ufdcimages.uflib.ufl.edu · web viewempirical examples of failed collective action institutions in...
TRANSCRIPT
An Analysis of Ostrom’s Principles of Collective Action Institutions
as Applied by the Coral Triangle Initiative
By
Julia Espy
Undergraduate Honors Thesis
University of Florida
College of Agricultural and Life Sciences
School of Natural Resources and the Environment
April 2013
TABLE OF CONTENTS
Introduction……………………………………………………………………………….……….3
Part I……..…………………………………………………….…….…………………....……….5
Ostrom’s Principles of Collective Action Institutions…………………………………….5
The Coral Triangle……………………………………………………………………….12
Comparison of Coral Triangle Initiative and Ostrom’s Principles.………..…………….13
Description of Study Areas and National Programs…………………………….……….17
Part II…………………………………………………………………………………………….22
Comparison of State of the Coral Triangle Reports and National Plans of Action..…….22
Other Management Issues in the State of the Coral Triangle Reports…………………..32
Findings and Discussion………………………………………………………………...……….38
Conclusions and Recommendations……………………………………………………………..43
Works Cited……………………………………………………………………………………...44
Figures………………………………………………………………………………..………….46
Figure 1: Map of the Coral Triangle………………………….………………………….46
Figure 2: Ostrom’s eight principles of collective action institutions…………………….47
Figure 3: 9 Guiding Principles of the CTI………………….…………………………....48
Figure 4: Flow chart of implementation, PNG Marine Program………………………...49
Figure 5: Indonesia comparison of Activities Completed vs. Intended vs. Total……….50
Figure 6: PNG comparison of Activities Completed vs. Intended vs. Total…………….51
Figure 7: Progress towards completion of CTI………………………………………..…52
Figure 8: Groups working to fund conservation programs in Indonesia………………...53
Espy 2
INTRODUCTION AND PURPOSE OF STUDY
My initial interest in Elinor Ostrom’s work developed upon reading her obituary, which
described her studies of collective action institutions and common pool resource management. At
the time, I was interning with Conservation International (CI) in their Global Marine department.
While I was not directly working on projects in the Coral Triangle, CI is very involved with the
area. It was first recognized that the natural resources in the area were largely of a shared nature,
therefore fitting the definition of common-pool resources. With the creation of the Coral Triangle
Initiative for managing those resources, the situation represented one to which Ostrom’s ideas
could be applied. The utilization of her principles of collective action institutions has been
studied in other locations around the world, though not in the Coral Triangle and mostly for
terrestrial areas and land-based resources. The Coral Triangle represented a new location, largely
dependent on marine resources, and a new management strategy that, at first glance, followed
many of her principles. By comparing her principles to the original plans under the Initiative and
then by assessing their actual utilization, the viability of these principles can be addressed. While
success or failure is not part of this discussion, there is much to be said with respect to how her
principles can also be applied to a marine-based common pool resource area and how they
possibly may not be applicable.
In this study, Ostrom’s alternative solution of collective action institutions will be
compared to those management practices the areas of the Coral Triangle plan to and have started
to implement. An expected finding is that many of her principles form the basis of the Regional
Plan of Action. It is also expected that this analysis will show that Papua New Guinea’s plans
depend more heavily on these collaborative action principles, while Indonesia relies more so on
Espy 3
the classic models of government intervention. The plans’ effectiveness is difficult to determine
at this time due to the young nature of these initiatives, but the extent to which her principles are
being employed will be analyzed.
This paper is composed of two parts. In the first part, the management practices
developed and employed by the Coral Triangle Initiative (CTI) will be compared with the
principles of collective action proposed and supported by Elinor Ostrom. Specifically, the CTI
Regional Plan of Action and the National Plan of Action (NPoA) will be examined for two
specific countries, Papua New Guinea and Indonesia in the Coral Triangle. These two locations
exemplify different management styles and will show how Ostrom’s theory of collective action
can be applied to varying extents. In part two, the State of the Coral Triangle Reports for both
countries, released three years after the start of the Coral Triangle Initiative, will be used to
assess progress along the original timeline set out in the NPoAs. The paper will then conclude
with a personal assessment of the extent to which Ostrom’s principles were effectively employed
and facilitated efforts to reach the Goals of the CTI, as well as areas where they were lacking.
Espy 4
PART I
Ostrom’s Principles of Collective Action Institutions
In Governing the Commons, Political Scientist Elinor Ostrom challenges three main
theories regarding the management of common-pool resources (CPRs)1. One is the “tragedy of
the commons,” another is the prisoner’s dilemma game, and the last is the logic of collective
action. She supports that while all are accurate when their required conditions exist, generally
those types of perfectly controlled situations are not present and an alternative theory is more
applicable in the real world. CPRs, their issues and these theories will be explained in detail
below, following a brief background of Ostrom.
Ostrom’s greatest recognition was for receiving The Sveriges Riksbank Prize in
Economic Sciences in Memory of Alfred Nobel in 2009 for “her analysis of economic
governance, especially the commons” (“Elinor Ostrom – Biographical”). She lived a modest life
growing up and encountered many obstacles in her scholarly and professional life due to her
gender. She obtained BA, MA and PhD degrees in Political Science at UCLA-the choice
partially due to the Economics department turning her away. Her initial research on collective
action did not begin by a direct purpose and she moved away from the topic to focus on police
industries across the United States. During this time she taught American Government at Indiana
University, her tenure lasting 15 years (“Elinor Ostrom – Biographical”). Eventually she returned
to the subject of the commons, with the goal of consolidating existing research that was
disconnected and scattered across disciplines and resources type. In 1990, she published
Governing the Commons – The Evolution of Institution for Collective Action, which was a
culmination of the empirical data she collected over years of study regarding the successes and
1 CPR is defined on page 4 of this paper as “a natural or man-made resource system that is sufficiently large as to make it costly (but not impossible) to exclude potential beneficiaries from obtaining benefits from its use” (Ostrom 30).
Espy 5
failures of CPR management. Her list of publications and contributions to other writings is
extensive and long. Her work is frequently cited in others’ examinations of natural resource
management as well. Toward the end of her life she established the Workshop in Political
Theory and Policy Analysis with her husband, Vincent Ostrom, as a research center to help
scholars located around the world ranging across various disciplines to work together and
enhance the results of research (“Elinor Ostrom – Biographical”). Throughout her life she served
on committees for various associations and societies, most notable the American Political
Science Association (“Elinor Ostrom Curriculum Vitae”). Ostrom died recently on June 12, 2012
at the age of 78.
In the following sections of part one of this paper, a CPR will be defined and the three
traditional models of natural resource management will be presented and discussed. Ostrom’s
arguments against these will then be described and her alternatives will be presented. Following
this background information, the Coral Triangle will be indentified and its resource management
problems presented. The Regional Plan of Action, developed through the CTI, will be described
and compared to Ostrom’s eight principles of collective action institutions. Two lower level
cases will show how her principles have been incorporated in different ways into the national
plans of Papua New Guinea and Indonesia. These plans are relatively new, so it will take further
measurement in the future to determine if one method is more successful than another. The two
areas will be compared with respect to the management style they chose. Finally, it will be
concluded that while Ostrom’s principles can be successfully incorporated into CPR
management plans, in different situations they are employed to different degrees.
Elinor Ostrom’s most famous work, Governing the Commons, outlines the issues
surrounding CPRs and their management, as well as the existing theories about them. Ostrom’s
Espy 6
definition of a common-pool resource is “a natural or man-made resource system2 that is
sufficiently large as to make it costly (but not impossible) to exclude potential beneficiaries from
obtaining benefits from its use” (Ostrom 30). The breadth of access to the resource does not
affect its status as a CPR. Common examples of CPRs include open pastures, fisheries, forests
and minerals. Management of these resources poses a problem since they are, as the name
suggests, common goods and therefore non-excludable, but rival3. The problem then lies in the
fact that while everyone has the right to use the resource, it is not possible for everyone to use it
freely and continuously into the future. There are three established models that describe how this
situation unfolds, if certain conditions are present. They are Garrett Hardin’s “tragedy of the
commons,” Dawes et al.’s “prisoner’s dilemma game” and Mancur Olson’s “logic of collective
action.”
Garrett Hardin presents the “tragedy of the commons” using the example of an open
pasture. Multiple herdsmen use this land to graze their cattle. Each individual herdsman wants to
maximize his personal benefit; therefore he wants to allow the maximum number of cattle to
feed on this land. Adding one additional animal creates a positive effect from the additional
proceeds the herdsman will receive from that additional healthy animal. The negative effect is
created by reducing the total amount of grass available for all the other cattle to graze upon. The
individual herdsman gains the entirety of the positive effect, but shares the negative effect
amongst all the other herdsmen. Therefore, the overall effect he feels is positive and it is in his
benefit to allow another animal to graze on the land. The dilemma lies in the fact that all the
herdsmen cannot keep adding animals limitlessly, for eventually the demand for the resource will
2 Ostrom makes a clear point to differentiate between a resource system (a fixed reserve) and the flow of resource units (the units being what are produced by the system to be used by people) (Ostrom 30).3 Non-excludable: no person can be prohibited from using the good; Rival: one person’s consumption of the good decreases the total amount available (Tietenberg)
Espy 7
outpace the supply and the resource will run out (Hardin)4. This is Hardin’s determination of
what will occur in a CPR situation, without other intervention in the natural tendency of human
beings.
According to Ostrom, the prisoner’s dilemma game5 can be thought of as a more
formalized version of the “tragedy of the commons” (Ostrom 3). The study done by Dawes et al.
examined a CPR situation in which the subjects are all made fully aware of their surrounding
circumstances and the consequences of their choices, and also are not allowed to communicate
with others involved6. Each individual in the group is presented with a set of choices, with
varying respective outcomes, each choice also dependent also on the choices of the others. The
study found that if each individual made the choice that would personally benefit them the most,
regardless of the others’ choices, then the collective group would end up with a worse outcome.
If the individuals each chose a slightly less preferable, but more equitable outcome, then the
collective group outcome would be the greatest. This exhibits the “paradox that individually
rational strategies lead to collectively irrational outcomes” (Ostrom 5). Similar to Hardin’s
conclusion, this study deduces that human beings seem incapable of collectively managing a
resource without outside intervention.
Mancur Olson developed a third perspective on the issue of the commons in his book,
The Logic of Collective Action7. The main purpose of his book was to argue against group
theory8 and show that individuals within a group do not act in the best interest of the group solely
4 For further reading on The Tragedy of the Commons, read Hardin’s original article (Hardin).5 For further reading on the prisoner’s dilemma game, read the original report (Dawes)6 Note that the situation was a noncooperative one, meaning that in most cases communication is not allowed or possible, but in certain cases it could be. In these particular cases communication is considered irrelevant and/or any verbal agreements are considered nonbinding (Ostrom 4)7 Reference Olson’s book for further reading (Olson)8 “There is a traditional theory of group behavior that implicitly assumes that private groups and associations operate according to principles entirely different from those that govern the relationships among firms in the marketplace or between taxpayers and the state...” (Olson 16)
Espy 8
for the reason that it would be in the best interest of the group. His most quoted argument is that
“unless the number of individuals is quite small, or unless there is coercion or some other special
device to make individuals act in their common interest, rational self-interested individuals will
not act to achieve their common or group interests. (Olson 1965, p. w. emphasis in original)”
(Ostrom 6). Here a third conclusion is made of the same nature-humans act in their own best
interest, with no regard for greater implications, without an outside incentive to do otherwise.
Ostrom concludes her brief discussion of these three models stating, “at the heart of each
of these models is the free-rider problem” (Ostrom 6). This occurs, as described above in
Hardin’s example, when a person is not forced to bear the full burden of their action and this
burden is shared among others. That person will get more immediate benefit by acting and will
do so in his or her own self-interest, even though the greater group is penalized. Ostrom goes on
to recognize the validity of the arguments made in the preceding three models, but contends that
these are very specific to the structure and circumstances outlined within the models. This is not
necessarily true to reality. In these models, participants are never able to affect or alter anything
regarding their surrounding circumstances, yet in the real world this is inaccurate (Ostrom 7).
She then goes on to make the point that historically policy makers have assumed that these strict
models are true to reality. They have acted in the belief that these represent only guide to
handling CPR problems, which leads to rigid government regulation, or a Leviathan force9. Here,
“proponents of centralized control want an external government agency to decide the specific…
strategy that central authority considers best for the situation” (Ostrom 9). This may be a
bureaucratically easier and more simplistic pathway to choose, but may not be the best choice in
the long run for managing resources effectively and sustainably. Ostrom then presents an
For further discussion refer to Olson’s section titled “C. The Traditional Theory of Groups”9 The Leviathan: “a coercive force outside their individual psyches” (Ostrom 9)
Espy 9
alternative solution, which forms the basis for her research and the rest of the book. When
comparing her alternative theory to the previously described models, she indicates the most
important difference is that in her proposed solution, “participants themselves design their own
contracts” (Ostrom 17). This means that no external agent is defining the rules of management or
enforcement, but the people who will be actually following these rules are the ones who set
them. The advantage of this is best described in her authentic language:
“The self-interest of those who negotiated the contract will lead them to monitor each
other and to report observed infractions so that the contract is enforced. A Regulatory
agency, on the other hand, always needs to hire its own monitors. The regulatory agency
then faces the principal-agent problem of how to ensure its monitors do their own job”
(Ostrom 17).
It is generally accepted that humans are self-interested and it logical to utilize that natural
tendency in any solution. Human beings are going to pay attention to what is occurring around
them when their livelihoods are at risk of being impacted by others’ actions. To illustrate, a
person who directly depends on wild caught fish to make a living will be much more likely to
monitor survival of the fish than will someone who gets paid by an external group to monitor
that same species.
Ostrom concludes by clearly stating that this is not the only solution, there is no single
silver bullet. She simply is proposing an alternative idea that she has found to be effective in
many specific cases. She also notes that in her studies she has come across cases in which this
model of management did not work. She suggests that the reason for this difference is likely an
internal factor within those involved10 (Ostrom 21). The last point Ostrom makes in introducing
10 Empirical examples of failed collective action institutions in Turkey, Sri Lanka, Nova Scotia and California can be found in Chapter 5 (Ostrom 143).
Espy 10
these issues is that the use of metaphorical models in reality is usually quite limited and they are
difficult to implement successfully. Actual situations and the actions of a human being do not
always follow the path set out in these models, so it is unrealistic to expect a policy based on
those models to work successfully. She states, “scientific knowledge is as much an
understanding of the diversity of situations for which a theory or its models are relevant as an
understanding of its limits” (Ostrom 24). This is a key perspective to keep in mind when
assessing strategies of natural resource management, specifically because these scientifically
based models should not be expected to fit flawlessly into a practical situation.
Later on in her book, Ostrom outlines eight specific attributes that identify successful
collective action institutions for managing CPRs in the long-term. They are listed in Figure 2,
Table 3.111 and form the framework for this analysis of the Coral Triangle. In short, the eight
principles are: clear boundaries, congruent rules, collective-choice arrangements, monitoring,
graduated sanctions, conflict-resolution, minimal recognition of rights to organize and nested
enterprises (Ostrom 90).
The Coral Triangle
The Coral Triangle12 is the “ region is located along the equator at the confluence of the
Western Pacific and Indian Oceans… covering all or part of the exclusive economic zones of six
countries: Indonesia, Malaysia, Papua New Guinea, the Philippines, the Solomon Islands and
Timor-Leste” (CTI-CFF CTI Regional Plan of Action 5). This area is quite small relative to Earth
but contains largely disproportionate amounts of biodiversity, sources of food and critical natural
11 See Figure 2: Table 3.1 - Reproduced from text (Ostrom 90)12 See Figure 1: Map of the Coral Triangle
Espy 11
habitats. The mangrove and coral habitats are essential to the inhabitants of these nations both in
terms of the coastal protection they provide and as a driver of important tourism revenue. They
are also critical habitats for tuna and other species of fish that provide food for locals and also
create revenue though food and product sales. The estimated value of these habitats is US $2.3
billion (CTI-CFF CTI RPoA 5). These areas are all in danger of decimation due to the global
trends of industrialization and expansion. In response to these threats, it was proposed by
President Yudhoyono of Indonesia that the six countries of the Coral Triangle should form a new
multinational initiative, later named the Coral Triangle Initiative (CTI), to work together to
protect their precious shared natural resources (CTI-CFF CTI RPoA 6). Following his proposal, a
number of events were held to collaboratively organize a plan of action. The CTI Regional Plan
of Action (RPoA) is the product of these efforts.
Nine guiding principles13 were outlined for all countries to follow when creating and
implementing their own national plans. Furthermore, a four-level structure was outlined. The
first level solidifies the five Goals shared by all six nations: “(i) priority seascapes14; (ii)
ecosystem approach to managing fisheries and other marine resources; (iii) marine protected
areas15; (iv) climate change adaptation; and (v) threatened species” (CTI-CFF CTI RPoA 9). The
second level requires that timetables be set for Targets determined within the plan. The third
level defines that there will be regional Actions or Activities that all countries will adopt or
pursue. The fourth and final level consists of national Actions or Activities that are country-
13 See Figure 3: Section 2 of the RPoA, 9 Guiding Principles14 Seascapes: “Large, multiple-use marine areas, defined scientifically and strategically, in which government authorities, private organizations, and other stakeholders cooperate to conserve the diversity and abundance of marine life and to promote human well-being” (Atkinson et al. 2).15 Marine Protected Area (MPA): “Any area of intertidal or subtidal terrain, together with its overlying water and associated flora, fauna, historical and cultural features, which has been reserved by law or other effective means to protect part or all of the enclosed environment” (Kelleher xviii)
Espy 12
specific (CTI-CFF CTI RPoA 9). All of the six countries use these five Goals as the basic
structure of their national plans. In the following discussion, Goal 4 was not a focus, as it dealt
with the broader environmental issue of climate change rather than a natural resource issue.
Comparison of Coral Triangle Initiative and Ostrom’s Principles
At this point, the comparison can be made as to how closely these CTI principles align
with those defined by Ostrom. It is clear that the CTI RPoA makes it a priority to include all
affected stakeholders in the processes outlined in the plan. The ideas of “capacity building”,
“collaboration” and “data & knowledge sharing” are littered throughout the document. Of
Ostrom’s eight principles, three are outlined extensively, two are intuitively present, and three
are only hinted at for future design and implementation.
The first three principles Ostrom lists appear frequently in the outlined Actions for Goals
1, 2, 3 and 5. The description of the plan for Goal 1, “priority seascapes”, begins with Target 1,
which is the process of delineating the seascapes – directly in line with Ostrom’s first principle,
“clearly defined boundaries” (CTI-CFF CTI RPoA 10). Another place this principle is employed
is under Goal 3, “MPAs”. The second Regional Action is to create a map of the MPA networks
to be designated. In the detail of the plan, it is stated that this is to be done in consultation with
local communities, other stakeholders and the government (CTI-CFF CTI RPoA 19). The idea of
consultation and consideration for the local communities and ecosystems already in place
appears somewhere in every Target plan. Details from Goal 1 and Goal 2 highlight this. In the
annotations explaining Target 1, it is stated that plans must “balance diverse societal objectives
by taking account of the knowledge and uncertainties of biotic, abiotic and human components
of ecosystems and their interactions…[and that] governance should ensure both human and
Espy 13
ecosystem well-being and equity (CTI-CFF CTI RPoA 12).” In the annotations explaining Target
3, acquiring an understanding of the tuna’s life history and local importance is made a priority
before action is taken. Later, it is stated that in order “to make significant progress toward this
target, all of the major relevant stakeholder groups will need to be engaged…” (CTI-CFF CTI
RPoA 15). Ostrom’s third principle deals with the fact that it is close to impossible to implement
a management plan that has not taken into account local circumstances. It is clear from the first
part of highlighted sections above that the CTI directs countries to pay attention to the specifics
of localities. The capacity of the ecosystem to provide resources, the existing needs of the people
and the current stresses and trends must all be weighed together in order to create an effective
management plan. Similarly, the RPoA makes the point to recognize the different categories of
importance, both economic and cultural, of tuna to the coastal people and include those in the
analysis of future action. As would be expected, a crucial part of accommodating these factors
requires local input from all sectors. These groups must be included in the planning, execution
and future monitoring of these plans. Other plans for collaborative opportunities include national
and sub-national stakeholder forums regarding Goal 1,16 a CTI Forum on Tuna Governance,17
and a CTI Forum on Management of and International Trade in Coral Reef-Based Organisms18
regarding Goal 2 (CTI-CFF CTI RPoA 12; 16; 17). These are only a few of many examples that
illustrate how Ostrom’s first three principles have been incorporated into the RPoA.
16 The stated goal of these national and sub-national stakeholder forums is to “promote dialogue on sustainable fisheries management and EAFM (Ecosystem Approach to Fisheries Management)” (CTI-CFF CTI RPoA 12).17 The goal of the CTI Forum on Tuna Governance is to “serve as an informal dialogue and partnership mechanism to share information, advance the…work program…[and] promote practical solutions toward sustainable management of shared tuna stocks, including through public-private partnerships” (CTI-CFF CTI RPoA 16).18 The goal of the CTI Forum on Management of and International Trade in Coral Reef-Based Organisms is the same as the Forum on Tuna Governance, just with a focus on other reef-based organisms aside from tuna (CTI-CFF CTI RPoA 17).
Espy 14
An interesting change in language is found in the section regarding Goal 5. While the
overarching themes are still present, the Targets and related Actions are more regionally strict in
their direction. Regional Actions 1 through 6 include distinctly region-wide conservation plans
for sharks, sea turtles, sea birds, marine mammals, reef fish and invertebrates and a protection
plan against invasive species. The last two Regional Actions focus on enhancing the ability of
the individual nations to implement these regional initiatives, rather than individualize their own.
This is likely due to the fact that these animals are not physically limited to habitats by legal
boundaries. Since it is hard to delineate boundaries for marine species’ territories by nation, it is
only reasonable to expect that the entire Coral Triangle will have to work together to share in the
responsibilities for preserving and protecting these species. As Ostrom’s first principle points
out, it is essential that boundaries be clearly defined for collective action institutions to perform
well. The smallest living environment that can be defined for these marine species is the entire
Coral Triangle itself, explaining why this Goal takes on a tone less concerned with each
individual nation.
Ostrom’s fourth, fifth and sixth principles mainly deal with issues of monitoring and
enforcement. Both topics are hinted at in the RPoA, but are not outlined in detail. It is noted in
multiple locations at the end of a Goal description that evaluations will have to be made
periodically and possibly upon those findings, adjustments would be made. The specifics of how
these evaluations will be completed are not outlined and it would be expected that this be due to
the infancy of this initiative. The most specific description of enforcement is found under Goal 2,
Regional Action 2, which identifies the objective of a Target as to “improve enforcement of
IUU19 fishing through greater collaboration” (CTI-CFF CTI RPoA 13). Here the specific types of
19 IUU: Illegal, Unreported, Unregulated (CTI-CFF CTI RPoA 13)
Espy 15
infractions are mentioned20, as well as some recommendations21 for how this monitoring should
be conducted. Despite these brief mentions, it is suggested that these plans would need further
overall development before effective monitoring and enforcement tactics could be advanced.
The last two principles Ostrom defines are not as explicitly mentioned as the previous
and are inferred from the structure of the plan. In application to the Coral Triangle, her seventh
principle would describe a situation in which individual countries were not prohibited from
defining their own action plans. This is the situation constructed by the CTI. It is inherent in the
composition of the RPoA that the individual nations will be able to construct their own national
plans without obstacles by higher authorities. Her eighth principle describes a situation in which
there are different levels of resource management. This is present as well, as there are plans for
multiple levels of committees. At the top will be the CTI Coordination Committee which “must
become a ‘large tent’ under which major stakeholder groups and related initiatives can combine
and coordinate their actions to achieve shared visions for communities, large-scale seascape,
entire countries, markets and the CTI Implementation Area as a whole” (CTI-CFF CTI RPoA
26). Following this statement plans for coordination at the regional, sub-regional and country
levels are explained. At the country level, National Coordination Committees take point on
national plans and are the main mediator between the Coral Triangle region and the individual
nation. Within each of these areas the committees communicate information and organize actions
among the various stakeholders. This structure fits the type that Ostrom describes in her eighth
principle, “nested enterprises”, which is specific to larger systems, such at the Coral Triangle.
20 Specific infractions include “IUU fishing as transnational organized crime”; “illegal, cross-border fishing by small-scale, large-scale and trans-boundary fishing” (CTI-CFF CTI RPoA 13).21 An example recommendation is “Encouragement of Vessel Monitoring Systems (VMS) in monitoring fishing activities of large-scale and transboundary fishing fleet” (CTI-CFF CTI RPoA 13).
Espy 16
Description of Study Areas and National Programs
I have selected two of the six countries to focus on in more detail regarding their National
Plans of Action. Both Indonesia and Papua New Guinea used the RPoA as strong guidance in
forming their plans. While the overall compositions of the two plans are similar, the level of
emphasis on community involvement is greatly different. Indonesia’s National Plan of Action
(NPoA) is very similar in language to the RPoA. There is little extra information added. This
contrasts with Papua New Guinea’s, which begins the plan document with a long description of
the individual issues the country faces and the current situations the citizens find themselves in.
Throughout the entire document, the importance of participation by local communities in
management decisions and processes is expressed. The differences between the two will be
explored in some more detail in the next section.
Indonesia’s NPoA mirrors the RPoA structurally, although the specific plans are tailored
to the nation’s needs and abilities (CTI-CFF Indonesia 9). These plans were tied into the already
existing governmental regulations for these resources. One of the main themes throughout their
NPoA was consistency across national and local levels. While all stakeholders were included in
the development of strategies for achieving Goals, the direction came mostly from the top-down.
It is designated that the government agencies are to lead working groups that are focused on
maintaining consistency amongst themselves, as well as work with “other stakeholders including
international, national and local Non-Governmental Organizations, provincial and district
governments, universities and experts” (CTI-CFF Indonesia 10). It is important to note that there
is no mention of the public in this list. In the latter part of the NPoA, an Appendix of Indicative
Activities is found, where specific details of planned priority Activities are presented. Here is
where the emphasis on primary government policy is highlighted. Many of the intended
Espy 17
“outputs” from Activities are simply government regulations to be implemented or studies to be
done to supplement those regulations. The inclusion of local people and intent to enhance their
ability to contribute and manage the resources they are in daily contact with is predominately
absent from the details of Goal 1. It is expected that mostly officials and action at higher levels
will handle the management of seascapes and their delineations22. There is some mention of
collaboration with locals in Action 2 under Target 1, Goal 2. Here, plans for training regarding
sustainable fishing practices are laid out (CITE 32). Throughout the detailed plans for this Goal
are the few direct references to local capacity building in Indonesia’s NPoA. Goal 3, regarding
MPAs, and Goal 5, regarding threatened species, are also place more emphasis on national
policy and broader terms of regulation. An interesting note about Goal 5 is that it is by far the
most clear about plans for monitoring and enforcement. Ostrom’s fourth principle emphasized
the need for active auditing of CPR conditions and accountability. Here we find within the
Detailed Activities that there are specific plans for “[a] monitoring and enforcement mechanism
involving trade associations,” “outreach on the enforcement of Government Regulation[s],” “[a]
wildlife crime unit,” and “enforce[ment of a] turtle by-catch reduction program” (CTI-CFF
Indonesia 50-52). Unlike in the RPoA, Indonesia has set out specific actions to be taken with
respect to enforcing these grand plans. This is one of the few differences between Indonesia’s
NPoA and the RPoA. Both documents are otherwise similar in style and language, which is not
surprising as it was stated distinctly that the NPoA mirrored the RPoA (CTI-CFF Indonesia 9).
The structure of the National Plan of Action (NPoA) for Papua New Guinea (PNG) strays
from the format of the RPoA and Indonesia’s NPoA. PNG includes more information regarding
the nation’s cultural and social situation and the programs already in existence. It is literally
22 See pages 27-31 in Indonesia’s NPoA. There is a focus on national policy and data collection across the entire nation, but little mention of local capacity building except for one “Detailed Activity” under Action 2.
Espy 18
written in the National Constitution of Papua New Guinea that the country's “natural resources
and environment [are] to be conserved and used for the collective benefit for us all, and to be
replenished for future generations” (CTI-CFF Papua New Guinea 3). These themes of inclusivity
and sustainability at all levels are constantly found throughout this NPoA and are central values
of PNG. The community is mentioned with the government in a way that states or indicates a
partnership, rather than one serving or reporting to the other. The usage of the word
“partnership” comes for the stated purpose of the PNG Marine Program (CTI-CFF Papua 8).
This program and its purposes were in place prior to the creation of CTI and have only been
supplemented or enhanced since then. The importance of local community is obvious throughout
the NPoA, which is not surprising after learning that “over 90% of coastal and near shore
resources are under customary ownership,” meaning that locals use traditional knowledge when
managing these resources rather than new scientific data and studies (CTI-CFF Papua 9). It’s
explicitly stated that awareness of the impact of Marine Program actions be made a priority
among these communities. Another example of the emphasis on including locals in decision-
making can be found in the plans for program implementation. The Department of Environment
and Conservation (DEC) is assigned to take the lead in coordinating the program, but it is made
clear that the DEC must identify ways for stakeholders at all levels to participate (CTI-CFF
Papua 19). Multiple times in this section, concern for stakeholders is set as a priority, as well as
the importance of stakeholder participation in implementation is recognized-there is an entire
section describing how other stakeholders will be involved (CTI-CFF Papua 20). In the plan,
there is a graphic illustration of the “flow of implementation”, which shows the interconnectivity
of all stakeholders23. Following the lengthy description of PNG’s existing situation and
programs, the details of Activities planned in accordance with the Goals outlined in the RPoA
23 See Figure 4: Flow chart of implementation, PNG Marine Program
Espy 19
are addressed. Here you find little derivation from the general plans and ideas of the RPoA.
Although as stated above, the emphasis lies more on connections with the local community
compared to the emphasis on government-led regulation in the Indonesian NPoA.
After reviewing the Regional Plan of Action and both National Plans of Action of
Indonesia and Papua New Guinea, it is can be concluded presently that Ostrom’s ideas regarding
collective action institutions are being applied. As Ostrom stated in her own work, her principles
are not strictly applicable, nor are they the only solution. The Coral Triangle, as well as both
nations have taken these ideas of managing at the collective level and applied them to their plans
in ways that fit their individual situations. Her eighth principle regarding nested enterprises is the
basis for structuring the CTI RPoA and also can be found in both NPoAs, although more
strongly in Indonesia’s. The first three principles regarding clear boundaries, well-fitting rules
and collective choice are referenced or inferred repeatedly in all three Plans of Action. The
principles regarding monitoring and enforcement are only lightly touched on, if at all, due to the
newness of the CTI and its corresponding plans. It will take further development of these plans
to determine the full extent to which Ostrom’s ideas in this area are actually implemented and the
level to which they are successful. There is an opportunity for further research and exploration in
measuring the success of these plans and the Coral Triangle Initiative. At this time, it can only be
concluded that Elinor Ostrom’s main principles regarding institutions of collective action are
being employed in the Coral Triangle Initiative’s Regional Plan of Action, as well as at a lower
level in the National Plans of Action for Indonesia and Papua New Guinea.
Espy 20
PART II
Comparison of State of the Coral Triangle Reports and National Plans of Action
In part two of this paper, the State of the Coral Triangle Reports will be compared with
the National Plans of Action for Indonesia and Papua New Guinea. The State of the Coral
Triangle Reports (SCTR_ were released by each country in the Coral Triangle in 2012, three
years after the start of the Coral Triangle Initiative, containing an evaluation of their progress
towards completing the Goals of the CTI. To compare intended progress with actual progress,
the original timelines set for each Activity will be evaluated with what was reportedly
accomplished. Refer to Figures 5 and 6 for a bar chart representing this comparison. After
assessing progress for each individual country, the countries’ progress under each Goal will be
Espy 21
compared to each other and areas where one country is exceeding the other or they are on par
with one another will be identified. Lastly, the final conclusions will be presented regarding
where Elinor Ostrom’s principles of collective action institutions are being effectively employed
or are lacking with respect to the implementation of the CTI.
Indonesia is one of the leaders in the Coral Triangle with respect to seascapes. In the past
few years since the creation of the Initiative, they have largely stayed on track with respect to
Goal 1, regarding seascapes, having at least started all Activities under this Goal. There are nine
seascape priority areas that have been designated, and plans for the creation of more are in the
works. They have been consistently developing priority seascapes each year since the start of the
Coral Triangle Initiative (CTI). These plans are continuously being addressed and finalized,
along with discussions regarding strategies for and sources of sustainable financing. Overall,
Target 1, dealing with delineation of seascapes, has been completed or is ongoing per the
original timeline. Target 2, focusing on sustainable management of seascapes, is also well
underway, with only the funding situation remaining unclear (Dirhamsyah et al 180-183).
Under Goal 2, Indonesia is mostly on track with Targets 1 and 2. Target 1 dealt with
regulatory frameworks to achieve Ecosystem Approach to Fisheries Management (EAFM),
drafts have been completed and baseline information compiled, but these policies have not been
finalized. Effective regulation of IUU fishing is being set up and there are plans to enact
community training and international cooperation between Indonesia and Australia. These
Activities are mostly on track with the original timeline. Target 2 addressed COASTFISH, or the
CTI Sustainable Coastal Fisheries and Poverty Reduction Initiative. All Activities under this
Target are underway per the National Plan of Action (NPoA), which provides that they will
continue to strengthen institutional capacity, develop cooperation between industry and
Espy 22
government, as well as develop fishery product standards. The report indicates that the length of
time needed to complete these Activities will be longer than originally expected. Target 3,
dealing with sustainable management of tuna fisheries, is also underway with a Cold Chain
System24 developed and tagging programs established. Other Activities have yet to begin, but are
in sync with the original timeline. The final Target has seen the least progress, as there are at
least eight Activities to be completed under each of the three Actions needed to reach Target 4.
With respect to sustainable life-reef fish trading and reef-based ornamental fish trading,
Indonesia has developed a Database of Marine Ornamental Fish and is finalizing and
implementing a management plan for the Banggai cardinalfish25. There is still much to be done
to complete management, monitoring and evaluation plans as designated in the NPoA. These
were to have been commenced in 2012, but Indonesia is only in the early stages of preparing for
this type of comprehensive management (Dirhamsyah et al 183-187).
Indonesia is also doing quite well with Goal 3, Marine Protected Area (MPA)
management. This is similar to seascape management, so it is understandable that they would be
excelling under this Goal as well. Almost all Actions under this Goal have been initiated and are
well on their way to completion and on track with the original timeline. It is stated in the State of
the Coral Triangle Report (SCTR), “development of [a] national MPA system is in progress and
will [be] integrated into [a] regional and global network” (Dirhamsyah et al. 188). The
involvement of local communities and indigenous people is mandated in policy26, aiding in other
24 A cold chain system consists of refrigeration technology to ensure freshness and viability of the product, in this case tuna (Making a Good Catch).25 The Banggai cardinalfish is a popular aquarium fish and previous to this Initiative, their collection had been largely unregulated (Lunn). More information can be found in the cited article.26 Ministerial Decree No Per.02/MEN/2009 cites that MPA designation process should consult, discuss with and be agreed upon by local communities (Dirhamsyah et al. 189)
Espy 23
capacity building plans. This policy is an example of the many27 that have been adopted that
enhance the ability of Indonesia as a whole to address MPA management effectively. Even
sustainable funding has been addressed, which is a problem that most other countries in the Coral
Triangle have yet to address. A Sustainable Financing Working Group has been created and has
begun work to establish a Trust Fund for Conservation. The general management plans for
MPAs have been developed and implemented, as well as annual monitoring of these areas.
Action 2, regarding trans-boundary protected areas, is the only one yet to be implemented, as it is
still under review by the central government. Looking forward, they are on track to create a
learning network for MPA management, further assessments for the effectiveness of their MPA
management programs and continue work on the Trust Fund for Conservation (Dirhamsyah et al
187-191).
Indonesia has begun to address climate change, the subject of Goal 4. About half of the
Activities that were schedule to begin by the date of the SCTR have actually seen progress.
While this is not substantial progress, it should be noted that the majority of Activities under
Goal 4 are much more long-term than Activities for other Goals. Target 1 is aimed to develop a
climate change adaptation plan. Most of the current research has been completed on coral reefs
and their threats. These records are growing and are quite in depth, so it would seem that
Indonesia is primed to begin the implementation processes. Also, public awareness programs and
training for local authorities on climate change preparedness are underway and ongoing. The
research to support Target 2, regarding Networked National Centers of Excellence on Climate
Change Adaptations, has also been ample which will help propel policy in the future. The stated
plans for the next three years do not include all Actions under this Goal, but it is clear some
progress is being made. Many of the Activities designated in the NPoA are long term or set to
27 Other policies in place are listed in Indonesia’s SCTR (Dirhamsyah et al. 189)
Espy 24
begin in the future. In the NPoA, only about half of the Activities were planned to have been
commenced prior to the release of this SCTR. Of this half only a few have seen specific
progress, although the research being completed can be applied to multiple Actions under this
Goal (Dirhamsyah et al 191-193).
There are no specifics provided for Action updates for Goal 5, which addresses
conservation of threatened species. The title of the section is listed as “Implementation of Action
Plans for 2010-2012,” but through additional research it is believed that the dates are meant to be
2012-2015 to indicate future plans. One of the designated Actions is to determine species
protection status for the Napoleon Wrasse (Dirhamsyah et al 194). At the end of 2012, scientists
and conservationists were still pushing for more protection of the species. Special status has not
been designated past specific quotas for harvest, which have been lowered year after year with
continuously declining populations (Nurhayati). This leads me to conclude that formal protection
is a planned future endeavor. Additional research did not lead to a record of a specific turtle trade
facilitation Discussion Meeting, which is also listed. While essentially no progress has been
recorded in the SCTR, there are specified actions to be taken in the near future. It is reasonable to
assume these will be addressed, as Indonesia has set the foundation for action through its efforts
to complete other areas of its National Plan of Action effectively.
Papua New Guinea (PNG) is considerably behind Indonesia relative to their original plan
in developing seascapes under Goal 1. Only one of eight Activities under the first Target of
designating priority seascapes appears to have started; and that one has yet to be completed. All
of these Activities were planned to have begun in 2010 or 2011. Likewise, the second Target, of
sustainably managing resources within these seascapes, has seen no progress. For most of these
Activities, there is no status provided in the SCTR, which is likely because resources cannot be
Espy 25
managed if the areas in which they reside are not defined. Here again Ostrom’s principle of
definite boundaries is applicable. One discrepancy found deals with Seascape Investment Plans.
In the overview paragraph, it is stated that “Seascape Investment Plans for priority seascapes are
completed, along with arrangements for sequencing investments in line with the PNG Vision
205028” (National CTI 35). PNG also lists each specific Activity under the Targets in a chart with
their current status, in which the Activities dealing with Investment Plans are marked as “not
started” or without a status. It is unclear as to why this discrepancy exists, so the choice was
made to follow the information listed in the chart, as it was the most detailed and in the same
format as other Goals (National CTI 35-37).
Goal 2 of the Marine Program dealt with Ecosystem Approach to Fisheries Management
(EAFM) and PNG has made more progress toward these Targets, but there are some that were
scheduled to be underway and have seen no progress. There are a few areas in which PNG is on
track and a few areas in which steps have been taken, but not as many as originally planned for
by this point in time. Target 1 has seen the least progress, with only two Activities commenced.
This is mostly due to the fact that assessment and strengthening of current legislation has yet to
take place, making implementing EAFM amendments difficult. Target 2 has seen the most
progress, with seven out of eight Activities underway as outlined in the National Plan of Action
(NPoA). Almost all of these dealt with efforts to improve community involvement in
management and are ongoing and on track with the original schedule. Targets 3 and 4 deal with
sustainable tuna stock and the live reef trade and have both experienced moderate progress. Most
of the Activities are ongoing or at least have been started – the ones that have not been deal with
28 PNG Vision 2050 is the National Strategic Plan whose mission states, “we will mobilize to create wealth through smart innovative ideas, quality services and equitable distribution of benefits for all citizens” (CTI-CFF Papua 11).
Espy 26
conducting SWOT29 type analyses and building local capacity and knowledge. PNG recognizes
that the current policies are not directly aimed at EAFM and their programs are more ineffective
due to this fact. It is expected that several proposed amendments will be adopted in the near
future that will directly address and support EAFM Targets, which is a major theme throughout
Goal 2. With the passage of these directly relevant amendments, progress towards meeting
Targets will be facilitated and therefore speedier. With respect to training for local communities,
efforts have been largely supported by The Nature Conservancy. While there has been good
progress overall, there are specific holes in this training with respect to tuna and live reef
fisheries that should be addressed. PNG concludes their status assessment by defining the main
gaps in their EAFM efforts, which include a formally endorsed policy, specific provisions in
existing legislation, development of Fisheries and Ecosystem Management Plans modified from
traditional Fisheries Management Plans, and further training of EAFM for all involved in its
operations (National CTI 37-41).
Marine Protected Areas (MPAs) are the subject of Goal 3. PNG’s SCTR states that there
currently are no MPAs within PNG territory. However, this overlooks the Maza Wildlife
Management Area. While not officially a MPA, it serves a similar purpose as a refuge for turtles
and dugong. It could benefit from a government endorsed protected area plan now, rather than
MPAs that still need to be designed. There are also plans to create Locally Managed Marine
Areas, which will become part of the MPA network when it is approved and operational, as is
the stated Target. So far, efforts to develop a national MPA system have been slow to get off the
ground. While initial plans have been developed and awareness has increased, implementation
all depends on support from all stakeholders and the government. As of the completion of the
SCTR, a discussion paper had been circulated leading to a draft Protected Area Policy. There are
29 SWOT analyses identify Strengths, Weaknesses, Opportunities and Threats
Espy 27
plans to consult with stakeholders about this proposed plan, but no action has been taken. So
even though six of the twelve Activities have been commenced, Goal 3 has yet to see much
tangible progress past discussion and intent (National CTI 42-44).
The report on Goal 4 did not have specific updates with respect to individual Activities.
From the overall discussion though, it can be concluded that almost all Targets are underway
except for the last – the integration of climate resilience into PNG policy. The country seems to
be making an all-around effort to raise awareness of climate change and its impacts as well as to
develop coastal protection. This has been done through the Activities designated in the original
NPoA. These include vulnerability mapping, large mangrove planting projects30, development of
an early warning system, increased coral reef protection programs and provincial consultations to
educate people on climate change and issues specific to them. Even though it cannot be
specifically said how far along PNG is with respect to each Activity, it would seem that Goal 4
has seen the most progress (National CTI 44).
Goal 5 was not specifically addressed in the SCTR.
The observations from the individual SCTRs are largely in line with the Regional
SCTR’s assessment of effort allocated to completing each Goal under their NPoAs. In Figure 7,
the “relative level of allocation of effort” is shown for each country and each Goal with colors
corresponding to the “proportion of effort allocated per CTI Goal” (Alino 23). Indonesia is far
ahead of PNG in MPA development (Goal 3) and shows more progress as well in seascape
development (Goal 1). Indonesia is ahead in EAFM regulations (Goal 2), but only by one
quantitative category of effort. Both countries are then in the lowest categories of effort for both
climate change adaptation (Goal 4) and threatened species protection (Goal 5), but it is not
30 An example is the “Millions of Mangroves” project, which, as the name suggest, “aims to facilitate the planting of millions of mangrove trees” through workshops, supporting nurseries and distribution network of mangroves and seed stock (National CTI 44).
Espy 28
discernable from this chart whether within that category one country has made further efforts
than the other. Though through this assessment, it seems that PNG has a bit of head start on
Indonesia for Goal 4.
It is not surprising that Indonesia would be far ahead of PNG in seascape and MPA
development. Prior to the CTI, seascapes and MPAs were already established or in the works in
Indonesia. Specifically, the Bird’s Head Seascape was designated in 2004 and is composed of
“10 multiple-use MPAs” (Conservation International). It is also stated in this description that the
Bird’s Head Seascape has a “strong focus on policy engagement with governmental institutions
at [all] levels,” as well as involvement by multiple NGO partners and local communities
(Conservation International). It is even stated that this is a model for other countries trying to
implement similar initiatives. Two other seascapes designated prior to the creation of the CTI are
the Karimunjawa and Sulu-Sulawesi Seascape (Atkinson). With existing programs such as this,
Indonesia was primed to meet the Targets of Goals 1 and 3 on track and with relative ease. The
PNG government did not have these types of formal seascape programs in place, making it more
difficult to develop seascapes on their own. The main existing MPA system in place was
researched organized and mainly managed by The Nature Conservancy (TNC). The Governor of
PNG has expressed his support of TNC initiatives in this area, but has largely relied on TNC to
carry out the related activities. This is the Kimbe Bay MPA network, which in 2007 was
proposed through identification of 15 Areas of Interest (Green). Additional research did not
result in any readily available information indicating that the PNG government had previously
organized seascapes or MPAs. There clear difference in the base that was set for seascape and
MPA development in each country. From the SCTRs, it can be assessed that Indonesia is well on
its way to achieving Goals 1 and 3, while PNG seems to be slow to get implementation programs
Espy 29
off the ground. This assessment is well supported by the information above regarding the status
of seascapes and MPAs in each country prior to the inception of the CTI.
Both Indonesia and PNG have made clear progress towards reaching 3 of the 4 Targets
under Goal 2, although these Targets differ in exact content. Each country is lacking progress
toward different Targets though. Indonesia has been slow to fully develop and implement plans
to management live-reef fish trading. PNG has made progress implementing community level
management programs, specifically with sustainable tuna fishing and life-reef trading. On the
other hand, Indonesia has regulatory policies in the final stages of development or in place for
EAFM and IUU fishing, whereas, PNG has struggled with implementing and finalizing EAFM
friendly legislation. With respect to Goal 2, the two countries are having difficulties with the
areas that the other is making progress. Indonesia’s implementation tends to come from the top-
down, which could be why it has been slow to implement management at a lower level. PNG is
likely having difficulty getting legislation passed because it has typically operated with a bottom-
up structure relying on traditional knowledge and less formal regulation of resources.
Climate change is a topic that both countries have recognized as important and have
started overall efforts to addressing Goal 4. Only Indonesia outlines specific progress with
respect to individual Targets under the Goal, so it is hard to directly compare the amount of
tangible progress. From each country’s qualitative assessment of progress it can be observed that
progress is being made and that these actions will be played out over the long term. Both are
working to fortify current climate change research, develop forms of adaptation plans and
increase public awareness. Although this presents a slight contrast with the RSCTR, which found
that both countries were in the lowest category of effort allocated to addressing climate change.
Espy 30
It can be inferred that both countries have recognized the importance of this Goal, but are slower
to implement its long-term Activities.
Neither country had recorded progress with respect to Goal 5. PNG fails to even address
specific future actions to be taken. Indonesia identifies a few specific Activities to be completed
in recent years to come. It is immediately unclear as to why specific progress has not been
recorded in this report and will require more research to determine this. The lack of specific
evidence is in line with the RSCTR’s finding that both countries have committed minimal effort
to this Goal.
Other Management Issues in the State of the Coral Triangle Reports
In addition to assessing their progress with respect to the original 5 Goals of their NPoAs,
both countries identified other management issues they were currently experiencing and
expected to continue in to the future. It is interesting to note that both countries identified the
same main three issues: capacity building, public awareness and sustainable financing.
Sustainable financing is by far the most significant management challenge facing both
Indonesia and PNG as they proceed to implement their NPoAs. “The fundamental outcome of
sustainable financing is to have a plan or strategy designed to have diversified income streams,
increased administrative efficient, cost-effective linkage between income and activities to
address key management challenges, good governance characteristics, and incentives for local
institutions for manage activities and budgets in a more cash-sustainable manner” (National CTI
44). Both countries discuss how the issue sustainable financing is caused by the free-rider
problem31, the root of the problem Ostrom’s collective action principles address. Both countries
31 The free-rider problem is the problem that arises from the “Tragedy of the Commons,” as discussed on page 5 of this paper
Espy 31
note that sustainable financing is key to the success of program implementation and operation in
the future.
Indonesia has taken more tangible moves to address this issue, although very few steps
resulting in actual funding have been completed. Even though the government has been irregular
in its commitment to provide funds toward conservation and resource management activities,
they have passed legislation32 to establish a Trust Fund with the objective of conserving
biodiversity in Indonesia. With the enactment of this legislation came the development of the
Sustainable Financing Working Group, composed of 5 ministries and NGOs. It is charged with
analyzing the budget and potential availability of funds. At the time of the report, the most
current information provided by the SFWG was that there is a gap of 150 billion rupiah, which is
equivalent to $27.7 million, between available funds and funds needed to implement CTI
Activities, and that this gap would grow in the future without a proper sustainable financing plan
(Dirhamsyah 197). There are other groups working to estimate and fund conservation programs
in Indonesia, listed in Table 6.133. The product of most of these efforts has been estimations of
project costs. The only mechanisms currently in place and operating to provide funding are the
Bappenas Indonesia Climate Change Trust Fund and debt-swaps with countries such as the US
and Germany.
PNG finds themselves even further behind in determining needs for or developing
methodologies for sustainable financing. It is stated bluntly that attempting to estimate the costs
of the 5 Goals of the NPoA is “unrealistic and impractical” (National CTI 45). There are no
budgets for existing MPA projects, nor has there been a strategy developed for public sector
conservation. This makes it very difficult to even begin to determine financing needs. PNG also
32 Government Regulation No 80/201133 Included as Figure 8 (Dirhamsyah et al. 198)
Espy 32
addresses the fact that there are multiple objectives within the NPoA that are not SMART34 and
therefore are again difficult to attempt to finance. The only existing sources of funding are
donors and development partners, which are organized on a regional level, and the Coral
Triangle's political partners, the US and Australia. PNG also notes that the NPoA “does not
explore new internal sources of funding” (National CTI 47). The report does not provide
evidence that PNG is in any stage of planning for sustainable financing. It is clear that PNG
recognizes that this is a key need for the future sustainability of these programs, but does not
seem to be in the position to address this need at the current time.
There is also a need for further capacity building in both countries to support operation of
programs that have been implemented and are to be implemented in the future under the CTI.
Currently, the Coral Triangle Center (CTC), operated by The Nature Conservancy, completes the
majority of training. The CTC has developed training modules and implemented site-based
trainings. The development of the MPA Learning Network is in progress, which will aid in
coordination of trainings between the CT6 (the six countries of the Coral Triangle) and will
eventually be linked with the CTC. In PNG civil society organizations and provincial or local
level governments are the two main groups involved in implementing capacity building
programs. To date, civil society organizations are the only ones that have the required capacity to
carry out their responsibilities, but their training programs can potentially aid governments in
building capacity themselves. There have been two main workshops35 that have resulted in
tangible programs. In 2001 the Strengthening Conservation Capacity Project was initiated which
resulted in the creation of 8 training modules for capacity development and in 2010 the PNG
Learning and Training Network was created. Despite these initiatives, PNG still is lacking in
34 SMART goals are ones that are Specific, Measurable, Attainable, Relevant, and Timely35 Workshops were held in 2001 and 2010 (National CTI 62)
Espy 33
leadership at all levels, especially with a high turnover rate in managers. One of the main
problems hindering PNG progress is the lack of available technical expertise. While there are
technical experts, they have been largely too busy to participate in conservation efforts. This
contributed to PNG being the last country to complete its SCTR. Indonesia is generally in the
same position as PNG, with multiple capacity building initiatives in the works, but still lacking
in capacity at all levels. In 2013, Indonesia is starting to develop a School for Marine Resource
Conservation and Management. The objective is to “enable 30% of [the] MPA system in
Indonesia to be managed under the leadership of qualified managers by 2015” – the idea being
that graduates of this school would be trained to successfully become these managers (Indonesia
National)36. The Indonesian government will be contributing about two-thirds of the funds
needed to complete this project on schedule and has requested the remaining funds be provided
by donors and partners. This is achievable especially with the existing partnerships and
cooperative relationships Indonesia maintains with other governments and NGOs. Looking
forward, Indonesia plans to align government strategic plans with capacity development needs
for marine resource conservation, as well as institutionalizing training strategies to ensure
continuation in the future (Dirhamsyah et al. 203). From each of their individual SCTRs, it seems
that both countries recognize capacity as a serious need and have made concrete efforts to
address this.
Public awareness was also named as key to the success of both countries efforts to fulfill
the CTI. The bulk of Indonesia’s effort to raise public awareness lies with the Coral Reef
Rehabilitation Management Project, also known as COREMAP. This project was implemented
in 1999 and is planned to continue through 2017. There are 3 areas of COREMAP that address
issues of public awareness. The first consists of activities that “support behavioral change for
36 See cited source for more information
Espy 34
sustainable coral reef co-management through the provision of public awareness materials,
campaigns and advocacy at [all levels]” (Dirhamsyah et al. 210). Indonesia has actually been
able to assess the outreach of this program through the COREMAP II 2010 survey, which found
that “75% of project area residents are aware of the importance of coral reefs” (Dirhamsyah et al.
211). The current strategies are for the most part operating smoothly, but in the future Indonesia
notes that internet and mobile phones should be incorporated for information dissemination and
that there needs to be further outreach to political, religious, governmental and cultural leaders.
The second component deals with integrating coral reef conservation and sustainable use into
education. Education materials addressing these issues, including textbooks at all levels, have
been distributed and are in use. These efforts have been effective and Indonesia plans to continue
and expand the programs, hopefully with better coordination among government agencies to
ensure uniformity. The last component is effective communication of program “philosophy,
objectives, activities outputs and outcomes” to all those involved (Dirhamsyah et al. 212). This
has included standardizing messaging and PR protocols that Indonesia could use in the future for
other public awareness efforts. Other public awareness efforts besides those through COREMAP
have been conducted by local organizations and are much smaller in scale. Public awareness
through COREMAP is by far the largest in Indonesia regarding marine conservation.
PNG also has a large public awareness effort, although more concentrated at the local
effort. There are education programs, similar to those in Indonesia, which have developed marine
conservation resource materials. There are also media development programs that include both
print and electronic outreach materials. Outreach efforts frequently provide opportunities for
locals to participate in the marine management process, in that locals raise awareness of
additional issues that need to be addressed – these have ranged from the size of fishing nets, the
Espy 35
need for alternative sources of income and the loss of trust or interest without regular awareness
programs. PNG has no specific statistics, but felt comfortable estimating that through direct
public awareness efforts, about 40% of the populations had been reached (National CTI 54). The
results PNG has seen have been positive – changes in attitude, more collaboration and the rising
inclusion of women. There are still many issues that much be address including lack of skills and
capacity, lack of funding, lack of coordination among stakeholders, lack of a tool to assess
awareness and lack of effective and standardized enforcement. All of these needs are identified
as areas to be addressed in the future by PNG. Both Indonesia and PNG are making deliberate
efforts to increase public awareness, although it seems Indonesia has access to more resources
and existing institutions, such as COREMAP, to be able do so.
Espy 36
FINDINGS AND DISCUSSION
After assessing the status of each country with respect to the timelines originally set out in
their respective National Plans of Action and then comparing the two countries’ results to one
another, another look was taken at Ostrom’s principles. As would be expected considering the
original comparison of the eight principles and the NPoAs, most of these had been applied. In
some areas it was found that according to the State of the Coral Triangle Reports, certain
principles had been employed to different extents than implied in the NPoAs. There were also
some key findings indicating where Ostrom’s principles may be lacking or not applicable to real
world natural resource management situations. The findings are as follows:
1. In the original comparison, it was stated, “it will take further development of these plans
to determine the full extent to which Ostrom’s ideas in this area are actually implemented
and the level to which they are successful” (Espy 18). This observation still stands, in
particular with regard to PNG. They are generally far behind Indonesia in the actual
implementation of any programs, as well as having no basis of internal sustainable
financing for these projects. It is very difficult to conclude overall how Ostrom’s
Espy 37
principles are aiding or hindering their efforts to implement their NPoA. Indonesia has
made more tangible efforts that can be judged more effectively. That being said, both
countries NPoAs are still young and while some observations can be made, further time
to develop is still required to assess successes and failures.
2. In the original comparison, it was found that Ostrom’s first three principles were the most
apparent in the NPoAs. As they are implemented, this is largely proven to be true and
these principles seem to be aiding in the implementation process. Her first principle
regarding clear delineations of resource areas are proving to be essential to management
success. Indonesia has been able to designate multiple MPAs and seascapes each year
since the CTI began and implement or develop management strategies. PNG has been
largely unable to do the same. Consistent with Ostrom’s first principle; these countries’
experiences confirm that without designating unambiguous boundaries, it is very
difficulty to manage the resources within that area.
3. With respect to Ostrom’s second principle, again two specific cases of PNG’s difficulties
highlight the importance of the concept of appropriate rules. Quite frankly, PNG states
that some of the Goals or Targets set out in the NPoA are not SMART37 goals, most
important to Ostrom’s principle meaning that they are not attainable. By their own
evaluation, PNG does not currently have the needed capacity to meet the Targets set out
by the CTI. Second, in the discussion of Ecosystem Approach to Fisheries Management
and Goal 2, PNG points out that the existing legislation that can be applied to EAFM
does not directly address the approach, and therefore the current regulations will not
effectively enforce the EAFM policies or support EAFM Targets.
37 SMART goals are defined on page 34 of this paper
Espy 38
4. Ostrom’s third principle emphasizes the importance of involving the local community in
management and decision-making when actions affect them and has been well supported
by both countries in practice. This concept was emphasized in PNG’s NPoA, and
continues to be as they proceed with implementation. While less notable in their NPoA,
Indonesia has made tangible efforts to increase community involvement in practice. In
particular, they passed legislation in 2009 around the time the CTI was approved, that
mandates the inclusion of locals in the MPA designation process. In PNG, public
outreach programs provide platforms for consultation with locals when implementing
conservation programs. Also, as previously mentioned, PNG is still largely dependent on
traditional forms of knowledge and management, which employ collective choice-type
arrangements.
5. Ostrom’s fourth, fifth and sixth principles were mostly hinted at or inferred in the NPoAs,
which is about the same depth to which they are employed in the SCTR. There is little
development in these processes that would provide for assessment of principles in action.
The fourth principle regarding monitoring is the most directly apparent in the language of
the SCTRs, but not more so than originally stated in the NPoA. The development for
these monitoring systems is in the works, but the actual results are limited or non-
existent. Specific plans for or measures regarding graduated sanctions, Ostrom’s fifth
principle, are even less evident. Ostrom’s sixth principle, dealing with conflict resolution
mechanisms, is not specifically outlined but there is some evidence for their existence in
PNG’s discussion of community outreach. As mentioned with respect to Ostrom’s third
principle, there are platforms for discussion of local issues within public awareness
programs. It is at this time that locals have the opportunity to raise problems they have
Espy 39
with the CTI programs about which they are learning. An arena for conflict-resolution
can be envisioned here that would occur at minimal additional cost. The information
gained from locals can be gathered and returned to the decision-makers who can then
incorporate their concerns into program adjustments. While this was only pointed out in
PNG’s SCTR, this same type of interaction could be encouraged through Indonesia’s
public awareness efforts, if not already going on.
6. Ostrom’s seventh principle is much more strongly observed in PNG. The leadership is
supportive of local community efforts, as well as of efforts by NGOs. For example, the
Governor of the West New Britain Province pledged support of TNC for the Kimbe Bay
MPA project, including all stakeholders in that pledge as well (Kimbe Bay nature.org 5).
The intentional or unintentional reliance on local community activities moves PNG away
from Ostrom’s final principle regarding nested enterprises in that there aren’t many layers
and networks operating in PNG. There are plans to implement locally managed marine
areas as a part of a larger MPA network, but these plans have yet to come to fruition.
Indonesia’s situation is essentially opposite. There is already an MPA Network in place,
along with a coordinated learning network. On the other hand, Indonesia’s actions have
come from the top down and have relied much less on community involvement. While
the Indonesian government is not discouraging community-level organization, its
facilitation is not as great as in PNG.
7. One possible cause for the differences in progress seen between Indonesia and PNG
could be the extent to which they are utilizing collective-choice arrangements. As stated
above, PNG does so to a further extent than Indonesia. It is possible that this fact is
hindering PNG’s progress, in that the structure for legislation and large or national
Espy 40
conservation projects does not exist as it does in Indonesia. In short, PNG is trying to
implement the NPoA from the bottom up while Indonesia does the opposite, working
from the top down. From this analysis, it seems possible that utilizing Ostrom’s
principles may operate the most smoothly and as intended at the smaller scale – when
dealing with local management, implementation and monitoring rather than coordinating
with a larger group like the Coral Triangle. It may be easier for Indonesia to employ
Ostrom’s principles in individual management efforts after they have set the stage for a
national project. Similarly, PNG may have difficulty doing so without the overarching
common national strategy in place. This could prove to be an area where Ostrom’s
principles are not applicable in the early stages of planning a nationwide initiative. This
analysis cannot prove this observation, although the finding is intriguing and could
benefit from further research.
8. Quite possibly the starkest finding was that the concept of sustainable financing is
nonexistent in Ostrom’s eight principles. Prior to assessing the implementation of the
CTI, it was not apparent that sustainable financing was a large point of concern – it was
only mentioned directly in a couple of the Targets or individual Activities as part of the
NPoAs. This contrasts with the huge emphasis placed on financing in both countries’
SCTR. Each country had a discussion of what sustainable financing was in general and
then as it applied to their individual situations. Both countries raised the point that
sustainable financing becomes an issue when the free-rider problem arises, the very root
of the problem Ostrom addresses with her theory of collective action. In addition, both
countries clearly state that sustainable financing is key to the success of conservation
efforts under the CTI. Through initial research there is not clear evidence of Ostrom
Espy 41
addressing this important component of resource management through collective action
or why that is so. This raises another potential weakness in Ostrom’s principles as applied
to the Coral Triangle to be further investigated.
CONCLUSIONS AND RECOMMENDATIONS
The eight findings above highlight that Elinor Ostrom’s principle can and are being
effectively employed in the Coral Triangle. While some are employed more directly than others,
all eight of her principles are utilized to some extent. The principles most strictly in use by the
Coral Triangle and proving to be valuable are the first (clearly defined boundaries) and third
(collective-choice arrangements). The fourth (monitoring), fifth (graduated sanctions) and sixth
(conflict-resolution mechanisms) principles are ones that show potential to aid in progress, but
cannot fully be assessed for actual effectiveness at this time due to their application to processes
not yet implemented under the CTI. The second (congruence between appropriation and
provision rules and local conditions) and eighth (nested enterprises) principles are not being fully
adhered to in PNG and underlines how its lack of use is detrimental to progress. On the other
hand, the seventh principle (minimal recognition of rights to organize) is not being fully adhered
to in Indonesia, but its lack of use is proving to potentially be beneficial. Lastly, Ostrom’s
principles seem to miss a crucial requirement for the success of collective action institutions,
which is sustainable financing. There are opportunities for future research in a few areas. First, a
longer-term analysis to determine success or failure of the Coral Triangle Initiative could be
Espy 42
completed. Second, it is odd that only one of Ostrom’s principles seems to be disadvantageous to
progress in the Coral Triangle; an answer to why that is could be explored. Lastly, the
importance of sustainable financing on its own accord could be studied, as well as the reasoning
behind its apparent absence from Ostrom’s principles of collective action institutions.
WORKS CITED
Alino, Dr. Porfirio. Highlights of the Regional State of the Coral Triangle Report (RSCTR). 7 July 2012. Presentation.
Atkinson, S., et al. The Seascapes Guidebook: How to Select, Develop and Implement Seascapes. Arlington, VA, USA: Conservation International, 2011. Print.
Conservation International. Bird's Head Seascape. N.p.: Conservation International, n.d. Web. <http://www.conservation.org/Documents/field_demonstrations/CI_Field_Demonstration_Birds-Head_English.pdf>.
Coral Triangle Initiative on Coral Reefs, Fisheries and Food Security (CTI-CFF). CTI Regional Plan of Action., 2009. Web. 2 July 2012.
---. CTI-CFF Regional Boundaries Map, 2011.
---. Indonesia National Plan of Actions., 2009. Web. 2 July 2012.
---. Papua New Guinea Marine Program on Coral Reefs, Fisheries and National Security: National Plan of Action 2010-2013., 2009. Print.
Dawes, Robyn M., Jeanne McTavish, and Harriet Shaklee. "Behavior, Communication, and Assumptions about Other People's Behavior in a Commons Dilemma Situation." Journal of Personality and Social Psychology 35.1 (1977): 1-11. Print.
Dirhamsyah Et Al. "Chapter 6: Plan of Action Initiatives and Future Plans." The State of the Coral Triangle in Indonesia: Coral Triangle Marine Resources: Their Status, Economies, and Management. N.p.: N.p., 2012. 180-215. Print.
"Elinor Ostrom - Biographical." Web. <http://www.nobelprize.org/nobel_prizes/economics/laureates/2009/ostrom.html>.
"Elinor Ostrom Curriculum Vitae." June 19, 2012. Web. The Vincent and Elinor Ostrom Workshop in Political Theory and Policy Analysis, Indiana University. <http://www.indiana.edu/~workshop/people/lostromcv.htm>.
Espy 43
Green, A., P. Lokani, S. Sheppard, J. Almany, S. Keu, J. Aitsi, J. Warku Karvon, R. Hamilton, and G. Lipsett-Moore. Scientific Design of a Resilient Network of Marine Protected Areas. Rep. no. 2/07. Kimbe Bay, West New Britain, Papua New Guinea: n.p., 2007. Print. TNC Pacific Island Countries.
Hardin, Garrett. "The Tragedy of the Commons." Science 162.3859 (1968): 1243-8. Web. 15 July 2012.
Indonesia National Secretariat of CTI-CFF Indonesia. Strengthening the Marine Capacity of Marine Protected Areas in Indonesia - School for Marine Resources Conservation and Management. N.p.: Indonesia National Secretariat of CTI-CFF Indonesia, n.d. Web. <http://www.coraltriangleinitiative.org/sites/default/files/resources/leaflet_Strengthening%20the%20Management%20Capacity%20of%20MPA_Final.pdf>.
Kelleher, G. Guidelines for Marine Protected Areas. Gland, Switzerland and Cambridge, UK: IUCN Print.
Lunn, Kristin E., and Marie-Annick Moreau. "Conservation of Banggai Cardinalfish Populations in Sulawesi, Indonesia: An Integrated Research and Education Project." SPC Live Reef Fish Information Bulletin #10 (2002): 33-34. Print.
Making a Good Catch: Non-CFC Technologies in the Fishery Cold Chain. [Paris, France]: United Nations Environment Programme, Division of Technology, Industry and Economics, OzoneAction Programme, 2000. Print.
National CTI Coordinating Committee of Papua New Guinea. "POA Initiatives and Future Plans; Other Management Issues." State of the Coral Reefs of Papua New Guinea: Coral Triangle Marine Resources: Their Status, Economies, and Management. N.p.: n.p., 2012. 35-64. Print.
Nurhayati, Desy. "Scientists Urge Cessation of Napoleon Fish Trade." The Jakarta Post. N.p., 20 Nov. 2012. Web. 20 Mar. 2013.
Olson, Mancur. The Logic of Collective Action: Public Goods and the Theory of Groups. Revised ed. United States of America: Harvard University Press, 1971. Print.
Ostrom, Elinor. Governing the Commons: The Evolution of Institutions for Collective Action.
New York, NY: Press Syndicate of the University of Cambridge, 1990. Print.
Tietenberg, Tom, and Lynne Lewis. "Chapter 4. Property Rights, Externalities, and
Environmental Problems." Environmental and Natural Resource Economics. 8th ed.
Addison Wesley, 2008. Print.
Espy 44
FIGURES
Figure 1: Map of the Coral Triangle (CTI-CFF Regional Boundaries
Map)
Espy 45
Figure 2: Table 3.1 – Ostrom’s eight principles of collective action
institutions (Ostrom 90)
Table 3.1 Design Principles illustrated by long-enduring CPR institutions1. Clearly defined boundaries
Individuals or households who have rights to withdraw resource units from the CPR must be clearly defined, as must the boundaries of the CPR itself.
2. Congruence between appropriation and provision rules and local conditionsAppropriation rules restricting time, place, technology, and/or quantity of resource units are related to local conditions and to provision rules requiring labor, material, and/or money.
3. Collective-choice arrangements.Most individuals affected by the operational rules can participate in modifying the operational rules.
4. MonitoringMonitors, who actively audit CPR conditions and appropriator behavior, are accountable to the appropriators or are the appropriators.
5. Graduated sanctionsAppropriators who violate operational rules are likely to be assessed graduated sanctions (depending on the seriousness and the context of the offense) by other appropriators, by officials accountable to these appropriators, or by both.
6. Conflict-resolution mechanismsAppropriators and their officials have rapid access to low-cost local arenas to resolve conflicts among appropriators or between appropriators and officials.
7. Minimal recognition of rights to organizeThe rights of appropriators of devise their own institutions are not challenged by external government authorities
For CPRs that are parts of larger systems:8. Nested enterprises
Appropriation, provision, monitoring, enforcement, conflict resolution, and governance activities are organized in multiple layers of nested enterprises.
Espy 46
Figure 3: Section 2 of the RPoA, 9 Guiding Principles of the CTI
(CTI-CFF RPoA 8)
Espy 47
Figure 4: Flow chart of implementation, PNG Marine Program
(CTI-CFF Papua 20)
Espy 48
Espy 49
Figure 5: Indonesia comparison of Activities Completed vs. Activities Intended for Completion
vs. Total Number of Activities (Dirhamsyah et al.)
Figure 6: Papua New Guinea comparison of Activities Completed vs. Activities Intended for
Completion vs. Total Number of Activities (CITE)
Espy 51
Figure 7: Progress towards completion of CTI (Alino 23)
Notes:
The six countries are Indonesia, Malaysia, Papua New Guinea, Philippines, Solomon
Islands, and Timor-Leste
Seascapes: see page 12, Goal 1
EAFM: Ecosystem Approach to Fisheries Management, Goal 2
MPA: Marine Protected Areas, Goal 3
CCA: Climate Change Adaptation, Goal 4
Threatened Species: Goal 5
Figure 8: Groups working to estimate costs for and fund
conservation programs in Indonesia (Dirhamsyah 198)
Espy 53