wdr 2006(sample version)
TRANSCRIPT
-
7/27/2019 WDR 2006(Sample Version)
1/4
Water Desalination ReporT
Saudi Arabia
IWPP put on hold
A planned power and desalination plant at Jubail on SaudiArabias east coast has been postponed for the time being,
reports Saline Water Conversion Corporation (SWCC)
governor Feheid Alshareef. The plant, which was to have
produced 340,000 m3/d (90 MGD) of water and 1,100
MW of power, has been combined with another project
at Jubail being undertaken by Maraq. The Maraq
project, which involves construction of an 800,000 m3/d
(211 MGD) desal plant and 2,500 MW power facility,
attracted three offers in late April, including one based
on MED technology (WDR 15 May, issue 19).
Of the 800,000 m3/d of water produced in the Maraqplant, 500,000 m3/d will be supplied to SWCC and the
Water & Electricity Company (WEC), the off-taker of
power and water from the Kingdoms IWPPs. For the
time being, the Jubail IWPP is postponed as the water
quantity needed will be met by the Maraq project,
said Alshareef.
Alshareef also reported that a proposed 30,000 m3/d (8
MGD) desalination facility for the oil city of Khafji,
also on the Kingdoms east coast, is under technical and
economic evaluation. The plant would supply water to
areas inside the Eastern Province. An alternative, whichis also under consideration, is to get the water through a
pipeline from the town of Nairea in the Eastern Province
and connect Khafji to the Ras Azzour, Nairea, Hafr Al-
Batn, Riyadh pipeline system.
California
SWRO project takes next step
The Municipal Water District of Orange County
(MWDOC) will issue RFPs on Tuesday of this week
for a preliminary engineering report to determine the
feasibility for a full-scale 25 MGD seawater desalination
plant to be located at Dana Point. Project deliverables
are understood to include six technical memos (TM)
addressing the following areas:
TM-1 Feedwater supply system evaluation of slant-well,
subsurface intake arrangement currently being tested.
TM-2 SWRO desalination, pretreatment and post-
treatment systems.
TM-3 Distribution pumping connection to the regional
distribution system.
TM-4 Concentrate and residuals disposal arrangement,
with the preferred approach involving concentrate co-
discharge with wastewater plant efuent.
TM-5 Power supply system evaluation.
TM-6 Preliminary cost estimate for a 25 MGD seawater
desalination plant.
Only the above described engineering report will be
authorized under this contract, however consultantswill be encouraged to submit information on a proposed
team that could continue on in the role of Owners
Representative (OR) if the project moves forward. If that
occurs, the OR will be responsible for developing a pilot
plant design, engineering studies, handling permitting
requirements, and preparing a 10 to 30 percent cost
estimate and DBO bid package.
The budget for this portion of the project is estimated
at $200,000 and responses will be due by 20 June. For
further information, or to obtain the RFP, contact Richard
Bell at [email protected]
Jordan
Local rm provides ro expertise
After completing the rst full year of operation at the Abu
Zeghan Brackish Wells Desalination Plant, AquaTreats
Tarek Abu Dehays told WDR that the company was
looking forward to operating the system for the next four
years of the contract, and possibly longer.
The 60,000 m3/d (15.8 MGD) BWRO plant was installed
on a design, build basis in October 2004 for $4.99 million,which included an initial operating services contract.
On 26 April 2005, AquaTreat was awarded a $7 million
contract to operate the plant for the next ve years.
Although the operations contract includes all labor and
chemical costs, the electrical costs are the responsibility
of Jordans Ministry of Water & Irrigation.
Tom Pankratz, Editor, P.O. Box 75064, Houston, Texas 77234-5064 USA
Telephone: +1-281-857-6571, www.globalwaterintel.com/wdr, email: [email protected]
2006 Media Analytics. Published in cooperation with Global Water Intelligence
22 May 2006Volume 42, Number 20
The international weekly for desalination and advanced water treatment since 1965
-
7/27/2019 WDR 2006(Sample Version)
2/4
Dehays describes the system, Seven brackish wells
furnish the plant with feedwater that has a TDS ranging
from 5,000 to 7,000 mg/L. The water is high in sulphates,
bicarbonates, CO2
and iron, and has a high temperature.
We rst pre-aerate the water to oxidize the iron then it isltered in one of 15 horizontal pressure lters, followed
by 5-micron cartridge lters. Filtrate is then injected
with an anti-scalant and pressurized using ve high
pressure pumps, each with a capacity of 500 m3/hr and
an operating head of 23 bars (335 psi).
The two-stage RO plant operates at a 75% recovery with
RO concentrate and lter backwash water are discharged
to the Dead Sea via a low-ow river referred to in Arabic
as a wadi.
Like the nearby Wadi Main BWRO plant (WDR, 27
March, issue 12) scheduled to be commissioned later this
year, the Abu Zeghan product water must pump up to the
city of Amman, a change in elevation of 1,125 meters
(3,690 ft).
Colorado
UF with & without pretreatment
Consolidated Mutual Water Company (CMWC) in has
selected Zenon UF membranes for a new, 15 MGD
(56,775 m3/d) surface water treatment plant in Lakewood,
Colorado. CMWC is a nonprot corporation that followsthe original pattern of early cooperatives where the
ownership is held by its water users. Since it was rst
formed by the merger of four water companies in 1910,
ten other water systems have joined the company.
The new water system will treat reservoir water that is
prone to turbidity, algae and manganese excursions. Prior
to selecting the new system, a pilot study involving Pall,
Memcor and Zenon systems was conducted. Based on a
20-year life cycle cost analysis, a $3.9 million Zeeweed
1000 system was selected. Zenon regional manager Ron
Maness told WDR that The system will operate withoutocculation or sedimentation for the rst years operation.
After the pretreatment system has been constructed, we
believe the ux will be able to be increased by a minimum
of 15 percent. The resulting increased capacity and long
cycles between chemical cleanings should easily offset
the cost of the pretreatment systems capital cost.
The project is scheduled for an early 2008 startup, and
the project engineer/manager were Malcolm Pirnies
Jack Bryck (Phoenix) and Laurie Sullivan (Denver).
Israel
SWRO product quality options
Bids for Hadera desalination project have been extended
from 31 May until the end of June. The three teams
understood to be bidding include GE, Inima/Aqualia and
IDE Technologies. Specications outline a 272,765 m3/d
(72 MGD) SWRO project similar to Ashkelon, but with
a slightly different product water quality specication.
Requirements are to achieve a product water boron
concentration of less than 0.3 mg/L to satisfy agricultural
concerns. An interesting twist is having a choice to
produce water with a chloride concentration of either 20
mg/L or 70 mg/L. The same boron requirement applies
to both options, but the higher chloride concentration
will carry an automatic penalty of $0.015/ m3.
It would seem that the boron limit which is lower than
the WHO 0.5 mg/L guideline would be the limiting
requirement here. The question seems to be: will a
partial second pass followed by boron selective ion
exchange have a lower evaluated tariff when the penalty
is applied? Bidders must choose one chloride level to
base their design upon so well have to wait and see if
competing congurations and technologies are offered.
RO Warranties
The value of paperA warrantys purpose is to ensure a buyer receives the
quality and performance they have been promised for
a reasonable period of time. Fundamentally, membrane
warranties are good for business and should protect both
the manufacturer and end user. If a membrane warranty
is to be practical, effective and enforceable, certain
commercial facts of life must be recognized. Although
the clich that a membrane warranty is not worth the
value of the paper on which it is printed is commonly
heard, can a manufacturer really be expected to provide
a meaningful guarantee for conditions or performancebeyond its reasonable control?
When RO membranes were rst introduced in the 1960s,
they were sold with a fairly simple, 12-month materials
and workmanship (M&W) warranty. Although the
early systems operated well enough that the industry
continued to grow, there was still a lot to learn about
the importance of pretreatment and proper O&M, and
scaling and/or fouling issues contributed to more than
their fair share of warranty claims.
Page 2 WATER DESALINATION REPORT - 22 May 2006
-
7/27/2019 WDR 2006(Sample Version)
3/4
In response to these problems, the original equipment
manufacturers (OEM), consultants and end users started
asking for a performance warranty that went beyond a
simple M&W warranty. DuPont Permasep offered a three
year prorated warranty on individual membrane elementsin the early 1970s. Torays Randy Truby told WDR, I
wrote my rst 36-month performance warranty in 1976.
Those early warranties offered to replace elements up
to one full load, or 100 percent limit of liability, on a
battery-basis where the prorated fee was equal to the
time the elements met performance criteria in terms of a
minimum ow and salt rejection. If an element lasted 18
months, it was replaced at half price.
Another industry expert agrees, noting, In the old days,
warranty issues were easy: if a membrane failed in less
than three years, it was replaced, even when the servicewas severe. But as the system sizes grew, the stakes
increased and membrane warranties can now easily end
up in arbitration.
Membrane warranties have evolved into systems
warranties covering the full complement of membranes
operating on a specied feedwater under a range of
conditions to meet minimum ow and salt rejection
characteristics. Variations in warranty provisions may
mean that each train or stage in a system may have a
unique warranty where its possible for individual
elements to be underperforming, but if the entire train/stage meets the specication, the individual element(s)
would not have to be replaced.
These warranties can be very wordy as manufacturers
try to dene and limit the range of operating conditions
and prescribe specic remediation or maintenance steps
required by the operator. In some cases, a warranty may
read like a design manual; a situation that seems to make
everyone nervous, especially if end users interpret it as a
confusing array of contradictory limitations or believes
that a 15-minute excursion beyond a specied SDI limit
will void a warranty. Truby says this is usually not thecase, Most warranties have provisions where a brief
excursion outside the operating boundaries does not void
the warranty unless membrane damage has occurred.
Hydranautics contract specialist Scott Jackson toldWDR,
Membrane companies manufacture a product that is
incorporated into a system designed, manufactured,
operated and maintained by others, and we usually have
no control whatsoever over their activities. Keep in mind
that in todays market, RO membranes represent less than
ten percent of the total brackish system cost and no
more than ve percent of a seawater systems cost. At
the same time, membrane manufacturers are routinely
expected to bear the bulk of the nancial risk for the
long-term performance of the complete system.
Recently, some manufacturers have even been asked
to supply an evergreen warranty that requires each
element that is replaced under a ve-year performance
warranty include an additional ve-year warranty.
Because such an arrangement carries a liability in
excess of 100 percent, most manufactures usually
refuse. From a technical standpoint, it is also a
questionable practice to replace only some individual
elements within a pressure vessel. Mixing new and old
elements leads to an imbalance of ux and differential
pressures where new elements tend to produce morewater at lower pressure and over-ux while the older
elements may see less feedwater. This could result in
accelerated fouling or scaling. Element replacement
should be done with an eye to balancing the loading
of old and new elements if they are to be mixed in the
same train.
Most membrane warranties are now required to
normalize operating data as a condition of warranty.
Normalization occurs when a membranes performance
at a current operating condition is stated against its
expected performance based on the design conditions.Some membrane companies have the capability to
access real-time membrane performance data over the
internet to guide end users in the operation of their
plants.
Jackson correctly notes, Todays generation of
membrane products provide superior, stable, and very
long term performance when operated on the feedwater
quality specied by the membrane manufacturers,
under the proper hydraulic conditions, and with regular
and proper maintenance.
It is this newspapers view that the trend to place evergreater and longer term nancial risk on the membrane
manufacturers does not serve either the end users,
OEMs, consultants or membrane manufacturers. It is a
bit like the current US health care system that everyone
doctors, hospitals and patients seem to dislike:
substantial additional cost is added to the health care
system and the only ones who prot are insurance
companies and lawyers.
The more elaborate and safe a warranty appears, the
Page 3WATER DESALINATION REPORT - 22 May 2006
-
7/27/2019 WDR 2006(Sample Version)
4/4
more it will inevitably cost. Assuming membranes
are purchased from a reputable manufacturer who
practices good quality control, the best warranty
prevention strategy appears to be a sound design with
proper pretreatment and accurate, normalized data
monitoring, and one in which the end user, consultant,
OEM and membrane manufacture understand they arein a long-term partnership.
In brief
Poseidon Resources is continuing with the evaluation of
the EPC proposals for the Carlsbad and Huntington
Beach SWRO projects. Although one expected bidder
reportedly didnt submit a proposal, the other turnkey
offers were in line with previous indicative pricing.
EPC contracts are still planned to be awarded at the
end of June. Poseidon also told WDR that it received
the draft NPDES permit for Carlsbad last week.Abu Dhabi Water and Electricity Department
(ADWEA) has opened talks with Suez Energy, the
second-ranked bidder, relating to the acquisition of
the Fujairah IWPP in the UAE. The Suez offer is
0.4 percent higher than the $1.343.8 million apparent
low bid for the 454,000 m3/d (100 MIGD) hybrid
desalination plant and 662 MW power plant offered
by SembCorp Utilities of Singapore. SembCorp is
said to remain condent of a contract award.
The National Water Research Institute (NWRI)
has named Dr Philip C. Singer of the University ofNorth Carolina as this years recipient of the Athalie
Richardson Irvine Clarke Prize for excellence in water
research. His water research activities have spanned
a broad range of water quality issues, particularly in
areas of drinking water disinfection. The award will
be presented in a ceremony on 13 July.
Chemical engineering students at Qatar University
presented their senior projects to university and
industry representatives last week. Projects included
those from Mohamed al-Shahwani (An experimental
study in dynamics of desalination using MED),Mohamed al-Mohamady (Desalination of brackish
water using RO), and Lee Hodder (Sustainable
industrial water treatment pilot plant design).
Alberta, Canadas Court of the Queens Bench has
issued a nal order approving the acquisition of
Rate for one-year: US$400. Subscribe and renew online at www.globalwaterintel.com/wdr.
Reproduction or electronic distribution is forbidden. Subscribers may circulate their copy on their immediate premises. To e-mail or
create additional copies for other ofce locations, contact Alison Ireland ([email protected]) to arrange a site license.
Zenons outstanding common and non-voting shares
by GE. The court determined the terms and conditions
of the acquisition to be fair and reasonable to the
security holders. The arrangement is expected to be
completed about 1 June.
To promote water conservation, San Diegos
Olivenhain Municipal Water District awarded giftcerticates to local residents who did the best job in
installing water-wise landscapes. Residents were
judged on the basis of water conservation and function
using local plants, energy efciency, and the use of
water harvesting designs. 50 to 70 percent of household
water in the area is used outdoors. Information on
water conservation landscape techniques are available
at http://www.bewaterwise.com/
People
Christ Kennicott Water Technology has announced
that Scott Barrie has joined the company to support
its growth in the municipal water sector, including an
expanding interest in the desalination market. Barrie
was with Weir Westgarth for 17 years and will now be
based in Christs newly established Glasgow, Scotland
ofce. He can be contacted at Scott.Barrie@christwt.
co.uk
Robert J. Quint was named director of operations for
the US Bureau of Reclamation. He began his career
Reclamation in 1978 and served as regional liaison
ofcer and chief of staff. He also spent 2005 in Iraq as
senior consultant to the Ministry of Water Resources.
Transition
Long time desalter Ron Magnani, passed away last
week from injuries received in an automobile accident.
Ron worked for Hydranautics from 1980 to 1995 where
his last project was the successful construction and
installation of the Oceanside, California BWRO. He
joined TriSep in 1995 where he managed engineering
and facilities. He was also responsible for converting
the equipment used to produce at sheet membranes.
TriSep general manager Peter Knappe told WDR, Ron
was an energetic and passionate person who loved the
water industry. Ron was 62 years old and leaves two
children, Jonathon and Alicia. A service was held at the
Santa Barbara Mission last Wednesday.
Page 4WATER DESALINATION REPORT - 22 May 2006