framework for Capacity Development in the Water Sector has been provided to 65 representatives from CBOs and CSOs in February, 2010.

Logistical support and Technical assistance to EWURA in regulation Administration

Training of 201 staff from UWSAs, LGAs, and Regional Secretariats was conducted on licensing and other regulatory procedures in Mwanza in June 2009, Morogoro in July 2009, Mbeya in September 2009. Under WSDP support, EWURA was provided with (7) laptops, (6) digital cameras and (1) printer to be used by Zonal Engineers.

Page 48: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

40

4 PROGRESS ON ENVIRONMENTAL AND SOCIAL SAFEGUARDS Safeguards comprising Environmental and Social Management Framework (ESMF) provide

mechanisms for ensuring that potential environmental and social impacts of the project are

identified, assessed and mitigated as appropriate, through an environmental and social

screening process. In this way, the results of the screening process can complement the

Environmental Impact Assessment (EIA) process.

The safeguard issues include procedures for meeting the environmental and social

management requirements, as outlined in the EIA guidelines. It also complements Operational

Procedures for environmental management of projects where specific details are not yet

known.

The Environmental Assessment category assigned for the WSSP is “A”. The Safeguards policies triggered for the Project include: (i) Environmental Assessment (OP/BP 4.01), (ii) Involuntary Resettlement (OP/BP 4.12), Safety of Dams (OP/BP 4.37), and Projects on International Waterways (OP/BP 7.50). Both the Environmental and Social Management Framework (ESMF) and the Resettlement Policy Framework (RPF) were in place when the implementation of the project commenced in July 1, 2008. The program finances the implementation of civil works and the environmental and social impacts of these activities are supposed to be monitored by MoWI’s Environmental Compliance Unit (ECU) staff.

Planned Activities carried out in this category are outlined below:- Sub-Project Screening

Continue with a retrospective review of the approved sub-projects in the annual work plans of the districts and business plans of the utilities that have been approved for funding or have received funds under the WSDP;

To determine if and how the environmental screening was done and whether any corrective action is required;

Carry out awareness and training on the utilization of the ESMF and RPF to all Implementing Agencies.

Communication Strategy Action Plan

Develop a Public Consultations and Participation Plan at National, District and Community levels and intensify the program awareness/sensitization/implementation process particularly to Regional/District/community level;

Conduct Stakeholder Workshop and Develop Water Sector Reform Poverty and Social Impact Analysis ToRs.

Page 49: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

41

4.1 Component 1- Water Resources Management

Environmental and social screening exercise has been undertaken for 16 projects out of 34

projects including basin office buildings, out of which three (3) projects fall under category “A”

which are Kimbiji well field, Kidunda and Ndembera dams and the remaining 7 (Office building)

are of category C. The screening criteria used were the one provided in the ESMF. Moreover on

this year also, the environmental and social screening exercise has been completed in 18 dams

in the internal drainage basin and one dam in Lake Victoria Basins. 622 dams have been

evaluated in all 9 basins. 18 dams have been prioritized for rehabilitation and hence the

screening forms were completed for final evaluation. Engineering drawings for all 18 prioritized

dams of Internal Drainage Basin and one dam in Lake Victoria Basins has been completed.

Preparation of tender documents have already been prepared, six tender were prepared. Also

topographical survey of Mchema profiling in Masasi district, Mtwara region has been carried

out. Designs BOQ, and engineering drawings will be produced, and tender document will be

produced for also procurement process.

Safeguards reports for projects from Rukwa, Wami-Ruvu, Rufiji, Pangani and Lake Victoria basins were received. Pangani basin has 43 projects, 37 projects were screened, 35 projects fall under category C and 2 projects fall under category B; Lake Victoria basin has no new projects; Rufiji basin has 2 projects but screening has not being done; Wami-Ruvu basin has 60 projects, only 2 projects have been screened (Kidunda dam and Karibu Textiles Ltd) and fall under category A, in that case EIA was required. EIA for Kimbiji and Mpera well fields has been done; the EIS has been distributed to stakeholders for comments. Consultant for conducting EIA for Kidunda dam has been procured and the work to be conducted after down payment is done. Meanwhile the consultant is collecting data and establishing office premises. Karibu Textiles Ltd has completed and submitted EIA and Environmental audit reports.

Municipal/Industrial/Mines inspections for environmental/social compliancy

Other activities on environmental protection includes Municipal/Industrial/Mines inspections

and water quality monitoring for compliance were conducted where by 3,380 samples were

analyzed to ensure the quality of water and results showed that 96.6% of samples were of good

quality for human consumption.

The water pollution control was also conducted, where by the Ministry continued to ensure the

quality of effluent before discharged to the water bodies. About 265 samples were collected

from sewerage systems at Arusha, Morogoro, Dodoma and Iringa municipalities, Dar es salaam

and Mwanza Cities for analysis. The results showed that 88% of the samples were of required

standards of effluent prior to discharge.

Page 50: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

42

4.2 Component 2 – Local Level: Scaling –Up of Rural WSS Delivery

Only 32 districts have submitted their environment reports. Those districts are the ones within Kagera, Tanga, Morogoro, Tabora, Rukwa, and Singida regions. Only 208 projects have been screened and only 10 projects need full EIA, those projects should be tendered for EIA (see Table 3). The remaining category C projects shall proceed with construction after establishing a checklist for environmental and social management and monitoring plan.

4.3 Component 3: Scaling Up of Urban WSS Delivery

Under the Urban WSS there were 56 approved sub-projects including small towns in the annual

work plans. Only 31 projects have undertaken screening process and 21 qualified for full EIA,

the remaining 10 projects fell under category C that required a checklist. 4 projects have

completed the EIA reports but not yet submitted to NEMC for approval. All the projects under

DAWASA were screened and classified as “B Category” while the project in Mwanza Water

supply and Sanitation phase II was “A Category” hence both are preparing ToR for EIA.

Songea, Dodoma, Mbeya and Pangani Urban Water Supply Authority have done the screening

and classified their projects as “C Category” of which after screening no further assessment was

required except an environmental management checklist. The remaining projects are at

different stages of preparation.

In general UWSS is implementing water supply projects to meet MDGs target at 95% while the

provision of sewerage services is at 35%. This ratio is insufficient to reduce the impacts of

wastewater pollution in urban areas. UWSS have been urged to review their plans and include

in their immediate intervention the issue of wastewater removal from un-sewered settlements

areas.

Total number of projects qualified for environmental screening under WSDP and the current

status are outlined in the table below:-

Table 3: WSDP Funded projects which are listed for screening and EIA assessments

WSDP

Component

Number of Projects

Qualified for Screening

Screened

Projects

Projects to be

screened

Projects qualified

for EIA

WRM 34 16 18 3

RWSS 572 208 364 10

UWSS 56 31 25 21

Page 51: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

43

Total 662 255 407 34

4.4 Component 4 – National Level: Support to Sector Institutional Strengthening and

Capacity Building

Environmental and Social aspects in the Ministry has been strengthened by being recruiting 11 and 8 environmental engineers and social experts from the industry respectively, the procedure of allocating them is already completed. To date in order to strengthen the MOWI’s Environmental Unit, 2 Community Development officers were recruited and allocated to strengthen the unit. Also, training on safeguards in the implementation of WSDP was conducted to Tanga Regional Administrative Secretariat. The trainees included DWE, RWA and LGAs.

Page 52: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

44

5 FINANCIAL PERFORMANCE

5.1 Component 1: Water Resources Management

The funds allocation for Component 1-WRMD of the WSDP is mostly invested in the activities implemented at the Basins level and small amount is allocated at the national level for monitoring, coordination and oversee sectoral and cross-sectoral activities done at the headquarter. Approved Budget and Expenditures for Development The approved budget of WRMD-Component for FY 2009/2010 is Tshs. 24.47 billion of which,

Tshs 3.1billion was for water laboratory. Actual performance recorded shows that the total of

Tshs. 16.55billion was released during the year. The total amount spent in this financial year is

Tshs. 15.45 billion this amount include expenditure of tshs 6.6billion from basins. The total of

Tshs. 282.3million was received from other Agencies/sources.

Financial Performance of Lake Victoria Environment Management Project II During the period under review the project received a total of USD 2,779,333 from the World Bank as per approved Six month Work plan and budget of USD 2,434,240. The Bank allocated and deposited USD 2,779,333 into LVEMP account. As of 20th February 2010 a total amount of USD 1,000,000 (TShs. 1,300,000,000) was transferred to Project’s account for implementation of planned activities, the remaining USD 1,779,333 were carried forward to FY 2010/2011.No grants were disbursed to date. As counterpart funds the project received a total of TShs. 526,000,000 from the MoWI to meet recurrent expenditure mainly for paying LVEMP I outstanding debts, setting up the LVEMP-II office premises, salaries for support staff, costs related to hosting NTAC, NPSC meetings, familiarization meeting/visits to project areas, national and international days such as Lake Victoria Day, World Environmental Day, Project Launching Day. Revenues Collection The total amount of TShs 979.5 million has been collected as Economic Water User Fee, Application Fees and Water Analysis Charges (Table No.4).

Table 4: Revenues Collection

Basin Economic Water User Fee

(TShs)

%

collectiApplication Fees (TShs)

%

colle

Tanesco

Royalty

Page 53: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

45

Projec

tion per

quarter

Collected

on Projected

per quarter Collected

ction Collected

Pangani Basin 120,000,000 102,995,626 85.8 4,000,000 2,620,000 65.5 24,825,000

Internal Drainage

Basin

90,000,000 52,288,795 58 5,000,000 0.00 0.0 16,550,000

Rufiji Basin 111,537,344 115,009,144 103 1,200,000 1,850,000 154 41,375,000

Ruvuma Basin 38,990,000 3,383,730 8.7 10,000,000 5,030,000 50.3 13,240,000

Wami/Ruvu Basin 370,986,606 426,436,811 114.94 11,933,333 4,890,000 19,860,000

Lake Rukwa Basin 20,000,000 23,283,359 116 680,000 860,000 126 8,275,000

L. Victoria Basin 63,000,000 57,742,781 97.7 3,180,000 2,590,000 81 18,205,000

Lake Tanganyika

Basin

24,000,000.00 6,278,243 26 6,000,000 740,000 12 11,585,000

Lake Nyasa Basin 18,000,000 6,181,717 34.3 2,788,800 2,270,000 81.3 11,585,000

TOTAL 856,513,950 793,600,206 92.7 44,782,133 20,850,000 46.7 165,500,000

Table 5: Annual Expenditure

Office

Total Income (TShs) Total Expenditure

(Tshs)

Balance

(Tshs) Funds brought

forward

Received from

various sources

Pangani Basin 302,014,014 888,665,025 1,041,234,810 176,444,229

Internal Drainage Basin 249,397,436 834,144,937 829,154,206 254,388,167

Rufiji Basin 437,173,747 842,566,498 1,221,079,205 58,661,040

Ruvuma Basin 163,413,144 355,600,156 361,810,761 157,202,539

Wami/Ruvu Basin 219,230,974 980,263,238 1,195,109,049 4,385,163

Lake Rukwa Basin 135,160,125 343,191,520 290,509,187 187,842,458

Lake Victoria Basin 118,589,055 853,595,410 833,099,372 139,085,093

Lake Tanganyika Basin 154,136,162 362,403,727 362,610,128 153,929,761

Lake Nyasa Basin 175,795,412 406,159,602 529,228,338 52,726,676

Page 54: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

46

TOTAL 1,954,910,069 5,866,590,113 6,663,835,057 1,157,665,125

5.2 Component 2: Scaling Up of Rural Water Supply and Sanitation

The financial requirements for implementation of WSDP for Financial Year 2009/2010 has been calculated considering the slow pace of implementation in the first two years (FY 2007/2008 and FY 2008/2009). The first two years marked as a preparatory phase which focused on procurement of goods, works and services. It is now expected that for the FY 2009/2010, the priority will be scaling up the implementation of large scale schemes. Approved Budget and Expenditures

The total approved budget for the year 2009/2010 for Rural Water Supply and Sanitation Sub programme was TShs. 120billion (Local contribution TShs. 14.37billion and foreign contribution TShs105.7 billion), out of which, the released funds were TShs 78.6 billion, was released including those for earmarked projects. This is equivalent to 66% of the total budget approved. A total of TShs. 60.54 billion was spent by the component which is equivalent to 80 %. However, total funds available for this component including opening balance totaled Tshs 132.7billion therefore, this represent a performance of 45%. Of the amount spent by LGAs infrastracture sub-componet shows expenditure performance of only 33% because most of the works were in the initial stages. Most expenditure were recorded in the sub component of office construction and consultancy.

Other sources of funds

For FY 2009/2010, a total of Shs 8.26billion were utilized in implementation of sub projects of

water supply and sanitation. Out of this amount Donors contributed Shs 6.6billion LGAs

contributed Shs 1.59billion and communities contributed Shs 70million. Some of the donors

are: TASAF, WORLD VISION, KfW/EU, UNICEF, CONCERN, World Bank, JICA, PLAN international,

CARE SAIPRO, UN HABITAT, Living Water International, TAG and RC Church. A total of 3625

water points were reported to have been built using other sources of funds. Out of 132 LGAs,

only 10 LGAs reported on community contribution. Those LGAs are Muleba DC, Kigoma DC,

Mwanga DC, Lindi DC, Ileje DC, Mbarali DC, Mbeya CC, Kilombero DC, Ulanga DC and

Sumbawanga MC. Contribution of in-kind is not reported; the only contribution reported is

cash.

Other sources of funds For FY 2009/2010, a total of Shs 8,261,746,025 were utilized in implementation of sub projects of water supply and sanitation. Out of Shs 8,261,746,025, Donors contributed Shs 6,601,645,986, LGAs contributed Shs 1,589,946,224 and communities contributed Shs 70,153,816. Some of the donors are: TASAF, WORLD VISION, KfW/EU, UNICEF, CONCERN, World Bank, JICA, PLAN international, CARE SAIPRO, UN HABITAT, Living Water International, TAG and RC Church. A total of 3625 water points were reported to have been built using other

Page 55: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

47

sources of funds. Out of 132 LGAs, only 10 LGAs reported on community contribution. Those LGAs are Muleba DC, Kigoma DC, Mwanga DC, Lindi DC, Ileje DC, Mbarali DC, Mbeya CC, Kilombero DC, Ulanga DC and Sumbawanga MC. Nevertheless, there is still confusion between contribution for operation and maintenance and contribution for construction of projects. It is not reported if the contribution is for O&M or construction of projects. Also, contribution of in-kind is not reported; the only contribution reported is cash. Annex B5 shows the amount of funds spent from other sources quarterly and annually.

5.3 Component 3: Scaling Up of Urban Water Supply and Sanitation

Approved Budget and Expenditures For the FY 2009/2010 UWSS had approved budget of Tsh 127.4. This budget constituted 13%

local budget while foreign funds was 87%. Funds received in the Component 3 for this year was

TShs 84 billion including Tshs 49billion from basket including local funds and Tshs 35billion

from earmarked partners. This release is equivalent to 66% of the total budget approved. Total

expenditure for this component during the year amounted to Tshs 75.6 billion. Total

management support expenditure for this year totaled Tshs 8.3billion while Tshs 61.2billion

went to investment, large part of this investment went to DAWASA.

5.4 Component 4: Institutional Strengthening and Capacity Building

Approved Budget and Expenditures In FY 2009/2010, the total budget planned for Component 4 amounted to TShs. 21.9billion. Of this budget 4% was from local while 96% was foreign funds. Out of that only TShs 14.6 billion was released equivalent to 65.7%. The total expenditure for the period amounted to TShs 14.5 which was 99.8% of the released funds. Table below summarizes the Approved budget and actual release of funds

Component Approved Budget

Actual Release Release as Percentage of Approved budget

Component 1: Strengthening of WRM Framework – Basin Level 24,475,000,000 16,559,975,361 67

Component 2: Scaling up of Rural WSS Services Delivery to meet MDGs – support to LGAs through LGCDG system

120,073,348,000 78,689,666,563 66

Component 3: Scaling up of Urban WSS Services Delivery to meet MDGs

143,119,684,000 84,113,831,723 59

Component 4: Sector Institutional Strengthening and Capacity building.

21,948,309,000 14,666,448,551 67

Grand Total 309,616,341,000 194,029,922,198 63

Page 56: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

48

6 PROGRESS ON PROCUREMENT

6.1 Component 1: Water Resources Management

Pangani, Rufiji and Wami/Ruvu Basin Water Board have established Procurement Management Unit (PMU) and their Tender Boards in 2009. Pangani Basin Water Board prepared an Annual Procurement Plan (2009/2010) which was divided into two areas namely:-

(a) Procurement Plan for Goods, Works, and Non Consultancy Services In this financial year, 11 items were expected to be processed, but only 5 items were procured. Among the 5 items, tender documents for drilling of thirty 30 exploratory cum production boreholes in Hai and Rombo Districts in Pangani Water Basin; 2 motorcycles were purchased in Wami/Ruvu Basin. Three tenders for supply of goods and services (Supply of Computers and Accessories, Rehabilitation of office rooms in Dodoma, maintenance of motor vehicles and equipment) were completed in Wami/Ruvu Basin.

(b) Procurement Plan for Consultancy Services Procurement of 6 items was expected to be carried out in Pangani Basin but unfortunately none have been procured so far. Expression of interest (EoI) for Provision of Consultancy Services for preparing an IWRMD Plan was prepared and sent to MoWI for further steps; In Rufiji Basin the consultant for drilling the borehole in Ikwiriri village has been procured. 10 consultancies are in preparation stage and five (5) in execution stage in Wami/Ruvu Basin. Details of the Procurement progress during the reporting period can be viewed in Annex 3.

6.2 Component 2: Rural Water Supply and Sanitation

Procurement of consultants for LGAs

All 132 LGAs carried on the procurement of consultants for provision of technical and facilitation services in their areas. 123 LGAs out of 132 LGAs have signed the contracts to support LGAs in provision of technical and facilitation consultancy services in the RWSSP of WSDP. Consultants engaged by LGAs are in the different stages of implementation. The implementation status for procurement of consultants as of June 2010 has been categorized into 8 groups and is as follows: Group 1: This is the first group of LGAs that are in the stage of collecting demographic data, identifying water sources and assisting the communities to select the appropriate technological option they prefer. In this group, there are 6 LGAs as follows: Dar es Salaam (2)-Ilala and Temeke; Kilimanjaro (1)-Rombo; Manyara (1)-Kiteto; Morogoro (1)-Mvomero; and Pwani (1)-Kisarawe. Group 2: This is group of LGAs which have received inception reports from consultants. In this group there are 12 LGAs as follows: Manyara (1)- Babati Township; Mara (1)-Rorya; Mbeya (7)-

Page 57: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

49

Chunya, Ileje, Kyela, Mbarali, Mbeya City Municipal, Mbozi and Rungwe; Pwani (1)- Bagamoyo; Ruvuma (1)- Songea Municipal; and Shinyanga (1)-Maswa.

Group 3: This is a group of LGAs that have received scoping study from consultants. In this group there are 45 LGAs as follows: Arusha (2)-Meru and Ngorongoro; Dar es Salaam (1)-Kinondoni; Dodoma (1)- Dodoma Municipal. Iringa (8)-Kilolo, Njombe, Mji wa Njombe, Iringa, Manispaa ya Iringa, Ludewa, Makete and Mufindi; Kagera (5)-Bukoba, Bukoba Municipal, Ngara, Muleba and Biharamulo; Kigoma (2)-Kasulu and Kigoma; Kilimanjaro (2)-Moshi and Moshi Muniocipal; Morogoro (2)-Ulanga and Kilombero; Mwanza (3)-Kwimba, Misungwi and Ukerewe. Rukwa (2)-Sumbawanga and Sumbawanga Municipal; Ruvuma (2)-Mbinga and Tunduru; Shinyanga (3)-Kahama, Bukombe and Meatu; Tabora (6)-Igunga, Urambo, Sikonge, Tabora, Tabora Municipal and Nzega; and Tanga (6)-Handeni, Tanga City Municipal, Korogwe, Korogwe Township, Kilindi and Lushoto. Group 4: This group consists of LGAs which have prepared bidding documents for procuring contractors for drilling exploratory boreholes and reaming them if found to be productive. In this group there are 19 LGAs as follows: Dodoma (4)-Kondoa, Mpwapwa, Bahi and Chamwino; Mara (1)-Tarime; Pwani (1)-Mafia; Kagera (2)-Misenyi and Karagwe; Kilimanjaro (1)-Siha; Mara (2)-Musoma and Serengeti; Ruvuma (2)-Namtumbo and Songea; Rukwa (3)-Nkasi, Mpanda and Mpanda Township; and Tanga (3)- Muheza, Mkinga and Pangani. Group 5: The fifth group consists of LGAs that have advertised for drilling tenders for drilling exploratory boreholes. In this group there are 17 LGAs as follows: Arusha (5)-Arusha, Arusha Municipal, Karatu, Longido and Monduli; Dodoma (1)-Kongwa; Lindi (1)- Lindi Township. Mara (1)-Bunda. Mtwara (2)- Mtwara Municipal and Masasi; Mwanza (1)-Mwanza City Municipal; Pwani (3)-Kibaha, Kibaha Township and Mkuranga; and Shinyanga (3)-Shinyanga, Shinyanga Municipal and Kishapu. Group 6: The fifth group consists of LGAs which have advertised the drilling tenders for exploratory boreholes and prepared evaluation reports on the submitted tenders. In this group there are 13 LGAs as follows: Kagera (1) Chato; Kilimanjaro (2)-Mwanga and Same;Lindi (2)-Kilwa and Nachingwea; Manyara (2)-Mbulu and Hanang’; Mbeya (1)-Mbeya; Mtwara (1)-Tandahimba; Mwanza (3)-Geita, Magu and Sengerema; and Singida (1)-Manyoni. Group 7: The seventh group consists of LGAs which have completed evaluation process of procuring the drilling contractors and signed contracts with the contractors. In this group there are 9 LGAs as follows: Lindi (3)-Lindi, Liwale and Ruangwa; Mtwara (3) - Nanyumbu, Newala and Mtwara; Pwani (1)-Rufiji; and Singida (2)-Iramba and Singida. Group 8: The eighth group consists of LGAs in which consultants have completed designs of gravity water schemes and submitted draft design reports and bidding documents for procuring contractors for construction of water sub projects. In this group there are 2 LGAs as follows: Kilimanjaro (1) Hai; and Manyara (1) Babati.

Page 58: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

50

6.3 Component 3: Urban Water Supply and Sanitation

Procurement under this component covers 19 UWSAs, DAWASA/DAWASCO, 118 small towns/DUWSAs and some National Projects (KASHWASA, Chalinze, Wanging’ombe, Mugambo/Kiabakari, Maswa, HTM and Makonde). Although this component has been able to contract consultancy services more rapidly than component 2, nevertheless 41.5% of the planned tenders have been initiated as scheduled in the procurement plan. This can be attributed to the delays in the completion of design and tender documents. Likewise some works contracts were frontloaded on the basis that consultants would be procured as scheduled. The main procurement challenges in this Component include: Delays in the completion of design and preparation of tender documents; The designed works estimates are far beyond Procurement Plan estimates; The consultants will be instructed by the user departments to scale down the activities by putting them into phases.

6.4 Component 4: Institutional Strengthening and Capacity Building

Procurement under this component covers the procurement done by MoWI (including WDMI, DDCA and MCS). A total of 36 contracts have been signed. About 26.4% of component 4 contracts were initiated as scheduled in the Procurement Plan. It has been agreed that one consultant will be hired in FY 2009/2010 to do annual ESMF/RPF audits, annual financial audits and annual procurement audits; evaluation report has been approved by the Bank and NOL obtained for further process. For the financial year 2008/09 procurement audit has been executed by National Audit Authority (NAO). Regarding supply and distribution of capacity building equipment, three aggregated tenders on supply of motorcycles, motor vehicles and office equipment for Ministry of Water and Irrigation and all other WSDP implementing entities were tendered out under the MoWI. Contracts have been signed and delivery and supply of goods has been achieved well though there are delays in shipping of items. Distribution of the motor vehicles, motor cycle and office equipment has been done for about 50%. Experience during the first two years of implementation of WSDP has clearly demonstrated that the traditional annual planning and budgeting exercise is of limited practical use on a large sector program where the project cycle from release of the EoI to the conclusion of works may span well over 3 years and will rarely take less than 2 years. Added to this the many uncertainties and externalities in the procurement process make any accurate planning and budgeting extremely difficult. The decentralized design of WSDP, that has delegated the responsibility for program’s procurement and contract and financial management to almost 200 implementing entities, further compounds this difficulty.

Page 59: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

51

7 PROGRESS IN MONITORING AND EVALUATION

Monitoring by MoWI, DPs and PMO-RALG

In September 2009 and March 2010 MoWI, PMO-RALG and donor partners conducted the fourth and fifth joint supervision mission to LGAs. The main issues raised during the field visits were: monitoring and evaluation system is still inadequate as a result there is still lack of a comprehensive and accurate sector monitoring performance data, problems in the operation and maintenance of the schemes because tariffs are too low for sustainability, degradation of the water source catchment areas, limited capacity at all levels in the sector as there are major shortfalls in the number of engineers and technicians in the water departments of all visited LGAs, concern on the quality, timeliness and accuracy of program reporting, selection criteria for 10 villages projects were applied in such a way that projects did not only serve the most needy villages and sanitation has not received adequate prioritization at all levels.

Technical Oversight and Monitoring by RSs

Out of 21 RSs, 19 RSs reported to have visited LGAs and out of these 13 incorporated comments in their progress reports and 6 have reported to have no comments. The comments include: Execution of the contract agreement should be honored accordingly i.e. working schedule by consultants. In sanitation and hygiene promotion training, the area of household water treatment should be highlighted during awareness creation to the community. There are delays of report submission from the consultant. There is incompetence of consultants due to lack of experienced technical personnel in the consultant office in respective LGA. Also the consultant should have to make sure all key personnel as stipulated in the contract agreement spend their man month in the field effectively. The baseline sanitation data of the earmarked village in the program should be provided (the consultant should come up with Sanitation baseline data for earmarked villages with project). Water quality should be tested and the report to be included in the documents that consultant has to submit to the client. The consultant should start building awareness on formulation of water user entity instead of VWCs. Training on preparation of environmental screening forms (Safeguard) should be conducted. The Consultant is advised to use solar energy in pumping schemes where is applicable and appropriate. Awareness creation on sense of water project ownership should continue so that vandalism of water infrastructure can be stopped. The District advised to reinforce the supervision of rural water supply and sanitation project consultant. Community should be facilitated on awareness on community contribution as well as O&M. Also LGAs are advised to take action on registration of water user groups to make operation and maintenance of water projects sustainable. It is advised that LGA water department offices should not be utilized with other council departments. Details can be seen in Annex B3.

Page 60: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

52

Monitoring Reports of Urban Water Supplies and Sewerage Utilities: There are 19 Urban Water supply and sewerage authorities (UWSAs) in operation. These Authorities have been managed by the Board of Directors which are fully responsible for carrying out all functions and supervise business and affairs of the Authorities including tariff setting, revenue collection and budgeting. The Authorities are graded under three categories of A, B and C as per water regulation of 1997, and are monitored, regulated and supported by the Urban Water Supply and Sewerage Division and EWURA. The annual report gives a brief summary of the performance attained by the UWSAs measured by using the indicators stipulated in the Memorandum of Understanding MoU. The basis of analysis and evaluation in this report is on the respective monthly, quarterly and annual reports submitted by the authorities and match up with the data reported in the Maji Information System database (MajIs). The total outstanding TANESCO bills for the 19 authorities excluding DAWASCO by the end of this year was Tshs 841 million while the total debt to suppliers amounted to Tshs 1.989billion compared to Tshs 1.53 billion of the previous year. The total amount of arrears during the year 2009/2010 was Tshs 8.672 billion compared to Tshs. 7.74 billion reported in the previous year and amongst these, the Government Institutions arrears are Tshs. 2.822 billion and private customer’s arrears are Tshs. 5.850 billion.

Page 61: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

53

8 CHALLENGES The reported challenges from the WSDP components, that have in one way or another contributed to

bottlenecks in the implementation of some of the Programme planned activities during the reporting

financial year include aavailability of reliable data from various sources to enhance timely

preparation of quarterly reports, approval and sharing of reports; delayed and inadequate

disbursements that cause delay in implementation of the sub sector work plans, Overdue

payments of signed Contracts which needs to be paid as most works have stalled . Challenges

reported by each component are shown below:

Component I : Water Resource Management

(i) Limited enforcement mechanism contingent on the new water law as the regulations are not yet in place;

(ii) Delayed and inadequate disbursement and incompatible to Basin work and plans and budgets;

(iii) Limited human resources with requisite knowledge in IWRM, negotiation skills, conflict resolution, social assessment, water resources economics and international water law;

(iv) Inadequate and old working facilities, monitoring equipments and tools; (v) Inadequate transport to facilitate the implementation of activities such as data

collection and monitoring; and (vi) Low rate of collection of economic water user fees.

Component 2: Rural Water Supply and Sanitation

(i) The new reporting format provided, which lead to missing some important and relevant information such as monitoring, sanitation and financial issues was adopted; Some RSs and LGAs did not manage to submit their reports in time;

(ii) Sanitation issues are still not given priority in some LGAs and RSs;

(iii) Inadequate number of competent, qualified and skilled staff at all levels including the Ministries, RSs, LGAs and private sector. The situation hinders routine operations of water user entities, supervision and monitoring and reporting progress on water schemes in time; and

(iv) Low response of the community in participation in the implementation of water sub-projects in terms of cash and in kind.

Component 3: Urban Water Supply and Sanitation (i) Shortage of funds that led to omitting the implementation of projects including towns

that has finished studies, for instance, Tabora (Urambo and Sikonge), Babati (Orkesumet, Karatu and Katesh);

(ii) Delay by UWSAs in acquiring title deeds for construction of offices for utilities; (iii) Delay of submission of implementation reports by UWSAs, small towns and national

projects that led to difficulties on preparation of progress report on time;

Page 62: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

54

(iv) Delay and inadequate release of funds contributes to delay in payment to contractors and service providers which result to payment of extra (interest) funds as a result of mishandlings of contract conditions. The delay also caused some of the projects like the study for Kidunda dam and construction of Kibaigwa water supply project ceases to start as the consultant and contractors are not yet paid the advance payment;

(v) Accumulation of unpaid bills for the utilities that the programme is helping in supporting. This led to power cut by TANESCO to some utilities like Mugango/Kiabakari National Project which resulted in shortage of water supply to the service area. This was caused by delay in release of funds from WSDP financiers;

(vi) Non-availability of competent and qualified staff in utilities especially in small towns, district UWSAs and National project schemes contributes to delay in projects implementation, decision making and also in reporting.

Page 63: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

55

9 CONCLUSIONS AND RECOMMENDATIONS

9.1 CONCLUSIONS

(i) During the FY 2009/2010 achievements for component one are as explained in the

previous chapters of this report. Level of implementation differs. Some of the plans

were successfully implemented and others partially. IAs applied a number of measures

to overcome the problems funds , such measures included optimal utilization of funds

and soliciting financial resources from other sources;

(ii) Partial implementation has to a large extent been contributed by the untimely

disbursement of financial resources and lack of transport facilities since most of the

plans need field visits and physical follow up. Irregular funds flow to the implementing

agencies has posed problem of implementation as some of the planned activities need

to be done at a specific period/time of the year. However, self efforts were made by the

DWR and BWOs to prioritize the use of financial resources in areas which can have

direct impact to the improvement of the water resources management;

(iii) Awareness campaigns on various issues such as water user fees were conducted to

stakeholders in some Basins to create awareness on value of water. Besides, the

collection and analysis of 3,655 water samples (i.e. 104%) from basins, rural, urban and

private sectors was achieved due to sensitization and awareness creation on the

importance of protecting water sources through different media;

(iv) Various stakeholders (municipalities, industries and authorities) are becoming aware on

pollution control; this is proved by regular effluent monitoring. 302 wastewater samples

analyzed, 280 (i.e. 92.7 %) were found to be within the required standard;

(v) Inadequate experienced staff and technical knowhow for the Basin staff especially for

the new Basins, retard the smooth implementation of the planned activities; In efforts

to minimize the negative effects, from time to time, technical personnel from

MoWI/Department level has supported the Basins in the implementation of various

activities including training of staff on various areas of expertise;

(vi) Implementation of the sub-projects is still slow due to various reasons including long

procurement procedures taken by some LGAs in procuring consultants for ten villages,

and low capacity of local contractors in the water sector;

Page 64: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

56

(vii) In RWSS, there is no improvement in submission of progress reports. However, reports

from five RSs of Ruvuma, Dodoma, Mbeya, Arusha and Mara did not follow the new

format provided;

(viii) DCWSS has prepared the concept paper to be sent to financing partners example BADEA

and Saud Fund to request funds for implementation of the projects for the towns that

have finished their studies and designs; and

(ix) Roaster of technical staff from the DCWSS has been prepared so that the towns which

are implementing immediate works will be visited regularly.

9.2 RECOMMENDATIONS

As a matter of clarity, recommendations have been presented specifically for each component.

Therefore, in order to achieve the Components objectives, targets and plans it is recommended

that:-

1. Component 1: Water Resources Management

(i) Disbursement of WSDP funds should be on time for effective implementation of the plans;

(ii) Training and technical support is needed to strengthen BWO Skills gaps need to be filled through recruitments to facilitate or fast track the implementations of WSDP activities;

(iii) Basins Tender Boards needs to be strengthened to enable Basin Water Offices carry out their own procurement;

(iv) Awareness campaigns for the Water Resources Management Act are needed for the better implementation and effective enforcement;

(v) Offices construction and associated equipments such as furniture, computers etc. should be given priority, due to insufficient offices to accommodate new employees;

(vi) New water supply scheme should always be tested before use and old sources should be periodically checked for water quality changes; and

(vii) It is advised to consult Water Laboratory Services Division for determination of whether your water is safe for human consumption (periodic bacteriological tests) and also for mineral test content in order to classify usage requirements and other possible problems in order to select the methods and materials necessary for their correction.

2. Component 2: Rural Water Supply and Sanitation

(i) RSs are to provide technical support to LGAs and incorporate comments in the quarterly progress reports;

(ii) Expenditures should be reported by components; (iii) Implementation of earmarked projects should be reported; and (iv) RSs should make timely submission of progress reports to PMO-RALG and MoWI, and

review all the reports from LGAs.

Page 65: WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT ... · WATER SECTOR DEVELOPMENT PROGRAMME ANNUAL PROGRESS REPORT FY 2009/2010 ... MTB Ministry Tender Board ... PPR Public

57

3. Component 3: Urban Water Supply and Sanitation

(i) In order to avoid payment of interest and to facilitate timely completion of the project,

disbursement of WSDP funds should be released on time.

4. Component 4: Institutional Strengthening and Capacity Building

The success of any programme depends on how the implementers are involved in every stage

of implementation process. This is important to assist every stakeholder to perform his/her

duties as required. Therefore there is a need to improve the understanding of the programme

implementation among sector staff, especially for those who are directly involved in the day to

day activities of WSDP particularly the preparation of reports.