concor.co.za · web viewproject type: topsoil & overburdenclient: anglo coal start date: may...

1
KLEINKOPJE WITBANK, MPHUMALANGA PROJECT TYPE: TOPSOIL & OVERBURDEN CLIENT: Anglo Coal START DATE: May 2009 END DATE: April 2010 PROJECT DURATION: 11 months AVERAGE MONTHLY VOLUMES: 90 000 m 3 PROJECT DESCRIPTION: Removal of topsoil and soft over burden for Anglo Coal. Total volumes moved were 925, 000m³ of soft over burden and 63, 00m³ of topsoil www.concor.co.za

Upload: others

Post on 14-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: concor.co.za · Web viewPROJECT TYPE: TOPSOIL & OVERBURDENCLIENT: Anglo Coal START DATE: May 2009 END DATE: April 2010 PROJECT DURATION: 11 months AVERAGE MONTHLY VOLUMES: 90 000

KLEINKOPJEWITBANK, MPHUMALANGA

PROJECT TYPE: TOPSOIL & OVERBURDEN

CLIENT:Anglo Coal

START DATE:May 2009

END DATE:April 2010

PROJECT DURATION:11 months

AVERAGE MONTHLY VOLUMES:90 000 m3

PROJECT DESCRIPTION:Removal of topsoil and soft over burden for Anglo Coal. Total volumes moved were 925, 000m³ of soft over burden and 63, 00m³ of topsoil

www.concor.co.za